This is a Solicitation/Contract for Commercial Products and Commercial Services for asbestos remediation services at the Cold Regions Research and Engineering Laboratory (CRREL) in Hanover, New Hampshire. The U.S. Army Corps of Engineers is seeking a contractor to remove approximately 3,884 square feet of asbestos-containing floor tile and mastic, and 881 linear feet of sheetrock across multiple laboratory rooms, with work to be completed in phases between January 2026 and July 2026.

The solicitation is a Women-Owned Small Business (WOSB) set-aside with a firm fixed price arrangement. Key requirements include having five years of asbestos remediation experience, possessing a valid New Hampshire Asbestos Remediation Entity License, maintaining an established location within 250 miles of Hanover, and demonstrating capability to meet specified performance schedules. Quotes are due by 12:00 PM CDT on January 20, 2026, with evaluation criteria focusing on technical capability, project experience, licensing, location, and performance schedule compliance. The contract will be awarded based on best value to the government, with price not necessarily being the determining factor.

View the file

Other files for this federal contract opportunity

Other files attached to Asbestos Abatement, newest first.
File Type Posted
B04.30 Attachment 1 - Wage Determination 2015-6075 Revision 2.pdf PDF

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

WOMEN-OWNED SMALL

BUSINESS (WOSB)

SOLICITATION/CONTRACT/ORDER FOR COMMERCIAL PRODUCTS AND COMMERCIAL SERVICES

1. REQUISITION NUMBER PAGE 1 OF

2. CONTRACT NUMBER 3. AWARD/EFFECTIVE

DATE

4. ORDER NUMBER 5. SOLICITATION NUMBER 6. SOLICITATION ISSUE

DATE

7. FOR SOLICITATION

INFORMATION CALL:

a. NAME b. TELEPHONE NUMBER (No collect 8. OFFER DUE DATE/

LOCAL TIME

9. ISSUED BY

13b. RATING

14. METHOD OF SOLICITATION

CODE

15. DELIVER TO 16. ADMINISTERED BY CODE

18a. PAYMENT WILL BE MADE BY CODE17a. CONTRACTOR/

OFFEROR

CODE

FACILITY

CODE

CODE

TELEPHONE NUMBER

17b. CHECK IF REMITTANCE IS DIFFERENT AND PUT SUCH ADDRESS IN

OFFER

18b. SUBMIT INVOICES TO ADDRESS SHOWN IN BLOCK 18a UNLESS BLOCK

BELOW IS CHECKED

REQUEST

FOR QUOTE

(RFQ)

INVITATION

FOR BID

(IFB)

REQUEST

FOR

PROPOSAL

(RFP)

SEE ADDENDUM

19.

ITEM NUMBER

20.

SCHEDULE OF SUPPLIES/SERVICES

21.

QUANTITY

22.

UNIT

23.

UNIT PRICE

24.

AMOUNT

(Use Reverse and/or Attach Additional Sheets as Necessary)

25. ACCOUNTING AND APPROPRIATION DATA 26. TOTAL AWARD AMOUNT (For Government Use Only)

28. CONTRACTOR IS REQUIRED TO SIGN THIS DOCUMENT AND RETURN

COPIES TO ISSUING OFFICE. CONTRACTOR AGREES TO FURNISH

AND DELIVER ALL ITEMS SET FORTH OR OTHERWISE IDENTIFIED ABOVE AND

ON ANY ADDITIONAL SHEETS SUBJECT TO THE TERMS AND CONDITIONS

SPECIFIED

29. AWARD OF CONTRACT: REFERENCE OFFER

DATED . . YOUR OFFER ON SOLICITATION

(BLOCK 5), INCLUDING ANY ADDITIONS OR CHANGES WHICH ARE

SET FORTH HEREIN, IS ACCEPTED AS TO ITEMS:

30a. SIGNATURE OF OFFEROR/CONTRACTOR

30b. NAME AND TITLE OF SIGNER (Type or print) 30c. DATE SIGNED

31a. UNITED STATES OF AMERICA (SIGNATURE OF CONTRACTING OFFICER)

31b. NAME OF CONTRACTING OFFICER (Type or print) 31c. DATE SIGNED

AUTHORIZED FOR LOCAL REPRODUCTION

PREVIOUS EDITION IS NOT USABLE

STANDARD FORM 1449 (REV. 11/2021)

Prescribed by GSA - FAR (48 CFR) 53.212

10. THIS ACQUISITION IS UNRESTRICTED OR

NORTH AMERICAN

INDUSTRY CLASSIFICATION

STANDARD (NAICS):

SIZE STANDARD:

13a. THIS CONTRACT IS A

RATED ORDER UNDER

THE DEFENSE PRIORITIES

AND ALLOCATIONS

SYSTEM - DPAS (15 CFR 700)

SET ASIDE: % FOR:

11. DELIVERY FOR FREE ON

BOARD (FOB) DESTINATION

UNLESS BLOCK IS MARKED

SEE SCHEDULE

12. DISCOUNT TERMS

ARE ARE NOT ATTACHED

ARE ARE NOT ATTACHED

27a. SOLICITATION INCORPORATES BY REFERENCE (FEDERAL ACQUISITION REGULATION) FAR 52.212-1, 52.212-4. FAR 52.212-3

AND 52.212-5 ARE ATTACHED. ADDENDA

27b. CONTRACT/PURCHASE ORDER INCORPORATES BY REFERENCE FAR 52.212-4. FAR 52.212-5 IS ATTACHED. ADDENDA

8(A)

ECONOMICALLY

DISADVANTAGED

WOMEN-OWNED SMALL

BUSINESS (EDWOSB)

SERVICE-DISABLED

VETERAN-OWNED

SMALL BUSINESS

(SDVOSB)

HUBZONE SMALL

BUSINESS

SMALL BUSINESS

NOTE: OFFEROR TO COMPLETE BLOCKS 12, 17, 23, 24, AND 30.

calls)

Solicitation/Contract Form Continuation

Asbestos RemediationInstrument Name:

Product Service Code : F108

POINTS OF CONTACT (POC):

NOTE: Only a warranted Contracting Officer (KO), acting within his/her delegated limits, has the authority to issue modifications or otherwise change the terms and conditions of this contract. If an individual other than the Contracting Officer attempts to make changes to the terms and conditions of this contract, the Contractor shall not proceed with the change and shall immediately notify the Contracting Officer. Proceeding with any work not authorized by the Contracting Officer will be at the Contractor's own risk.

CONTRACTOR POC:

Name: TBD at time of award

Phone Number:

Email:

GOVERNMENT POCs:

Technical Point of Contact (TPOC):

Name: TBD at time of award

Phone Number:

Email:

Contract Specialist (CS):

Name: Kim Roberson

Phone Number: 217-373-3478

Email: Kim.D.Roberson@usace.army.mil

Contracting Officer (KO):

W913E526QA002

mailto://Kim.D.Roberson@usace.army.mil

Name: TBD at time of award

Phone Number:

Email:

*** END OF NARRATIVE 1 ***

W913E526QA002

Continuation of Supplies or Services and Prices/Costs

Additional Information/Notes

Item Supplies/Service Quantity Unit Unit Price

Amount

0001 The Contractor shall provide asbestos remediation services in the CRREL Main Lab, rooms 32A & 32B, as outlined and in accordance with the Performance Work Statement (PWS).

Pricing Arrangement: Firm Fixed Price

1 Job

0002 The Contractor shall provide asbestos remediation services in the CRREL Main Lab, rooms 34 and 174, as outlined and in accordance with the Performance Work Statement (PWS).

Pricing Arrangement: Firm Fixed Price

1 Job

0003 The Contractor shall provide asbestos remediation services in the CRREL Main Lab, rooms 154, 154A, 154B, 154C, 154D, 154H, 156, and 158, as outlined and in accordance with the Performance Work Statement (PWS).

Pricing Arrangement: Firm Fixed Price

1 Job

Continuation of Description

PERFORMANCE WORK STATEMENT

Asbestos Abatement of Lab Spaces

1 Introduction:

The Cold Regions Research and Engineering Laboratory (CRREL) in Hanover, New Hampshire has a requirement for a Contractor to provide asbestos abatement services. The Contractor shall remove and dispose of asbestos materials in accordance with state and federal regulations. The asbestos-containing materials consist of approximately 3,884 square feet of floor tile and attached mastic, as well as 881 linear feet x 4"- 6" of sheetrock.

1.1 Scope

Approximate total area to be treated is 3,884 square feet of floor tile and mastic and 881 linear feet of cove molding and mastic. The Contractor shall perform asbestos abatement as follows:

300 square feet of floor tile and mastic and 78 feet of cove molding and mastic in room 32A. This room has carpet over the top of the tiles. The Contractor is responsible for removal and disposal of carpet.

176 square feet of floor tile and mastic and 63 feet of cove molding and mastic in room 32B. This room has carpet over the top of the tiles. The Contractor is responsible for removal and disposal of carpet.

235 square feet of floor tile and mastic and 61 feet of cove molding and mastic in room

34. This room has carpet over the top of the tiles. The Contractor is responsible for removal and disposal of carpet.

1103 square feet of floor tile and mastic and 127 feet of cove molding and mastic in room 154.

44 square feet of floor tile and mastic and 21 feet of cove molding and mastic in room 154A.

503 square feet of floor tile and mastic and 92 feet of cove molding and mastic in room 154B.

192 square feet of floor tile and mastic and 133 feet of cove molding and mastic in room 154C.

297 square feet of floor tile and mastic and 72 feet of cove molding and mastic in room 154D.

27 square feet of floor tile and mastic and 21 feet of cove molding and mastic in room 154H.

91 square feet of floor tile and mastic and 42 feet of cove molding and mastic in room 156.

322 square feet of floor tile and mastic and 72 feet of cove molding and mastic in room 158.

594 square feet of floor tile and mastic and 99 feet of cove molding and mastic in room 174.

Within the confines of the above rooms, there is 83 linear feet of the remains of a wall (sheetrock on studs) 4" to 6" high. This wall was anchored in place by fasteners through the asbestos tile. Accordingly, the Contractor shall remove and properly dispose of the wall remnants and the asbestos tile and mastic.

Rooms 32A and 32B must be completed separately and sequentially. There is sensitive equipment in each that must be moved to the other when each room is abated. The Government will move the equipment to room 32A immediately following room 32B abatement.

Then 32A can be abated.

The Contractor shall ensure that no asbestos fibers remain or otherwise enter other parts of the facility. The Contractor and is responsible for all licensing, state notifications, and administrative submissions required by the state of New Hampshire to accomplish this task. The Contractor shall remove the asbestos-containing materials from the campus and dispose of in accordance with all state and federal regulations.

The defined spaces are not contiguous. The Contractor shall sequentially partition off each space, remove the asbestos materials, and clean up. It is acceptable to have multiple crews on site to complete the abatement. It is not acceptable to partition spaces off with no removal of materials occurring for more than one business day. Exceptions to this are permitted but must be coordinated with the Contracting Officer's Representative (COR) before work commences.

CRREL is a working laboratory and partitioning off spaces creates delays in ongoing work that must be minimized.

All activities must be coordinated with the COR.

The Contractor shall designate a primary POC for work being performed during the execution of the contract. The Contractor primary POC shall keep the COR informed of the work progress and be available to the COR in the event of a change in the schedule or if any problems arise.

The Contractor shall inform the COR in advance of any hazardous material introduced onto the campus by the Contractor (if applicable); at a minimum, the quantities brought onto the campus and the intended amount to be used will be provided to the COR (email is sufficient). For any hazardous material the Contractor brings onto the CRREL campus, the Contractor must produce Safety Data Sheets upon request by the COR. Any spills caused by the Contractor must be cleaned up by the Contractor. The Contractor is responsible for all disposal of Contractor-provided hazardous material.

The Contractor shall notify the TPOC of any potentially hazardous situations which may occur during performance of this contract. (Possible example: the noise emitted from the equipment precludes unprotected personnel from being closer than 50 feet.)

The Contractor shall notify the TPOC if any part of the laboratory must be isolated from all Government personnel during performance of this contract. (Possible example: the Contractor must build a negative pressure enclosure to prevent the building's air handling system from sucking in asbestos fibers - this enclosure may preclude Government personnel from conducting their normal activities.)

2 General Requirements

2.1 Non-Personal Services. The Government shall neither supervise the Contractor employees nor control the means or methods by which the Contractor performs the required tasks. Under no circumstances shall the Government assign tasks to, or prepare work schedules for, individual Contractor employees. It shall be the responsibility of the Contractor to manage its employees and to guard against any actions that are of the nature of personal services or give the perception of personal services. If the Contractor believes that any actions constitute, or are perceived to constitute personal services, it shall be the Contractor's responsibility to notify the Contracting Officer (KO) immediately.

2.2 Business Relations. The Contractor shall successfully integrate and coordinate all activity needed to execute the requirement. The Contractor shall communicate the timeline, and continuously monitor the ice thickness throughout the winter, regularly provide updates to CRREL personnel.

2.3 Contract Administration and Management. The following subsections specify requirements for contract, management, and personnel administration:

2.3.1 Contract Management. The Contractor shall establish clear organizational lines of authority and responsibility to ensure effective management of the resources assigned to the requirement.

2.3.2 Contract Administration. The Contractor shall establish processes and assign appropriate resources to effectively administer the requirement. The Contractor shall have the responsibility for supervising the support required and provide a POC for the Government to notify in case of emergency, proposed additions to the scope of work, and Government complaints about the performance of the work.

2.4 Subcontract Management. The Contractor is responsible for the development of subcontract awards and oversight of all actions of the any subcontractor, as needed.

2.5 Contractor Personnel, Disciplines, and Specialties. The Contractor shall accomplish the assigned work by employing and utilizing qualified personnel with appropriate combinations of education, training, and experience. All applicable work will conform to applicable federal, state, and local rules and regulations, such as proper operator licensing and certifications. The Contractor shall match personnel skills to the work or task with a minimum of under/over employment of resources. The Contractor shall ensure the labor categories, labor rates, and man-hours utilized in the performance of this PWS will be the minimum necessary to accomplish the required outcome. The Contractor shall provide the necessary resources and infrastructure to manage, perform, and administer the contract.

2.6. Period of Performance

Rooms 32A, and 32B must be completed by 28 February 2026 Rooms 34 and 174 must be completed by 31 July 2026 Rooms 154, 154A, 154B, 154C, 154D, 154H, 156, and 158 must begin no earlier than 1 June 2026 and be completed by 31 July 2026.

2.7. Contractor Location and Qualifications

The Contractor shall have a minimum of five (5) years of experience in asbestos remediation and hold a State of New Hampshire Asbestos Remediation Entity License.

The Contractor shall be located within 250 miles of CRREL so that in the event critical contractor equipment failure, replacement equipment can be made available the following business day.

In accordance with New Hampshire Code of Administrative Rules chapter Env-A 1800 "Asbestos Management and Control", the Contractor shall notify the town of Hanover, NH at least ten (10) days in advance of the commencement of work.

2.8 Non-Personal Services. The Government shall neither supervise the Contractor employees nor control the means or methods by which the Contractor performs the required tasks. Under no circumstances shall the Government assign tasks to, or prepare work schedules for, individual Contractor employees. It shall be the responsibility of the Contractor to manage its employees and to guard against any actions that are of the nature of personal services or give the perception of personal services. If the Contractor believes that any actions constitute, or are perceived to constitute personal services, it shall be the Contractor's responsibility to notify the Contracting Officer (KO) immediately.

2.9 Business Relations. Once notified by the Government of an executed contract, the Contractor shall successfully integrate and coordinate all activity needed to execute the requirement. The Contractor shall manage the timeliness, completeness, and quality of the deliverables.

2.10 Contract Administration and Management. The following subsections specify requirements for contract, management, and personnel administration:

2.10.1 Contract Administration. The Contractor shall have the responsibility for supervising the support required and provide a POC for the Government to notify in case of emergency, proposed additions to the scope of work, and Government complaints about the performance of the work.

2.10.2 Quality Assurance. The Government will periodically evaluate the Contractor's performance in accordance with the Quality Assurance Surveillance Plan (QASP) and PWS.

t. The Contractor shall be responsible for any subcontract 2.10.3 Subcontract Managemen management necessary to integrate work performed on this requirement and shall be responsible and accountable for subcontractor performance on this requirement.

2.11 Location and Hours of Work. The work location is the U.S. Army Corps of Engineers, Cold Region Research and Engineering Laboratory (CRREL) facilities located at 72 Lyme Road, Hanover, NH 03755 The Contractor shall be allowed access to the CRREL campus .

Monday through Friday between 6am and 6 pm. If the Contractor requests access earlier than 6 am, this request must be coordinated the day before with the COR. If the Contractor requests access after 6 pm, this must be coordinated by 5 pm that day with the COR. Similarly, if work on the weekends is desired, this must be coordinated by COB Wednesday that week with the

COR.

2.12 Travel / Temporary Duty (TDY). The Contractor is responsible for arranging all travel to accommodate the PWS including mobilization of necessary contractor employees to accomplish all tasks stated in PWS, or through management of subcontractors as directed by Contractor.

2.13 Information Management. Controlled Unclassified Information (CUI). Regarding DFARS clauses 252.204-7012 and 252.204-7020, CRREL does not plan to deliver or receive CUI data under this contract effort.

3 Performance Requirements. The Performance Requirements Summary (PRS) specifies the performance objectives, performance standards, methods of surveillance, and rating methodology for contractor performance.

. The following surveillance matrix ensures that the Government and 3.1 Surveillance Matrix contractor have a clear understanding of how contract performance will be monitored and evaluated. The surveillance matrix outlines task performance standards, methods of surveillance, acceptable performance standards, and relevant incentives/remedies.

Performance Objective Method of Surveillance

Standards /Acceptable Quality Level (AQL)

Ratings Incentive /Remedy

The Contractor shall remove all asbestos materials as identified in this PWS

100% COR

Inspection

100% Compliance

In accordance with PWS Section 3.2, Ratings

Re-performance at no additional cost to the Government.

The Contractor shall provide the COR the full names of contractor personnel requiring access to CRREL no less than 48 hours before the required access date.

100% COR

Inspection

100% Compliance

In accordance with PWS Section 3.2, Ratings

Re-performance at no additional cost to the Government.

The Contractor shall provide to the COR proof of NHDES licensure of each on-site contractor employee before any work commences.

100% COR

Inspection

100% Compliance

In accordance with PWS Section 3.2, Ratings

Re-performance at no additional cost to the Government.

The Contractor shall prepare and provide applicable Disposal Manifest Sheets to the COR as a record of the hazardous waste removal.

100% COR

Inspection

100% Compliance

In accordance with PWS Section 3.2, Ratings

Re-performance at no additional cost to the Government.

The Contractor shall remove from CRREL all owned tools, supplies, and equipment, and shall remove any Contractor generated trash, debris, or hazardous materials.

100% COR

Inspection

100% Compliance

In accordance with PWS Section 3.2, Ratings

Re-performance at no additional cost to the Government.

. The COR will use the following ratings to evaluate the quality of the 3.2 Performance Ratings Contractor's performance.

Performance Rating

Criteria

Excellent /Outstanding

Performance meets contractual requirements and exceeds many to the Government's benefits. The contractractual performance of the element or sub-element being assessed was accomplished with no problems and the Contractor's action were highly effective.

Very Good Performance meets contractual requirements and exceeds some to hte Government's benefits. The contractual performance was accomplished with few minor problems for which corrective actions taken by the Contractor were effective.

Good Performance meets contractual requirements. The contractual performance contains some minor problems for which corrective actions taken by the Contractor were satisfactory.

Marginal Performance does not meet some contractual requirements. The contractual performance reflects a serious problem for which the contractor has not yet identified corrective actions. The Contractor's proposed actions appear marginally effective or were not fully implemented.

Unsatisfactory Performance does not meet most contractual requirements and recovery is not likely in a timely manner. The contractual performance contains serious problem(s) for which the Contractor's corrective actions appear or were ineffective.

4 Other Provisions. Covering requirements for personnel conducting the work.

4.1 Overview: This contract is subject to the requirements of and shall be in accordance with EM 385-1-1, U. S. Army Corps of Engineers Safety and Health Requirements Manual, OSHA 29 CFR 1910 regulations covering personnel protective equipment, the CRREL Safety Office, and to any other local, state, and federal regulations that apply to the work. All Contractor personnel shall always maintain safe practices and procedures while on the CRREL site.

4.2 Personal Protective Equipment (PPE): Contractor personnel performing work on site shall comply with OSHA PPE standards for protective equipment. Each specific task will be assessed, and the appropriate PPE shall be used. Examples include but are not limited to protective clothing and respiratory protection. Contractor is required to supply his employees with proper PPE.

4.3 Routes of Egress: The Contractor shall ensure work does not block egress routes in the case of an emergency.

4.4 Barriers/Barricades and Signage: The Contractor shall provide barriers or barricades and signage as necessary to ensure unauthorized pedestrian or vehicle traffic cannot enter into work areas until safe to do so.

4.5 The Contractor shall provide the COR with the full name of any contractor employee requiring access to the CRREL campus no less than 48 hours in advance so that the CRREL Security Force can place the contractor personnel on the Approved Visitor List. All Contractor personnel requiring access to the CRREL campus must have their Real ID state issued driver's license or passport scanned by the Security Force upon entry to the CRREL campus. The contractor personnel will then receive a 'Visitor's Badge' which must be displayed on their person at all times when on the CRREL campus and returned to the Security Force when departing the campus for the day.

The Contractor is prohibited from introducing any product containing Trichloroethylene 4.6 (TCE) onto the campus. TCE is a common degreaser available in any hardware store for use in cleaning circuit boards, etc. (Note: the CRREL campus is home to extensive testing for presence of TCE and any introduction of TCE to the campus will skew results from the TCE test plan.)

5 Antiterrorism/Operations Security (AT/OPSEC)

A. General security requirements and guidance: The security requirements described below apply to all contract personnel (including employees of the prime Contractor ("Contractor") and all subcontractor employees) supporting the performance requirements of this contract. The Contractor is responsible for compliance with these security requirements. Questions regarding security matters shall be addressed to the designated Government representative (e.g., Contracting Officer Representative (COR), Requiring Activity (RA) representative, or Contracting Officer (if a COR or other RA representative is not appointed)). Contract personnel are critical to the overall security and safety of US Army Corps of Engineers (USACE) installations, facilities and activities, and security awareness training contributes to those efforts. The Department of Defense (DoD) and Army security training requirements specified below, if applicable, are performance requirements; all applicable contract personnel shall complete initial training within 30 days of contract award or the date new contract personnel begin performance on the contract. Within five business days from the completion of training, the Contractor shall provide written documentation (e.g., email or memorandum) to the Government representative. The documentation shall include the names of contract personnel trained and which training they completed; the Contractor shall maintain training records as part of their contract files and be prepared to provide copies of training certificates to the Government representative. Contractor personnel and vehicles are subject to search when entering federal installations. Additionally, all contract personnel shall comply with Force Protection Condition (FPCON) measures, Random Antiterrorism Measures (commonly referred to as "RAMs"), and Health Protection Condition (HPCON) measures. The Contractor is responsible for meeting performance requirements during elevated FPCON and/or HPCON levels in accordance with applicable RA plans and procedures--this includes identifying mission essential and non-mission essential personnel. In addition to the changes otherwise authorized by the changes clause of this contract, should the FPCON or HPCON levels at any individual facility or installation change, the Government may implement security changes that affect contract personnel. The Contractor shall ensure all contract personnel are aware of their security responsibilities, including any site-specific requirements identified in local policies or procedures.

.B Antiterrorism (AT) Level I Training. This applies to any contractor needing multi-day access onsite at ERDC, excluding contractors visiting ERDC for a short 1-day or less visit to meet with ERDC staff using standard visitor protocols. All contractor employees, to include subcontractor employees, requiring access to Army installations, facilities, controlled access areas, or require network access, shall complete AT Level I awareness training within 30 calendar days after contract start date or effective date of incorporation of this requirement into the contract, whichever is applicable. Upon request, the contractor shall submit certificates of completion for each affected contractor employee and subcontractor employee, to the COR or to the contracting officer (if a COR is not assigned), within 5 calendar days after completion of training by all employees and subcontractor personnel. AT Level I awareness training is available as provided by the COR in a PowerPoint presentation form and completion will be documented via memorandum.

C. Physical security and access control requirements: All contract personnel requiring physical access to a federal installation or facility shall comply with the access control procedures of that location. Contract personnel requiring unescorted access to meet contract performance requirements on a DoD installation in the US shall be vetted by the installation /facility Provost Marshal/Directorate of Emergency Services/Security Office using the National Crime Information Center-Interstate Identification Index (commonly referred to as "NCIC-III") and Terrorist Screening Database (commonly referred to as "TSDB"). Contract personnel shall comply with all personal identity verification requirements specified in installation/facility policies and procedures. Contract personnel who do not meet requirements for unescorted access to USACE facilities shall coordinate escorted access with the Government representative, as needed. Contract personnel who receive keys, access cards, or lock combinations that provide access to government-owned property shall comply with key and lock control procedures of the

RA.

D. iWATCH Suspicious Activity Reporting Training. This applies to any contractor needing multi-day onsite access at ERDC, excluding contractors visiting ERDC for a short 1-day or less visit to meet with ERDC staff using standard visitor protocols. The contractor and all associated subcontractors shall brief all employees on the USACE iWATCH program. This locally developed training will be used to inform employees of the types of behavior to watch for and instruct employees to report suspicious activity to the COR. This training shall be completed within 45 calendar days of contract award and within 45 days of new employees commencing performance on the contract. The contractor shall provide certification of completion to the COR within 10 days of training completion. Training documents will be provided by the COR during the kick-off meeting, or earlier upon request of the vendor.

E. Personnel Security Pre-Screening using E-Verify Program: Contractors shall comply with the requirements set forth in FAR clause 52.222-54 Employment Eligibility Verification and FAR Subpart 22.18 in using the E-Verify Program at (https://www.e-verify.gov/) (website subject to change) to meet the contract employment eligibility requirements. Contractors are encouraged to cooperate with Federal and State agencies responsible for enforcing labor requirements to include eligibility for employment under United States immigration laws in accordance with FAR 22.102-1(i). An initial list of verified/eligible candidates shall be provided to the COR no later than three business days after the initial contract award. When contracts are with individuals, the individuals will be required to complete a Form I-9, Employment Eligibility Verification, and submit it to the Contracting Officer to become part of the official contract file.

F. CRREL Security Requirements. All Contractor employees shall comply with all security requirements as written in these specifications and as directed by the CRREL Security Office, the COR/TPOC, and as follows:

U.S. Citizens. Contractor personnel must be U. S. citizens. Only U. S. Citizens may enter on site.

Positive Picture ID. All Contract personnel shall be prepared to show positive picture identification (such as a valid picture driver's license or other government picture ID) when entering onto the site or at any other time as required by the CRREL Security Office.

Access and General Protection/Security Policy and Procedures. The contractor and all associated subcontractors' employees shall comply with applicable installation, access and local security policies and procedures. In addition to the changes otherwise authorized by the changes clause of this contract, should the Force Protection Condition (FPCON) at any individual facility or installation change, the Government may require changes in contractor security matters or processes.

Sign-in and Badges. Contractor personnel are required to sign in with Security and shall wear security identification badges furnished by the CRREL Security Office while on the CRREL site. The Contractor shall return the badges at the security gate or as otherwise directed by the CRREL Security Office at the end of each workday. Contractor employees shall keep badges available at all times while on site and shall be prepared to show them at any time. The Contractor is responsible for the proper use and return of all badges issued to his employees.

Weapons. No weapons of any kind are allowed on site either in vehicles or on persons.

All persons and vehicles entering a U.S. Government site are subject to inspection by the Security office.

Deliveries. The Contractor shall notify the COR minimally two days prior to when a delivery of equipment and supplies is planned to occur. This will facilitate access on to the site. Contractor shall notify the TPOC the day before or as soon as possible when contractor or his subcontractors are to arrive, or deliveries of equipment and/or supplies are to occur. Contractor must receive his or his subcontractor's own deliveries.

Government personnel are not allowed to receive deliveries for any contractor.

General Disruption. General disruption by contractor is limited to the immediate work areas. Contractor products, tools, and/or equipment shall stay within the immediate work areas.

Tools/Equipment. Contractor is strictly responsible for the security of all products, tools, and/or equipment used during the duration of this contract.

Smoking. Smoking shall comply with the CRREL Smoking Policy, which, in general, prohibits smoking on site except in a designated smoking area. Designated smoking areas will be discussed at the post award conference.

5.1 Government-Furnished Utilities. The Government will furnish to the Contractor, in reasonable quantities, electricity to successfully complete this contract.

5.2 Control of Waste. During performance of all work on site, Contractor shall control waste and debris to ensure that it stays within the work area. Contractor shall remove waste and debris from the site and properly dispose of it daily.

5.3 Tools and Equipment. Tools and equipment used under this contract shall be maintained in good condition and shall be used and stored always using safe practices and procedures in accordance with manufacturer's instructions and recommendations. Tools and equipment shall be restricted to the immediate work area unless alternate arrangements are requested and approved through the COR.

5.4 Damage to Worksite. Test stand relocation shall not cause any damage to CRREL facilities. The Contractor shall repair at its own expense all damages that occur to CRREL facilities if damages are caused as a result of contractor negligence. All repairs shall be done as directed by the Government.

5.5 Contractual Disclaimer. Contractor is hereby notified that NO CRREL EMPLOYEE has the authority to direct contract employees in any way to alter their contractual obligations. If the Government does desire to alter requirements, changes may only be issued in writing and signed by the Contracting Officer (KO) sited in your contract. Contractor's employees shall take no action on any changes unless and until the POC receives authorization in the form of a fully executed contract modification approved by the KO.

6 Inspection and Work Completion

a. Overview: This contract is subject to routine Government inspections throughout the performance of Contractor work and a final Government inspection upon completion of each task.

b. Inspections: Routine Government inspections will, among other things, help ensure continuous quality assurance and more quickly identify defects. Contractor shall repair defects as directed by the Government at Contractor's own expense.

c. Work Completion: Upon Contractor completion of the Work, the Government will make a final inspection to confirm the following:

All defects have been corrected as directed.

All work has been completed.

All work areas are left clean.

*** END OF NARRATIVE 1 ***

Product Service Code : F108 North American Industry Classification System (NAICS) : 562910

Product Service Code : F108 North American Industry Classification System (NAICS) : 562910

Product Service Code : F108 North American Industry Classification System (NAICS) : 562910

Continuation of Packaging and Marking

Continuation of Inspection and Acceptance

Overall Contract Inspection/Acceptance Locations

0001 Inspection and Acceptance Location

Both Destination Instructions: Refer to Performance Work Statement (PWS)

DoDAAC: W913E5 CountryCode: USA

W2R2 COLD RGNS RSCH ENG LAB

KO CONTRACTING OFFICE VCCO, 72 LYME ROAD

HANOVER, NH 03755-1290

UNITED STATES

Harwood Bartlett Email: Bartlett.Harwood@usace.army.mil Telephone: 603-646-4608

0002 Inspection and Acceptance Location

Both Destination Instructions: Refer to Performance Work Statement (PWS)

DoDAAC: W913E5 CountryCode: USA

W2R2 COLD RGNS RSCH ENG LAB

KO CONTRACTING OFFICE VCCO, 72 LYME ROAD

HANOVER, NH 03755-1290

UNITED STATES

Bartlett Harwood Email: Bartlett.Harwood@usace.army.mil Telephone: 603-646-4608

0003 Inspection and Acceptance Location

Both Destination Instructions: Refer to Performance Work Statement (PWS)

DoDAAC: W913E5 CountryCode: USA

W2R2 COLD RGNS RSCH ENG LAB

KO CONTRACTING OFFICE VCCO, 72 LYME ROAD

HANOVER, NH 03755-1290

UNITED STATES

Bartlett Harwood Email: Bartlett.Harwood@usace.army.mil Telephone: 603-646-4608

Continuation of Deliveries or Performance

0001 Delivery Schedule Delivery Period From 26 Jan 2026 to 27 Feb 2026

1 JobQuantity

Address and POC Place of Performance DoDAAC: W14GQK CountryCode: USA

W2R2 COLD RGNS RSCH ENG LAB

SUPPLY SECTION, 72 LYME ROAD HANOVER, NH 03755-1290 UNITED

STATES

BARTLETT HARWOOD,III, DELIVER_TO_EMP_ID_NO

Email: BARTLETT.HARWOOD@USACE.ARMY.MIL

Period of Performance From 26 Jan 2026 To 27 Feb 2026

0002 Delivery Schedule Delivery Period From 26 Jan 2026 to 31 Jul 2026

1 JobQuantity

Address and POC Place of Performance DoDAAC: W14GQK CountryCode: USA

W2R2 COLD RGNS RSCH ENG LAB

SUPPLY SECTION, 72 LYME ROAD HANOVER, NH 03755-1290 UNITED

STATES

BARTLETT HARWOOD,III, DELIVER_TO_EMP_ID_NO

Email: BARTLETT.HARWOOD@USACE.ARMY.MIL

Period of Performance From 26 Jan 2026 To 31 Jul 2026

0003 Delivery Schedule Delivery Period From 01 Jun 2026 to 31 Jul 2026

1 JobQuantity

Address and POC Place of Performance DoDAAC: W14GQK CountryCode: USA

W2R2 COLD RGNS RSCH ENG LAB

SUPPLY SECTION, 72 LYME ROAD HANOVER, NH 03755-1290 UNITED

STATES

Bartlett Harwood III Email: Bartlett.Harwood@usace.army.mil Telephone: 603-646-4608

Period of Performance From 01 Jun 2026 To 31 Jul 2026

Continuation of Accounting and Appropriation Data

INVOICING INSTRUCTIONS:

A proper invoice must include the below listed items. Invoices missing any of these elements will be rejected.

Name and address of the contractor (must match SAM registration information) Invoice date and invoice number Contract number (ex., W913E526P0000) Exact dollar values requested against specific CLINs (aka "Item No" in Section B).

Description, quantity, unit of measure, unit price, and extended price of supplies delivered, or services performed Shipping and payment terms (e.g., shipment number and date of shipment, discount for prompt payment terms) Any other supporting materials required by the contract to be sent with the invoice

If this is a supply contract delivering supply items to CRREL as contract deliverables, Contractors shall only submit invoices once the shipment has been received by CRREL as verified by shipment tracking numbers. Invoices submitted prior to receipt of the shipment at CRREL will be rejected.

The Contractor shall submit each invoice via email to the following POCs. Failure to include these POCs may result in payment delays.

To: Primary Invoice Receivers: TBD at time of award

Cc: Backup Invoice Receiver: CRREL-Contractor-Invoices@usace.army.mil

The Contractor should receive CRREL's confirmation of invoice acceptance or rejection within seven (7) days of submission. If this has not occurred, please 'reply all' to the original invoice email sent to CRREL to obtain a status update. It is important to always include CRREL-on invoice related emails.Contractor-Invoices@usace.army.mil

If more than one (1) invoice is required, the Contractor's final invoice shall be submitted within forty-five (45) days after the final period of performance date specified in the contract. The invoice must be clearly marked "FINAL" and submitted as outlined above.

*** END OF NARRATIVE 1 ***

mailto://CRREL-Contractor-Invoices@usace.army.mil mailto://CRREL-Contractor-Invoices@usace.army.mil mailto://CRREL-Contractor-Invoices@usace.army.mil

Contract Clauses

FAR Clauses Incorporated by Reference

Number Title Effective Date

Alternate Deviation

Variation Effective Date

52.204-13 System for Award Management Maintenance.

2018-10

52.204-18 Commercial and Government Entity Code Maintenance.

2020-08

52.212-4 Contract Terms and Conditions- Commercial Products and Commercial Services.

2023-11

DFARS Clauses Incorporated by Reference

Number Title Effective Date

Alternate Deviation

Variation Effective Date

252.203-7000 Requirements Relating to Compensation of Former DoD Officials.

2011-09

252.203-7002 Requirement to Inform Employees of Whistleblower Rights.

2022-12

252.204-7004 Antiterrorism Awareness Training for Contractors.

2023-01

252.204-7012 Safeguarding Covered Defense Information and Cyber Incident Reporting.

2024-05

252.204-7015 Notice of Authorized Disclosure of Information for Litigation Support.

2023-01

252.204-7018 Prohibition on the Acquisition of Covered Defense Telecommunications

2023-01

Equipment or Services.

252.204-7020 NIST SP 800-171 DoD Assessment Requirements.

2023-11

252.223-7008 Prohibition of Hexavalent Chromium. 2023-01

252.225-7001 Buy American and Balance of Payments Program.

2024-02

252.225-7056 Prohibition Regarding Business Operations with the Maduro Regime.

2023-01

252.225-7060 Prohibition on Certain Procurements from the Xinjiang Uyghur Autonomous Region.

2023-06

252.232-7003 Electronic Submission of Payment Requests and Receiving Reports.

2018-12

252.232-7010 Levies on Contract Payments. 2006-12

252.244-7000 Subcontracts for Commercial Products or Commercial Services.

2023-11

252.247-7023 Transportation of Supplies by Sea. 2024-10

DFARS Clauses Incorporated by Full Text

Date

Alternate Deviation

Variation Effective Date

252.232-7006 Wide Area WorkFlow Payment Instructions.

2023-01

SEE SECTION FOR INSTRUCTION ON HOW TO SUBMIT INVOICING INSTRUCTION

INVOICES

Addendum to 52.212-4, Contract Terms and Conditions - Commercial Products and Commercial Services

Contract Terms and Conditions Required To Implement Statutes or Executive Orders — Commercial Products and Commercial Services

FAR Clauses Incorporated by Full Text

Number Title Effective Date

Alternate Deviation

Variation Effective Date

52.212-5 Contract Terms and Conditions Required to Implement Statutes or Executive Orders - Commercial Products and Commercial Services. (DEVIATION 2025-O0003 and 2025-O0004)

2025-10 Deviation 2025- O0004

2025-03

Contract Terms and Conditions Required To Implement Statutes or Executive Orders- Commercial Products and Commercial Services (MAR 2025) (DEVIATION 2025-O0003 and 2025-O0004)

(a) The Contractor shall comply with the following Federal Acquisition Regulation (FAR) clauses, which are incorporated in this contract by reference, to implement provisions of law or Executive orders applicable to acquisitions of commercial products and commercial services:

(1) 52.203-19, Prohibition on Requiring Certain Internal Confidentiality Agreements or Statements (Jan 2017) (section 743 of Division E, Title VII, of the Consolidated and Further Continuing Appropriations Act, 2015 (Pub. L. 113-235) and its successor provisions in subsequent appropriations acts (and as extended in continuing resolutions)).

(2) 52.204-23, Prohibition on Contracting for Hardware, Software, and Services Developed or Provided by Kaspersky Lab Covered Entities (Dec 2023) (Section 1634 of Pub. L. 115-91).

(3) 52.204-25, Prohibition on Contracting for Certain Telecommunications and Video Surveillance Services or Equipment. (Nov 2021) (Section 889(a)(1)(A) of Pub. L. 115-232).

(4) 52.209-10, Prohibition on Contracting with Inverted Domestic Corporations (Nov 2015).

(5) 52.232-40, Providing Accelerated Payments to Small Business Subcontractors (Mar 2023) (31 U.S.C. 3903 and 10 U.S.C. 3801).

(6) 52.233-3, Protest After Award (Aug 1996) (31 U.S.C. 3553).

(7) 52.233-4, Applicable Law for Breach of Contract Claim (Oct 2004) (Public Laws 108-77 and 108-78 ( 19 U.S.C. 3805 note)).

(b) The Contractor shall comply with the FAR clauses in this paragraph (b) that the Contracting Officer has indicated as being incorporated in this contract by reference to implement provisions of law or Executive orders applicable to acquisitions of commercial products and commercial services:

[Contracting Officer check as appropriate.]

[ ] (1) 52.203-6, Restrictions on Subcontractor Sales to the Government (Jun 2020), with Alternate I (Nov 2021) (41 U.S.C. 4704 and 10 U.S.C. 4655).

[ ] (2) 52.203-13, Contractor Code of Business Ethics and Conduct (Nov 2021) (41 U.S.C.

3509)).

[ ] (3) 52.203-15, Whistleblower Protections under the American Recovery and Reinvestment Act of 2009 (Jun 2010) (Section 1553 of Pub. L. 111-5). (Applies to contracts funded by the American Recovery and Reinvestment Act of 2009.)

[ ] (4) 52.203-17, Contractor Employee Whistleblower Rights (Nov 2023) (41 U.S.C. 4712);

this clause does not apply to contracts of DoD, NASA, the Coast Guard, or applicable elements of the intelligence community-see FAR 3.900(a).

[X] (5) 52.204-10, Reporting Executive Compensation and First-Tier Subcontract Awards (Jun 2020) (Pub. L. 109-282) ( 31 U.S.C. 6101 note).

[ ] (6) [Reserved].

[ ] (7) 52.204-14, Service Contract Reporting Requirements (Oct 2016) (Pub. L. 111-117, section 743 of Div. C).

[ ] (8) 52.204-15, Service Contract Reporting Requirements for Indefinite-Delivery Contracts (Oct 2016) (Pub. L. 111-117, section 743 of Div. C).

[X] (9) 52.204-27, Prohibition on a ByteDance Covered Application (Jun 2023) (Section 102 of Division R of Pub. L. 117-328).

[ ] (10) 52.204-28, Federal Acquisition Supply Chain Security Act Orders-Federal Supply Schedules, Governmentwide Acquisition Contracts, and Multi-Agency Contracts. (Dec 2023) (Pub. L. 115-390, title II).

[ ] (11)

(i) 52.204-30, Federal Acquisition Supply Chain Security Act Orders-Prohibition. (Dec 2023) (Pub. L. 115-390, title II).

[ ] (ii) Alternate I (Dec 2023) of 52.204-30.

[X] (12) 52.209-6, Protecting the Government's Interest When Subcontracting With Contractors Debarred, Suspended, Proposed for Debarment, or Voluntarily Excluded. (Jan 2025) (31 U.S.C. 6101 note).

[ ] (13) 52.209-9, Updates of Publicly Available Information Regarding Responsibility Matters

(Oct 2018) (41 U.S.C. 2313).

[ ] (14) [Reserved].

[ ] (15) 52.219-3, Notice of HUBZone Set-Aside or Sole-Source Award (Oct 2022) (15 U.S.C.

657a).

[ ] (16) 52.219-4, Notice of Price Evaluation Preference for HUBZone Small Business Concerns (Oct 2022) (if the offeror elects to waive the preference, it shall so indicate in its offer) (15 U.S.C. 657a).

[ ] (17) [Reserved]

[X] (18)

(i) 52.219-6, Notice of Total Small Business Set-Aside (Nov 2020) (15 U.S.C. 644).

[ ] (ii) Alternate I (Mar 2020) of 52.219-6.

[ ] (19)

(i) 52.219-7, Notice of Partial Small Business Set-Aside (Nov 2020) (15 U.S.C. 644).

[ ] (ii) Alternate I (Mar 2020) of 52.219-7.

[X] (20) 52.219-8, Utilization of Small Business Concerns (Jan 2025)(15 U.S.C. 637(d)(2) and (3)).

[ ] (21)

(i) 52.219-9, Small Business Subcontracting Plan (Jan 2025) (15 U.S.C. 637(d)(4)).

[ ] (ii) Alternate I (Nov 2016) of 52.219-9.

[ ] (iii) Alternate II (Nov 2016) of 52.219-9.

[ ] (iv) Alternate III (Jun 2020) of 52.219-9.

[ ] (v) Alternate IV (Jan 2025) of 52.219-9.

[ ] (22)

(i) 52.219-13, Notice of Set-Aside of Orders (Mar 2020) (15 U.S.C. 644(r)).

[ ] (ii) Alternate I (Mar 2020) of 52.219-13.

[ ] (23) 52.219-14, Limitations on Subcontracting (Oct 2022) (15 U.S.C. 657s).

[ ] (24) 52.219-16, Liquidated Damages-Subcontracting Plan (Sep 2021) (15 U.S.C. 637(d)(4) (F)(i)).

[ ] (25) 52.219-27, Notice of Set-Aside for, or Sole-Source Award to, Service-Disabled Veteran-Owned Small Business (SDVOSB) Concerns Eligible Under the SDVOSB Program (Feb 2024) (15 U.S.C. 657f).

[X] (26)

(i) 52.219-28, Postaward Small Business Program Rerepresentation (Jan 2025) (15 U.S.C.

632(a)(2)).

[ ] (ii) Alternate I (Mar 2020) of 52.219-28.

[ ] (27) 52.219-29, Notice of Set-Aside for, or Sole-Source Award to, Economically Disadvantaged Women-Owned Small Business Concerns (Oct 2022) (15 U.S.C. 637(m)).

[ ] (28) 52.219-30, Notice of Set-Aside for, or Sole-Source Award to, Women-Owned Small Business Concerns Eligible Under the Women-Owned Small Business Program (Oct 2022) (15 U.S.C. 637(m)).

[ ] (29) 52.219-32, Orders Issued Directly Under Small Business Reserves (Mar 2020) (15 U.

S.C. 644(r)).

[ ] (30) 52.219-33, Nonmanufacturer Rule (Sep 2021) (15 U.S.C. 637(a)(17)).

[X] (31) 52.222-3, Convict Labor (Jun 2003) (E.O.11755).

[X] (32) 52.222-19, Child Labor-Cooperation with Authorities and Remedies (Jan 2025)(E.O.

13126).

[ ] (33) [Reserved]

[ ] (34) [Reserved]

[ ] (35)

(i) 52.222-35, Equal Opportunity for Veterans (Jun 2020) (38 U.S.C. 4212).

[ ] (ii) Alternate I (Jul 2014) of 52.222-35.

[X] (36)

(i) 52.222-36, Equal Opportunity for Workers with Disabilities (Jun 2020) (29 U.S.C. 793).

[ ] (ii) Alternate I (Jul 2014) of 52.222-36.

[ ] (37) 52.222-37, Employment Reports on Veterans (Jun 2020) (38 U.S.C. 4212).

[ ] (38) 52.222-40, Notification of Employee Rights Under the National Labor Relations Act

(Dec 2010) (E.O. 13496).

[X] (39)

(i) 52.222-50, Combating Trafficking in Persons (Nov 2021) (22 U.S.C. chapter 78 and E.O.

13627).

[ ] (ii) Alternate I (Mar 2015) of 52.222-50 (22 U.S.C. chapter 78 and E.O. 13627).

[ ] (40) 52.222-54, Employment Eligibility Verification (Jan 2025) (Executive Order 12989).

(Not applicable to the acquisition of commercially available off-the-shelf items or certain other types of commercial products or commercial services as prescribed in FAR 22.1803.)

[ ] (41)

(i) 52.223-9, Estimate of Percentage of Recovered Material Content for EPA-Designated Items (May 2008) ( 42 U.S.C. 6962(c)(3)(A)(ii)). (Not applicable to the acquisition of commercially available off-the-shelf items.)

[ ] (ii) Alternate I (May 2008) of 52.223-9 (42 U.S.C. 6962(i)(2)(C)). (Not applicable to the acquisition of commercially available off-the-shelf items.)

[ ] (42) 52.223-11, Ozone-Depleting Substances and High Global Warming Potential Hydrofluorocarbons (May 2024) (42 U.S.C. 7671, et seq.).

[ ] (43) 52.223-12, Maintenance, Service, Repair, or Disposal of Refrigeration Equipment and Air Conditioners (May 2024) (42 U.S.C. 7671, et seq.).

[ ] (44) 52.223-20, Aerosols (May 2024) (42 U.S.C. 7671, et seq.).

[ ] (45) 52.223-21, Foams (May 2024) (42 U.S.C. 7671, et seq.).

[ ] (46) 52.223-23, Sustainable Products and Services (MAR 2025) (DEVIATION 2025- O0004)) (7 U.S.C. 8102, 42 U.S.C. 6962, 42 U.S.C. 8259b, and 42 U.S.C. 7671l).

[ ] (47)

(i) 52.224-3 Privacy Training (Jan 2017) (5 U.S.C. 552 a).

[ ] (ii) Alternate I (Jan 2017) of 52.224-3.

[ ] (48)

(i) 52.225-1, Buy American-Supplies (Oct 2022) (41 U.S.C. chapter 83).

[ ] (ii) Alternate I (Oct 2022) of 52.225-1.

[ ] (49)

(i) 52.225-3, Buy American-Free Trade Agreements-Israeli Trade Act (NOV 2023) (19 U.S.C.

3301 note, 19 U.S.C. 2112 note, 19 U.S.C. 3805 note, 19 U.S.C. 4001 note, 19 U.S.C.

chapter 29 (sections 4501-4732), Public Law 103-182, 108-77, 108-78, 108-286, 108-302, 109-53, 109-169, 109-283, 110-138, 112-41, 112-42, and 112-43.

[ ] (ii) Alternate I [Reserved].

[ ] (iii) Alternate II (Jan 2025) of 52.225-3.

[ ] (iv) Alternate III (Feb 2024) of 52.225-3.

[ ] (v) Alternate IV (Oct 2022) of 52.225-3.

[ ] (50) 52.225-5, Trade Agreements (NOV 2023) (19 U.S.C. 2501, et seq., 19 U.S.C. 3301 note).

[X] (51) 52.225-13, Restrictions on Certain Foreign Purchases (Feb 2021) (E.O.'s, proclamations, and statutes administered by the Office of Foreign Assets Control of the Department of the Treasury).

[ ] (52) 52.225-26, Contractors Performing Private Security Functions Outside the United States (Oct 2016) (Section 862, as amended, of the National Defense Authorization Act for Fiscal Year 2008; 10 U.S.C. Subtitle A, Part V, Subpart G Note).

[ ] (53) 52.226-4, Notice of Disaster or Emergency Area Set-Aside (Nov…

This is the start of the file's text. The full file is on GovTribe.

File details come from the government source that posted it. Updated .