B08_Solicitation_Attachment_1_SOW.docx

DOCX document 221 KB Posted

Attached to
ASSATEAGE ISLAND - INSTALL COMFORT STATIONS Federal contract opportunity
Solicitation number
140P4326R0038
Issued by
Department of the Interior National Park Service Northeast Region

About this file

This is a Statement of Work (SOW) for construction services at Assateague Island National Seashore in Berlin, Maryland, issued by the National Park Service Northeast Region. The contractor must procure and install pre-cast concrete vault-style comfort stations at popular day-use areas with a minimum of 5 years of relevant experience. The period of performance runs from October 1, 2026, through April 30, 2027, with a firm delivery date of 90 days after award that is non-negotiable. The base bid requires installation of two ADA-compliant double-vault comfort stations at South Beach Parking Lot (6156 Bayberry Drive, Berlin, MD 21811), while Bid Option 1 includes a single-vault comfort station at Old Ferry Landing (12100 Ferry Landing Road, Berlin, MD 21811), approximately 2 miles away, with final grade 1 foot above current elevation.

The pre-cast concrete vault restrooms must meet specific technical requirements, including minimum dimensions of 14 feet wide by 11 feet long by 9 feet high, reinforced concrete construction with 4-inch walls and 5-inch floors per ASTM standards, polyethylene liners, ADA-compliant components, stainless steel grab bars rated for 300-pound loads, dual manhole covers for pumper truck access, 12-inch diameter vent pipes, HDPE toilet risers, galvanized steel doors, and specified interior and exterior finishes including epoxy floors and water-repellent stains. Material submittals demonstrating compliance with specifications are required with the quote package, along with superintendent designations with resumes, active SAM registration, contractor's license, and certificate of insurance. Additional deliverables include SF 1413 forms for subcontractors (10 days after award), Schedule of Values (14 days), site-specific safety plan (14 days), construction schedule in Gantt chart format (14 days and every 14 days thereafter), weekly daily work logs and certified payroll, and warranty letters at closeout. The contractor is responsible for all site preparation, excavation, grading, material handling, and compliance with OSHA safety standards, environmental regulations, Davis-Bacon wage requirements, and NPS operational hours of 7:00 am to 3:30 pm ET, Monday through Friday. An organized pre-bid site visit is scheduled for Wednesday, September 2, 2026, at 10:00 am EDT at 6633 Bayberry Drive, Berlin, MD 21811.

View the file

Other files for this federal contract opportunity

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

National Park Service U.S. Department of the Interior

Northeast Region Assateague Island National Seashore Facility Management Division

REPLACE COMFORT STATIONS AT POPULAR DAY USE AREAS

Project Location: 6156 Bayberry Drive, Berlin, MD 21811

STATEMENT OF WORK FOR CONSTRUCTION SERVICES

1. GENERAL

Assateague Island National Seashore (ASIS), headquartered in Berlin, Maryland seeks a contractor with a minimum of 5 years to procure and install pre-cast concrete vault type style comfort stations. Period of Performance on this contract shall take place between 10/1/2026, through 4/30/2027. The delivery date is 90 Days After Award and not negotiable.

It is strongly recommended that the contractor’s visit and inspect the site during the pre-bid site visit to verify all estimated quantities, and existing conditions provided by the Government and to observe the complexities of conducting the scope of work. All quantities are provided as informational only. Contractors shall be responsible for verifying all measurements and acquiring all quantities to complete this requirement. Quotes will be broken down by using a government provided price schedule, which will provide a lump sum for all elements.

The term ‘Contractor’ herein, includes the prime contractor and all subordinate contractors employed on their behalf, and are subject to the same guidelines for this contract.

The term ‘Park” herein, refers to the National Park Service unit, Assateague Island National Seashore.

2. PURPOSE AND BACKGROUND

Assateague Island provides day-use and camping facilities 24/7/ 365 days a year. Most of these facilities on the island utilize primitive vault toilet structures that collect waste and are pumped out using specialty pumper equipment. These vault toilet structures are currently in poor condition due to high use and the corrosive island environment. The structures require constant maintenance for them to continue to function as intended and require special procedures to ensure further damage isn’t sustained to them. This project would be to procure and install a prepacked/pre-engineered pre-cast concrete vault style comfort station in select locations around the park.

3. TASKS

Provide all labor, supervision, materials, tools, supplies, transportation, license, certificates, permits, personal protection equipment, professional services, and equipment incidental to and necessary to provide services, as specified in the SOW at Assateague Island National Seashore. The contractor shall know and understand the complexities and intricacies of work in the scope of work.

Requirements

Base Bid:

3.1.1. Prepare site for new pre-cast vault restrooms. This could include measuring, marking, and surveying locations to ensure proper placement of structure.

3.1.2. Provide earthworks following manufacturers specifications and recommendations. This could include excavating, grading, compaction and hauling in materials (stone etc.) to ensure solid foundation base.

3.1.3. Procure, deliver to site and fully install (2) pre-cast concrete ADA compliant double vault style comfort station at the “South Beach Parking Lot”. South Beach Parking Lot address is 6156 Bayberry Drive, Berlin, MD 21811. Installation will occur at this address but at two different locations (please see “General Location South Beach Parking Lot”) for reference.

3.1.4. See below minimum requirements for pre-cast concrete vault waterless restroom:

3.1.4.1. General:

3.1.4.1.1. Needs to be categorized by the manufacturer as a “vault restroom and or vault comfort station” or similar type of verbiage. It can’t be a piece of equipment that has “variable” uses or “could” be used for type of use.

3.1.4.1.2. Vault needs to be a pre-cast reinforced double vault concrete building that has two single user waterless restrooms

3.1.4.1.3. Structure needs to meet all applicable accessibility requirements, needs to be ADA compliant and meet building code requirements

3.1.4.1.4. If you are looking at the structure from the front (where the doors are) the house structure needs to be a minimum of 14’ wide, 11’ long and 9’ high (to apex of roof, not including vent pipe)

3.1.4.1.5. Minium interior space of each partition/room 6’ wide and 6’ long with a minimum of 60” turning radius inside the toilet (ADA)

3.1.4.1.6. Vault needs to be able to hold around (within 100 gallons +/-) 1,000 gallons of waste total

3.1.4.1.7. Underground vault portion can’t be over 5 feet high

3.1.4.2. Structure:

3.1.4.2.1. Structure needs to be pre-cast reinforced concrete meeting ASTM A615and is a low alkali type I/II or III conforming to ASTM C-150.

3.1.4.2.2. Vaults buildings need to be a one-piece unit and at structural joints there needs to be rebar, plates and/or wire mesh that laps over the edge.

3.1.4.2.3. Vault building structure needs to have a minimum of 4” walls, 4.5” roof and 5” floor thickness

3.1.4.2.4. Structure needs to have a minimum of a 3/12 pitch roof

3.1.4.2.5. Vault needs to be lined with a type of polyethylene liner that is a minimum of .1” thick

3.1.4.2.6. Bonding compound/tape between vault and toilet needs to be manufactured for pre-cast concrete structures

3.1.4.3. Components:

3.1.4.3.1. Structure needs to have grab bars meeting ADA standards at site of toilet riser that are a minimum of 304 stainless steel and able to handle 300-pound top load

3.1.4.3.2. Vault needs to have a minimum of (2) manhole-type covers installed on the rear of the building (behind each partition) and accessible to pump out the underground vault with a tanker style pumper truck. The manhole needs to have a locking mechanism or be able to be locked to secure manholes

3.1.4.3.3. Vent pipe needs to be installed at a minimum of 12” in diameter and minimum of 2 feet above the roof.

3.1.4.3.4. Risers toilet need to meet ADA standard and be a white one-piece HDPE polyethylene

3.1.4.3.5. Doors need to be a painted flush panel style door that is 1 ¾” thick and made of galvanized steel with all applicable hardware.

3.1.4.3.6. Signs need to have raised pictograms, letters and braille. Signs need to include, “No Trash in Vault” inside restroom, “Unisex stall” outside of each partition, “Handicap Accessible” outside of each partition

3.1.4.3.7. Each unit needs to have a wall vent suitable to ventilate the structure that is minimum of 304 stainless steel and anchored into concrete wall with rust-resistant hardware. Vent needs to come with an insect screen.

3.1.4.3.8. Need to have a commercial grade, ANSI/BHMA certified Grade 1 mortise locket for each door that includes a deadbolt with thumb turn privacy function. This lockset needs to be rated for exterior use/door

3.1.4.4. Finishes:

3.1.4.4.1. Interior Floors: Minium (1) coat grey chemical resistant epoxy

3.1.4.4.2. Interior Walls: Minimum (2) coats white acrylic water repellent penetrating stain with a clear acrylic sealer

3.1.4.4.3. Exterior Slab: Minium (1) coat clear sealer

3.1.4.4.4. Exterior Walls: Minimum (2) coats NPS chosen color that is water repellent penetrating stain with a clear acrylic sealer

3.1.4.4.5. Exterior Texture: Pho-Wood texture for siding, pho-cedar for roof

3.1.4.4.6. Metal surfaces: Minium (2) coats direct to metal alkyd paint

Bid Option 1:

3.1.5. Provide (1) additional restroom in another geographical location at the park called “Old Ferry Landing” at 12100 Ferry Landing Road, Berlin, Maryland 21811. This location is approximately 2 miles away from “South Beach Parking Lot” location

3.1.6. Follow all scoped work as in base bid for this restroom, but this comfort station will be a single-style vault comfort station, and this restroom final grade will need to be (1) foot above current grade.

3.2. Project Specifications

Required (Not Limited To) Deliverables
Due
1
Written Designation of Superintendent and Alt Superintendent
With quote package
2
Designated Superintendent & Alt. Superintendent Resumes
With quote package
3
Active SAM Registration w/ UEI # Clearly Visible
With quote package
4
Contractor’s License Pertinent to Requirements
With quote package
5
Certificate of Insurance
With quote package
6
Material Submittal For Proposed Vault Style Restroom
With quote package
7
SF 1413 for all Subcontractors
10 Days After Award
8
Schedule of Values (SOV)
14 Days After Award
9
Site Specific Safety Plan
14 Days After Award
10
Construction Work Schedule in Gantt Chart Format
14 Days After Award & Every 14 Days
11
Daily Work Logs
Weekly
12
Certified Payroll on WH-347 w/Updated Schedule and SOV
Weekly
13
Release of Claims DI-137
Closeout/With Final Invoice
14
Warranty Letter
Closeout/With Final Invoice

3.2.1. For Material Submittal of Pre-Cast Concrete ADA Compliant Waterless Vault Restroom during bidding, please clearly define how this unit fits the specification (this is a technical element). This could be through manufacturers’ information, manuals, brochures etc. If the NPS can’t determine through the materials submittals it could disqualify bid from further review.

3.2.2. Any excavation on site will be typical of a mid-Atlantic coastal island environment, which includes sand, compact sand and mud with little rock/hardened materials. The water table is sometimes inches below grade, and any excavation will fill in with water and soil materials almost as quickly as you can excavate material out. Please understand this when bidding.

3.2.3. The NPS understands there might be slight specification changes from the double style vault restrooms vs the single style vault restroom, such as the single style vault restroom might have (1) vault access manhole vs (2) but most of these specifications should be applicable for both units.

4. SAFETY

4.1. The contractor shall comply with all pertinent provisions of the Occupational Safety and Health Administration (OSHA) Standards, 29 CFR 1910 and provide all necessary supervision, safety protection devices, and certified personal protective equipment (ANSI etc.), required for complete and safe operations on site in accordance with OSHA guidelines. All OSHA requirements may be obtained without cost to the general public at www.osha.gov. NPS will request from contractor any pertinent safety communication, certifications or required trainings for any employee(s) engaged in work that require such. Protective measures shall prevent injury to the public, Federal employees, contractors, visitors, Contractor’s employees, and damage to or contamination of surrounding property and/or the environment.

4.2. All tools/machinery/equipment/vehicles shall be safeguarded from the public. Tools/machinery/equipment/vehicles shall not be left unattended. All tools/equipment shall not be allowed to lie around except in the immediate work area. Any tools not in immediate use shall be staged or stowed in such manner so as not to create a hazard. The government and contractor will agree on delineating the work area around the project.

4.3. The Contracting Officer (CO) or Project Manager may include additional safety measures or procedures if determined necessary or required by other Federal, State, or local law, or park policy.

4.4. Contractor shall provide a comprehensive site-specific safety plan for approval before any work begins. An onsite qualified Safety Representative shall be identified including contact information.

4.5. Traffic Control (If Applicable):

4.5.1. The contractor is responsible for placing warning signs to warn the public of any work area or closed areas. Whether this is through signs, cones, flagger, labels or danger signals, the public or employees need to be fully aware of the risk associated with the contractor’s work.

4.5.2. Maintain open traffic on Park roads outside of the work closure to the greatest extent possible. Temporary traffic delays shall be kept to the minimum and only as necessary. Limit traffic impacts to 10 minutes maximum for each delay period, unless otherwise authorized by the COR.

4.6. Staging and Access:

4.6.1. All work, parking of vehicles, equipment, materials, and all other operations in connection with this contract shall be confined to the specified hours and stagging/work areas designated and approved in writing by the CO and/or COR.

4.6.2. Temporary stagging and storage locations shall be coordinated with the COR 14 calendar days in advance of work

4.6.3. No overnight parking in the park is authorized unless prior approval is requested and received in writing from the COR--NO EXCEPTIONS. Violators will be towed at the Contractor’s expense.

4.6.4. Confine on-site material and equipment for storage and laydown equipment in staging or storage areas or other areas specifically designated by the COR.

5. ENVIROMENTAL

5.1. The Contractor shall comply with Executive Order 13834, pertaining to Sustainability, work shall incorporate the following:

5.1.1. Reduce waste and implement recycling programs for construction and demolition materials whenever possible.

5.2. The Contractor shall comply with all Federal, State and Local government regulations pertaining to waste disposal, recycling and hazardous material use, storage, and disposal.

5.2.1. Materials and chemicals shall be stored, used, and disposed of in such a manner as to not endanger or threaten the environment and the health and safety of Park employees and visitors.

5.3. The Contractor shall have a Hazard Communication Program in place as required by 29 CFR 1910.1200 where Safety Data Sheets (SDS) / Technical Data Sheets shall be obtained by the contractor for all hazardous materials to be used in the performance of this contract. This plan shall be furnished to the NPS prior to the start of work. These SDS’s and an inventory of hazardous materials must be provided to the CO or COR prior to bringing the material on site. SDS shall be maintained at any jobsite where a substance requiring a SDS is being used. It shall also be available in any vehicle carrying such substance while in the Park. These SDS will be available to all employees of the Contractor, employees of the Park, concessionaires and the public when any member of these groups might come in contact with, or be exposed to, any substance requiring a SDS due to its hazardous status.

5.4. Any waste must be re-claimed/captured for recycling by the contractor. Waste and/or recycling landfill tickets shall be submitted prior to final invoice.

5.5. The park has both natural and man-made protected resources. It is the Contractor’s sole responsibility to ensure they are always protected during this project.

5.5.1. The Contractor is responsible for confirming with NPS Staff regarding the identification of these assets prior to the start of work or at any time any questionable or unforeseen items arises. Work shall stop until clarification by the NPS is made.

5.6. Work prescribed in the scope, stated or not, might require work in dangerous conditions including extreme temperatures and environmental conditions, tight or uneven spaces, exposed to chemicals/fumes.

5.7. Erosion, Waste and Sediment Control (If Applicable):

5.7.1. The Contractor is responsible for the design, installation, maintenance and removal of all erosion, waste, and sediment control devices in accordance with all local, state, and federal regulations having jurisdiction, as required for the project.

5.7.2. Prior to project start, submit proposed erosion, waste and sediment control plan for approval by the COR/CO/CS.

5.7.3. Install sediment/refuse barriers and other measures intended to trap sediment or refuse before land disturbance takes place.

5.7.4. Maintain all erosion and sediment control devices to assure continued performance of their intended function. Replace damaged and deteriorated control devices as needed.

5.7.5. During construction, stabilize or protect soil stockpiles, on-site borrow areas, and soil transporting with sediment trapping measures.

5.7.6. When approved by the COR, remove all temporary waste, erosion and sediment control measures within 30 days after final site stabilization or after the temporary measures are no longer needed.

6. CONTRACTORS RESPONSIBLITIES AND REQUIREMENTS

6.1. A written designation of a supervisor(s) and an alternate supervisor(s) with the same qualifications as the proposed supervisor will need to be submitted (see required submittals): The supervisor and/or alternate supervisor is required to be always present on-site during all operations to direct contract personnel and maintain operations. The on-site supervisor MUST:

6.1.1. Be fluent in the English language in order to effectively communicate with the contractor’s employees and/or subcontractors as well as the COR and other Government personnel.

6.1.2. Be available for phone calls during all working hours, and have the authority to stop all work for unsatisfactory performance as directed by the COR.

6.1.3. Possess 5-years verifiable experience and technical competence in work prescribed in 3.1 (Requirements) as well as 2-years supervisory experience, submitted as a resume.

6.1.4. Be responsible for controlling the quality of work and inspecting all completed work to ensure that correct performance requirements are met.

6.2. Communications:

6.2.1. The contractor and the government should always strive to keep open communications about the project. The government will expect the contractor to respond in a timely manner to any communications (e-mail, phone calls, text messages etc.), even if it is just an acknowledgment response.

6.2.2. Timely manner is being defined as within 72 hours of any type of communication during hours of operation (see section 8)

6.2.3. If the main point of contact (POC) is unavailable (vacation, sick, field work etc.) they need to delegate authority to an alternate POC. There needs to always be a point of contact available in a timely manner during the entirety of the project whether site work is being conducted or not. For planned events where the main POC is unavailable, they need to notify the government within 48 hours of when an event will occur, and an updated delegation of authority.

6.3. The requirements set forth are intended to provide general guidelines for the services that shall be provided by the Contractor. The contractor needs to use their knowledge to understand the project scope and nuisances of work even if not stated in scope. All work performed by the contractor shall be performed in accordance with manufacturers specifications, guidelines and recommendations, industry standards, and commercial practices.

6.4. Provide sufficient trained, certified (up to date pertinent certifications), and experienced manpower and equipment to complete the project within the period of performance. The total daily productive man hour requirements and quantity of personnel necessary to performance of all services specified herein is the sole responsibility of the contractor and shall be quoted accordingly. Davis Bacon Wages shall be utilized.

6.5. Quality workmanship is required at the full performance level of specified work, beginning at the contract start date. The contractor shall be responsible for professional quality, technical accuracy, project coordination, equipment installation, training, disposal of existing equipment, and all other ancillary items required and provide all deliverables that meets the requirements of the NPS.

6.6. Contractor shall take into consideration the existing ancillary equipment, building support systems, and environment, as well as the potential presence of unknown structures, utilities, and ancillary infrastructure to provide a proposal that meets the project objectives.

6.7. Submittals:

6.7.1. The contractor shall maintain a daily work log by filling out completely with pictures, as applicable. The Daily Work Log Form will be provided to them by the Government. The daily work log or approved equivalent shall be submitted to the COR, courtesy copying the CS/CO via email after a week of work and or any time requested by the COR, CS/CO.

6.7.2. The contractor shall also note in the daily work log the presence of any damage or conditions that may affect the contractor ability to perform work. The contractor shall note and report to the COR any issues or problems that arise, which are within the statement of work.

6.8. Provide Submittals and implement them after approved by the CO/COR. A CM 16 Submittal Form shall be used as a cover sheet for every submittal and will be provided by the Government to the contractor at award. Multiple submittals may be listed on a single CM 16 submittal form.

6.9. Contractor will be required submit all pertinent manufacturer’s data for all equipment, components, and materials BEFORE install occurs. Pertinent data could include installation, operations and maintenance manuals, product data and warranty information. All data shall be annotated to show the specific material identification information, catalog number, type, color, and size of each item.

6.10. All work performed for the performance of this contract must carry a minimum one-year warranty from the date of final inspection.

6.11. Submit a construction schedule no later than 14-days after project award and update it as the project progresses to reflect the most current timeline (two-week look ahead). Include a revised Construction Work Schedule in all pencil copies and attached to all payment applications. Invoices shall be rejected if this document is not attached.

6.12. Contractor Employee Conduct:

6.12.1. The Contractor’s employees shall conduct themselves in a professional, orderly, and safe manner will on the job site. A contractor’s employee shall be subject to removal from the premises upon determination by the Contracting Officer that such action is in the best interests of the Government. Such removal from the job site or dismissal from the premises shall not relieve the Contractor of the requirement to provide sufficient personnel to perform the service as specified.

6.12.2. Rudeness, fighting, being under the influence of alcohol and/or drugs or bringing and/or consuming alcohol and/or drugs, gambling, soliciting, stealing, and any immoral or otherwise undesirable conduct shall not be permitted on the job site. Any employee engaging in such conduct shall be immediately removed from the job site.

6.12.3. Music being played/listened to at the job site shall be kept to a minimum and at the discretion of the COR to determine if it is appropriate for the work site.

6.13. Photographs, social media posts, online content, or any form of communication is strictly prohibited regarding all aspects of this requirement unless authorized in writing by the COR.

6.14. In instances where the contractor finds pre-existing conditions or damage to park resources that may reflect upon the quality of the work or cause undue liability, the contractor shall not start work until the contractor and COR have agreed on the responsibility for these pre-existing conditions.

7. GOVERNMENT PROVIDED INFORMATION

7.1. Forms:

7.1.1. CM-16 Submittal Form

7.1.2. Daily Work Log

7.2. Links to Pertinent Information Related to This Work:

Management - Assateague Island National Seashore (U.S. National Park Service) (nps.gov)

MUTCD

OSHA

Code of Federal Regulations (CFR)

ANSI

Federal, State and Local Environmental Laws, Regulations, and Policies

7.3. Attachments:

1
General Map of Locations

8. HOURS OF OPERATION

8.1. Construction operations shall be conducted between the hours of 7:00 am –3:30 pm ET, Monday – Friday, except when there’s a federal government holidays (Federal Holidays), local or national emergencies, administrative closings, or similar Government directed facility closings.

8.2. The contractor will be notified by the COR (7) business days in advance, if possible, for days there shall be no work conducted outside of regularly scheduled federal holidays.

8.3. All work outside of the designated performance hours are required to be requested three (3) business days in advance, in written form, by the Contractor to the Contracting Officer’s Representative (COR) for approval.

8.4. Access to the work site may be limited at times due to unforeseen weather and/or tidal events. The government will not be liable for any burdens associated with unforeseen circumstances.

9. ADDITIONAL APPLICABLE REGULATIONS AND POLICIES

9.1. All supplies, materials, equipment, processes, and tools are subject to the submittal process and approval by the COR/CO/CS. Supplies, materials, tools, processes, and equipment that doesn’t meet the project requirements set forth in this contract could be rejected. Contractor shall take this into consideration during the bidding process.

9.2. Only changes as approved in writing by the CO shall be deemed authorized. Any other form of changes performed under this contract that are unauthorized shall be the burden of the Contractor and shall be at no cost to the Government.

9.3. Damages and liability for any loss (tangible or intangible) during the performance of this contract caused by the contractors’ operations:

9.3.1. The contractor shall assume full responsibility for any and all damages or claims for damage resulting from injury to persons, property, or equipment, which might result from any work performed under this contract.

9.3.2. All damage resulting from such operations shall be repaired to its original condition to the satisfaction of the COR at no additional cost to the Government.

9.3.3. The contractor shall take all immediate actions necessary to prevent further damage.

9.3.4. All losses and/or damages shall be reported to the COR, within two (2) hours of any loss and/or damage being determined and before leaving the area loss occurred. Contractor shall provide a detailed written documentation of the loss and/or damage to the CO and COR within 24 hours of occurrence.

9.3.5. The contractor is responsible for all costs associated with reported damages and/or losses to persons, property or environment that occur because of the contractor’s negligence.

9.3.6. Liquidated damages, per FAR 11.5 – Liquidated Damages, may or may not apply to this contract, please refer to contracting documents for more information.

END OF STATEMENT OF WORK