This document is a project specification for the replacement of the backup generator at the Jewel Cave National Monument Visitor Center in Custer, South Dakota. The current 125 kW diesel generator has failed multiple times and needs to be replaced with a new 125 kW propane-powered generator and automatic transfer switch. The work includes removing the existing generator, fuel tank, and associated equipment, and installing the new generator, propane line, and electrical connections. The project must be completed within 320 calendar days of the Notice to Proceed, and the generator must be offline for no more than 7 days to minimize disruption to the facility's operations. Key requirements include providing shop drawings, product data, and samples; following National Park Service safety and environmental requirements; and providing a comprehensive testing and commissioning plan to ensure the new generator works reliably.
View the file
Other files for this federal contract opportunity
| File | Type | Posted |
|---|---|---|
| B09_Solicitation_AMD_P6324Q0031_Generator_Install_QA_0001.pdf | ||
| Sol_140P6324Q0031_Amd_0001.pdf | ||
| B08_Solicitation_Atch_2_Experience_Questionnaire.xls | XLS spreadsheet | |
| B08_Solicitation_Atch_3_DOL_Wage_Determination_SD20240025.pdf | ||
| Sol_140P6324Q0031.pdf |
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Div. 1 V. 2023-11-11 Page | 1
Jewel Cave National Monument Custer, SD 57730
Visitor Center Generator Replacement
PMIS337138
PROJECT SPECIFICATIONS
NATIONAL PARK SERVICE
03/27/2024
Page | 2
TABLE OF CONTENTS
DIVISION 01 - GENERAL REQUIREMENTS
Section 01 10 00 - Division 01 Short Form General Requirements
DIVISION 03 – CONCRETE
Section 03 13 13 – Concrete
DIVISION 23 – HEATING, VENTILATING AND AIR CONDITIONING
Section 23 11 26 Facility Liquefied-Petroleum Gas Piping/Tanks
DIVISION 26 – ELECTRICAL
Section 26 05 00 – Electrical: Basic Requirements Section 26 05 19 – Low-Voltage Electrical Power Conductors and Cables Section 26 05 26 – Grounding and Bonding for Electrical Systems Section 26 32 13.16 – Gaseous Emergency Engine Generators Section 26 36 00 – Transfer Switches
DIVISION 31 – EARTHWORK
Section 31 21 33 – Trenching, Backfilling, and Compaction for Utilities
LIST OF SUBMITTALS
AREA OF SITE-SPECIFIC MAPS
CONSTRUCTION DRAWINGS AND PHOTOGRAPHS
Page | 3
DIVISION 1 SHORT FORM GENERAL REQUIREMENTS
PART 1 – GENERAL
ITEM 1 - DESCRIPTION OF WORK
1.1 Background: The current Onan 125 kw emergency generator is over 20 years old and has failed on multiple occasions. This backup generator is the sole source of power for our cave elevators when the power routinely is interrupted. (see photographs at end of document for current system) JECA provides guided tours to over 120,000 visitors a year. The tour route starts nearly
300’ below the surface. At any given moment during operating hours there could be over 50 individuals in the elevators and over 150 people in the cave. When the electrical service is interrupted, the backup generator automatically engages and ensures that visitors will not be entrapped 300’ below the surface or in the elevator shaft. The replacement of the outdated diesel-powered generator and transfer switch with a new propane powered generator and automatic transfer switch of equal capacity will ensure safe and reliable operation for years to come.
1.2 Work Covered by the Contract Documents:
A. Project Location: Jewel Cave National Monument 11149 US Hwy 16 Custer SD 57730
B. Work consists of: Replacing the Onan 125 DGEA, Specification 53643F genset with an equal
125 kw propane fueled generator, automatic transfer switch and load bank. A possible replacement generator that meets these requirements is an Onan Cummins Model: C125N6 propane generator 60 Hz with Load bank Model:OSM1-0100.1-208V33-0600-(4) and automatic transfer switch PowerCommand OTEC transfer switch 40A-1200 A or equal. (See photographs of current specifications at end of the document). All bidders will be required to ensure that the new genset has an equal load bank, specified with automatic battery tending, oil heater and weather Protected Sound Attenuated Enclosure Level 2.
C. To ensure safe operation of the Visitor Center and Elevators during the project the generator will be offline for no more than 7 days. The contractor will coordinate this outage with the COR at least 30 days prior to the outage so tours may be adjusted. The work includes completing all electrical connections to NEC code. The contractor may reuse the existing conduit and wiring if they meet the new generator needs. If not, the contractor will install all necessary conduits and wiring according to NEC code. Propane line installation shall include, but not limited to a buried propane main connection, riser, fully connected and appropriately sized regulator to supply service to the Generator. The generator line connection will not be serviced by the Visitor
Center regulator or riser. The current 2” poly propane line is buried approximately 2’ deep and approximately 10’ from the desired location of the new generator. The contractor is responsible for verifying that the replacement generator and transfer switch will provide the same or more power to the Elevator Operation and the Visitor Center.
D. The current generator, 250-gallon fuel tank, its associated concrete pad, fuel, fuel lines, electrical lines, and bollards will be removed from the premises. All disconnected electrical lines will be properly terminated to NEC specifications. The disturbed areas will be compacted to the surrounding soil strength, graveled with approved by COR ¾ minus road base and compacted.
Disturbed vegetation will be reseeded where necessary with approved seed mixture. The
Page | 4 installation of the new 125Kw generator that has the same capabilities as the old genset will be installed in the same approximate location as the old generator. The onsite work may not take place from May 1 through September 15 due to park requirements. (see photographs at end of document for current system).
E. All work will be performed under a single contract.
F. Period of performance: Work shall be completed within 320 calendar days of the start date provided on the Notice to Proceed.
a. Clarification: The Notice to Proceed will be issued with a period of performance that is all inclusive of supply lead times, material deliveries, decommissioning, installation, anticipated average weather days for location, final commissioning, and acceptance of completed work. The contractor will be expected to provide a project schedule with adequate critical path details to ensure all work is completed within the stated calendar days from issuance of the Notice to Proceed. If weather impacts project beyond typical average weather patterns, contractor shall provide documentation in request for additional days.
ITEM 2 – PROTECTING EXISTING UTILITIES
2.1 Protecting Existing Utilities: Notify Contracting Officer (CO), Contracting Officer’s Representative
(COR) and utility companies as required to request location services prior to and to coordinate any excavation/digging operations, and/or for demolition if within Scope of Work.
2.2 Contractor shall be responsible for locating and preventing damage to known utilities on site or indoors. If contractor damage occurs, alert CO and COR as soon as safely possible, and repair utility at no additional expense to the Government. If damage occurs to an unknown utility, contact CO and COR as soon as safely possible.
2.3 Existing Utility Interruptions: Do not interrupt utilities serving facilities occupied by Government or others unless permitted under the following conditions and then only after arranging to provide temporary utility services according to requirements indicated below:
A. Notify CO and COR not less than two business days in advance of proposed utility interruptions.
B. Hours for Utility Shutdowns: Shutdowns shall not exceed 2 to 3 hours. Temporary provisions will be needed by the Contractor for periods longer than stated allowance or if required for critical systems as determined by COR.
ITEM 3 - CONTRACTOR’S USE OF PREMISES
3.1 Conduct of Operations: At all times the contractor shall conduct his operations in conformance with the rules and regulations promulgated by the Secretary of the Interior for the National Park
Service, and applicable park rules and regulations prescribed by the Park Superintendent.
https://www.nps.gov/jeca/learn/management/superintendent-s-compendium.htm
A. Communications: Contractor shall provide the Contracting Officer and COR with methods of communications including land and/or cell phone numbers (note some areas of work have https://www.nps.gov/jeca/learn/management/superintendent-s-compendium.htm
Page | 5 limited service coverage), email and in case of emergency 24-hour contact options for duration of time operations.
B. No signs or advertisements (except those specified herein and as required for safety) shall be displayed on the construction site or within the park unless approved by the Contracting
Officer.
C. Smoking is not permitted within any Federal building or within 25 feet of entrances, operable windows, or outdoor air intakes.
D. Public Use of Site: Contractor shall at all times conduct operations to ensure the least inconvenience to the public.
3.2 On-site work hours: Work shall be generally performed during normal business working hours of
7 A.M. to 4:30P.m., Monday through Friday, except when otherwise indicated.
A. Work on Saturdays, Sundays, Federal holidays, early morning, or at night may not be performed without prior consent from the CO and COR. Submit requests for work outside of the stated normal business hours to the CO and COR for approval at least 48 hours in advance of the work.
The following Federal holidays are observed by the National Park Service:
New Year Day
Martin Luther King, Jr’s Birthday
Washington’s Birthday
Memorial Day
Juneteenth National Independence Day
Independence Day
Labor Day
Columbus Day
Veterans Day
Thanksgiving Day
Christmas Day
B. Note: Any of the above holidays falling on a Saturday will be observed on the preceding
Friday; holidays falling on Sunday will be observed on the following Monday. The specific day that each holiday is recognized for each year can be found at the following site: Federal
Holidays (opm.gov).
3.3 Contractor Use of Site:
A. General: Contractor shall have limited use of the site for construction operations. Limit use of premises to construction area as shown on site plan that is provided at the end of the document. Do not disturb portions of Project site beyond areas in which the Work is indicated.
B. Driveways and Entrances: Keep driveways, access roads, and entrances serving premises clear and available to Government, Government's employees, and emergency vehicles at all https://www.opm.gov/policy-data-oversight/pay-leave/federal-holidays/#url%3D2022 https://www.opm.gov/policy-data-oversight/pay-leave/federal-holidays/#url%3D2022
Page | 6 times. Do not use these areas for parking or storage of materials. Schedule deliveries to minimize use of driveways and entrances.
C. Do Not disturb site outside of noted disturbance area, including earthwork and clearing of vegetation, to: remain within the approximate area of work/staging provided on site plan at end of the document
D. Utilities
1. General: Cost or use charges for temporary facilities shall be included in the Contract Sum as required.
2. Water Service: Water from existing water system is available for use without metering and without payment of use charges. Provide connections and extensions of services as required for construction operations without any additional permit costs. Use resources wisely and minimize waste of water.
3. Electric Power Service: Electric power from existing system is available for use without metering and without payment of use charges. Provide connections and extensions of services as required for construction operations without any additional permit costs. Power may or may not meet your construction power tool requirements, provide generators if questionable. Use power in a resourceful manner and avoid excess power waste.
4. Waste Operation:
a. Toilets: Contractor must provide toilets for contractor personnel, sufficiently lighted and ventilated toilet facilities in weatherproof, sight proof, handicap accessible (if required), sturdy enclosures with privacy locks. Coordinate with COR for approved location if not shown on attached site plan.
b. Waste Removal / Recycling: Contractor is responsible for removing all waste created by the project. Contractor shall recycle to the highest degree possible and empty dumpsters as necessary to avoid debris on site. Locate as shown on site plan or coordinated with COR.
E. Security and Protection facilities:
1. Environmental Protection: Provide protection, operate temporary facilities, and conduct construction in ways and by methods that comply with state and federal environmental regulations and that minimize possible air, waterway, and subsoil contamination or pollution or other undesirable effects.
2. Cleaning of Equipment: The Contractor shall ensure that prior to moving on to the Project
Area, all equipment, is free of soil, seeds, vegetative matter, or other debris that could contain or hold seeds. Ensure that all equipment has been pressure washed and is free of exotic species prior to start-up of operations and moving of equipment to Project Area.
Equipment shall be considered free of soil, seeds, and other debris when a visual inspection does not disclose such material. Disassembly of equipment components or specialized inspection tools are not required.
3. Tree and Plant Protection: Provide Tree Protection fence at drip line of trees impacted in construction area. Coordinate with COR. Restore damaged areas to original condition, Page | 7 repairing or replacing damaged trees and plants, at no additional expense to the Government.
a. Provide temporary barriers to protect existing trees and plants and root zones.
b. Do not remove, injure, or destroy trees or other plants without prior approval. Consult with Contracting Officer Representative and remove agreed-on roots and branches that interfere with construction.
c. Do not fasten ropes, cables, or guys to trees.
d. Carefully supervise excavating, grading, filling, and other construction operations near trees to prevent damage.
4. Pest Control: Follow best practices to minimize attraction and harboring of rodents, roaches, and other pests and to perform extermination and control procedures at regular intervals so Project will be free of pests and their residues at project completion. Perform control operations lawfully, using environmentally safe materials.
5. Temporary Enclosures: Provide temporary enclosures such as snow fence as required for protection of construction in progress and completed, from access by visitors or staff, other construction operations, and similar activities.
6. Site Enclosure Fence: N/A
7. Hot Work Permit: Submit HW-1 Hot work permit form and receive approval from COR prior to Hot work activities commencing on site.
3.4 Storage - Staging Areas:
A. Confine Storage of materials and equipment to the project staging area noted on the plans/aerial. Specific storage units shall be provided by the contractor and exact location within staging area may be discussed at the preconstruction briefing. All storage units provided by the contractor shall be in a clean and acceptable condition to the COR. Security of the materials and equipment on site is the Contractor’s responsibility. See site plan (A) at end of the document.
3.5 Preservation of Natural Features: N/A.
3.6 Hauling Restrictions: Contractor shall verify and be responsible for the path accessing the site and obtaining / maintaining all local, state and federal permits/licenses associated with hauling/road requirements and dumping of materials associated with the project.
3.7 Housekeeping:
A. Keep project neat, orderly, and in a safe condition at all times.
1. Dispose of waste materials and recycling legally outside the park. The contractor shall not use park dumpsters
2. Address Recycling: Government goal is to salvage and recycle as much nonhazardous construction waste as possible. Use sustainable methods to extent possible during this project, recycling material as is probable with local means. Maintain accurate documentary records for submittal of all recycled materials used including fly ash and slag cement.
Page | 8
3.8 Occupancy Requirements for Buildings:
A. Existing Buildings:
1. Full Government Occupancy: Government will occupy buildings that will be under construction during the entire contract period. Cooperate with Government during construction operations to minimize conflicts and facilitate Government usage. Perform the Work so as not to interfere with Government's day-to-day operations. Maintain existing exits, unless otherwise indicated.
a. Maintain access to existing walkways, corridors, and other adjacent occupied or used facilities. Do not close or obstruct walkways, corridors, or other occupied or used facilities without written permission from the CO or COR.
b. Maintain existing building in a weather tight condition throughout construction period. Repair damage caused by construction operations. Protect building and its occupants during construction period.
B. New /Existing Buildings Unoccupied: N/A
3.9 Photo Documentation:
A. Contractor must provide existing condition, progress, and completion photos. All photos shall be in focus, show maximum range of depth of field general photo and then close up detail photo as needed. Shall be in JPEG digital form and submitted preferably electronically by email or optional via CD-R Archival Gold or DVD-R Archival Gold media with printed labels and 8 mega pixels minimum within 7 days from time of taken or as approved by COR.
B. Existing Condition Images:
1. Before starting construction, take color, dated, digital images of project site and adjacent property/roads/etc. that may be impacted by construction activity/traffic. Include existing items to remain or be salvaged from different vantage points and with context for location identification.
C. Construction Progress Images:
1. Document all sub-surface work/ trenches etc. prior to backfill with photos covering enough overall field view to show location and then zoom in for details. (Locations and dimensions shall also be noted on as built drawing set.)
2. Maintain organized index for photos with date, description, etc.
3. Additional images as needed when questions or emergency situations occur. Submit within 24 hours.
D. Completion Images:
1. Document all completed work within scope of work.
2. Maintain organized index for photos with date, description, etc..
Page | 9
3. Additional images as needed when questions or emergency situations occur. Submit within 24 hours.
3.10 Fire and Life Safety:
A. As a minimum, conduct one weekly 15 minute "toolbox" safety meetings. These meetings shall be conducted by a foreman or supervisor and attended by all construction personnel at the worksite. Topics need to coincide with work scheduled for the following week. Document and submit meeting minutes to the CO and COR within one day after the meeting and document the meetings on the daily reports.
B. Comply with the requirements of NFPA 241 (Standard for Safeguarding Construction, Alteration, and Demolition Operations). Take all necessary precautions to prevent fire during construction. Provide adequate ventilation during use of volatile or noxious substances.
C. Store and handle hazardous materials in accordance with manufacturers and OSHA
29CFR1926 Subpart D requirements 1926 | Occupational Safety and Health Administration (osha.gov). Maintain readily available, on site, MSDS/Safety Data Sheets (SDS) for each chemical.
1. Immediately report all spills of hazardous materials to the CO, COR, and park.
2. Maintain a spill emergency response kit.
3. Train employees how to respond to a spill and use the emergency response kit.
3.11 Noise and Acoustics Management
A. Contractor shall not have personal radios or other media sources and they shall not be broadcast within NPS property.
B. Noise Control: Perform operations to minimize noise. Perform noise-producing work in less sensitive hours of the day or week as directed by the Contracting Officer or COR.
C. Repetitive and/or intermittent, high-level noise: N/A
ITEM 4 - COMMENCEMENT, PROSECUTION, AND COMPLETION
4.1 The Contractor shall commence work in accordance with the terms and conditions of the contract.
Contractor shall coordinate and incorporate long lead and delivery time items within the schedule.
ITEM 5 - EXAMINATION OF THE SITE
5.1 All bidders are urged to visit the job site and examine existing conditions before submitting bids.
Contractors will be accountable for understanding existing conditions. No cost changes for items visible during site visit will be allowed.
ITEM 6 - ABBREVIATIONS
6.1 The list of abbreviations, standards and organizations which may be used in/referred within the
Construction Specifications or Special Provisions, may be found linked from the listed page below. On the home page, follow the link under “Contracting and Procurement” labeled “NPS
Reference Standards.” https://www.nps.gov/orgs/1671/do-business-with-us.htm https://www.osha.gov/laws-regs/regulations/standardnumber/1926 https://www.osha.gov/laws-regs/regulations/standardnumber/1926 https://www.nps.gov/orgs/1671/do-business-with-us.htm
Page | 10
ITEM 7 - ACCIDENT PREVENTION
7.1 Description: The work of this section consists of establishing and implementing an effective accident prevention program (APP) and providing a safe environment for all personnel and visitors.
7.2 Submittals:
A. Accident Prevention (Safety) Plan (APP): Submit a site-specific accident prevention (safety) plan. The Plan shall be written to comply with OSHA and project requirements (a generic plan is not acceptable) including but not limited to the following:
1. Name and qualifications of responsible supervisor to carry out the program.
2. First aid and rescue procedures.
3. Training, both initial and continuing.
4. Outline of each phase of the work, the hazards associated with each major phase, and the methods proposed to provide for property protection and safety of the public, National
Park Service personnel, and Contractor's employees. Identify the work included under each phase, with a Job Hazard Analysis (JHA)/Job Safety Analysis (JSA), etc. A sample
JHA template may be provided upon request.
5. Planning for possible emergency situations.
6. Contractor to identify nearest location of medical facility for emergencies
7. Recognition that works will be performed in remote areas with limited communication or cell phone coverage if applicable.
8. Supplemental hazard specific plans may be required IAW 29 CFR 1926 or 1910.
B. Meeting and Inspection Reports: Safety Meetings: As a minimum, conduct 15 minute
"toolbox" safety meetings. These meetings shall be conducted by a foreman and attended by all construction personnel at the worksite. Submit a report of safety meetings and inspections to CO and COR within one day after the meeting and document the meetings on the daily reports.
7.3 Qualification of Employees:
A. Ensure that employees are physically qualified to perform their assigned duties in a safe manner to include operators of vehicles and equipment. Provide operating instructions for all equipment.
B. Do not allow employees to work whose ability or alertness is impaired because of drugs, fatigue, illness, intoxication, or other conditions that may expose themselves or others to injury.
7.4 Accident Reporting: The Contractor shall report all accidents to the CO and COR as soon as safely possible and assist the CO and COR and other officials as required in the investigation of the accident.
7.5 First Aid Facilities: Provide access to facilities for the number of employees and appropriate to the hazards associated with the types of ongoing construction work at the site.
Page | 11
7.6 Emergency Instructions: Post telephone numbers and reporting instructions for ambulance, physician, hospital, fire department, and police in conspicuous locations at the work site.
7.7 Personal Protective Equipment (PPE): It is the Contractor's responsibility to require all those working on or visiting the site to wear necessary protective equipment at all times.
A. PPE must meet requirements of applicable ANSI standards. Selection shall conform to OSHA
29CFR 1926 Subpart E.
B. A hard hat use area shall be designated by the Contractor. The hard hat area shall be posted by the Contractor in a manner satisfactory to the Contracting Officer.
C. All PPE will be always serviceable. At a minimum, maintain 2 extra sets of PPE including hard hats and all other Accident Prevention Plan required equipment.
7.8 Hazardous Materials: It shall be the responsibility of all operators and contractors, functioning within the park to properly cleanup, mitigate and remediate if necessary, all unauthorized discharges of hazardous materials or non-hazardous chemical and biological products released from fleet and/or other support vehicles or stationary sources. Response shall be consistent with guidelines established by federal, state, and local regulations, and as outlined within the operator's Safety or Hazardous Materials Business Plan.
A. If a spill, leak, or other release occurs, the operator shall as soon as possible, without impeding cleanup, notify the local 911 Emergency Response, COR and or the National Park
Service Emergency Dispatch.
ITEM 8 - PRECONSTRUCTION CONFERENCE
8.1 If the Contracting Officer decides to conduct a preconstruction conference, the successful offeror will be notified and will be required to attend. The Contracting Officer’s notification will include specific details regarding the date, time, and location of the conference, any need for attendance by subcontractors, and information regarding the items to be discussed. See Item 9.1C below.
ITEM 9 - SUBMITTALS
9.1 General Contracting Submittal Procedures:
A. General: Prepare and submit submittals required by individual Technical Specification
Sections. Types of submittals are indicated in individual specific sections.
1. CM-16 Transmittal Form: All submittals shall be transmitted via electronic email using
National Park Service form CM-16 form. The form will be provided by the Contracting
Officer. No action will be taken on a submittal item unless accompanied by the CM-16 transmittal form. Submit completed CM-16 forms to the CO and the COR
B. Submittal List: administrative required submittals are listed below in 9.1.C and does not include technical section submittal requirements included in each technical section.
Page | 12
C. Preconstruction Conference Submittal: Satisfactory evidence of liability insurance coverage and workman’s compensation, and any applicable bonds, must be submitted within 10 calendar days of Notice of Award. The following items are to be submitted prior to the
Preconstruction Conference or as specified at the CO’s discretion. The timeline for the documents to be submitted will be addressed at the pre-construction conference for those items that were not received and approved prior. Notice to Proceed may not be issued, and the Contracting Officer will consider other contractual remedies if not resolved as directed.
Work shall not commence until written Notice to Proceed has been issued. Contracting
Officer will notify Contractor of tentative date for the Pre-Construction Conference:
1. Letter designating Project Superintendent.
2. Construction Schedule. (Must include shop drawings, procurement time including long lead time items, mobilization, trade work progression and completion at minimum.)
3. A comprehensive breakdown of the Schedule of Values.
4. Accident Prevention (Safety) Plan (see section 7 of this document).
5. A list of Subcontractors for this project.
6. Written statements from subcontractors certifying compliance with applicable labor standard clauses (SF1413).
7. Quality Control Plan.
8. Waste Management Plan.
9. Contractors Commissioning Plan. Contractor shall ensure installed Genset works correctly and reliably while COR is present.
9.2 Project Submittal Process (Shop Drawings, Product Data, and Samples): Contracting Officer will provide sample cover sheet and a list of required submittals is included in each technical specification or attached at the end of this document.
A. Shop Drawings: Indicate all coordinating materials and work impacting the installation coordination, connection details, anchorage requirements, hardware locations, and installation details and locations.
1. Submit Shop Drawings according to Part 9.1 of this section to include one digital file (.PDF or .TIF) and two full size hardcopy documents to COR.
B. Product Data: Provide component construction and specification data sheets, anchorage requirements and any other product specific data.
1. Submit Product Data according to Part 9.1 of this section to include one digital file (.PDF or .TIF) to COR.
C. Samples: Submit 2 color samples 4” x 6” minimum in size for all product color selections.
Paint samples shall be actual paint finish drawdown for all project colors.
1. Submit Samples CM-16 Transmittal Form according to Part 9.1 of this section to include one digital file (.PDF or .TIF) and physical samples of actual material to COR.
D. For submittals specified above, forward submittals to Contracting Officer and COR at least 15 days before need for approval (depends on length of project).
Page | 13
E. After approving submittals, Contracting Officer and/or COR will return one copy to the
Contractor. If submittals are not approved, Contracting Officer will return all copies to
Contractor with reasons for rejection. Resubmit, identifying changes. Any work done before approval shall be at Contractor's own risk.
9.3 Approved Equals: All brand names noted are subject to ‘or equal’ products. If an item in this solicitation is identified as “brand name or equal” or lists more than 1 manufacturer, the description of the proposed item must reflect the characteristics and level of quality that will satisfy the Government’s needs as demonstrated by the salient physical, functional, or performance characteristics that “equal” products must meet and/or exceed that as specified in the solicitation or relevant specification. Contractor shall incorporate and be responsible for all collateral costs due to the or equal proposed as required to provide a complete project.
A. For each item proposed as an “approved equal,” submit supporting data, including:
1. Drawings and samples as appropriate.
2. Comparison of the characteristics of the proposed item with that specified and with the salient characteristics provided.
3. Changes required in other elements of the work because of the substitution.
4. Name, address, and telephone number of vendor.
5. Manufacturer’s literature regarding installation, operation, and maintenance, including schematics for electrical and hydraulic systems, lubrication requirements, and parts lists.
Describe availability of maintenance service, and state source of replacement materials.
B. A request for approval constitutes a representation that General Contractor:
1. Has investigated and shall provide documentation in request showing that the proposed item is equal or superior in all respects to the salient characteristics specified.
2. Will meet or exceed warranties for the proposed item specified.
3. Has determined that the proposed item is compatible with interfacing items.
4. Will coordinate the installation of an approved item and make all changes required in other elements of the work because of the substitution.
5. Waives all claims for additional expenses that may be incurred as a result of the substitution.
C. Approved Equals will be evaluated and approved/disapproved during the submittal process.
9.4 Schedule of Values: Submit the Schedule of Values a minimum of one week prior to the
Preconstruction Conference for COR review. Schedule of Values shall include defined work line items with cost break downs including labor, material, and equipment for COR approval.
9.5 Progress Reporting: The initial Construction Schedule and Schedule of Values are required a minimum of one week prior to the Preconstruction Conference. After the Notice to Proceed is issued and after on-site work begins, progress will be documented via daily logs and by providing an updated Construction Schedule and Schedule of Values when requested, but minimally with each pay application. Submit digital copy electronically (PDF preferred) of all required documents.
Construction Schedules are normally in bar chart form and indicate estimated starting and completion dates for each part of the work. For a pay application to be reviewed and processed in
Page | 14 a timely manner, the following information must either be submitted prior to or accompany submission of the pay application:
A. Daily/weekly progress reports during construction as part of the administration process.
B. Updated Schedule of Values: Breakdown each lump-sum item into component work activities used in the schedule, for which progress payments may be requested. The Schedule of
Values will form the basis for payment. The work activities broken out within the schedule of values shall be integrated into and made a logical part of the construction baseline schedule submitted under this specification. The total costs for the component work activities shall equal the contract price for that lump-sum item. The Contracting Officer may request data to verify accuracy of dollar values. A sample Schedule of Values format may be provided upon request.
ITEM 10 – TEMPORARY SERVICES
10.1 It is the Contractor’s responsibility to provide temporary services, equipment, tools, and skilled labor as required for the chosen means and methods to perform the work in accomplishing this
Contract.
ITEM 11 - PROJECT CLOSEOUT
11.1 Description: The work of this section consists of final cleanup, closeout submittals, final inspection procedures working toward Final Acceptance.
11.2 Cleaning: Remove all tools, equipment, surplus materials, and rubbish. Move attic stock to location coordinated with COR. At time of final inspection, project shall be thoroughly clean and ready for intended use. Inspector holds the right to reschedule if project is not ready for inspection.
11.3 Completion and Final Inspection: Contractor shall submit written certification of project completion and request a final inspection to the Contracting Officer and COR. The Contracting
Officer or designee will make an inspection within 10 days of receipt of request or at a mutually agreeable time.
A. If the work is determined to be complete following the final inspection with minor comments, the COR will prepare and provide the Contractor a Punch List noting outstanding items to be addressed.
B. If the work is not determined to be complete following the final inspection, the Contracting
Officer will notify Contractor in writing, stating reasons. Contractor, after completing the work according to the Contract Documents, shall resubmit completion and request a new final inspection. Re-inspection costs may be charged against the Contractor in accordance with the Inspection of Construction contract clause.
C. Contractor shall complete the Punch List within 30 calendar days, or a time directed by the
CO.
D. Once Contractor completes all items of work on the Punch List and all contractually required items are accepted, Contracting Officer will issue Letter of Final Acceptance of Work and request the final pay application.
E. If the Contractor fails to complete the work within the time frame, the Contracting Officer may correct the work with an appropriate reduction in contract price or charge for re-inspection costs in accordance with the Inspection of Construction contract clause.
F. Disposition of any permits and warranties required by the specifications in this section.
11.4 Final Acceptance of the Work: After all punch list deficiencies have been corrected, a Letter of
Final Acceptance will be issued. A Release of Claims document must be executed and submitted to the Contracting Officer before final payment can occur.
11.5 Warranties
A. Construction Warranty shall be based on date of final acceptance of the work and remain in effect for one year.
B. Provide all manufacturer warranty information of products installed organized by Division. All contact information, extent of coverage and conditions shall be clearly noted as well as date of overall final acceptance.
C. Information shall include operation and maintenance manuals for each warranted product.
ITEM 12 - DEFINITION OF CONTRACT LINE ITEMS
12.1 Summary
A. The intent of this section is to explain, in general, what is and what is not included in a contract line item, and the limits or cut off points where one item ends and another begins.
B. If no contract line item exists for a portion of the work, include the costs in a related item.
12.2 List of Contract Line Items
A. Contract Line Item No.010 Replace Diesel Generator with Propane.
1. This item consists of removal of the existing 125 KW 3 Phase generator and replace it with a propane generator of the same size.
2. Payment will be made per the contract and percentage of completion level.
PART 2 – PRODUCTS (NOT USED)
PART 3 – EXCUTION (NOT USED)
END OF SECTION
SEED
A. Grass Seed: Fresh, clean, dry, new-crop seed complying with AOSA's "Rules for Testing Seeds" for purity and germination tolerances.
B. Seed Species:
1.
SITE RESTORATION
C. Renovate turf damaged by Contractor’s operations, such as storage of materials or equipment and movement of vehicles.
1. Reestablish turf where settlement or washouts occur or where minor regrading is required.
2. Install new planting soil as required.
D. Remove sod and vegetation from diseased or unsatisfactory turf areas; do not bury in soil.
E. Remove topsoil containing foreign materials, such as oil drippings, fuel spills, stones, gravel, and other construction materials resulting from Contractor's operations, and replace with new planting soil.
F. Mow, dethatch, core aerate, and rake existing turf.
G. Remove weeds before seeding. Where weeds are extensive, apply selective herbicides as required. Do not use pre-emergence herbicides.
H. Remove waste and foreign materials, including weeds, soil cores, grass, vegetation, and turf, and legally dispose of them off Owner's property.
I. Till stripped, bare, and compacted areas thoroughly to a soil depth of 6 inches.
J. Apply soil amendments and initial fertilizer required for establishing new turf and mix thoroughly into top 4 inches of existing soil. Install new planting soil to fill low spots and meet finish grades.
K. Sow seed with spreader or seeding machine. Do not broadcast or drop seed when wind velocity exceeds 5 mph.
1. Evenly distribute seed by sowing equal quantities in two directions at right angles to each other.
2. Do not use wet seed or seed that is moldy or otherwise damaged.
L. Sow seed at a total rate of 4.5 lb./1000 sq. ft. per park specific seed specifications or according to manufacturer’s recommendation.
M. Rake seed lightly into top 1/8 inch of soil, roll lightly, and water with fine spray.
N. Protect seeded areas by spreading straw mulch and crimping into soil with suitable mechanical equipment.
O. Water newly planted areas and keep moist until new turf is established.
SECTION 23 11 26 - FACILITY LIQUEFIED-PETROLEUM GAS PIPING
PART 2 - GENERAL
2.1 SUMMARY
A. Section Includes:
1. Pipes, tubes, and fittings.
2. Piping specialties.
3. Piping
4. Valves.
5. Pressure regulators.
6. Storage containers.
2.2 DEFINITIONS
A. LPG: Liquefied-petroleum gas.
2.3 PERFORMANCE REQUIREMENTS
A. Minimum Operating-Pressure Ratings:
1. For Piping Containing Only Vapor:
a. Piping and Valves: 125 psig (862 kPa) unless otherwise required.
2. For Piping Containing Liquid:
a. Piping between Shutoff Valves: 350 psig (2413 kPa) unless otherwise required.
b. Piping Other Than Above: 250 psig (1723 kPa) unless otherwise required.
c. Valves and Fittings: 250 psig (1723 kPa) unless otherwise required.
3. Minimum Operating Pressure of Service Meter: 5 psig (34.5 kPa) unless otherwise required
B. Delegated Design: Design restraints and anchors for LPG piping and equipment, including comprehensive engineering analysis by a qualified professional engineer, using performance requirements and design criteria indicated.
2.4 ACTION SUBMITTALS
Product data for each type of the following:
1. Piping
2. Valves.
3. Pressure regulators.
4. Storage containers.
2.5 CLOSEOUT SUBMITTALS
A. Operation and Maintenance Data: For LPG equipment and accessories to include in emergency, operation, and maintenance manuals.
2.6 QUALITY ASSURANCE
A. Electrical Components, Devices, and Accessories: Listed and labeled as defined in NFPA 70, by a qualified testing agency, and marked for intended location and application.
2.7 PROJECT CONDITIONS
A. Perform site survey, and mark, verify commercial and park existing utility locations. Contact utility-locating service for area where Project is located using South Dakota 811.
PART 3 - PRODUCTS
3.1 PIPES, TUBES, AND FITTINGS
A. Steel Pipe: ASTM A 53/A 53M, black steel, Schedules 40 and 80, Type E or S, Grade B.
B. Corrugated, Stainless-Steel Tubing Complying with ANSI/IAS LC 1//CSA 6.26, and Protective
C. Drawn-Temper Copper Tube: Comply with ASTM B 88, Type K (ASTM B 88M, Type A)
D. Annealed-Temper Copper Tube: Comply with ASTM B 88, Type K (ASTM B 88M, Type A)
E. Tin-Lined Copper Tube: ASTM B 280, seamless, annealed, with interior tin-plated lining.
F. PE Pipe: ASTM D 2513, SDR 11.
3.2 MANUAL GAS SHUTOFF VALVES
A. Metallic Valves, NPS 2 (DN 50) and Smaller for Liquid Service: Comply with ASME B16.33 and
UL 842.
B. PE Ball Valves: Comply with ASME B16.40.
3.3 PRESSURE REGULATORS
A. General Requirements:
1. Single stage and suitable for LPG.
2. Steel jacket and corrosion-resistant components.
3. Elevation compensator.
4. End Connections: Threaded for regulators NPS 2 (DN 50) and smaller; flanged for regulators
NPS 2-1/2 (DN 65) and larger.
B. Service Pressure Regulators: Comply with ANSI Z21.80.
C. Line Pressure Regulators: Comply with ANSI Z21.80.
3.4 LABELING AND IDENTIFYING
A. Detectable Warning Tape: Acid- and alkali-resistant PE film warning tape manufactured for marking and identifying underground utilities, a minimum of 6 inches (150 mm) wide and 4 mils (0.1 mm) thick, continuously inscribed with a description of utility, colored yellow.
PART 4 - EXECUTION
4.1 EXAMINATION
A. Examine roughing-in for LPG piping system to verify actual locations of piping connections before equipment installation.
B. Proceed with installation only after unsatisfactory conditions have been corrected.
4.2 OUTDOOR PIPING INSTALLATION
A. Comply with NFPA 58 and requirements for installation and purging of LPG piping.
B. Install underground, LPG piping buried at least 24 inches (900 mm) below finished grade. Comply with requirements in Section 312133 for excavating, trenching, and backfilling.
1. If LPG piping is installed less than 36 inches (914 mm) below finished grade, install it in containment conduit.
C. Install underground, PE, LPG piping according to ASTM D 2774.
D. Steel Piping with Protective Coating:
1. Apply joint cover kits to pipe after joining to cover, seal, and protect joints.
2. Repair damage to PE coating on pipe as recommended in writing by protective coating manufacturer.
3. Replace pipe having damaged PE coating with new pipe.
E. Install fittings for changes in direction and branch connections.
F. Joints for connection to inlets and outlets on vaporizers, air mixers, regulators, and valves may be flanged or threaded to match the equipment.
G. Install pressure gage downstream from each service regulator.
4.3 VALVE INSTALLATION
A. Install manual gas shutoff valve for each gas appliance ahead of corrugated stainless-steel tubing, aluminum, or copper connector.
B. Install regulators and overpressure protection devices with maintenance access space adequate for servicing and testing.
4.4 CONNECTIONS
A. Connect to propane line according to manufactures procedures and requirements.
B. Install LPG piping electrically continuous and bonded to gas appliance equipment grounding conductor of the circuit powering the appliance according to NFPA 70.
C. Sediment Traps: Install tee fitting with capped nipple in bottom to form drip, as close as practical to inlet of each appliance.
4.5 PAINTING
A. Paint exposed, exterior metal piping, valves, service regulators, service meters and meter bars, earthquake valves, and piping specialties, except components with factory-applied paint or protective coating.
1. Alkyd System: MPI EXT 5.1D.
a. Prime Coat: Alkyd anticorrosive metal primer.
b. Intermediate Coat: Exterior alkyd enamel matching topcoat.
c. Topcoat: Exterior alkyd enamel gloss.
d. Color: Sandstone
1) PMS: 4248C
2) HEX COLOR: D5C2A5
3) RGB: (213, 194, 165)
4) CMYK: (12, 18, 29, 0)
B. Paint exposed, exterior metal piping, except components with factory-applied paint or protective coating.
C. Damage and Touchup: Repair marred and damaged factory-applied finishes with materials and by procedures to match original factory finish.
4.6 FIELD QUALITY CONTROL
A. Perform tests and inspections.
B. Tests and Inspections:
1. Test, inspect, and purge LPG according to NFPA 58 and requirements of authorities having jurisdiction.
C. LPG piping will be considered defective if it does not pass tests and inspections.
D. Prepare test and inspection reports.
4.7 DEMONSTRATION
A. Engage a factory-authorized service representative to train Owner's maintenance personnel to adjust, operate, and maintain LPG equipment.
4.8 OUTDOOR PIPING SCHEDULE
A. Aboveground LPG liquid piping shall be one of the following:
1. NPS 2 (DN 50) and Smaller: Schedule 40 steel pipe, malleable-iron threaded fittings and threaded joints. Coat pipe and fittings with protective coating for steel piping.
2. NPS 2-1/2 (DN 65) and Larger: Schedule 40, steel pipe with wrought-steel fittings and welded joints, or mechanical couplings. Coat pipe and fittings with protective coating for steel piping.
3. Drawn-temper copper tube, Type L (Type B,) with wrought-copper fittings and brazed joints.
Coat pipe and fittings with protective coating for copper tubing.
4. Corrugated stainless-steel tubing with mechanical fittings having socket or threaded ends to match adjacent piping.
B. Underground LPG vapor piping shall be the following:
1. PE pipe and fittings joined by heat-fusion, or mechanical couplings; service-line risers with tracer wire terminated in an accessible location.
2. Drawn-temper copper tube, Type L (Type B) with wrought-copper fittings and brazed joints.
Coat pipe and fittings with protective coating for copper tubing.
4.9 ABOVEGROUND MANUAL GAS SHUTOFF VALVE SCHEDULE
A. Aboveground Liquid Piping:
1. Two-piece, regular-port, bronze ball valves with bronze trim.
B. Valves for pipe NPS 2 (DN 50) and smaller at tank regulator shall be one of the following:
1. One-piece, bronze ball valve with bronze trim.
2. Two-piece, regular-port, bronze ball valves with bronze trim.
3. Bronze plug valve.
C. Valves for pipe NPS 2-1/2 (DN 65) and larger at service meter shall be one of the following:
1. Two-piece, regular-port, bronze ball valves with bronze trim.
2. Bronze plug valve.
3. Cast-iron, nonlubricated plug valve.
D. Distribution piping valves for pipe NPS 2 (DN 50) and smaller shall be one of the following:
1. One-piece, bronze ball valve with bronze trim.
2. Two-piece, regular-port, bronze ball valves with bronze trim.
3. Bronze plug valve.
E. Distribution piping valves for pipe NPS 2-1/2 (DN 65) and larger shall be one of the following:
1. Two-piece, regular-port, bronze ball valves with bronze trim.
2. Bronze plug valve.
3. Cast-iron, nonlubricated plug valve.
F. Valves in branch piping for single appliance shall be one of the following:
1. One-piece, bronze ball valve with bronze trim.
2. Two-piece, regular-port, bronze ball valves with bronze trim.
3. Bronze plug valve.
SECTION 26 05 00 - ELECTRICAL: BASIC REQUIREMENTS
PART 1 – GENERAL
1.0 SUMMARY
A. Section Includes: Basic requirements for electrical systems.
1.2 QUALITY ASSURANCE
A. Referenced Standards:
1. Aluminum Association (AA).
2. American Iron and Steel Institute (AISI).
3. ASTM International (ASTM):
4. A123/A123M, Standard Specification for Zinc (Hot-Dip Galvanized) Coatings on Iron and Steel Products.
5. A153/A153M, Standard Specification for Zinc Coating (Hot-Dip) on Iron and Steel Hardware.
6. ETL Testing Laboratories (ETL).
7. Institute of Electrical and Electronics Engineers, Inc. (IEEE):
8. C2, National Electrical Safety Code (NESC).
9. National Electrical Manufacturers Association (NEMA):
10. 250, Enclosures for Electrical Equipment (1000 Volts Maximum).
11. National Fire Protection Association (NFPA):
12. 70, National Electrical Code (NEC).
13. Underwriters Laboratories, Inc. (UL).
14. Where UL test procedures have been established for the product type, use UL or ETL approved electrical equipment and provide with the UL or ETL label.
1.3 DEFINITIONS
A. For the purposes of providing materials and installing electrical work the following definitions shall be used.
1. Outdoor area: Exterior locations where the equipment is normally exposed to the weather and including below grade structures, such as vaults, manholes, handholes and in-ground pump stations.
2. Non-architecturally finished interior area: Pump, chemical, mechanical, electrical rooms and other similar process type rooms.
3. Shop fabricated: Manufactured or assembled equipment for which a UL test procedure has not been established.
1.4 SYSTEM DESCRIPTION
A. Replace Onan 125 DGEA, Specification 53643F genset with an equal 125 kw propane fueled generator and automatic transfer switch. The replacement generator will be an Onan Cummins Model: C125N6 propane generator with Level 2 weather proof enclosure 60 Hz with Load bank Model:OSM1-0100.1-208V33-0600-(4) and automatic transfer switch PowerCommand OTEC transfer switch 40A-1200 A or equal
1.5 SUBMITTALS
A. Operation and Maintenance Manuals:
1. See Item 9 for submittal requirements for:
a. The mechanics and administration of the submittal process.
b. The content process of Operation and Maintenance Manuals.
1.6 DELIVERY, STORAGE, AND HANDLING
A. Protect nameplates on electrical equipment to prevent defacing.
1.7 AREA DESIGNATIONS
A. Designation of an area will determine the NEMA rating of the electrical equipment enclosures, types of conduits and installation methods to be used in that area.
1. Outdoor areas:
a. Wet.
2. Indoor areas:
a. Dry.
PART 2 - PRODUCTS
2.1 ACCEPTABLE MANUFACTURERS
A. Submit request for substitution in accordance with Specification Section 01 67 0.
B. Provide all components of a similar type by one (1) manufacturer.
2.2 MATERIALS
A. Electrical Equipment Support Pedestals and/or Racks:
1. Approved Manufactures:
a. Modular Strut
b. Unistruct Building Systems
c. Eaton B-Line
d. Globe Strut
e. Thomas & Betts Superstrut
2. Material requirements:
a. Modular strut:
1) Galvanized steel: ASTM A123/123M or ASTM A153/A153M.
b. Mounting hardware:
1) Galvanized steel.
2) Stainless steel.
c. Anchorage per drawings.
B. Field touch-up of galvanized surfaces.
1. Zinc-rich primer.
a. One (1) coat, 3.0 mils, ZRC by ZRC Products.
PART 3 - EXECUTION
3.1 INSTALLATION
A. Install and wire all equipment, including prepurchase equipment, and perform all tests necessary to assure conformance and…