United States Department of the Interior
U.S. FISH AND WILDLIFE SERVICE
IRON RIVER NATIONAL FISH HATCHERY
10325 FAIRVIEW ROAD IRON RIVER WI 54847
STATEMENT OF WORK
ASBESTOS BUILDING ASSESSMENT SURVEYS
AT
Iron River Nation Fish Hatchery
The U.S. Fish & Wildlife Service (USFWS) Iron River NFH located in Bayfield County, WI is requesting a Request For Quote (RFQ) to perform all work necessary for and incidental to the inspection of structures prior to building renovations, demolition and/or deconstruction to determine the presence of asbestos until 3:30 pm central time on August 31, 2022. Any Request for Proposals received after that time will be rejected for consideration. The Request for Quote will be awarded to the bidder who is qualified and has the lowest price.
This Scope of Work is requested to provide sufficient sampling, testing and an assessment for Asbestos Containing Material (ACM) prior to the demolition of building(s) and/or to perform repairs or maintenance to building(s) that are occupied.
The barn located at Quarters #25 at 74250 Weidenaar Road, Iron River, WI 54847 is scheduled for demolition shall include destructive testing to determine presents of asbestos.
The survey shall be performed in applicable safe working conditions as defined by Occupational Safety and Health Administration (OSHA) and the United States Environmental Protection Agency (EPA).
The RFQ(s) are being solicited from qualified firms to perform site inspection of the barn in Attachment #1. The site inspection will entail inspecting both the interior and exterior of the building and attachments for asbestos as needed and supplying Iron River NFH with a written report indicating the presence of asbestos materials. The report will identify the type of material, condition, location, and accurate square and/or linear footage. Cost estimates for removing any confirmed asbestos containing materials areas shall be provided for each type. Two (2) written reports (one (1) to the Station, one (1) to the Regional Environmental Compliance Coordinator (RECC)) and an electronically submitted report to the station and the RECC.
The building surveys shall be performed in accordance with Regulatory Agencies:
1) Environmental Protection Agency (EPA)
2) Occupational Safety and Health Agency (OSHA)
3) State of Wisconsin
a) Wisconsin Department of Health Services
b) Wisconsin Department of Natural Resources
The building surveys shall be performed in accordance with:
a) Asbestos
1) NESHAP - 40 CFR Part 61, Subpart M – National Emission Standard for Asbestos
2) TSCA - 40 CFR Subpart D, Section 763 – Asbestos
3) 29 CFR 1910.1001: General Industry Occupational Safety and Health Standards
4) 29 CFR 1926.1101: Safety and Health Regulations for Construction
5) Wisconsin Admin. Code ch. DHS 159, Certification and Training Course Requirement for
Asbestos Activities
6) Wisconsin Admin Code ch. NR 447, Control of Asbestos Emissions
Before a firm will be awarded a contract, the firm must have supplied to the U.S. Fish and Wildlife Service the firm's resume with business references and the following information particularly relative to the activity being undertaken in this project:
1. Name and address of submitter (Contractor), plus name and telephone number of the individual to contact for further information.
2. Persons conducting inspections for asbestos must be certified by the State of Wisconsin Department of
Health Services Program.
3. Name of lab being used to analyze asbestos samples and the National Voluntary Laboratory
Accreditation Program (NVLAP) Asbestos Fiber Analysis Program Certification Number.
4. All proposal shall include a Sample Report (Asbestos) with Individual Identification Number for
Sample, Location of Sample, Description of Sampled Material, Sample Result, Estimated Square Footage or Linear Footage with Descriptions (i.e. 6 Inch Pipe Insulation, 6 Foot Pipe Insulation) of Material.
5. Any other information which will demonstrate abilities to perform the required services should also be included.
6. Proof of Insurance.
1. PERIOD & PLACE OF PERFORMANCE
Period of Performance: The selected Contractor shall have 45 days to complete the survey.
Office Location: Site Location:
U.S. Fish and Wildlife Service U.S. Fish and Wildlife Service Iron River NFH Quarters 25 10325 Fairview Rd 74250 Weidenaar Road Iron River, WI 54847 Iron River, WI 54847
Iron River NFH – Quarters 25 Barn Building
The Quarters 25 Barn Building (RPI Asset Code – 35800500, RPI# 10011040) was built around 1956, The building is a wood constructed building with cedar shingle roofing. The building is approximately 1576
sq. ft. The assessment survey will consist of a comprehensive sampling of the entire structure for asbestos.
The following materials were observed during walkaround of site: windows (possible caulk), electrical wire coating, tar paper, and chipboard installation. Photo documentation of current status of building and site location is provided in Attachment 1.
2. GUIDELINES
The inspector's primary contact will be Carey Edwards, Hatchery Manager located at Iron River NFH.
The inspector shall take sufficient samples of all suspected ACM building materials and commercial products in accordance with guidance provided in this document or stricter state regulations and have them analyzed by a lab with accreditation for Asbestos and is a Wisconsin state certified laboratory.
Suspect asbestos samples shall be collected following professional protocols with appropriate sampling tools and leak-tight containers.
Each suspect sample shall be individually numbered, recorded on a sample log, description of material, quantified, and submitted under chain-of-custody to a laboratory certified under the Environmental Laboratory Accreditation Program.
Any sampling debris (i.e. protective clothing, contaminated wipes, respiratory cartridges, etc.) will be the responsibility of the contractor. As such the contractor assumes all liability for the correct disposal of suspect ACM and RACM waste.
A) ASBESTOS
The building assessment surveys will identify friable and non-friable asbestos-containing-materials (ACM) and asbestos containing commercial products. The survey shall consist of the identification, measuring, quantifying, testing and estimating the cost of removal of Regulated Asbestos-Containing Material ( RACM), Category I and Category II non-friable asbestos containing building materials, and commercial products that contain asbestos material. This survey shall be performed by a Wisconsin Licensed Asbestos Building Inspector.
1) INSPECTION PROCEDURE
I. Proper bulk sampling methods for suspect ACM will be followed. Proper bulk sampling methods are defined as wetting with amended water, encapsulation after sample collection, and clean-up of debris associated with sample collection.
II. Obtain randomly distributed samples from each homogeneous area as listed in Table I. A material may be assumed to be ACM without sampling or based on the analytical results of fewer samples.
III. Locate and quantify all homogeneous areas of surfacing materials, thermal system insulation, miscellaneous materials, and asbestos commercial products in areas to be demolished or renovated. Note any possible asbestos debris that is present due to deterioration or damage in the above areas. Unless assumed to be ACM, all types of floor tiles in all layers must be inspected and sampled. Whenever necessary, destructive sampling must be done to access ducts and/or pipes in walls or chases and in areas above suspended ceilings to determine if ACM is present for buildings scheduled for demotion. In buildings that are not scheduled for demolition, the report shall identify areas where destructive testing was not conducted.
IV. Analysis of suspect ACM bulk samples through Polarized Light Microscopy (PLM) shall be performed by persons or laboratories with proficiency demonstrated by current successful participation in a nationally recognized testing program such as the National Voluntary Laboratory Accreditation Program (NVLAP) or the National Institute for Standards and Technology (NIST) or the Round Robin for bulk samples administered by the American
Industrial Hygiene Association (AIHA) or an equivalent nationally recognized round robin testing program.
V. The laboratory should delineate sample layers (i.e. VAT and mastic; drywall, mud, and tape;
cloth wrap and mag; etc.).
VI. Tabulate results by property address. Show the location and square or linear footage of each homogeneous area. Quantify all assumed materials such as floor tile and resilient roofing and siding as ACM (note multiple layers). If ducts and pipes inside walls could not be visually inspected, they must be assumed ACM. The inspector's name, address, phone number, certification number and date of inspection must appear on each report.
VII. Provide and estimate for remediation of asbestos containing material.
2) ACM sample material shall be analyzed and retained by the laboratory for 30 days in case the Service requests follow on point count analysis.
TABLE I - Minimum Sampling Requirements for Asbestos Containing Materials (The materials listed in this table are provided as common examples and are not a complete list of building components or equipment that require testing.)
Quantities of samples to be obtained per homogeneous area are:
(NOTE: Discretion shall be exercised when defining homogeneous areas, giving consideration to all factors which could reduce the number of samples required.)
Material Type Number of Samples Size of Homogenous Area
Surfacing materials 3 <= 1,000 square feet 5 > 1,000 square feet and <=5,000 square feet 7 > 5,000 square feet
Thermal System Insulation
3 each homogeneous area
1 Each homogenous area of patch less than 6 linear or 6 square feet
3 Each homogeneous group valves, fittings, elbow tees, hangers
0*
Inspector has determined that the thermal system insulation is fiberglass, foam glass, rubber, or other non-ACBM. * Need to note on inspection that location of material was seen.
Miscellaneous Material*
- Each layer of floor tile,
- Resilient sheet goods,
- Paper backing of sheet flooring,
- Mastic,
- Resilient roofing,
- Siding materials
- Each homogeneous areas of ceiling tiles,
- Slate flooring and roofing.
- Slate or transite siding,
- Drywall/drywall joint compound systems,
- Ect.
3 The minimum of three samples
Additional sample may be obtained at the discretion of the inspector based upon the square footage of the homogenous area:
3 <= 1,000 square feet
5 > 1,000 square feet and <=5,000 square feet
7 > 5,000 square feet
Other – Asbestos Containing Products:
- Asbestos Gloves
- Fireproof Safes
- Asbestos Gasket
- Etc.
1* Material that are labeled asbestos containing do not need to be sampled but shall be inventoried.
Note: When debris is identified that corresponds with identifiable suspect ACM or ACBM, utilize the correct Homogeneous Area Numbers corresponding with the suspect material.
1) ASBESTOS, LEAD AND HAZARDOUS MATERIAL BUILDING INSPECTION REPORT
A) Following laboratory identification of the suspect samples:
1) The report findings shall adhere to professional standards and contain at a minimum:
a. Company name, building inspector name(s), report preparer name (if different from inspector), company mailing address, and company telephone number.
b. Station Name, Name of Building (if any), and street address, city, state, zip code for structure(s) inspected.
c. Date of inspection, and date of report preparation (if different).
d. Printed name and signature of each individual involved in the inspection.
e. Asbestos Building Inspector License number and expiration date for each individual
f. Lead Inspector or Lead Assessor License number and expiration dated for each individual
g. Provide a separate, detailed discussion for each building inspected, if multiple buildings are included in the same report.
h. For each building, identify and provide a detailed description of all exterior and interior building materials. Indicate how samples locations and/or materials are labeled/identified in the building to assist with abatement. Document sample locations and areas that were not accessible during the inspection.
i. Provide an estimated square or linear footage for asbestos or lead of suspect building material.
This may be calculated by room size or actual measurement.
j. Clearly state the number of samples collected for each type of suspect material based on the estimated or actual square or linear footage.
k. Discuss the type, amount (square or linear footage) and condition of all suspected material testing positive or assumed positive for asbestos, lead exceeding regulatory standard, and hazardous materials.
l. Include a written recommendation for disposition of all identified asbestos-containing materials (ACM) or presumed asbestos-containing materials (PACM), Lead Paint, and Hazardous Material and a cost estimate for each activity.
m. Include photographs, building drawings or sketches.
n. A map of the building indicating sample location and locations of other hazardous waste identified in the report.
o. Provide a copy of all sample collection data, chain of custody form(s), and lab analysis reports.
p. Copy of the inspector’s certification card for lead and asbestos.
B) The report findings shall also contain recommendations for any actions needing to be completed prior to demolition and an estimate cost. A draft electronic report shall be provided to the Service for a five working day review/comment period prior to issuing the final report.
C) Final Reports shall be provided:
1) Contractor must submit and electronic copy of each report via email to the U.S. Fish and Wildlife
Service, (Insert Station) Project Leader and Regional Environmental Compliance Coordinator.
Reports must be submitted in either Microsoft Word Document or PDF Format.
2) Contractor must submit a hard copy of the report the U.S. Fish and Wildlife Service, Iron River National Fish Hatchery Project Leader and Regional Environmental Compliance Coordinator.
Reports must be submitted in either Microsoft Word Document or PDF Format.
Attachment 1:
Iron River National Fish Hatchery in location to Duluth, Superior, and Ashland
Iron River, WI to Iron River NFH showing roads.
Iron River NFH to Quarters 25
Outside View of Barn
Interior View of Barn