B08_Attachment_1_-_Statement_of_Work_(2).pdf

PDF 139 KB Posted

Attached to
Cape Cod National Seashore - Marconi HQ Solar Arra Federal contract opportunity
Solicitation number
140P4325R0032
Issued by
Department of the Interior National Park Service Northeast Region

About this file

This Statement of Work (SOW) details a solar array installation project at the Marconi Headquarters in Wellfleet, MA for the Cape Cod National Seashore. The project requires a complete turnkey installation of a 20 kW ground-mounted photovoltaic system, including site preparations, engineering, procurement, and construction. The contractor must obtain all necessary permits, conduct utility verifications, perform system calculations, and secure Eversource interconnection approval, ensuring compliance with International Building Codes, NEC 2023, and Massachusetts State Electrical Code.

The SOW includes four optional line items: (1) cedar split rail fencing, (2) a photovoltaic system monitor, (3) a prefabricated weatherproof enclosure installation, and (4) removal and disposal of existing concrete footings. The project has a 214-calendar-day performance period, and the work must be scheduled to minimize disruption to daily park operations. All power outages must be pre-scheduled and conducted on weekends. Final project acceptance is contingent upon obtaining Eversource's written interconnection approval and demonstrating successful system operation.

View the file

Other files for this federal contract opportunity

Other files attached to Cape Cod National Seashore - Marconi HQ Solar Arra, newest first.
File Type Posted
Sol_140P4325R0032_Amd_0002.pdf PDF
Attachment_11_-_RFIs_1-3_0002.pdf PDF
Sol_140P4325R0032_Amd_0001.pdf PDF
B08_Attachment_4_-_Drawings_2_of_5.pdf PDF
B08_Attachment_5_-_Drawings_3_of_5.pdf PDF
B08_Attachment_9_Construction_Contract_Administration.docx DOCX document
Sol_140P4325R0032.pdf PDF
A06_CACO_237974_Final_SD_Spec_R2_v2.pdf PDF
B08_Attachment_7_-_Drawings_5_of_5.pdf PDF
B08_Attachment_6_-_Drawings_4_of_5.pdf PDF
B08_Attachment_10_-_Limitation_on_Subcontracting_Report.xlsx XLSX spreadsheet
B08_Attachment_3_-_Drawings_1_of_5.pdf PDF
B08_Attachment_8_-_Davis_Bacon_Wage_Rates_-_5-16-2025_MA20240001.pdf PDF
Show all 13

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

STATEMENT OF WORK

PMIS 237974

SOLAR ARRAY MARCONI HEADQUARTERS

1.0 INTRODUCTION

This project’s purpose is to provide all site preparations, grading, grubbing (removal of stumps, root systems, and vegetation), and all engineering, procurement, and construction (EPC) required to provide a fully operational, utility-approved three phase, 20 kW ground-mounted photovoltaic system. The contractor shall be solely responsible for the complete turnkey installation of the photovoltaic system, including calculations, engineering, shop drawings, procurement, construction, commissioning, and obtaining final Eversource approval. The contractor shall obtain and secure all necessary permits, approvals, and agreements, including final Eversource interconnection approval. This work includes coordinating power outages for tie-ins, conducting utility verification using ground-penetrating radar, and performing a land survey to locate and verify existing hydrants, valves, transformers, and cleanouts. The contractor shall be responsible for all system calculations, including load flow, voltage drop, fault current analysis, and system performance modeling, ensuring compliance with International Building Codes, NEC 2023, Massachusetts State Electrical Code (527 CMR 12.00), and Eversource utility standards. Final project acceptance and payment shall be contingent upon obtaining Eversource’s written approval for system interconnection and demonstrating successful system operation.

Option 1 will provide cedar spilt rail fence and gate in accordance with specification 32 82 60, Wood Fencing, and applicable contract provisions at the perimeter of the photovoltaic system

Option 2 will provide a photovoltaic system monitor (Modbus TCP/IP) in accordance with specification 25 50 00, Building Automation and Control Specifications and applicable contract provisions.

Option 3 will provide the turn-key installation of a factory-built, prefabricated, weatherproof, walk-in style enclosure with foundation. Work shall be in accordance with specification 13 12 00, Enclosure, and applicable contract provisions.

Option 4 will provide a unit cost for the removal and off site disposal of existing concrete footings, block foundation walls or other conglomerated solid materials, measuredon a per cubic yard basis

The contractor shall schedule and sequence work to ensure that daily park operations are not negatively impacted. All power outages shall be scheduled in advance and on weekends per the contract documents.

The project location is the Marconi Headquarters Building and its adjoining site, 99 Marconi Station Road, Wellfleet MA 02667.

The period of performance for the base contract is 214 calendar days.

The periods of performance for Options 1-4 are within the base period of performance.

--END--