This document is the Scope of Work (SOW) for the Estrella-Wayside Recreation Area Phase 2A project, which is part of the Sonoran Desert National Monument in Arizona. The Bureau of Land Management (BLM) is seeking a qualified contractor to deliver 6,500 cubic yards of ADOT Class II Aggregate Base (AB) rock to be used for the project. The contractor will be required to provide all labor, transportation, equipment, tools, supplies, and materials necessary to complete the delivery within a 45-day performance period. The delivery schedule calls for 16 truckloads per day over a 5-day work week for 4 consecutive weeks. The contractor must provide weighmaster certificates and document daily quantities. The government reserves the right to inspect the material source prior to contract award. The related federal contract opportunity, Solicitation Number 140L1224Q0025, is for the purchase of the Aggregate Rock Base in accordance with this SOW. It will be awarded as a fixed-price contract using Lowest Price Technically Acceptable (LPTA) procedures under Simplified Acquisition Procedures.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| Sol_140L1224Q0025_Amd_0001.pdf | ||
| Amend_0001_Q_A_0001.pdf | ||
| Sol_140L1224Q0025.pdf |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
SCOPE of WORK: BLM - SONORAN DESERT NATIONAL MONUMENT
Estrella-Wayside Recreation Area Phase 2A: Materials
OBJECTIVE:
The Bureau of Land Management (BLM) seeks a qualified contractor/vendor to deliver Class II, Aggregate Base (AB) rock to the Sonoran Desert National Monument. This base will never be covered in asphalt and will be loosely spread. The supplies to be delivered, under this contract include all labor, transportation, equipment, tools, supplies, and materials necessary for producing and delivering 6500 cubic yards of aggregate base as specified.
A. Description of Work: delivery of material on schedule, to complete the necessary work as described.
1) Deliver 6500 cubic yards of ADOT Class II AB per specification 321126
2) Delivery shall be by “belly dump” truck with the ability to manage a minimum of 20 cubic yards of said named material in each load.
B. Schedule and Method of Delivery:
1) Schedule of delivery shall consist of 16 truckloads per day, assumed to be in a 10-hour shift, distributed over a 5-day work week for 4 consecutive weeks for a total of 20 days. Slight modifications to scheduling may be approved by BLM field personnel.
2) The contractor shall provide the weighmaster certificate tickets to BLM Contracting Officer Representative (COR) at the end of each day for signature and receipts.
3) Daily total quantities shall be documented by the contractor by a certified scale master and available to the COR within 24 hours. No deliveries shall be made above the contracted amounts without the Contacting Officer’s written approval.
The government maintains the right to inspect the source of the offered materials and quarry sites prior to award of this contract and/or delivery of materials.
PERFORMANCE PERIOD:
Contractor will have (45) consecutive calendar days following a notice to proceed to deliver all AB no later than June 27, 2024 with weekend delivery only allowed if approved at the time that the notice to proceed is issued.
DELIVERY LOCATION
Various progressive stations along BLM route 8002 as directed by BLM personnel.
SONORAN DESERT NATIONAL MONUMENT DECEMBER 2023
ESTRELLA-WAYSIDE RECREATION AREA PHASE TWO
LOCATION MAP
Project Location
SONORAN DESERT NATIONAL MONUMENT DECEMBER 2023
ESTRELLA-WAYSIDE RECREATION AREA PHASE TWO