This document is a statement of work for herbicide application services on specified areas of the Edwin B. Forsythe National Wildlife Refuge in Forked River, New Jersey. The U.S. Fish and Wildlife Service seeks quotes from qualified vendors to apply herbicide to control and eradicate Bradford pear trees across approximately 56 acres, with work to occur from March 1st to April 15th, 2024. Vendors will use backpack sprayers and other equipment to apply the Pathfinder II herbicide provided by the refuge, targeting a minimum 95% treatment of identified infestation grids with at least 90% herbicide coverage and 90% tree mortality. Vendors must hold commercial herbicide applicator licenses, follow all safety and regulatory requirements including submitting an application plan and spill response procedures, and provide post-application documentation and mapping of treated areas. The solicitation number for this opportunity is 140FS323Q0172 and was issued by the Department of the Interior Fish and Wildlife Service.

View the file

Other files

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Statement Of Services:

Herbicide Application on

Edwin B. Forsythe National Wildlife Refuge at Forked River, NJ

1. GENERAL INFORMATION

1.1 U.S. Fish & Wildlife Service is seeking quotes from qualified vendors for the application of herbicide for the control and eradication of target Bradford Pear (Pyrus calleryana) on specified areas at Edwin B. Forsythe National Wildlife Refuge. Work shall consist of furnishing all necessary equipment, labor, and materials necessary to accomplish the specified vegetative control and eradication (with exception noted in 1.2, below). Spraying will occur by using hand pump sprayers, backpack sprayers, and electric pump tank sprayers.

1.2 Important note: Staff at Edwin B. Forsythe NWR will furnish necessary herbicide (Pathfinder II). The herbicide application shall occur either in the spring or fall to achieve the optimum results. The active translocation of the herbicide on the trees is optimum in the spring, summer, and fall. All herbicide applications shall be consistent with the product label instructions, manufacturer's guidance, and the requirements of this contract.

1.3 Period of Performance: The Period of Performance for this project is March 1, 2024, to April 15, 2024. This could be adjusted due to weather and other constraints.

2. LOCATIONS, CONTACTS

2.1 General Location: The work areas are located in Forked River, Lacey Township, NJ. Estimated application acres and chemicals to be used are included in the following table.

NWR Location Acres to treat Herbicide, surfactant, EPA registration numbers

E. B.

Forsythe

NWR

Forked River, NJ

Up to 56 acres Bradford Pear

Pathfinder II® (Triclopyr)

To be provided by refuge

PLEASE NOTE: Treatment area acreage was estimated using manual digitization from digital orthophotos. Actual acre amounts may be more or less than those listed above.

2.2 Site Location: Treatment areas are located on sites highlighted on the attached map. Unit is shown on a general environ map. The estimated extents of infestations to be treated are then depicted on more specific location maps and will be provided upon award. These maps include specific polygons of infestations to be treated.

3. TREATMENT AREAS, CONTROL GOALS AND HERBICIDES

3.1 General: Specific treatment areas are identified on the map and drawings. A site visit will be provide by a representative of the Edwin B. Forsythe National Wildlife Refuge (Game Farm Rd., Forked River, NJ 08731), on the specified date in the solicitation.

3.2 Treatment Methods: Methods for spraying will include Ground spraying using backpack sprayers, hand pump sprayers, or a sprayer attached to an ATV quad.

3.3 Vegetation Control Objectives: A minimum of 95% of all of the identified infestations grids will be treated with herbicide in the treatment areas, with each infestation grid receiving at least 90% coverage by basal bark spray, to the degree that at least 90% of the live stems and leaves die within 3-4 weeks of the spray, or contractor will have to re-apply in the fall (if sprayed in the spring) or in the spring the very next year (if sprayed in the fall), at his/her expense. The Project Officer will be responsible for documenting that less than 95% of the area was treated, and notifying the contractor, as soon as possible after the spraying activity (e.g. will survey the area, take digital photographs).

3.4 Herbicide Selection Procedure: The contractor will use Pathfinder II furnished by the refuge. The herbicide will be appropriately labeled for specific application (i.e. basal bark or cut stump treatment).

No restricted use herbicides are allowed. No herbicides can be used on National Wildlife Refuge property without prior approval from the Project Officer. In addition, all carriers must be non-toxic and registered for applications. FAR Clause 52. 223-2 Affirmative Procurement of Biobased Products Under Service and Construction Contracts will apply.

3.5 Minimizing Impacts to Non-Target Species: No broadcast spraying for the Bradford Pear shall be performed. There will be zero tolerance for direct spray or drift of herbicides into non-target vegetation or on adjacent property. No spraying shall be performed if more than a 50% chance of rain is forecast for the day of application or for 24 hour period following the planned application. The chemical will be applied between April 1 through May 27 or October 1 through November 30. Assessment of impact will be conducted by the Project Officer

4. NOTIFICATION OF TREATMENT:

The contractor will provide a 72-hour notice to the NWR Project Officer before arriving at the site locations for herbicide treatment work. This will ensure that Refuge staff is available to answer questions, if required, and also to participate in any reconnaissance that may be conducted.

5. HANDLING, MIXING, APPLICATION RATES AND METHODS

5.1 Handling and Mixing: All herbicides will be handled and stored in accordance with instructions on the

EPA registration label. The contractor is required to provide a secondary containment system around their herbicide filling area when herbicides are filled on government property. This containment system must be constructed of impervious materials. In addition, the contractor will ensure that no contamination of any water source occurs, and that emergency spill containment equipment is at the worksite and is capable of containing all potential herbicide spills from t h e contractor vehicles/equipment. Unused, mixed pesticides will be disposed of in accordance with local, state and EPA guidelines. Spray equipment cleaning will also be accomplished in accordance with these guidelines. Prior to leaving a worksite for the day, the contractor shall remove all equipment and unused materials, any waste materials, empty herbicide containers and litter resulting from contract activities on government property.

5.2 Equipment: The equipment used by the contractor shall be designed for such work and operated in a safe manner. The equipment will be capable of accurately delivering a predetermined rate per acre dosage of herbicide.

5.3 Rates and Method of Application: Application rates will be per the specification on the material safety data sheet, labeling and manufacturer's suggested rate tables, per chemical used, and the desired results identified in “3.2 Vegetation Control Objective”.

6. SAFETY AND CERTIFICATION

6.1 Safety Manual: Notwithstanding any other provisions of this contract, the Contractor shall comply with all safety and health requirements as outlined in OSHA Safety Standards to ensure the safe working conditions for themselves and others.

6.2 Hazard Communication: The contractor shall implement a hazard communication program in accordance with 29 Code of Federal Regulations (CFR) 1910.1200 or 1926.59. The written hazard communication program shall address, as a minimum, the following: training (to include potential safety and health effects from exposure), labeling, current inventory of hazardous chemicals on site, and the location and use of Safety Data Sheets (SDSs).

6.3 Licensing: The contractor or any employees or subcontractors performing any of the work under this contract shall possess a valid state commercial herbicide applicator's license for the state in which work is being performed and shall comply with all Federal, State, and local laws and regulations applicable to the contract work and to the products and materials used by the contractor in performing that work. A New Jersey Department of Environmental Protection license/permit for upland applications are required.

Evidence of such licensing shall be submitted prior to award and also with the "Application Plan" as outlined in Paragraph 7. 1.

6.4 Public Safety: Public safety must be ensured when spraying or using pesticides. Forked River Game

Farm is closed to public access, therefore interactions with the contractor and the public is highly unlikely. The public will be notified of all spraying activities via the refuge’s social media websites and press releases.

6.5 EPA Registration Label: All work shall be performed in accordance with the instructions on the EPA registration label of the chemical herbicide used. All safety instructions featured on the label shall be strictly adhered to.

6.6 Safety Data Sheets: Safety Data Sheets (SDS) shall be submitted to the Project Officer with the

“Application Plan” as outlined in Section 7.1. The Contractor shall also make these SDSs readily available to all affected contract employees.

6.7 Spills and Contamination: The contractor shall submit as part of the "Application Plan" described in

Section 7.1, the response measures to be implemented should a spill or contamination occur. The contractor's immediate response to a spill or contamination shall be to proceed with the required measures to limit the contamination. Immediately following this initial response, the contractor shall notify the appropriate Project Officer at the work location and other appropriate local, state, and federal officials. Subsequent to these actions, the contractor shall take actions to clean up the spill as recommended by the Project Officer. Should a personnel contamination occur, the contractor shall take immediate actions as prescribed by chemical manufacturer so as to protect the safety and health of the contaminated individual(s). Immediately following the contractor's initial response, the incident shall be reported to the appropriate Project Officer.

7. SUBMITTAL AND REPORTING

7.1 Application Plan: The contractor shall submit an electronic copy of an application plan to the Project

Officer. This plan shall outline, per National Wildlife Refuge site, the types of herbicides, planned application rates, hyperlinks to SDS's and labels for each chemical to be used, scanned copies of applicator licenses, and a spill and contamination action plan. Additionally, the contractor shall certify in writing that all employees engaged in handling, and spraying herbicides have read the MSDS's and that personal protective equipment as specified by the MSDS's will be provided to and worn by these persons.

Further, one hard copy of the approved plan shall be provided that will include a signed statement by the contractor that this plan complies with all state, local and federal regulations. This plan shall be submitted for review and approval within 10 working days of the notice of contract award and prior to the desired start of work. Government approval of this plan in no way relieves the contractor of any liability for compliance with all Federal, State, and/or local regulations, should there be omissions/errors within said plan.

7.2 Post-Application Documentation: The contractor shall submit a spray log to the Project Officer detailing: day(s) and time(s) sprayed, crew members, chemical applied, application rate, weather conditions (temperature, humidity, chance of precipitation). The contractor shall also provide ArcGIS shapefiles (or a similar type of electronic mapping) to the refuge Project Officer showing areas sprayed.

Shapefiles will be geo-referenced using the Grid Coordinate System: UTM zone 18 and Horizontal Datum: NAD 1983.

8. PREWORK MEETING:

Within 10 days after contract award, the contractor shall contact the Project Officer to arrange a meeting to discuss and develop a mutual understanding of the requirements and details of work. There may also be occasions when subsequent conferences will be called to reconfirm understandings or provide clarifications on contract requirements.

9. LIABILITY OF AND DAMAGES TO THE GOVERNMENT

9.1 Insurance: The contractor will carry liability insurance that will cover the application of pesticides as defined in this specification. This coverage will include as a minimum drift, run-off, and pollution (sudden and accidental) for all contract operations. The amount of coverage this insurance will provide will not be less than $ 1,000,000 per incident. A Certificate of Insurance form signed by the insuring agency shall be provided to the Contracting Officer prior to award of the contract. The insurance must provide coverage for the entire contract period. The insurance policy shall state that it cannot be cancelled without 30 days written notice to the Contracting Officer. Failure to secure insurance will be grounds for non-award and termination of the insurance during the performance period of this contract for any reason will be grounds for termination of this contract. The contractor will be in default and the contract terminated if the insurance lapses and is not immediately replaced with equal coverage. (If an insurance lapse occurs, work is suspended pending replacement insurance. The delay is not compensable to the contractor).

9.2 Government Liability: The Government assumes no liability from the contractor's performance of the contract work. The contractor shall hold and save the Government harmless from any and all liability arising from the performance of the contract.

9.3 Responsibility for Damages: The contractor is responsible for all damages to persons and property resulting from performance of the contract work. The contractor shall return any Government furnished property (if supplied) to the Government in the condition that it was received, ordinary wear and tear excepted. The contractor shall repair or replace, at the option of the Contracting Officer, any Government furnished property lost or damaged in the course of the contract work.

10. WARRANTY

The contractor warrants that:

10.1 Should the desired results not be achieved, as described in “3.2 Vegetation Control Objectives”, the contractor will, at no additional cost to the Government, reapply the herbicide to those areas where targeted vegetative growth continues or recurs. If needed, reapplications would occur during the spring, summer, and fall of the same year. The determination as to the acceptable performance of the contractor and the need to reapply the herbicides will rest solely with each NWR Project Officer, or his authorized representative. A request to retreat an area may be either verbal or in writing. A request to re-treat an area will be in the format of a contract modification.

10.2 The contractor is responsible for damages to persons or property, including unreasonable or unnecessary damages to non-target vegetation, within and outside the treatment areas resulting from the performance of the contract work. Damage costs as determined by government personnel will be charged in the form of a fine for the cost of rehabilitation or replacement of the affected resources.

Other penalties may be assessed based on local, State, or Federal laws.

11. INSPECTIONS AND ACCEPTANCE:

Work will be inspected periodically for conformance with these specifications for timeliness, safety and results achieved.

SPRAYING MAP FOR EDWIN B. FORSYTHE NWR, FORKED RIVER GAME FARM:

Figure 1. Treatment locations foand density for the Bradford Pear. Each square grid is 50 meters by 50 meters.

1. GENERAL INFORMATION
2. LOCATIONS, CONTACTS
PLEASE NOTE: Treatment area acreage was estimated using manual digitization from digital orthophotos. Actual acre amounts may be more or less than those listed above.
3. TREATMENT AREAS, CONTROL GOALS AND HERBICIDES
4. NOTIFICATION OF TREATMENT:
5. HANDLING, MIXING, APPLICATION RATES AND METHODS
6. SAFETY AND CERTIFICATION
7. SUBMITTAL AND REPORTING
8. PREWORK MEETING:
9. LIABILITY OF AND DAMAGES TO THE GOVERNMENT
10. WARRANTY
11. INSPECTIONS AND ACCEPTANCE:
SPRAYING MAP FOR EDWIN B. FORSYTHE NWR, FORKED RIVER GAME FARM: