This is a Request for Quote (RFQ) issued by the U.S. Army Corps of Engineers, Rock Island District, for aggregates under a Blanket Purchase Agreement (BPA) to support the Lake Red Rock Remedial Levees Project located in Pleasant Hill, Iowa.
The solicitation requests quotes for three aggregate materials: Shot Rock (6,000 tons), 3-inch Bedding Stone (625 tons), and Class E Rip Rap (3,000 tons). All materials must be quoted on an FOB delivery basis to 4681 Vandalia Rd., Pleasant Hill, IA, with delivery occurring Monday through Friday between 8:00 a.m. and 4:00 p.m. CST. Estimated delivery will commence October 13, 2026, and continue through December 2026. Contractors must submit unit pricing per ton and total pricing for each material line item. Actual quantities may vary by ±15% at government discretion, with minimum and maximum order quantities specified: Shot Rock (5,100–6,900 tons), 3-inch Bedding Stone (552.5–747.5 tons), and Class E Rip Rap (2,550–3,450 tons). Contractor point of contact must contact the government representative, Jade Mockenhaupt, at the Lake Red Rock Project Office ((641) 277-2047) no later than seven calendar days after award to schedule services and coordinate delivery. No response deadline or award date is specified in the document.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| B08 - Concrete Purchase Order Terms for SAM postings_REV1.pdf | ||
| B08 - Map Red Rock BPA Aggregate 2026.pdf |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Concrete & Aggregates-Blanket Purchase Agreement (BPA) U.S. Army Corps of Engineers, Rock Island District
Request for Quote Aggregate For
Lake Red Rock Remedial Levees Project
Location: Lake Red Rock Project
1) The aggregates shall be delivered to 4681 Vandalia Rd., Pleasant Hill, IA. Quotes shall include delivery to the specified location – see attached “B08 - Map - Red Rock BPA Aggregate 2026" for delivery location.
2) All materials must be quoted to include FOB delivery to the location specified. Normal working/delivery hours days shall be Monday through Friday between 8:00 a.m. and 4:00 p.m. CST.
3) Actual quantities may vary +/-15%. Please price the quantities listed below; however, the actual quantity delivered may be adjusted by +/-15% due to site working conditions.
4) All materials shall be delivered to the Red Rock remedial levees in Pleasant Hill, IA and coordinated by Maintenance Supervisor, Jade Mockenhaupt, as materials are needed to support the project. It is estimated delivery will begin October 13, 2026, and continue through December 2026. Contractor Point of Contact (POC) must make contact and schedule services with Government POC no later than seven (7) calendar days after award.
5) For questions and delivery coordination, contractors can call the government representative, Jade Mockenhaupt, at the Lake Red Rock Project Office at (641) 277-2047.
Request for Quote (RFQ):
Item # Supply/Material Quantity Unit Cost Total Cost
1. Shot Rock 6,000 $_______/Ton $_______6500 Tons (±15%)*
2. 3-inch Bedding Stone 625 $_______/Ton $_______650 Tons (±15%)*
3. Class E Rip Rap 3,000 $_______/Ton $_______3000 Tons (±15%)*
TOTAL
* The (±15%) is at the discretion of the government. Example variation in quantities below.
Material Minimum Order (Tons) Maximum Order (Tons) Shot Rock 5,100 6,900
3-inch Bedding Stone 552.5 747.5 Class E Rip Rap 2,550 3,450