This is a Price Schedule attachment for a road striping project at Yosemite National Park. The schedule details seven line items for various types of reflectorized road markings and associated services across multiple park roads and highway segments. Line items include centerline double yellow with black divide-reflectorized markings (69,985 linear feet), centerline broken white 4" reflectorized markings (39,400 linear feet), single solid yellow 4" shoulder reflectorized markings (39,000 linear feet), centerline broken yellow 4" reflectorized markings (7,200 linear feet), single solid white 4" shoulder line reflectorized markings (139,900 linear feet), and solid white 8" reflective markings (600 linear feet). The schedule also includes line items for sweeper costs and traffic control, both quoted on a lump sum (LS) basis. Specific road segments are identified for each marking type, including Curry Lane, Awahnee Road, Village Drive, Highway 41, Tioga Road, Chilnualna Falls Road, Hodgdon Meadow Road, Big Oak Flat tunnels, Southside Drive, Northside Drive, River Straight, and Happy Isle Loop.

The price schedule is associated with solicitation 140P8526Q0083, a Small Business set-aside Request for Quote issued by the National Park Service under NAICS code 237310 with a $45.0 million size standard. The construction magnitude is between $100,000 and $250,000. The contractor must provide all mobilization, labor, supervision, materials, equipment, transportation, site rehabilitation, cleanup, and demobilization. Proposals are due at 12:00 p.m. Pacific Standard Time on Thursday, August 20, 2026, via email only. Questions must be submitted to Brian Roppolo at brian_roppolo@nps.gov by August 13, 2026, with answers posted on SAM.gov.

View the file

Other files

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Sheet1

UNIT OF MEASUREQUANTITYUNIT PRICINGCOST
1.CENTERLINE DOUBLE YELLOW
WITH BLACK DIVIDE-REFLECTORIZED69,985.00
Curry 4-Way to StablesLF3,200.00
Awahnee RoadLF2,600.00
Village DriveLF3,400.00
Oak Lane and Lost Arrow RoadLF1,100.00
Highway 41 (Tunnel down to Valley Loop)LF5,300.00
Tioga Road (Hwy 120) Starting at Crane FlatLF13,200.00
Hodgdon Meadow RoadLF5,500.00
Chilnualna Falls To Boundary (Highway 41)LF28,500.00
Chilnualna Falls RoadLF4,500.00
Big Oak Flat Tunnel #3 (Upper)LF2,087.00
Big Oak Flat Tunnel #2 (Middle)LF227.00
Big Oak Flat Tunnel #1 (Lower)LF371.00
2.CENTERLINE BROKEN WHITE 4" REFLECTORIZED39,400.00
Southside Drive El Cap Cross to Curry 4-WayLF18,500.00
River Straight/Curry 4-Way to RoundaboutLF3,400.00
Northside Drive/ Sentinel Dr to El Cap CrossLF17,500.00
3.SINGLE SOLID YELLOW 4" SHOULDER REFLECTORIZED39,000.00
Southside Drive El Cap Cross to Curry 4-WayLF16,500.00
River Straight/Curry 4-Way to RoundaboutLF4,000.00
Northside Drive/ Sentinel Dr to El Cap CrossLF17,000.00
Highway 41 (Wawona Road)LF1,500.00
4.CENTERLINE BROKEN YELLOW 4" REFLECTORIZED7,200.00
Happy Isle LoopLF7,200.00
5.SINGLE SOLID WHITE 4" SHOULDER LINE REFLECTORIZED139,900.00
Southside Drive El Cap Cross to Curry 4-WayLF18,500.00
River Straight/Curry 4-Way to RoundaboutLF4,000.00
Awahnee RoadLF5,500.00
Village DriveLF1,400.00
Northside Drive/ Sentinel Dr to El Cap CrossLF17,500.00
Highway 41 (Tunnel down to Valley Loop)LF10,600.00
Tioga Road (Hwy 120) Starting at Crane FlatLF26,400.00
Chilnualna Falls To Boundary (Highway 41)LF56,000.00
Big Oak Flat Tunnel #3 (Upper)LF4,174.00
Big Oak Flat Tunnel #2 (Middle)LF454.00
Big Oak Flat Tunnel #1 (Lower)LF742.00
6SOLID WHITE 8" REFLECTIVE600.00
Crane Flat Tioga Road IntersectionLF600.00

7 SWEEPER COSTS LS 1

8 TRAFFIC CONTROL LS 1