B08_Attachment_1_Newport_Ram_Pump_Replacement_SOW.pdf
PDF 755 KB Posted
- Attached to
- NEWPORT OBSERVATORY RAM PUMP REPLACEMENT
- Solicitation number
- 140G0226Q0130
About this file
This is a Statement of Work (SOW) for the Newport Geomagnetic Observatory Ram Pump Replacement project issued by the United States Geological Survey (USGS) Geologic Hazards Science Center (GHSC).
The project involves replacing an existing ram pump water system with a redesigned electric pump and hydroelectric turbine system at the USGS Newport Magnetic Observatory in Newport, Washington (832 Geophysical Observatory Road, Newport, WA 99156). The work spans approximately 3,500 feet from a spring box on U.S. Forest Service land to a pumphouse near the observatory's front gate. The contractor must furnish all labor, materials, equipment, and supervision to complete the scope of work, which includes: demolishing the existing ram pump and associated vault infrastructure; installing a new electric pump system with a metal base plate; upgrading the spring box with new CMU blocks and cap; installing a new hydroelectric turbine on the spring box discharge flange; constructing a new aluminum electrical enclosure with battery boxes, charger/inverter, autotransformer, and grounding systems; installing new altitude valve in the pumphouse; and training onsite USGS personnel on operations and maintenance. The project site has no utility power support; the contractor must provide portable generators. Work shall be completed within 90 calendar days of the Notice to Proceed, excluding weekends and holidays unless preauthorized. Normal working hours are 7:00 a.m. to 6:00 p.m., Monday through Friday. The contractor must obtain a current Washington State contractor license, provide OSHA 10-hour or 30-hour Construction Safety training verification for all workers, conduct pre-bid and post-award site inspections, hold a pre-construction meeting within 7 business days of NTP, and deliver acceptance test certificates, operation and maintenance manuals, product guarantees/warranties, and a completed punch-list document. The water system is time-sensitive as it supports onsite contractor operations, and all delay requests require Contracting Officer approval. Primary USGS points of contact are Facility Manager Kristen Lewis (klewis@usgs.gov) and Onsite Representative Trevor Shaw (Trevorshaw_newport@yahoo.com); prospective bidders may only contact the Contracting Officer and Facility Manager regarding pre-proposal site visits during solicitation.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| Sol_140G0226Q0130.pdf | ||
| B08_Attachment_2_RamPumpReplacement-Dwgs.pdf | ||
| B08_Attachment_3_Wage_Determination.txt | TXT text file |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Statement of Work Newport Geomagnetic Observatory
Ram Pump Replacement
The United States Geological Survey (USGS) Geologic Hazards Science Center (GHSC) is seeking a contractor to replace the existing ram pump water system with a redesigned water system, consisting of an electric pump with hydroelectric turbine at the USGS Newport Magnetic Observatory, located in Newport, Washington.
Background The Geologic Hazards Science Center (GHSC) conducts research and operations in geology, geophysics, seismology, engineering seismology, geomagnetism, and geomechanics in order to assess seismic hazards and risk, geomagnetic hazards, and ground-failure hazards on regional, national, and international scales. The mission of the USGS Geomagnetism Program is to monitor the Earth’s magnetic field. Using ground-based observatories, the program provides continuous records of magnetic field variations covering long timescales; disseminates magnetic data to various governmental, academic, and private institutions; and conducts research into the nature of geomagnetic variations for purposes of scientific understanding and hazard mitigation.
The USGS operates a network of fourteen geomagnetic observatories in the continental U.S., Alaska, Puerto Rico, Hawaii, and Guam.
Project Description The span of the project site is from the spring box north of the Newport Observatory on U.S.
Forest Service (USFS) land (Fig. 1a, 1b) to the pumphouse near the front gate of the observatory, an approximate distance of 3,500’. The project site does not have any utility power support. The objective of this project is to replace the existing ram pump, located in the Ram Vault, replace it with the redesigned electric pump that will pump the water to a 720-gallon Balancing Tank (Fig. 2a, 2b).
Project Location:
Newport Magnetic Observatory 832 Geophysical Observatory Road Newport, Washington 99156
USGS Points of Contact:
Facility Manager (FM):
Onsite Representative (OR):
Kristen Lewis klewis@usgs.gov
Trevor Shaw Trevorshaw_newport@yahoo.com
During the solicitation/source-selection phase of this project, prospective contractors shall not contact any of the individuals listed above except for the Contracting Officer (CO) and for communication with the Facility Manager (FM) directly relevant to a pre-proposal site visit (if one is scheduled). Failure to comply with this prohibition may result in elimination from further consideration.
Note: The water that is provided by the pump system directly supports the livelihood of onsite contractors as well as the site's operations. Therefore, this project is time sensitive, and any delays may cause contractual changes and cost increases affiliated with the Newport Observatory. All delay requests shall be submitted to the CO for approval or rejection.
Plan for the storage tank to be full prior to the start of construction.
Hours of Operation:
Normal working hours shall be between 7:00am - 6:00pm, Monday – Friday. The contractor shall not work Saturdays, Sundays, legal holidays, or non-normal working hours unless otherwise authorized by the Contracting Officer. Requests to work times other than normal hours shall be made in writing. The government reserves the right to change the working hours when the need arises.
SCOPE OF WORK
1.) Pre-bid Site Inspection Interested bidders should observe/inspect the site prior to submitting a bid in order to be fully aware of the Scope of Services. Visiting the site allows the Contractor to verify the nature and quality of the work to be performed, to inform themselves of the general and local conditions, and to compare the specifications with the work to be performed. Failure to do so will not relieve the successful contractor of their responsibility for estimating properly the difficulty or cost of furnishing materials and successfully performing in accordance with the strict intent and meaning of the statement of work without additional cost to the Government. All measurements shall be field verified and are the responsibility of the contractor.
2.) Post-Award Site Investigation/Inspection Within seven (7) calendar days after issuance of the Notice to Proceed, the awarded Contractor will coordinate a ‘Site Inspection’ through the FM and OR to verify all dimensions/measurements and site conditions before start of the work or the ordering of any equipment, parts and/or materials. Failure of the Contractor to do so shall not relieve the Contractor from performing in accordance with the strict intent and meaning of the statement of work without additional cost to the Government. If the contractor finds any deficiencies from the statement of work, provide a written recommendation of a solution to the FM and CO for review and approval prior to commencing work. It is recommended that the contractor document the existing site conditions by taking photos with date and time stamps.
3.) Pre-construction Meeting A pre-construction meeting shall be held with the USGS FM, CO, and/or OR to discuss timelines, questions, and concerns and any possible preconceived changes regarding the project as a whole. The pre-construction meeting shall be held within 7 business days of the Notice to Proceed (NTP). Additional meetings will be scheduled as deemed necessary by the contractor or USGS officials.
4.) General Requirements
• Furnish all labor, materials, equipment, and supervision necessary to complete the scope of work of this project.
• Perform all demolition and installation according to A&E design drawings (NEW-
RamPumpReplacement-Dwgs), contract Scope of Work, and this document.
• Whenever a material, article, or piece of equipment is identified on the plans or in the specifications by reference to manufactures' or vendors' names, trade names, catalogue, numbers, etc., said identification is intended to establish a standard. Any material, article, or equipment of other manufacturers and vendors which will perform satisfactorily the duties imposed by the general design will be considered equally acceptable provided the material, article, or equipment so proposed, is in the opinion of the USGS, of equal quality, substance, and function. It shall not be purchased or installed by the Construction Contractor without the written approval of the CO.
• Test the new system to ensure compliance with project scope and design regulations.
Any issues will be corrected at no cost to the government.
• Train onsite USGS personnel or representatives on operations and future maintenance at end of construction phase.
o Training shall be documented and provided to Facility Manager as a required deliverable.
• Maintain surrounding land and structures. Reclaim/fix any damage that has been done at no cost to the government.
• Ensure no downstream contamination. If this occurs, the contractor will immediately notify the USGS and USFS of the incident. Contractor will also be responsible for the costs for cleanup, repairs, and any long-term damages incurred. This includes any kind of imposed litigation due to the contaminant exposure.
• Practice OSHA safety guidelines. All safety issues will be recorded and reported to the
USGS.
5.) Work Description
• Demolish the existing ram pump and associated pump vault piping, valves, metal base plate, and base plate anchors.
o Retain 4” inlet pipe at flange.
o Retain 2” outlet pipe at threaded connection.
• Identify any resale-value or scrapping of old ram pump to the USGS.
o Resale value greater than $1,500 shall be identified with support documentation.
Cost return exceeding $1,500 shall be submitted to the CO for contract price or service adjustments.
o Any no-cost scrapping/recycling of the old pump shall be identified through documentation supplied to the USGS.
• Demolish the existing spring box cover including inset air vent and manhole/cover.
• Demolish the upper layer of concrete masonry unit (CMU) blocks in the spring box.
o Break up CMU blocks to be used for rip rap splash pad at new spring box discharge outlet near pond.
• Clean and polish existing spring box discharge flange for attachment of new PVC discharge piping and electrical system grounding connection.
• Install new spring box wall layers and cover.
o Install 2 new layers of CMU blocks, increasing existing spring box height by 1 block.
o Install new spring box cap with inset 1-1/2” air vent and composite manhole cover/frame.
• Install new water pump system in pump vault.
o Install new electric pump and metal base plate.
o Install new pump controller and terminate connections in new junction box.
Calibrate pump controller to turn pump ON when 720-gallon balancing tank level is +3.0 feet, then turn pump OFF when balancing tank level is +6.0 feet.
o Install 1/2” conduit between junction box in pump vault and new electrical enclosure near spring box discharge flange connection.
o Install tees with mechanical freeze protection valves at pump suction and discharge lines.
Ensure that tee on suction side is fitted with check valve to prevent air ingress.
Ensure that freeze protection valves point downward for drainage during operation.
• Install new hydroelectric turbine on existing spring box discharge flange.
o Install flanged, gasketed, PVC connection to serve new hydroelectric turbine.
o Install new turbine discharge piping at minimum 1/4” per 12” slope down to new rip rap splash pad at pond.
Support discharge piping run with materials available on site, except where hung from electrical enclosure roof braces.
• Install new aluminum electrical enclosure with removable front plate, B decking roof, 4x4 lumber and concrete deck block foundation with leveling studs.
o Locate new electrical enclosure so that new hydroelectric turbine is beneath the overhang of the roof.
o Prepare enclosure footprint by addition of new gravel bed, minimum two (2) inches thick, manually compacted, and level within 1/8 inches per 1 foot.
o Set concrete deck blocks according to enclosure footprint. Adjust leveling studs until enclosure is level within 1/8 inches per 1 foot.
o Hang new PVC spring box discharge piping from enclosure overhang braces as required.
o Route all electrical penetrations through plastic cable glands at side of enclosure beneath overhang.
o Install two (2) new battery boxes upon angle supports in electrical enclosure using 2 fasteners per angle.
o Install two (2) new batteries in new boxes. Each will be Absorbent Glass Mat
(AGM) type, group 27M, 12VDC wired in series for 24VDC input/output, with 88 A-hr capacity minimum each. All battery cables will be 1/0 AWG, stranded copper, insulated, color- coded red for positive (+) and yellow for negative (-).
Make battery connections using tin-plated copper lugs, crimp style.
o Install new autotransformer, Victron Energy 32A. Configure for use with charger/inverter to output 240VAC/1ph/60Hz, line-line voltage.
o Install new charger/inverter, Victron Energy Easy Solar 24/1600/40.
Configure for charging of 24VDC battery bank, AGM batteries. Configure for 60 Hz inverter output. Install optional temperature sensor on battery bank.
o Route new 12/3 wire from electrical enclosure to pump vault in 1/2” conduit.
o Connect charger/inverter ground relay to autotransformer ground relay per manufacturer’s recommendations.
o Connect autotransformer chassis ground to enclosure ground boss using 8
AWG wire, stranded copper, insulated color green. Connect matching ground wire from ground boss to clean, bare metal surface of existing spring box discharge flange using new flange connection bolt. All grounding wire terminations will be made using tin-plated copper lugs, crimp style.
o Connect 8 AWG wire from ground boss to new, secondary grounding rod within 10 feet of electrical enclosure. Ground rod will be 10 feet long, 3/4-inch diameter, copper or copper-clad, using a bronze clamp for wire connection.
o Provide bird screens at all openings between B decking and side plates for rodent- proofing, while allowing for natural ventilation.
• Install new altitude valve in existing pump house, in water supply line between 720-gallon balancing tank and 30,000-gallon storage tank.
o Altitude valve will be Cla-Val model 210-01, calibrated to close when storage tank level is one (1) foot beneath top of tank.
6.) Contractor Responsibilities
• Coordinate any required utility outages with USGS POC’s a minimum of 72 hours in advance.
• Take all necessary precautions to prevent fires or injury to the public, building occupant(s), or damage to property of others during the performance of this contract.
• Furnish and install appropriate construction signs, caution tape and/or barricades around hazardous work areas.
• Thoroughly clean the work area at the end of each workday to ensure that tenants and employees of the site are not exposed to any unsafe conditions. Any additional steps to ensure safety taken during and after daily construction shall be considered and implemented by the contractor and their employees.
• All construction debris and rubbish shall be removed from the site daily and disposed of properly according to local, government and federal guidelines.
• The contractor shall provide a project supervisor to be at the work site at all times during construction.
• The contractor shall be responsible, at all times, for the supervision and control of the employees that may be assigned to render services under the contract. Fully qualified work personnel shall be available for work at the project’s beginning and shall be maintained throughout the period of performance. At all times, the work under this contract shall be carried out in such a way that there is minimum interference with Government activities.
• Limited parking space is available on site. The USGS shall designate a parking area (or areas) for the contractor to park vehicles. Vehicles shall be limited to only those vehicles established for contractor operations and supervisor use. At no time should vehicles drive beyond the paved surface of the parking area, unless approved by the USGS Facility Manager or Onsite Representative.
• The USGS Facility Manager shall designate areas where the contractor can store or place materials and equipment for short-term storage in preparation for installation.
There is no inside storage space available. Storage and security of materials and equipment as required for the performance of the contract is the responsibility of the contractor. The contractor shall be responsible for the cleanliness of these areas and their temporary facilities.
• Contractor is to provide toilet facilities for construction workers. Contractor is not to use the Owner's facilities. Bathrooms (Porta Johns) are to be located at the discretion of the onsite USGS Representative and/or Facility Manager.
• The contractor shall be responsible for making all arrangements for the receipt of materials and supplies at the job site. Government personnel are not permitted to receive or sign for items delivered to the site.
• Upon completion of the contract, the contractor shall remove all equipment and excess materials, and shall restore the site to its original condition as approved by the CO or Facility Manager. No additional cost to the government shall be incurred for site restoration.
• In any case of discrepancy in the specifications, the matter shall be immediately submitted to the CO, without whose decision said discrepancy shall not be adjusted by the Contractor, save only at his own risk and expense. Any changes affecting the scope of the work shall originate from and be approved by the CO.
• All contractor site personnel are required to make all human food, pet food, garbage, and other attractants unavailable to bears and other wildlife. All attractants should be stored inside vehicles or containers unless they are in immediate use. USGS will not be held liable for damage caused by wild animals to contractor personnel or equipment.
7.) Availability and use of Utility Services Electricity: In case the Contractor requires electricity while in performance of this
Contract, the Contractor shall provide and utilize portable generators as necessary to complete the work.
8.) Schedule The awarded contractor shall (a) commence work under this contract once given the Notice to Proceed (NTP) by the CO, (b) execute the work diligently, and (c) complete all work within 90 calendar days. Work shall exclude weekends and holidays unless preauthorized, in writing, from the CO. The time for completion shall include final cleanup, reclamation of site, confirmation of system operation and receipt of final deliverables.
The contractor shall provide a Project Schedule that shows events, timelines, and dates within 10 days of NTP. Any changes to the schedule shall be submitted to the CO.
9.) Construction Safety Contractor shall ensure that all onsite construction workers (including subcontractors) have completed the OSHA 10-hour Construction Safety training or the 30-hour Construction Safety training (for supervisor and/or managers), and other relevant competency training. The Contractor shall provide verification of such training to the Contracting Officer and the Facility Manager prior to mobilizing and at any time requested during the course of the work, until the contract is completed.
10.) Contractor Quality Control The Contractor’s Site Superintendent will:
• be on site, at all times, whenever work is being performed by Contractor or subcontractors’ employees to ensure adequate supervision and communication.
• review and approve submittals.
• inspect the quality of work performed.
• certify the completed work for payment and other purposes.
11.) Quality Assurance
a. All materials and workmanship shall be subject to the inspection and approval of the USGS CO, FM or OR. All work unsatisfactorily performed shall be promptly corrected and made acceptable to the Government at no extra cost.
b. The USGS CO, FM or OR shall perform final inspection and acceptance with the contractor upon completion of job performance.
c. Any instructions, specifications or warranties that will be needed to manage the project’s final product shall be submitted to the USGS CO before the punch list meeting and submittal of final payment.
Other Deliverables:
• Acceptance Test Certificate – document showing that the system has been tested
• Operation and Maintenance Manuals
• Contractor Product Guarantee and Warranty
• Punch-list Completed document
12.) Material Submittals Submittals with material data sheets shall be submitted for approval and shall not be ordered until submittal is approved by FM and CO. The contractor shall furnish all supplies, materials, and equipment necessary for performance and completion of the work included in this contract unless otherwise specified.
13.) Conditions Affecting the Work It will be the responsibility of the contractor to inspect the site, determine quality of work involved, compare the specifications with the work to be done, and inform themselves as to all conditions, including other work, if any, being performed. Failure to do so will in no way relieve the successful contractor from the necessity of furnishing any materials or performing any work that may be required to carry out the contract in accordance with the true intent and meaning of the specifications without additional cost to the Government.
Contractor is required to have a CURRENT contractor license issued by the State of Washington.
14.) List of Subcontractors:
For purposes of monitoring compliance with the insurance and payroll reporting requirements of this contract, the contractor shall furnish a list of all subcontractors to the Contracting Officer. This list shall be sent with the performance and payment bonds.
15.) License - Permits The contractor shall, without additional expense to the Government, be responsible for obtaining any necessary licenses or permits, and for complying with any Federal, State, and Municipal laws, codes, and regulations in connection with the execution of the work.
16.) Indemnity The contractor shall confine all work on Government premises to areas authorized or approved by the Contracting Officer or Facility Manager. The contractor shall save and keep harmless and indemnify the Government against any and all liability claims, and costs of whatsoever kind and nature of injury to or death of any person or persons and for loss or damage to any property (Government or otherwise) occurring in connection with or in any way incident to or arising out of the occupancy, use, service, operations, or performance of work in connection with this contract, resulting in whole or part from the negligent acts or omissions of the contractor.
Figure 1a: Water System Plan
Figure 1b: Observatory Water System
Figure 2a: Existing Water Pump System Layout
Figure 2b: System Elements
END OF STATEMENT OF WORK
| Background |
| Project Description |
| Hours of Operation: |
| SCOPE OF WORK |
| 2.) Post-Award Site Investigation/Inspection |
| 3.) Pre-construction Meeting |
| 4.) General Requirements |
| 5.) Work Description |
| 6.) Contractor Responsibilities |
| 7.) Availability and use of Utility Services |
| 8.) Schedule |
| 9.) Construction Safety |
| 10.) Contractor Quality Control |
| be on site, at all times, whenever work is being performed by Contractor or subcontractors’ employees to ensure adequate supervision and communication. |
| 11.) Quality Assurance |
| 12.) Material Submittals |
| 13.) Conditions Affecting the Work |
| 14.) List of Subcontractors: |
| 15.) License - Permits |
| 16.) Indemnity |