B08_-_Attachment_1_-_SOW_FOWA_-_Termite_and_Drywall.pdf

PDF 3 MB Posted

Attached to
NACE REPAIR TERMITE DAMAGE FOWA
Solicitation number
140P3026Q0045
Issued by

About this file

This is a Statement of Work for termite assessment and treatment, and removal and replacement of damaged drywall at Fort Washington Park for the National Park Service.

The contract encompasses two interdependent scopes awarded as a single contract. Scope A requires comprehensive termite inspection, assessment, and treatment of two historic buildings using EPA-approved liquid termiticides, including interior and perimeter treatment, trenching, drilling, and injection to establish continuous treatment barriers while protecting historic materials and finishes. Work includes documentation of infestation conditions, moisture readings, treatment locations, mitigation of conducive conditions, coordination with NPS staff, and restoration of disturbed areas. Scope B requires removal and replacement of damaged drywall, insulation, and framing components (wooden ceiling joists and studs) in four rooms total across the two buildings (two lower level and two upper level). This includes selective demolition, protection of adjacent historic fabric, dust containment, installation of new gypsum board systems per ASTM standards using 5/8-inch Type X and moisture-resistant boards, finishing to Level 4 or Level 5, application of low-VOC primer, and matching existing wall planes, textures, trim profiles, and finishes. Work is located at Fort Washington Park, 13551 Fort Washington Road, Fort Washington, Maryland.

The contractor must perform a mandatory pre-bid site walk-through and shall be responsible for all labor, materials, equipment, supervision, field verification of quantities, permits, waste disposal, and site restoration. Work must proceed no later than 15 days after award, during normal business hours of 7:30 a.m. to 4:30 p.m., Monday through Friday, excluding Federal holidays. The contractor must comply with NPS Integrated Pest Management standards, OSHA requirements, environmental protection procedures, and all applicable federal, state, and local regulations. Key deliverables include pre-project plans (product data sheets, SDS, project schedules, dust control plans, quality control plans, and finish samples) and closeout documentation (final inspection reports, warranty certificates, and waste disposal records). The COR or authorized park management representative will review deliverables and notify the contractor of findings within 15 business days of normally scheduled review.

View the file

Other files

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Statement of Work Fort Washington Park - NACE

Scope A - Termite Assessment and Treatment Scope B – Removal and Replacement of Damaged Drywall

Required Services. The contractor shall provide all labor, materials, equipment, supervision, and technical expertise necessary to perform the two services as described herein under Section 2 of the Project Specific Requirements. This statement of work includes Scope A (Termite Assessment and Treatment) and Scope B (Removal and Replacement of Damaged Drywall.)

These scopes are interdependent and will be awarded as a single contract. The Contractor shall be responsible for managing and performing both scope areas, including any subcontracted effort.

Scope A – The Contractor shall inspect, treat, and control termite infestation in two historic buildings located at Fort Washington Park. Services shall include comprehensive termite inspection and assessment; interior and perimeter treatment using EPA-approved liquid termiticides; trenching, drilling, and injection as required to establish a continuous treatment barrier; and implementation of low-impact treatment methods that protect historic materials and finishes. Work shall also include documentation of infestation conditions, moisture readings, and treatment locations; mitigation of conditions conducive to termite activity where feasible;

coordination with National Park Service (NPS) staff to protect historic resources and maintain visitor safety; and restoration of disturbed areas following treatment. All work shall be performed by licensed pest control professionals in accordance with applicable federal, state, and National Park Service Integrated Pest Management (IPM) standards. Refer to Appendix A – Scope A Site Photos and Plans for initial reference. Photos shall not be used in place of a required site visit prior to bid.

Scope B – The Contractor shall remove and replace damaged drywall, insulation, and associated framing components, including wooden ceiling joists and studs, in two historic buildings located at Fort Washington Park (four rooms total, two lower level and two upper level.) Services shall include field verification of existing conditions; selective demolition and removal of deteriorated materials; protection of adjacent historic fabric; and preparation of work areas, including dust containment, ventilation, and safeguarding of architectural features. Work shall further include installation of new gypsum board systems in accordance with ASTM and other required standards, including 5/8-inch Type X and moisture-resistant boards as appropriate; fastening, taping, joint treatment, sanding, and finishing to Level 4 or Level 5 as required; and application of low-VOC primer to all new surfaces. The contractor shall match existing wall planes, textures, trim profiles, and finishes to maintain the character of the structure and shall prepare and obtain approval of finish mock-ups prior to full installation. Refer to Appendix B – Scope B Site Photos and Plans for initial reference. Photos shall not be used in place of a required site visit prior to bid.

Location of Work.

Fort Washington Park – Interior of Fort Washington 13551 Fort Washington Road Fort Washington, MD

20744

Pre-Bid Site Survey A pre-bid site walk-through must be performed prior to bid with Contracting Officer’s Representative or other authorized park management representative present. Any provided site plans, maps, or photos cannot be used as a substitute for a site visit.

Period of Performance Work is expected to proceed no later than 15 days after award. If this timeline needs to be amended, changes must be coordinated directly with the Contracting Officer that awarded the bid.

1. General Requirements

• Site to be left clean and orderly at the end of each day. No materials are to be left onsite that are not easily secured. The park assumes no liability for any equipment not properly secured that is stolen, missing, or damaged over the course of the contract period of performance.

• Disposal of any demolished building, site, or landscape materials will be done in accordance with applicable state and local laws. Park waste management facilities may not be used for disposal of any construction material.

• Site is to be closed to all visitors and vehicle traffic while work is being performed as well as while the site is left unattended. This is to be done with signage and appropriate, neatly placed closures such as stanchions, construction fencing, cones, or other sturdy materials.

• The contractor must exercise care and caution in all activities performed on or near historic structures, landscapes, and other NPS properties. Measures must be taken to protect the landscape and surrounding areas from damage during the execution of the work, ensuring that no harm comes to the landscapes, sites, or park structures throughout the project.

• Contractor is to stop work and alert the park’s contracting officer representative (COR) or other authorized management representatives of any accidental damage immediately so that it can be documented and handled according to proper NPS procedure.

• Contractor will be held responsible for all restoration of the site, both landscape and building, if damaged while work is performed. The restoration must bring the worksite to the appearance and condition that existed prior to the work being performed. The contractor is responsible for cleanup, removal, and disposal of any debris associated with their installation of equipment and restoration of the building if damaged.

• All planned service interruptions must be coordinated with the park, and the time-of-service interruption must be as short as possible. The park shall be notified of any scheduled utility or access interruptions as early as possible, but no less than 48 hours prior to any planned interruption. The contractor is expected to inform the government as soon as it is known that there may be an unplanned interruption.

2. Project Specific Requirements

2.1 Scope A – Termite Assessment and Treatment

2.1.1 Site Preparation

• Coordinate work activities with NPS site management and cultural resource staff prior to mobilization.

• Identify and mark all utilities, drainage features, historic fabric, and sensitive landscape features prior to trenching or drilling.

• Protect historic materials including masonry, wood finishes, fireplaces, trim, and flooring using drop cloths, protective barriers, and dust containment methods.

• Remove furniture and loose materials from treatment areas.

• Ensure crawlspaces and lower rooms are accessible for inspection and treatment where possible.

• Establish containment measures to prevent chemical spills, soil displacement, or damage to surrounding historic landscape features.

• Implement moisture mitigation measures where feasible (temporary ventilation or dehumidification) in areas where water damage has been identified as contributing to termite activity.

• Ensure all personnel are briefed on historic preservation requirements and the need to minimize disturbance to historic materials.

2.1.2 Inspection and Assessment

• Conduct a detailed termite inspection of both buildings, both upper and lower rooms.

• Focus inspection on areas of known damage including the fireplace, ceiling area, and adjacent structural members.

• Inspect for potential concealed infestation given the presence of moisture damage that could contribute to termite activity.

• Inspect crawl spaces, sill plates, foundation walls, wood framing, and masonry interfaces.

• Record moisture levels and identify potential moisture sources such as drainage issues or wood-to-ground contact.

• Document findings with photographs and moisture readings.

• Identify inaccessible areas (crawl spaces, voids, or structural cavities) and recommend additional treatment methods where required.

• Provide a written report including:

o Evidence of infestation or damage o Conducive conditions (moisture, wood contact, soil conditions) o Recommended treatment methods and locations o Areas requiring monitoring or follow-up inspection.

o Documentation of areas that could not be accessed for treatment

2.1.3 Interior Treatment

• Drill and inject termiticide into affected areas where active termite activity or damage has been identified.

• Focus treatment on the fireplace structures, ceiling framing, and wall voids where infestations have been documented.

• Apply liquid termiticide to interior foundation walls, crawlspace perimeter areas, and structural members susceptible to infestation.

• Use low-pressure injection methods in wall voids to distribute treatment evenly without excessive drilling. Limit drilling locations and patch holes using materials compatible with historic finishes

• Avoid treatment methods that would damage or remove historic masonry, woodwork, or architectural features.

• Clean and restore treated surfaces following completion of interior work.

• Monitor interior moisture conditions and recommend mitigation measures where excessive moisture is detected.

2.1.4 Perimeter Treatment

• Establish a continuous treatment zone around each building foundation.

• Trench and drill along the building perimeter where necessary to access foundation soils.

• Apply liquid termiticide to soil to form a continuous barrier against subterranean termites.

• Use low-impact trenching methods to avoid damage to historic masonry, foundation stones, or adjacent landscape features.

• Drill through hard surfaces (such as walkways or masonry) only where required and patch surfaces to match original materials. Notify COR prior to any resource disturbance.

• Backfill trenches with treated soil and compact to original grade. Restore disturbed landscaping, turf, and site features to their original condition.

2.1.5 Moisture and Conducive Conditions

• Identify and document moisture sources contributing to termite activity.

• Report drainage issues, plumbing leaks, roof leaks, or ventilation deficiencies.

• Identify wood-to-soil contact conditions.

• Provide recommendations for moisture mitigation or structural repairs.

• Notify NPS if conditions exist that may cause reinfestation.

2.1.6 Materials and Labor

• Work must be completed by a licensed pest control technician experienced in treatment of historic structures.

• All work must comply with National Park Service Integrated Pest Management (IPM) practices.

• Professional-grade liquid termiticide must be used.

• Termiticide must comply with EPA regulations and NPS environmental standards.

• All chemicals must be approved for use in historic structures and near environmentally sensitive areas

• Provide Safety Data Sheets (SDS) for all products prior to application.

• All personnel must follow OSHA safety requirements and environmental protection procedures.

2.1.7 Temporary Controls and Public Coordination

• Coordinate treatment schedule with park management to minimize impacts to visitors and park operations.

• Post temporary warning signage and restrict access to treatment areas during application.

• Maintain safe pedestrian access around buildings during perimeter work.

• Implement temporary barriers or fencing where excavation or drilling occurs.

• Prevent chemical runoff into adjacent soil, drainage systems, or nearby natural resources.

• Conduct work during approved park operational hours unless otherwise authorized by

NPS.

2.1.8 Closeout

• Restore all disturbed areas, including landscaping, soil, walkways, and interior surfaces.

• Provide written documentation of treatment locations, chemicals used, and quantities applied.

• Provide updated diagrams indicating treated areas and monitoring locations.

• Submit inspection photographs and treatment records to NPS project management.

• Recommend a monitoring and follow-up inspection schedule (typically annually or as directed by NPS IPM program).

• Confirm that all historic materials have been protected and restored following treatment activities.

2.1.9 Monitoring and Follow-Up

• Install termite monitoring stations or bait stations around building perimeter where appropriate.

• Conduct follow-up inspection within 6–12 months after treatment.

• Provide recommendations for annual inspection.

2.1.10 Environmental Protection Measures

• Prevent pesticide runoff into storm drains, waterways, or natural resources.

• Do not apply pesticides during rainfall or when soil is saturated.

• Avoid treatment within specified buffer distances of water resources unless approved.

• Contain and clean up any spills immediately.

• Dispose of pesticide containers in accordance with federal and state regulations.

2.2 Scope B – Removal and Replacement of Damaged Drywall

2.2.1 Demolition and Removal

• Remove existing damaged drywall only in areas identified during site inspection and confirmed by the COR.

• Remove damaged or deteriorated wooden ceiling joists, studs, and associated framing members in areas identified during site inspection and confirmed by the COR. Provide temporary shoring or support as necessary to maintain structural stability during removal of joists or framing members.

• Remove damaged or contaminated insulation materials associated with affected wall and ceiling assemblies.

• Carefully remove drywall around fireplaces, trim, and architectural features where prior damage has been documented.

• Protect and retain any historic wood trim, molding, or adjacent finishes for reinstallation.

Avoid demolition methods that generate excessive vibration or could damage historic plaster, masonry, or wood elements wherever possible.

• Document extent of structural damage and notify the COR prior to removal of any load-bearing components.

• Maintain clean, controlled demolition practices to minimize dust migration.

• Dispose of removed framing and insulation materials in accordance with applicable regulations (see section 2.5 for specific requirements.)

2.2.2 Site Preparation

• Conduct pre-work walkthrough with NPS staff to verify work limits and identify sensitive historic features.

• Protect floors, fireplaces, trim, windows, and adjacent finishes using drop cloths, plastic sheeting, and rigid barriers as needed.

• Establish dust containment zones using polyethylene sheeting and sealed partitions.

• Ensure adequate ventilation is provided during demolition and installation.

• Store gypsum boards off the ground, protected from moisture and humidity.

• Acclimate drywall materials to interior conditions per manufacturer recommendations prior to installation.

• Verify condition of existing ceiling joists, studs, and insulation prior to installation of new drywall.

• Verify framing alignment and substrate condition before installing new drywall.

• Coordinate access routes and staging areas to minimize impact to park operations.

2.2.3 Hazard Mitigation

• Assume potential presence of hazardous materials (e.g., lead-based paint or asbestos-containing joint compound) unless confirmed otherwise,

• If hazardous materials are suspected or encountered, stop work immediately and notify the COR for further direction.

• Comply with all applicable federal, state, and NPS regulations regarding hazardous material handling.

• Implement dust control measures including HEPA-filtered equipment where required.

• Maintain indoor air quality during work using ventilation and containment.

• Ensure worker safety through use of appropriate PPE (respirators, gloves, eye protection).

• Prevent exposure of park visitors and staff to dust or contaminants.

2.2.4 New Construction

• Provide and install new wooden ceiling joists, studs, or framing members to replace removed components, matching existing dimensions, spacing, and configuration unless otherwise directed by the COR.

• New framing lumber shall meet applicable building code requirements and be compatible with existing historic construction.

• Install new insulation in wall and ceiling assemblies where removed, matching or improving upon existing thermal performance where feasible and appropriate for historic structures.

• Ensure all new framing is properly aligned, anchored, and integrated with existing structural systems. Any deviation from existing structural configuration must be reviewed and approved by the COR prior to installation.

• Coordinate framing installation with drywall installation to ensure proper support and finish quality.

• Install new drywall panels in accordance with ASTM C840 and GA-214 standards.

• Use 5/8” Type X gypsum board for fire-rated assemblies.

• Use moisture- and mold-resistant boards in areas subject to elevated humidity or moisture.

• Fasteners shall comply with ASTM C1002; joint compounds shall comply with ASTM

C475.

• Install panels to match existing wall planes, alignments, and transitions.

• Tape, mud, and sand joints to achieve:

o Level 4 finish for standard painted surfaces o Level 5 finish in high-visibility or critical lighting areas

• Match existing textures, reveals, trim profiles, and bead conditions to maintain historic character.

• Ensure proper integration with existing trim, baseboards, and architectural features.

• Apply one coat of high-quality, low-VOC primer to all new drywall surfaces.

• Ensure all work complies with applicable building codes and National Park Service standards.

2.2.5 Disposal

• Collect and remove all demolished drywall, debris, fasteners, and associated materials from the site.

• Dispose of materials offsite at an approved disposal facility in accordance with local, state, and federal regulations.

• Segregate and properly dispose of any hazardous materials if encountered.

• Maintain waste containers in a neat and secure manner to prevent debris dispersal.

• Leave work areas free of debris at the end of each workday.

2.2.6 Temporary Controls and Public Coordination

• Coordinate all work with NPS staff to minimize disruption to park operations and visitor access.

• Establish clearly marked work zones with signage and barriers to restrict public entry.

• Always maintain safe access routes around work areas.

• Limit noise-generating activities to approved hours.

• Implement dust and odor control measures to prevent migration into adjacent occupied spaces.

• Secure tools, materials, and equipment when not in use.

• Ensure compliance with NPS safety and operational requirements.

2.2.7 Closeout

• Clean all work areas, removing dust, debris, and construction materials.

• Restore all disturbed areas to original condition, including adjacent finishes and surfaces.

• Provide documentation confirming compliance with specified materials and standards.

• Submit product data and any applicable warranties.

• Conduct final walkthrough with NPS COR to verify completion and acceptance of work.

• Address any punch list items identified during final inspection.

• Ensure all finishes match existing conditions and meet quality expectations for historic structures.

3. Additional Requirements

3.1 Field Verification of Quantities Prior to Bid

• Contractors shall perform a mandatory site visit prior to bid submission to verify existing conditions and quantities of framing, insulation, and drywall requiring removal and replacement.

• Quantities provided in drawings, photos, or other documentation are approximate and for reference only.

• Contractor shall be responsible for field measuring all areas, confirming extents of damage, and identifying access constraints.

• Failure to perform field verification shall not be grounds for additional compensation.

• Contractor shall account for all labor, materials, protection, and coordination necessary to complete the work as described.

• Any discrepancies between observed conditions and contract documents shall be brought to the attention of the Contracting Officer’s Representative (COR) prior to bid submission.

3.2 Mock-Up of Finish Level and Texture (Scope B)

• Prior to full installation, the contractor shall prepare a mock-up demonstrating the proposed drywall finish level and texture.

• Mock-up shall include:

o Joint treatment (tape and compound) o Sanding and surface finish (Level 4 or Level 5 as specified) o Texture application, where applicable o Primer coat

• Mock-up shall be constructed in a location approved by the COR.

• Mock-up shall replicate existing adjacent wall conditions, including texture, sheen, and visual appearance.

• Work shall not proceed beyond mock-up until written approval is provided by the COR.

• Approved mock-up shall serve as the quality standard for the remainder of the project.

• Mock-up may remain in place as part of the finished work if acceptable to NPS.

3.3 Miscellaneous

• All work will be performed in a safe, professional manner according to accepted, required, and mandated industry standards.

• Contractor is responsible for all permits from State, County, or Local offices.

4. Deliverables

4.1 Scope A – Termite Assessment and Treatment

• Pre-Project o Product data sheets and Safety Data Sheets (SDS) for all pesticides o EPA registration numbers for proposed termiticides o Application methods and dilution rates.

o Treatment diagram showing proposed drilling and injection locations.

o Work plan describing protection of historic materials and finishes.

o Proof of pesticide applicator license and insurance.

o Spill response plan for pesticide handling.

o A plan detailing plan for protecting historic fabric and character defining features adjacent to work area. (ex. no penetrations in historic substrates without written approval, padded floor/wall protection in travel paths.)

o A site-specific health and safety plan for dust, debris, and containment. Assume potential for legacy hazards in historic facilities such as lead, asbestos, and silica.

o Delivery plans with vehicle sizes and arrival times, and backup plans for weather/access disruptions.

o Project schedule o Waste disposal plan detailing compliance with federal, state, and local regulations.

• Closeout o Final site inspection report signed by contractor and COR/authorized park management representative o Warranty certificates for minimum 1 year o Waste disposal records to demonstrate compliant disposal

4.2 Scope B – Removal and Replacement of Damaged Drywall

• Pre-Project o Project schedule.

o Delivery plans with vehicle sizes and arrival times, and backup plans for weather/access disruptions.

o A Quality Control plan outlining inspections for substrate prep, fastening, joint treatment, and finish level.

o Work plan describing installation methods, sequencing, and protection for historic materials, o Dust control and containment plan. Assume potential for legacy hazards in historic facilities such as lead, asbestos, and silica.

o Finish and texture samples of joint compound finish levels and outlined in section

3.

o Safety Data Sheet (SDS) for all coatings and primers o Waste disposal plan detailing compliance with federal, state, and local regulations.

o Submittal register o Temporary occupant/visitor detour plan and accessibility compliance checklist

• Closeout o Maintenance and warranty plan for newly installed materials and coatings o Final site inspection report signed by contractor and COR/authorized park management representative o Warranty certificates as applicable o Waste disposal records to demonstrate compliant disposal

In the absence of other agreements negotiated with respect to time provided for government review, deliverables will be inspected and the contractor notified of the COR or other authorized management representative findings within 15 business days of normally scheduled review. If the deliverables are not acceptable, the COR or other authorized management representative will notify contractor immediately.

5. Government Furnished Staff, Property, Materials & Supplies None.

6. Business Hours The contractor shall complete on-site work during normal business hours of 7:30 am to 4:30 pm, Monday through Friday, excluding Federal holidays. The contractor shall coordinate specific on-site work schedule with the Contracting Officer and Contracting Officer Representative five days prior to performance start date. While on site, the COR or authorized management representative may be reached by mobile phone during normal business hours. Any work outside of normal business hours shall be pre-approved by the COR or other authorized management representative.

7. Site Access and Use The NPS issues access to government property as needed. The contractor shall initiate and coordinate all necessary access approvals no later than 15 business days before the project’s start date.

Access and use of NPS sites and property is limited to scheduled execution of contract work only. Contractor personnel shall not:

a) enter closed sites outside of approved working hours

b) use access credentials such as keys or codes for any purposes other than authorized work

c) visit, tour, recreate, or otherwise remain on the site for personal reasons at the end of the workday unless entering as a private citizen in accordance with park visitation rules and regulations of applicable entrance fees and operating hours, Superintendents Compendium, and other policy and law

d) bring non-authorized personnel onto the site during working hours, or

e) use site facilities, roads, trails, vehicles, equipment, utilities, or communications systems for personal or non-work purposes.

Misuse of site access can result in removal from the site, revocation of access, or termination for cause. Contractors shall ensure all subcontractors and suppliers comply with this clause.

8. Performance Management The contractor shall manage the total work effort in accordance with effective and efficient management principles and safe working practices to ensure the successful completion of contract work. The contractor shall immediately bring problems or potential problems affecting performance to the attention of the COR or other authorized management representative.

Problems affecting a particular action should be resolved prior to starting the specific task.

10. Contracting Officer’s Representative or Authorized Park Management Representative [Name of COR or Authorize Park Management Representative.]

9. Onsite Project Manager [Name of COR, project manager, or other authorized park management representative. It is important to specify here if this person is not authorized to provide instruction to the contractors or answer questions that could alter the scope of the work being performed. This is designated only to the COR or Park POC.]

11. Safety & Environmental Compliance

• The contractor shall comply with pertinent provisions of the Occupational Safety and Health Act (OSHA), and state, local, safety, laws.

• The contractor shall comply with pertinent Environmental Protection Agency laws and regulations.

• The COR or authorized management representative has the authority to issue restraint or cease-and-desist orders to the contractor when violations or unsafe acts are present and threaten Government and contractor employees or damage Government property.

• The contractor shall immediately stop work and report officer all accidents resulting in employee injury or death or damage to property while performing this contract to the COR or other authorized management representative of all accidents resulting in employee injury or death or damage to property while performing this contract.

12. Applicable Standards and Regulations The Contractor shall conform to, and be compliant with, all applicable Federal Communications Commission (FCC) rules and regulations, local construction codes, and established industry standards. The standards shall be applied during the engineering, fabrication, assembly, wiring, installation, testing, operation, maintenance, and management of the system(s) and service(s). If a conflict arises between standards, the contractor shall submit written request for clarification citing the specific particulars to the Contracting Officer. The Contracting Offer will respond with written direction.

13. Insurance The Contractor shall be insured in accordance with Prince George’s County, Maryland insurance regulations. The Government is not responsible for damage to Contractor’s equipment, vehicles, tools or materials or their employees and the personal property brought on-site. The Government will not accept any liability due to contractor employee negligence.

Workers Compensation and Liability: The contractor shall maintain workers compensation insurance to the Contracting Officer for those employees performing work related to this contract and shall comply with the Workman’s Compensation Laws of Maryland. The Contractor shall maintain a level of insurance that will protect the contractor and the Government from any claims as a result of bodily injury (including death) and property damage which may arise from and during the performance of this contract.

14. Invoices Invoices must show item details or work order references. Invoices without correct details will be returned as improper invoices.

Appendix A – Scope A Site Photos and Plans

Figure 1 - Main House Plan with Locations of Work Taking Place on 1st Floor

Figure 2 - Main House Plan with Locations of Work Taking Place on 2nd Floor

Figure 3 - Ceiling Damage in Guard Room, Showing Termite Damage to Wood Ceiling Beams

Figure 4 - Window Damage in Guard Room, Showing Termite Damage to Wooden Sill and Frame

Figure 5 – Floor Access in Jail Area, Potentially for Previous Pest Treatment Use

Figure 6 - Fireplace Damage in Guard Room, Showing Termite Damage to Wooden Mantle

Appendix B – Scope B Site Photos and Plans

Figure 2 - Main House Plan with Locations of Work Taking Place on 1st Floor

Figure 2 - Main House Plan with Locations of Work Taking Place on 2nd Floor

Figure 3 - Ceiling Damage in Guard Room – Left Side from Entry

Figure 4 - Ceiling Damage in Guard Room – Detail of Left Side

Figure 5 - Ceiling Damage in Guard Room – Right Side from Entry

Figure 6 - Ceiling Damage in Guard Room – Right Side from Entry and Above Fireplace

Figure 7 - Guard Room Ceiling Damage from Left to Right

Figure 8 - Ceiling Damage in Jail - Right Side From Entry

Figure 9 - Ceiling Damage in Jail - Detail of Right Side

Figure 10 - Ceiling Damage in Jail - Detail of Right Side