This Statement of Work (SOW) details water tank repair and cathodic protection services for the National Park Service at Glacier Bay National Park in Gustavus, Alaska. The project involves comprehensive repairs to two potable water tanks manufactured by Aquastore Tank Systems (1991, 108,000-gallon capacity) and Fusion Tank (2001, 109,000-gallon capacity), located at Bartlett Cove. Specific technical requirements include draining and isolating tanks, conducting internal inspections, installing six high-potential magnesium sacrificial anodes, sealing observed leaks, applying manufacturer-approved sealants, and performing 48-hour hydrostatic tests. The contractor must have prior experience with potable water tank repairs and cathodic protection installation, provide comprehensive documentation, and follow strict confined space and environmental preservation protocols. The anticipated period of performance is September 1-30, 2025, with a 12-month warranty on all work and materials, and all deliverables required to be submitted by September 30, 2025.

View the file

Other files

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

STATEMENT OF WORK

NATIONAL PARK SERVICE

GLACIER BAY NATIONAL PARK & PRESERVE

WATER STORAGE REPAIRS

GUSTAVUS, ALASKA

April 1, 2025

Introduction: The work under this contract consists of repairing leaks and installing cathodic protection on 2 potable water tanks and appurtenances for the National Park Service (NPS) water facilities located at Bartlett Cove. These tanks exhibit signs of leakage at bolted lap seams and are experiencing early signs of coating degradation and metal loss in submerged areas. This project will implement manufacturer-recommended repairs to leaking lap seams and install a sacrificial cathodic protection system to extend the tank’s service life and preserve water quality. Glacier Bays Bartlett Cove is located next to the gateway community of Gustavus an off-highway city in Southeast Alaska.

The contractor is required to supply all materials, parts, tools, equipment and labor necessary to complete the stated work. All work will be performed under a single contract.

Description of site: The NPS tank facilities at Glacier Bay include:

Two bolted steel, glass-fused-to-steel type constructed potable water tanks with the following attributes:

Both tanks are open to the atmosphere and co-located at the same elevation at the top of a small hill. They are at the highest elevation point in the water system.

Both tanks stand approximately 29 feet in height and have an approximate diameter of 25 feet. The older tank was constructed in 1991 and was manufactured by Aquastore Tank Systems. It has a 108,000 gallon capacity according to its manufacturers design plate on the tank. The newer tank was constructed in 2001 and was manufactured by Fusion Tank. It has an estimated volume of 109,000 gallons.

Both tanks can be individually isolated off-line as necessary during cleaning work.

Both water tanks have roof man-way hatches 24 inches inside-diameter.

Both tanks have perimeter man-way ladders with locked safety cages starting at approximately 6 feet above ground level.

Objectives

The Contractor shall furnish the necessary personnel, material, equipment, and services (except as otherwise specified), to make leak repairs and add cathodic protection to two potable water tanks as specified in the description of tasks below.

During the performance of the work, the contractor shall provide adequate professional supervision and quality control to assure the accuracy, quality, completeness and progress of work.

It is the responsibility of the contractor to verify that all the information provided in this solicitation is accurate.

All work is to be completed in accordance with this Scope of Work and other Contract Documents, as well as all applicable Codes and Standards. Contractor shall, without additional expense to the Government, be responsible for obtaining necessary licenses and permits, and for complying with any and all applicable federal, state, and borough laws, codes, and regulations pertaining to the performance of the service that is to be rendered.

The Contractor shall take proper safety and health precautions to protect workers, the public, and property. The Contractor shall provide the Government all requested reports, and supporting material developed during the performance of the work. The Contractor shall provide adequate professional supervision and quality control to assure the accuracy, quality, completeness and progress of work.

Description of tasks: The work to be completed under this contract consists of the following:

West Tank:

• Drain and isolate the tank.

• Access interior via confined space procedures per OSHA 29 CFR 1910.146 and ANSI Z117.1.

• Install six (6) high-potential magnesium sacrificial anodes per AWWA D106 standards.

Each anode shall weigh ≥20 lbs, include 10' AWG #12 copper leads, and be tested for continuity and resistance per ASTM G97.

• Seal observed leak between shell ladder and rest platform in the upper shell.

• Perform full internal inspection with photo documentation and identify additional penetrations or seam failures.

• Inject tank-manufacturer-approved caulk to all leaking lap seams and bolt penetrations.

Products must be NSF-61 certified and compatible with glass-fused steel.

• Coordinate directly with Aquastore for proprietary sealing techniques, where required.

East Tank

• Drain if required based on leak location accessibility.

• Inspect and document all lap seam leaks and staining areas identified in prior reports.

• Apply sealant as per manufacturer’s recommendations from interior or exterior depending on location and severity.

• Re-engage loose or non-functional anchor bolts and verify all anchors are torqued to specification per AWWA D100 and ASCE 7-16.

• Ensure no disruption to intact exterior coating.

General Requirements for Both Tanks:

• Perform full photographic inspection pre- and post-repair.

• Maintain full compliance with confined space protocols.

• Seal and test all repairs with a 48-hour hydrostatic fill-and-hold test.

• Submit repair logs, sealant datasheets, and cathodic protection as-builts to COR.

General work requirements:

Required Contractor Qualifications: The contractor must document prior experience with Potable water tank repairs and cathodic protection installation and must submit a list of projects with references substantiating such experience.

Site Access: The Water tanks are accessible by road. Park security requires that all work and site visits must be prescheduled.

Schedule: A construction schedule shall be submitted and approved 3 weeks in advance of performing the work

Staging Area/Worksite Timeframes: Establishment of a construction camp is not permitted.

The contractor is responsible to provide written notification to the Contracting Officer detailing any staging area needs that will be requested from the National Park Service (NPS) in advance of work to allow time for resource coordination. The contractor staging area will be at the parking areas adjacent to the tanks as directed by the NPS. Generally, access to the work sites and assets will be allowed Monday through Friday 07:00 to 17:30. Other times may be allowed with prior written approval from the COR.

Preservation of Natural Features: Confine all operations to work limits of the project, approximate location shown on drawings. Prevent damage to natural surroundings. Do not fasten ropes, cables, or guide wires to existing trees. Wasting of water to the natural surroundings during tank repairs will not be permitted except as follows. The contractor shall be required to use a Dechlorination Bazooka during the repair process to allow for the disposal of tank water within the parks boundaries. Water wasted from the tanks during cleaning shall be discharged at the location where the tanks overflow piping discharges. Restore damaged areas, repairing or replacing damaged trees and plants, at no additional expense to the Government

Cleanup: The worksite and any onsite staging areas shall be a neat and workmanlike manner;

trash shall be disposed of daily. Once the work under this project is complete the contractor shall perform a final cleanup of all worksite and staging areas. The contractor shall remove and dispose of all damaged and unused material from site.

Contractor Furnished Items: All materials shall be new. Shop drawings of all components and details shall be submitted for written approval prior to any fabrication.

Government Furnished Items: Government will provide Dechlor Bazooka and Dechlor tablets

Re-performance of Service

When service performed does not conform to contract requirements, or when service was not performed in a specific area, the contractor shall perform or re-perform the service in conformity with contract requirements at no additional cost to the government.

Non-Payment for Additional Work

Any additional contractor performed services not specified in contract, either at its own volition or at the request of an individual other than an appointed Contracting Officer, except as may be explicitly authorized, shall be performed at the financial risk of the contractor. Only an appointed Contracting Officer is authorized to bind the Government to a change in specifications, contract terms, or conditions.

Quality Assurance

The Government may utilize a Quality Assurance Surveillance Plan (QASP) throughout the life of the contract to ensure that the Contractor is performing the services required by this Scope of Services in an acceptable manner. The use or nonuse of any quality assurance methods by the

Government will not constitute a waiver of or excuse from contract requirements. The Government may implement or change quality assurance measures at any time during the term of the contract. Surveillance methods may include 100% inspection, periodic inspection, random sampling, or customer input.

Warranty Period

The Contractor shall warranty all work and materials for 12 months after project closure.

Period of Performance

The anticipated period of performance for the resultant contract is from September 1, 2025- September 30, 2025. All work must be completed and deliverables received prior to September 30, 2025. Field drawings to be provided to COR within 10 days of project completion.

Submittals:

Submit the following a minimum of 15 days prior to mobilization:

• Anode specification sheets and performance design life data

• Caulking manufacturer’s datasheet and NSF certification

• Confined space entry and rescue procedures

POINT OF CONTACT:

Contracting Officer’s Representative (COR) for Technical Support:

TBD

Contracting Officer for Contractual Support:

TBD

SUBMIT INVOICE(S) TO:

Submit the original invoice to the Invoice Processing Platform (IPP), https://www.ipp.gov/ and a copy, via email, to the COR.

Monthly Progress payments shall be made on this Contract on estimates of work accomplished which meets the standards of quality established under the contract.

Partial Payment will not be authorized for this contract.

Contracting Officer’s Authority:

https://www.ipp.gov/

The Contracting Officer is the only person with the authority to act as agent of the Government under this contract. Only the Contracting Officer has authority to:

(1) direct or negotiate any changes in the Statement of Work or specifications;

(2) modify or extend the period of performance;

(3) change the delivery schedule; or

(4) otherwise change any terms and conditions of this contract.

The Contracting Officer is the only person authorized to make or approve any changes in any of the requirements of this contract and not withstanding any provisions contained elsewhere in this contract, the said authority remains solely in the Contracting Officer. In the event the Contractor makes any changes at the direction of any person other than the Contracting Officer, the change will be considered to have been made without authority and no adjustment will be made in the contract price to cover any increase in costs incurred as a result thereof.