The document provided is the Technical Information Form (Attachment 4) for a Request for Quotation (RFQ) for the design and installation of a fire suppression system for buildings 16 and 17 at Lassen Volcanic National Park. The RFQ number is 140P8424Q0035, and the North American Industry Classification System (NAICS) code is 238220 with a size standard of $19 million in annual gross receipts. This acquisition is a Total Small Business Set-Aside.
The key details include: the contractor's information, whether the contractor plans to self-perform the work or use a subcontractor, a list of relevant experience and past performance references, and a technical approach narrative. The government anticipates awarding a firm-fixed-price purchase order resulting from this solicitation, with evaluation to be conducted in accordance with the simplified acquisition procedures outlined in FAR Part 13.106. A site visit is scheduled for April 3, 2024, and the quotation due date is specified in the SF 1442.
View the file
Other files for this federal contract opportunity
| File | Type | Posted |
|---|---|---|
| A04_Project_Specifications_LAVO_Fire_Suppression_REVISED_0001.pdf | ||
| Sol_140P8424Q0035_Amd_0001.pdf | ||
| Sol_140P8424Q0035.pdf | ||
| A06_Drawings_LAVO_Fire_Suppression.pdf | ||
| A04_Project_Specifications_LAVO_Fire_Suppression.pdf | ||
| B03_Wage_Determination_LAVO_Fire_Suppression.pdf |
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
TECHNICAL INFORMATION FORM
(Attachment 4)
Fire Suppression System
Lassen Volcanic National Park
RFQ No.: 140P8424Q0035
Quoters shall submit the following information:
Quoters Business Name: ___________________________________
Quoters Address: ___________________________________
Quoters UEI: ___________________________________
Quoters Phone: ___________________________________
Quoters Contact Name: ___________________________________
Quoters Signature: ___________________________________
CONTRACTOR’S PROPOSED TEAM:
Do you plan to self-perform all of the work? ___________________________
YES or NO answer
Are you proposing to use a subcontractor? ___________________________ YES or NO answer
List any proposed subcontractor(s) and indicate what key trade they may be assigned to perform:
Subcontractor Name Key Trade (Roofing, etc.)
If you are proposing to use a subcontractor, describe what work activities you plan to self-perform:
RFQ No. 140P8424Q0035, Attachment 4, Technical Information Form
LIST OF RELEVANT EXPERIENCE (LIST OF PROJECTS) & PAST PERFORMANCE REFERENCES:
1) Project Title: ___________________________ Contract # (if known): ______________
Agency/Owner: ___________________________ $ Amount: _______________________
Performance Period: ___________________________
Briefly describe how this project is similar in nature and scope to current advertised requirement:
Past Performance Reference (Name & Title): _______________________________________________
Phone Number: ___________________________ Email: __________________________
2) Project Title: ___________________________ Contract # (if known): ______________
Performance Period: ___________________________
Briefly describe how this project is similar in nature and scope to current advertised requirement:
3) Project Title: ___________________________ Contract # (if known): ______________
Performance Period: ___________________________
Briefly describe how this project is similar in nature and scope to current advertised requirement:
RFQ No. 140P8424Q0035, Attachment 4, Technical Information Form
TECHNICAL APPROACH: Technical approach is your means and methods to complete the technical aspects of the required work in this solicitation. Submit a brief written narrative limited to 1 page describing your technical approach to successfully accomplish this project, to be evaluated as described in Section M.1.