BROWN V BOARD OF EDUCATION NHS
1515 SE MONROE
TOPEKA, KANSAS 66612
EMERGENCY FLOOR REPAIR
PMIS 314923
PROJECT SPECIFICATIONS
NATIONAL PARK SERVICE
January 6, 2021
TABLE OF CONTENTS
DIVISION 01 - GENERAL REQUIREMENTS
Section 01 10 00 - Division 01 Short Form General Requirements
DRAWINGS AND PHOTOGRAPHS
Building Floor Plans
Existing floor condition Ranger Office Room 218
SECTION 01 10 00
DIVISION 1 SHORT FORM GENERAL REQUIREMENTS
PART 1 – GENERAL
ITEM 1 - DESCRIPTION OF WORK
1.1 Background: On April 6th, 2020 a leak in the building floor heat piping was discovered under the historic flooring in the Ranger office (Room 218) on the second floor. The water leaked down the ceiling above the south section of Education and Justice Gallery (Room 115) causing damage to the historic flooring in that area.
1.2 Work Covered by the Contract Documents:
A. Project Location: Brown v Board of Education NHS, 1515 SE Monroe, Topeka, Kansas 66612
B. Work consists of: The wood flooring that was removed in the Rangers office to access the piping will be replaced in-kind with the boards removed to the greatest extent possible. The opening of removed flooring measures approximately 2’9” X 8’6”. The removed boards are stored on site. Some planks were damaged beyond reuse and will have to be replaced with new planks. The replacement planks should be 2 ½” inches x 5/8” thick, tongue and grove vertical grain Yellow Pine B. Any new boards can remain unfinished.
The pine flooring in the Education and Justice Gallery south side will be sanded down to a smooth and even surface. Then stained to match flooring on the North side of the Gallery. The finish sheen will match the flooring on the North side of Gallery. The area to be refinished is approximately 28’ x 21’, however there is an area of carpeting and a display wall that will lesson the square feet to be refinished. Counters and displays, including wall panels and audio/visual stations will be protected during the sanding of the floor.
C. All work will be performed under a single contract.
D. Period of performance: 60 Days from award of contract
ITEM 2 - EXISTING UTILITIES
2.1 Existing Utilities: This section is not applicable
ITEM 3 - CONTRACTOR’S USE OF PREMISES
3.1 Conduct of Operations: At all times the contractor shall conduct his operations in conformance with the rules and regulations promulgated by the Secretary of the Interior for the National Park Service, and applicable park rules and regulations prescribed by the Park Superintendent.
A. No signs or advertisements (except those specified herein) shall be displayed on the construction site or within the park unless approved by the Contracting Officer.
B. Smoking is not permitted within any Federal building or within 25 feet of entrances, operable windows, or outdoor air intakes.
C. Pubic Use of Site: Contractor shall at all times conduct operations to ensure the least inconvenience to the public. This includes blocking areas where work is performed.
3.2 On-site work hours: Work shall be generally performed during normal business working hours of 8 a.m. to 5 p.m., Monday through Friday, except when otherwise indicated.
A. Work on Saturdays, Sundays, Federal holidays, early morning, or at night may not be performed without prior consent from the Contracting Officer. Submit requests for work outside of the stated normal business hours to the Contracting Officer for approval at least 48 hours in advance of the work.
3.3 Contractor Use of Site:
A. General: Contractor shall have limited use of the site for construction operations. Limit use of premises to Room 115 (Education and Justice Gallery and room 208 Rangers Office Public Restrooms in the building are available for contractors employees. Do not disturb portions of Project site beyond areas in which the Work is indicated.
B. Limits: No private Offices or other rooms except as notated above.
C. Driveways and Entrances: Keep driveways, access roads, and entrances serving premises clear and available to Government, Government's employees, and emergency vehicles at all times. Do not use these areas for parking or storage of materials. Schedule deliveries to minimize use of driveways and entrances.
D. Limit site disturbance: No Exterior work will be performed in this contract.
E. Security and Protection facilities installation:
This Section is not Applicable
3.4 Storage - Staging Areas:
A. Confine Storage of materials and equipment to the project area
3.5 Preservation of Natural Features: N/A
3.6 Hauling Restrictions: This section not Applicable
3.7 Housekeeping:
A. Keep project neat, orderly, and in a safe condition at all times. Store and use equipment, tools, and materials in a manner that does not present a hazard. Immediately remove all hazardous rubbish. Do not allow rubbish to accumulate. Provide onsite containers for collection of rubbish and dispose of it at frequent intervals during progress of work.
B. Dispose of waste materials legally off NPS property.
3.8 Occupancy Requirements for Buildings:
A. Existing Buildings:
1. Full Government Occupancy: Government will occupy buildings that will be under construction during the entire contract period. Cooperate with Government during construction operations to minimize conflicts and facilitate Government usage. Perform the Work so as not to interfere with Government's day-to-day operations. Maintain existing exits, unless otherwise indicated.
a. Maintain access to existing walkways, corridors, and other adjacent occupied or used facilities. Do not close or obstruct walkways, corridors, or other occupied or used facilities without written permission from the CO.
b. Maintain existing building in a weather tight condition throughout construction period. Repair damage caused by construction operations. Protect building and its occupants during construction period.
B. New Buildings: N/A
3.9 Photo Documentation: Park Designated COR will be responsible for documentation.
3.10 Fire and Life Safety
As a minimum, conduct one weekly 15-minute "toolbox" safety meetings. These meetings shall be conducted by a foreman or supervisor and attended by all construction personnel at the worksite. Topics need to coincide with work scheduled for the following week. Document and submit meeting minutes to the Contracting Officer within one day after the meeting.
A. Comply with the requirements of NFPA 241 (Standard for Safeguarding Construction, Alteration, and Demolition Operations).
B. Store and handle hazardous materials in accordance with manufacturer’s and OSHA 29CFR1926 Subpart D requirements. Maintain readily available, on site, MSDS/Safety Data Sheets (SDS) for each chemical.
i. Immediately report all spills of hazardous materials to the park.
ii. Maintain a spill emergency response kit.
iii. Train employees how to respond to a spill and use the emergency response kit.
3.11 Noise and Acoustics Management:
A. Noise Control: Perform demolition and re-roof operations to minimize noise. Perform noise-producing work in less sensitive hours of the day or week as directed by the Contracting Officer.
B. Repetitive and/or intermittent, high-level noise: Permitted only during Daytime.
1. Do not exceed the following dB(A) limitations at 50 feet:
Sound Level in dB(A) Time Duration of Impact Noise 70 More than 12 minutes in any hour 80 More than 3 minutes in any hour
2. Maximum permissible construction equipment noise levels at 50 feet:
EARTHMOVING dB(A) MATERIALS HANDLING dB(A) Compressors 75 Pneumatic Tools 80 Pumps 75 Saws 75 Generators 75 Vibrators 75
C. Ambient Noise:
1. Maximum noise levels (dB) for receiving noise area at property line shall be as follows:
a. Residential receiving area :
Daytime: 65 dB Nighttime: 45 dB
b. Commercial/Industrial receiving area:
Daytime: 67 dB Nighttime: 65 dB
ITEM 4 - COMMENCEMENT, PROSECUTION, AND COMPLETION
4.1 The Contractor shall commence work in accordance with the terms and conditions of the contract.
(Block 11 of the SF 1442 or relevant section of the award document)
ITEM 5 - EXAMINATION OF THE SITE
5.1 All bidders are urged to visit the job site and examine existing conditions before submitting bids. All bidders will be held to have the same knowledge concerning the site and the on ground conditions as if they had inspected the job site. No change orders will be approved for work obvious during a site visit.
Please see FAR 52.236-27 - Site Visit (Construction).
ITEM 6 - ABBREVIATIONS
6.1 The list of abbreviations, which may be used in the Construction Specifications or Special Provisions, refer to the organizations and specifications of the organizations may be found at the below https://www.nps.gov/orgs/1671/do-business-with-us.htm
ITEM 7 - ACCIDENT PREVENTION
7.1 Description: The work of this section consists of establishing and implementing an effective accident prevention program and providing a safe environment for all personnel and visitors.
A. It is the Contractor's responsibility to require all those working on or visiting the site to wear hard hats and other necessary personal protective equipment in good repair at all times. As a minimum, maintain four hard hats and all other APP required equipment.
7.2 Submittals:
A. Accident Prevention Program: At the preconstruction conference submit for approval a site specific accident prevention program. The Plan shall be written to comply with OSHA and project requirements (a generic plan is not acceptable) including but not limited to the following:
https://www.nps.gov/orgs/1671/do-business-with-us.htm
1. Name and qualifications of responsible supervisor to carry out the program
2. First aid and rescue procedures. Provide current certification for first aid/CPR of designated individual.
3. Training, both initial and continuing.
4. Outline of each phase of the work, the hazards associated with each major phase, and the methods proposed to provide for property protection and safety of the public, National Park Service personnel, and Contractor's employees. Identify the work included under each phase, with a Job Hazard Analysis (JHA)/Job Safety Analysis (JSA), etc.
5. Planning for possible emergency situations, such as Tornado or severe weather that may cause evacuations of the building. fires or power outages,. Such planning shall take into consideration the nature of construction, site conditions, and degree of exposure of persons and property.
6. Contractor to identify nearest location of medical facility for emergencies
7. Supplemental hazard specific plans may be required IAW 29 CFR 1926 or 1910.
7.3 Qualification of Employees:
A. Ensure that employees are physically qualified to perform their assigned duties in a safe manner to include operators of vehicles and equipment. .Provide operating instructions for all equipment. .
B. Do not allow employees to work whose ability or alertness is impaired because of drugs, fatigue, illness, intoxication, or other conditions that may expose themselves or others to injury.
7.4 Accident Reporting: The Contractor shall report all accidents to the Contracting Officer or designee as soon as possible and assist the Contracting Officer and other officials as required in the investigation of the accident.
7.5 Emergency Instructions: Post telephone numbers and reporting instructions for ambulance, physician, hospital, fire department, and police in conspicuous locations at the work site.
7.7 Personal Protective Equipment (PPE): It is the Contractor's responsibility to require all those working on or visiting the site to wear necessary protective equipment at all times.
A. PPE must meet requirements of applicable ANSI standards. Selection shall conform to OSHA 29CFR 1926 Subpart E.
B. B. A hard hat use area shall be designated by the Contractor. The hard hat area shall be posted by the Contractor in a manner satisfactory to the Contracting Officer.
C. C. It is the Contractor's responsibility to require all those working on or visiting the site to wear hard hats and other necessary PPE. All PPE will be serviceable at all times.
7.8 Hazardous Materials: It shall be the responsibility of all operators and contractors, functioning within the park to properly cleanup, mitigate and remediate if necessary, all unauthorized discharges of hazardous materials or non-hazardous chemical and biological products released from fleet and/or other support vehicles or stationary sources. Response shall be consistent with guidelines established by federal, state and local regulations, and as outlined within the operator's Safety or Hazardous Materials Business Plan.
A. If a spill, leak or other release occurs, the operator shall as soon as possible, without impeding cleanup, notify National Park Staff.
ITEM 8 - PRECONSTRUCTION CONFERENCE: See FAR 52.236-26
ITEM 9 - SUBMITTALS
9.1 General Submittal Procedures:
A. Submittal of stain and finish product will be reviewed on site and approved by the COR before use.
B. Preconstruction Conference Submittal: The following items shall be submitted a minimum of one week prior to the Preconstruction Conference. If all of these documents have not been received one week prior to the scheduled Pre-Construction Conference date, the conference will be cancelled, Notice to Proceed will not be issued, and the Contracting Officer will consider other contractual remedies. Work shall not commence until written Notice to Proceed has been issued. Contracting Officer will notify Contractor of tentative date for the Pre- Construction Conference:
1. Letter designating Project Superintendent.
2. Construction Schedule.
3. Accident Prevention Plan (see section 7 of this document).
1. A list of Subcontractors for this project.
2. Written statements from subcontractors certifying compliance with applicable labor standard clauses (SF1413).
3. Satisfactory evidence of liability insurance coverage and workman’s compensation for the
Contactor and all subcontractors.
10.2 Fire Prevention and Protection:
A. Hazard Control: Take all necessary precautions to prevent fire during construction. Provide adequate ventilation during use of volatile or noxious substances.
ITEM 11 - PROJECT CLOSEOUT
11.1 Description: The work of this section consists of final cleanup, closeout submittals, final inspection procedures, and safety precautions.
11.2 Cleaning: Remove all tools, equipment, surplus materials, and rubbish. At time of final inspection, project shall be thoroughly clean and ready for use.
11.3 Substantial Completion and Final Inspection: Submit written certification that project is substantially complete, and a final inspection must be requested to the Contracting Officer in writing. The Contracting Officer or designee will make an inspection within 10 days of receipt of request or at a mutually agreeable time.
A. If the work is determined to be substantially complete, following the final inspection, the.
Contracting Officer will prepare a Punch List and issue a Letter of Substantial Completion.
B. If the work is not determined to be substantially complete following the final inspection, the
Contracting Officer will notify Contractor in writing. Contractor shall request a new final inspection after completing the work. Re-inspection costs may be charged against the Contractor in accordance with the Inspection of Construction contract clause.
C. Contractor shall complete the Punch List within 30 calendar days, documented weather permitting.
D. If Contracting Officer determines that the work is not substantially complete; he will immediately notify Contractor in writing, stating reasons. After completing work, Contractor shall resubmit certification and request a new final inspection. Re-inspection costs may be charged against the Contractor in accordance with the Inspection of Construction contract clause.
E. If Contractor completes all items of work on the Punch List and all contractually required items, Contracting Officer will issue Letter of final acceptance of work.
F. If the Contractor fails to complete the work within the time frame, the Contracting Officer may correct the work with an appropriate reduction in contract price or charge for re-inspection costs in accordance with the Inspection of Construction contract clause.
G. Disposition of any permits and warranties required by the specifications in this section.
11.4 Acceptance of the Work: After all deficiencies have been corrected, a Letter of Acceptance will be issued. A Release of Claims document must be executed and submitted to the Contracting Officer before final payment can occur.
11.5 Warranties
A. Construction Warranty shall be based on date of Substantial Completion.
B. Provide All Warranty information of products installed organized by Division. All contact information, extents and conditions shall be clearly noted as well as date of overall project Substantial Completion.
C. Information shall include operation and maintenance manuals for each warranted material.
END OF SECTION
| E. Security and Protection facilities installation: |
| This Section is not Applicable |
| 3.10 Fire and Life Safety |
| As a minimum, conduct one weekly 15-minute "toolbox" safety meetings. These meetings shall be conducted by a foreman or supervisor and attended by all construction personnel at the worksite. Topics need to coincide with work scheduled for the followi... |
| A. Comply with the requirements of NFPA 241 (Standard for Safeguarding Construction, Alteration, and Demolition Operations). |
| B. Store and handle hazardous materials in accordance with manufacturer’s and OSHA 29CFR1926 Subpart D requirements. Maintain readily available, on site, MSDS/Safety Data Sheets (SDS) for each chemical. |
| i. Immediately report all spills of hazardous materials to the park. |
| ii. Maintain a spill emergency response kit. |
| iii. Train employees how to respond to a spill and use the emergency response kit. |
| A. Noise Control: Perform demolition and re-roof operations to minimize noise. Perform noise-producing work in less sensitive hours of the day or week as directed by the Contracting Officer. |
| B. Repetitive and/or intermittent, high-level noise: Permitted only during Daytime. |
| 1. Do not exceed the following dB(A) limitations at 50 feet: |
| 2. Maximum permissible construction equipment noise levels at 50 feet: |
| C. Ambient Noise: |
| 1. Maximum noise levels (dB) for receiving noise area at property line shall be as follows: |
| a. Residential receiving area : Daytime: 65 dB Nighttime: 45 dB |
| b. Commercial/Industrial receiving area: Daytime: 67 dB Nighttime: 65 dB |
A. It is the Contractor's responsibility to require all those working on or visiting the site to wear hard hats and other necessary personal protective equipment in good repair at all times. As a minimum, maintain four hard hats and all other APP re...