BUREAU OF LAND MANAGEMENT

FARMINGTON DISTRICT OFFICE

HVAC SYSTEM IMPROVEMENTS

PROJECT SPECIFICATIONS

Prepared by:

Bureau of Land Management National Operations Center

Architecture and Engineering Section OC-671 Denver, CO 80225

June 30, 2022

JUNE 2022

FARMINGTON DISTRICT OFFICE TABLE OF CONTENTS

HVAC SYSTEM IMPROVEMENTS TOC-1

FARMINGTON DISTRICT OFFICE

HVAC SYSTEM IMPROVEMENTS

SPECIFICATIONS TABLE OF CONTENTS

Division .... Section Title ................................................................................................................................ Pages

DIVISION 1 - GENERAL REQUIREMENTS

01010 ........ SUMMARY OF WORK

01200 ........ DEFINITION OF BID ITEMS

01310 ........ PROJECT MANAGEMENT

01320 ........ CONSTRUCTION SCHEDULE

01322. ....... PHOTO DOCUMENTATION

01330 ........ SUBMITTAL PROCEDURES

01350 ........ SAFETY REQUIREMENTS

01351 ........ LIFE SAFETY PLAN

01400 ........ QUALITY REQUIREMENTS

01420 ........ REFERENCES

01500 ........ TEMPORARY FACILITIES AND CONTROLS

01518. ....... INDOOR AIR QUALITY MANAGEMENT

01519. ....... NOISE AND ACOUSTICS MANAGEMENT

01600 ........ PRODUCT REQUIREMENTS

01700 ........ EXECUTION REQUIREMENTS

01731 ........ CUTTING AND PATCHING

01732. ....... SELECTIVE DEMOLITION

01770 ........ CLOSEOUT PROCEDURES

01781. ....... PROJECT RECORD DOCUMENTS

01782 ........ OPERATION AND MAINTENANCE DATA

01815. ....... SYSTEM DEMONSTRATION AND TRAINING

DIVISIONS 2 THROUGH 4

NOT APPLICABLE

DIVISION 5 - METALS

05120 ........ STRUCTURAL STEEL

05400 ........ COLD-FORMED METAL FRAMING

DIVISION 6 - WOOD AND PLASTICS

NOT APPLICABLE

DIVISION 7 - THERMAL AND MOISTURE PROTECTION

07213 ....... RETROFIT ROOF CURB ADAPTERS

07410 ....... METAL WALL PANELS

07620 ....... SHEET METAL FLASHING

07920 ........ JOINT SEALANTS

FARMINGTON DISTRICT OFFICE TABLE OF CONTENTS

HVAC SYSTEM IMPROVEMENTS TOC-2

Division .... Section Title ................................................................................................................................ Pages

DIVISION 8 - DOORS AND WINDOWS

08305 ........ ACCESS DOORS

DIVISION 9 - FINISHES

09250 ........ GYPSUM BOARD

09512 ........ ACOUSTICAL TILE CEILINGS

09653 ........ RESILIENT WALL BASE

09912 ........ PAINTING

DIVISIONS 10 THROUGH 12

NOT APPLICABLE

DIVISION 13 – SPECIAL CONSTRUCTION

13100 ........ LIGHTNING PROTECTION

DIVISION 14 – CONYEYING SYSTEMS

NOT APPLICABLE

DIVISION 15 - MECHANICAL

15010 ........ GENERAL MECHANICAL PROVISIONS

15050 ........ BASIC MATERIALS AND METHODS

15070 ........ MECHANICAL VIBRATION AND SEISMIC CONTROLS

15075 ........ MECHANICAL IDENTIFICATION

15080 ........ MECHANICAL INSULATION

15400 ........ PLUMBING SYSTEMS

15420 ........ PLUMBING EQUIPMENT

15530 ........ REFRIGERANT PIPING SYSTEMS

15700 ........ VARIABLE REFRIGERANT FLOW SYSTEMS

15730 ........ SPLIT-SYSTEM AIR CONDITIONING EQUIPMENT

15765 ........ ELECTRIC HEATERS

15785 ........ AIR-TO-AIR ENERGY RECOVERY EQUIPMENT

15810 ........ DUCTWORK

15850 ........ AIR OUTLETS AND INTAKES

15910 ........ DIRECT DIGITAL CONTROLS

15952 ........ TESTING, ADJUSTING AND BALANCING

DIVISION 16 - ELECTRICAL

16010 ........ GENERAL ELECTRICAL PROVISIONS

16050 ........ BASIC MATERIALS AND METHODS

16060 ........ GROUNDING

END OF TABLE OF CONTENTS

FARMINGTON DISTRICT OFFICE SUMMARY OF WORK

HVAC SYSTEM IMPROVEMENTS 01010-1

SECTION 01010 – SUMMARY OF WORK

PART 1 - GENERAL

1.1 SUMMARY

A. This Section includes the following:

1. Background.

2. Work covered by the Contract Documents.

3. Work Phases.

4. Work under other contracts.

5. Contractor use of premises.

6. Public use of site.

7. Occupancy requirements for buildings.

8. Work restrictions.

9. Security.

10. Field verification.

11. Contractor furnished items.

12. Government furnished items.

13. Hazardous materials.

14. Soils investigation report.

15. Specification formats and conventions.

1.2 BACKGROUND

A. The Farmington District Office building was constructed in 2013 and consists of 30,000 square feet of floor area. It is a flat roof, steel-framed building with masonry and metal cladding, composed of a two-story open office area to the west and a single-story private office and public area to the east – the two-story open office area has an atrium that is open to a roof monitor that provides daylighting in the core of the building. The public portion of the building contains the entry lobby, reception area, and public restrooms, along with a Public Room and a Multi- Purpose Room. The roof is accessible via a roof hatch and ladder located in the Mail Room.

B. Existing Mechanical Systems: The existing heating, ventilating, and air conditioning (HVAC) systems consist of two-stage rooftop mounted evaporative coolers with an underfloor air distribution system – most of the building has a raised floor system with an 18-inch deep plenum for air distribution. Two natural gas-fired modulating-condensing boilers have been installed to provide heat for the building, along with two hot water circulating pumps, air separator, and expansion tank. Fan-powered variable air volume (VAV) terminals with hot water reheat coils have been installed under the raised floor at the perimeter of the building, along with VAV and manual floor diffusers in the core of the building. The existing rooftop HVAC units are located in screened enclosures to the east and west of the central roof monitor.

HVAC SYSTEM IMPROVEMENTS 01010-2

The HVAC systems installed at the Farmington District Office have been problematic since construction on the building was completed. An abbreviated list of ongoing issues that have been experienced is as follows:

1. Even with remedial work completed at the end of the construction period, the underfloor air distribution plenum leaks supply air excessively, leading to comfort complaints due to lack of good air distribution.

2. The Multi-Purpose Room has been especially difficult to heat and cool properly. More generally, the entire east end of the building has been difficult to heat and cool properly.

3. The fan-powered VAV terminals and associated air filters located in the underfloor plenum are difficult to access for service and maintenance.

4. Dirt collecting in the floor diffusers is an ongoing maintenance issue. The dirt from people’s shoes causes both the manual damper and automatic damper mechanisms to jam and space temperature control suffers as a result.

5. Even with repeated investments and service contracts, the automatic control system (DDC BAS or direct digital control building automation system) still does not operate correctly and requires manual operation and adjustment to achieve acceptable comfort conditions.

6. The two-stage evaporative cooling rooftop units require frequent maintenance and use an excessive amount of potable water for their operation.

7. The heating system failed during the winter of 2017/2018. District Office personnel had to be sent home due to the lack of heat, and the fix took time and was expensive. Repair parts for the boilers have been difficult or impossible to obtain in recent years.

8. The HVAC systems that are installed in the Farmington District Office are overly complex and are not standard, which has historically led to a lack of understanding on how they should be operated and maintained.

All of this affects employee and visitor comfort, along with decreased BLM maintenance staff productivity and effectiveness. Current energy use at this facility is also higher than it should be, especially considering that the facility has 67 kW of photovoltaic (PV) solar energy systems installed. Replacement of the existing HVAC systems with new high efficiency variable refrigerant flow (VRF) systems will improve occupant comfort, increase system reliability, and increase energy efficiency.

C. Existing Electrical Systems: The existing electrical system consists of a 1000A, 480/277V, three phase service. A 225 kVA dry-type transformer has been provided to power all of the 208/120V circuits in the building.

1.3 WORK COVERED BY CONTRACT DOCUMENTS

A. Project Identification: Farmington District Office HVAC System Improvements.

B. Project Location: 6251 College Boulevard, Farmington, NM 87402 (LAT 36.78613, LONG - 108.15830, 505-564-7600, https://www.blm.gov/office/farmington-district-office)

C. The Work consists of but is not limited to the following:

1. HVAC System Demolition: Phased removal of the existing mechanical systems and equipment in the building to accommodate the new mechanical systems. Temporary

HVAC SYSTEM IMPROVEMENTS 01010-3

partitions (polyethylene sheeting) between portions of the building will be required for separation between the work phases, along with temporary protection for the floors and furnishings.

2. Electrical System Demolition: Phased removal of the existing electrical systems and equipment in the building as necessary to accommodate the new mechanical systems.

Temporary partitions (polyethylene sheeting) between portions of the building will be required for separation between the work phases, along with temporary protection for the floors and furnishings.

3. HVAC System Improvements: Installation of new HVAC systems consisting of VRF systems for heating and cooling the building, energy recovery ventilators (ERVs) for ventilating the building, new HVAC control system, and all ductwork, piping, and appurtenances necessary for a complete and operable HVAC system. This work also includes cutting, patching, spotting, taping, sanding, painting, access doors, minor structural modifications, installation of new domestic water heaters, minor plumbing system modifications, etc. Cutting and patching will be required for demolition and for routing new ductwork, piping, and conduit in existing walls and above existing ceilings.

Access doors will be required for access to piping, conduit, fan coil units, etc. as necessary for installation and maintenance purposes.

4. Electrical System Improvements, HVAC: Modification and expansion of the existing electrical systems as necessary to power all new HVAC systems, equipment, and controls.

D. Project will be constructed under a single prime contract.

1.4 WORK PHASES

A. The work of this contract shall be broken into three phases to limit the impact of construction activities on BLM operations during the construction contact period. The project phases shall be conducted in the following order, with each phase substantially complete before beginning the next phase:

1. Phase 1 HVAC System Improvements:

a. The BLM shall move employees out of the west end of the building (west of Grid Line 8). RTU-1 and associated ductwork and HVAC equipment shall be removed, but the existing perimeter heating system components shall remain in operation until the end of Phase 1. The existing HVAC systems shall be replaced with heat recovery VRF multi-split heat pump systems, with an energy recovery ventilator (ERV) installed to provide fresh air and exhaust service for the west end of the building. The VRF outdoor units and ERV shall be located above the roof, mounted on a new insulated curb adapter that shall take the place of RTU-1.

b. Temporary partitions constructed of polyethylene sheeting shall be suspended from the ceiling at Grid Line 8 on both levels to demarcate the Phase 1 work area from the occupied portions of the building. Temporary floor protection shall be provided as necessary west of Grid Line 8 to protect the floor during execution of the work. Temporary protection (tarping) of furnishings shall be provided as necessary west of Grid Line 8 to protect furnishings during execution of the work.

HVAC SYSTEM IMPROVEMENTS 01010-4

c. The Contractor’s main access to the Phase 1 work area shall be via the exterior door on the northeast end of the building (Mud Room 181). The Contractor’s staging area for the Phase 1 work shall be in the Warehouse wareyard.

d. Roof access shall be via a ladder and roof access hatch in Mail Room 208.

Contractor’s personnel shall use the existing walk pads on the roof as much as possible. Temporary roof protection shall be provided as necessary to protect the roof during execution of the work.

e. The HVAC, electrical, and life safety systems in the remainder of the building shall remain operational for the duration of the Phase 1 work.

f. As work in the Phase 1 work area progresses and the Contractor’s work crews are preparing to move on to the next phase of work, the Contractor shall give notice 10 calendar days prior to the BLM moving the Phase 2 work area employees to allow employees sufficient time to pack their belongings and to allow the work of Phase 2 to commence in a timely manner.

g. Contractor shall also give notice 10 calendar days prior to work of Phase 1 being substantially complete so that the Government can inspect the work before the BLM moves employees back into the Phase 1 work area.

h. Any punch list items resulting from the Government inspection shall be completed before the BLM moves employees back into the Phase 1 work area.

2. Phase 2 HVAC System Improvements:

a. After the completion of the Phase 1 work (and with the new Phase 1 HVAC systems operational), the BLM shall move employees back into the west end of the building and vacate employees out of the central portion of the building (Grid Line 8 to Grid Line 4). RTU-2 and associated ductwork and HVAC equipment shall be removed, but the existing perimeter heating system components shall remain in operation until the end of Phase 2. The existing HVAC systems shall be replaced with heat recovery VRF multi-split heat pump systems, with an energy recovery ventilator (ERV) installed to provide fresh air and exhaust service for the central portion and the east end of the building. The VRF outdoor units and ERV shall be located above the roof, mounted on a new insulated curb adapter that shall take the place of RTU-2.

b. Temporary partitions constructed of polyethylene sheeting shall be suspended from the ceiling at the Grid Line 4 openings on both levels, and the temporary partitions installed under Phase 1 at Grid Line 8 shall remain in place to demarcate the Phase 2 work area from the occupied portions of the building. Temporary floor protection shall be provided as necessary east of Grid Line 8 and west of Grid Line 4 to protect the floor during execution of the work. Temporary protection (tarping) of furnishings shall be provided as necessary east of Grid Line 8 and west of Grid Line 4 to protect furnishings during execution of the work.

c. Cap Phase 2 ductwork at Phase 2 work limits, anticipating connection of Phase 3 ductwork.

d. The Contractor’s main access to the Phase 2 work area shall be via the exterior door on the north side of the building between Grid Lines 4 and 5 (Open Office 150E). The Contractor’s staging area for the Phase 2 work shall be in the Warehouse wareyard.

e. Roof access shall be via a ladder and roof access hatch in Mail Room 208.

Contractor’s personnel shall use the existing walk pads on the roof as much as

HVAC SYSTEM IMPROVEMENTS 01010-5

possible. Temporary roof protection shall be provided as necessary to protect the roof during execution of the work.

f. The HVAC, electrical, and life safety systems in the remainder of the building shall remain operational for the duration of the Phase 2 work.

g. As work in the Phase 2 work area progresses and the Contractor’s work crews are preparing to move on to the next phase of work, the Contractor shall give notice 10 calendar days prior to BLM moving the Phase 3 work area employees to allow employees sufficient time to pack their belongings and to allow the work of Phase 3 to commence in a timely manner.

h. Contractor shall also give notice 10 calendar days prior to work of Phase 2 being substantially complete so that the Government can inspect the work before the BLM moves employees back into the Phase 2 work area.

i. Any punch list items resulting from the Government inspection shall be completed before the Contractor moves employees back into the Phase 2 work area.

j. The temporary partitions at Grid Line 8 shall be removed at the end of the Phase 2 work.

3. Phase 3 HVAC System Improvements:

a. After the completion of Phase 2 (and with the new Phase 2 HVAC systems operational), the BLM shall move employees back into the central portion of the building and vacate employees out of the east end of the building (east of Grid Line 4). RTU-3, associated ductwork, and the remainder of the HVAC equipment (including the boilers, hot water circulating pumps, and associated equipment) shall be removed. The existing HVAC systems shall be replaced with heat recovery VRF heat pump systems. The VRF outdoor units shall be located above the roof, mounted on a new insulated curb adapter that shall take the place of RTU-

3. The existing gas-fired domestic water heater shall be removed and replaced with two hybrid heat pump domestic water heaters – the natural gas pipe feeding the District Office building shall be capped inside the boiler room. A low-flow pressure reducing valve shall also be installed in parallel with the existing domestic water pressure reducing valve to mitigate water hammer issues.

b. The temporary partitions installed under Phase 2 at Grid Line 4 shall remain in place to demarcate the Phase 3 work area from the occupied portions of the building. Temporary floor protection shall be provided as necessary east of Grid Line 4 to protect the floor during execution of the work. Temporary protection (tarping) of furnishings shall be provided as necessary east of Grid Line 4 to protect furnishings during execution of the work.

c. The Contractor’s main access to the Phase 3 work area shall be via the exterior doors on the north side of the building between Grid Lines 2 and 3 (Boiler Room 105). The Contractor’s staging area for the Phase 3 work shall be in the Warehouse wareyard.

d. Roof access shall be via a ladder and roof access hatch in Mail Room 208.

Contractor’s personnel shall use the existing walk pads on the roof as much as possible. Temporary roof protection shall be provided as necessary to protect the roof during execution of the work.

e. The HVAC, electrical, and life safety systems in the remainder of the building shall remain operational for the duration of the Phase 3 work.

f. The front desk (Room 209) shall remain occupied by BLM employees and the main entry (Room 201A), lobby (Room 201), and public restrooms (Rooms 204

HVAC SYSTEM IMPROVEMENTS 01010-6

and 206) shall remain open for business as much as possible during the execution of the work in the Phase 3 work area. If any of the work in the Phase 3 work area cannot be performed safely or without interfering with the day-to-day business of the BLM, the Contractor shall schedule those portions of work after hours or over weekends.

g. The new HVAC systems in the Phase 1 and Phase 2 work areas shall be operational for the duration of the Phase 3 work. Contractor shall provide temporary heating and cooling in the normally occupied portions of the Phase 3 work area as necessary to maintain comfort conditions.

h. Contractor shall give notice 10 calendar days prior to work of Phase 3 being substantially complete so that the Government can inspect the work before the Contractor moves employees back into the Phase 3 work area.

i. Any punch list items resulting from the Government inspection shall be completed before the Contractor moves employees back into the Phase 3 work area.

j. The temporary partitions at Grid Line 4 shall be removed at the end of the Phase 3 work.

1.5 WORK UNDER OTHER CONTRACTS

A. Cooperate fully with separate contractors so work on those contracts may be carried out smoothly, without interfering with or delaying work under this Contract. Coordinate the Work of this Contract with work performed under separate contracts.

B. Concurrent Work: The Government has awarded a separate contract for the following construction operations at Project site. Those operations may be conducted simultaneously with work under this Contract.

1. Farmington Fire Facilities: A separate contract has been awarded to build new fire station and crew quarters buildings, along with utilities and site work. The Farmington Fire Facilities construction work commenced in May 2022 and is expected to continue until March 2023.

1.6 CONTRACTOR USE OF PREMISES

A. Use of Site: Limit use of premises to work in areas indicated. Do not disturb portions of the project site beyond areas in which the Work is indicated.

1. Limits: Confine construction operations to areas defined on the drawings.

a. Limit site disturbance, including earthwork and clearing of vegetation, to 10 feet beyond building perimeter and staging areas.

B. Driveways and Entrances: Keep driveways, loading areas, and entrances serving the premises clear and available to the Government, Government employees, public, and emergency vehicles at all times. Do not use these areas for parking or storage of materials. Parking for Contractor’s and Subcontractor’s employees will be limited to the Warehouse parking lot unless other areas are approved by the Contracting Officer.

HVAC SYSTEM IMPROVEMENTS 01010-7

a. Schedule deliveries to minimize use of driveways and entrances.

b. Schedule deliveries to minimize space and time requirements for storage of materials and equipment on-site.

C. Storage of Materials:

1. Confine storage of materials to the interior of the building work areas and to areas on the site as shown or approved by the Contracting Officer.

2. Volatile Storage: Store gasoline/diesel in approved storage containers (maximum 5 gallon containers) outside the building. Total quantity of volatile storage shall be limited to 20 gallons maximum.

D. Preservation of Existing Facilities: Confine all operations to work limits of the project. Prevent damage to building surfaces. Carefully supervise construction activities to prevent damage.

Restore damaged areas, repairing or replacing damaged areas at no additional expense to the Government.

E. Construction Camp: Establishment of a construction camp within the boundaries of the site will not be permitted.

F. Firearms: No firearms are allowed on the site.

G. Advertising: No commercial advertising or signage shall be permitted, other than that on Contractor vehicles or equipment.

H. Existing Utilities: Utilities are available on site. Restricted use of utilities will be allowed; see Section 01500 - Temporary Facilities and Controls.

I. Hauling Restrictions: Comply with all legal load restrictions in the hauling of materials.

J. Waste Disposal: All waste shall be disposed of in a legal and appropriate manner, and in accordance with Federal, State and local regulations.

K. Scheduling: Schedule and sequence operations necessary to complete the work, including coordination with other trades relative to the Contractor's requirements. Schedule work in such a manner as to avoid delays in overall construction schedule and permit proper installation of work.

L. Utilities: Service interruptions will not be allowed during normal operating hours unless required; see Paragraph 1.9B. below.

M. Nonsmoking Building: Smoking is not permitted within the building or within 25 feet of entrances, operable windows, or outdoor air intakes. No smoking signs shall be posted and visible during working hours.

1.7 PUBLIC USE OF SITE

A. The site will be open to the public during normal operating hours - the main entry (Room 201A), lobby (Room 201), and public restrooms (Rooms 204 and 206) shall remain accessible

HVAC SYSTEM IMPROVEMENTS 01010-8

to the public during business hours.. Contractor activities shall take into consideration office employees and visitors in order to limit interactions and disturbance. Provide orange safety tape to separate the public and Government employees from construction activities.

1. The Contractor shall at all times conduct contractor operations to keep the site clean and free of debris. Areas around the building may be closed to employees, public, or both, when required, upon specific approval of the Contracting Officer.

2. Material placed exterior to the building shall be utilized on a daily basis and cleaned up each evening and placed either inside the building or at a designated storage area. The Government shall not be responsible for the physical security of Contractor’s materials.

1.8 OCCUPANCY REQUIREMENTS FOR BUILDINGS

A. Government Occupancy: The Government will occupy portions of the building that will be under construction during the entire contract period. Cooperate with the Government during construction operations to minimize conflicts and facilitate Government usage. Perform the Work so as not to interfere with Government's day-to-day operations. Maintain existing building and site exits, unless otherwise indicated.

1. Maintain access to existing walkways, corridors, and other adjacent occupied or used facilities. Do not close or obstruct walkways, corridors, or other occupied or used facilities without written permission from the Contracting Officer.

2. Maintain existing building in a weather tight condition throughout construction period.

Repair any damage caused by construction operations. Protect building and its occupants during construction period.

3. Consideration shall be given to minimize disturbance of everyday activities when scheduling construction activities which may be noisy or otherwise disruptive.

4. The Contractor shall provide a minimum of 48 hours notice for concrete sawing, concrete coring, or other major demolition activities.

5. BLM employee and contractor emergency egress during each phase of construction shall be and verified and planned for. Elevator access for disabled persons shall also be verified and planned for during each phase of construction - a clear path for supervised elevator access through the active construction area shall be maintained.

6. BLM employees with proper authorization and equipped with personal protective equipment (hardhat) shall have access to the central file room (Room 110), LEO evidence storage (Room 183), and the FIMO file room (Room 202B) as necessary during the execution of the work.

7. BLM personnel will be continuously occupying the front desk (Room 209) and other areas of the building where each phase of work is not currently being performed during business hours. Conduct work in a manner that will minimize needs for disruption of normal Government operations. Provide a minimum of 72 hours advance notice to the Contracting Officer of all activities that will impact normal Government operations.

Contracting Officer's written approval is required prior to initiation of these activities.

8. If any of the work in the building cannot be performed safely or without interfering with the day-to-day business of the BLM, the Contractor shall schedule those sections of work after hours or over weekends.

HVAC SYSTEM IMPROVEMENTS 01010-9

1.9 WORK RESTRICTIONS

A. Work Hour Restrictions:

1. Farmington District Office normal business operating hours are from 7:45 AM - 4:30 PM Monday through Friday, except Federal holidays. Contractor’s work hours may be extended to 7:00 AM – 6:00 PM Monday through Friday, except Federal holidays

2. Contractor work hours during other times shall be subject to approval, but it is anticipated that several contractor activities will need to be scheduled at times other than normal working hours in order to avoid disruption to the normal business activities. Provide list of activities that Contractor proposes to be accomplished after normal operating hours.

B. Existing Utility Interruptions: Do not interrupt utilities serving the Farmington District Office facilities unless permitted under the following conditions and then only after arranging to provide temporary utility services according to requirements indicated:

1. Notify the Contracting Officer in writing not less than 2 days in advance of proposed utility interruptions.

2. Do not proceed with utility interruptions without Contracting Officer’s written permission.

3. If extended outages (over 4 hours in duration) are required, they shall occur over a weekend. Extended outages shall be subject to minimum 14 day prior notice and approval prior to outage.

1.10 SECURITY

A. Security Clearance:

1. Contractor shall submit a Security Plan at the Pre-Work Conference outlining the procedures proposed to maintain a secure project. After project award, the Contractor shall identify two key personnel who will receive a security clearance (HSPD-12) credential from the BLM and these personnel will be responsible for implementing the security plan. One of these employees shall be on the premises at all times that Contractor’s work/activities take place.

2. Contractor and Subcontractor employees shall be required to display a badge with a picture ID with their name and company any time they are on site. Visitors shall be required to check in at the Contractor’s trailer and obtain a visitor’s badge to be worn when the individual is on site. Visitors must be accompanied by a credentialed Contractor employee.

B. Keys and Passes:

1. The building requires a key card for entry and most of the interior rooms require a standard key for access.

2. The Contractor’s HSPD-12 credentialed employees may be issued key card passes as well as standard keys, subject to verification, security checks, and training.

C. Openings:

HVAC SYSTEM IMPROVEMENTS 01010-10

1. During the course of the work, access to the occupied portions of the building must remain secured. Means and methods of securing access points shall be subject to approval by the Contracting Officer.

D. Personnel:

1. Contractor shall maintain security for all construction personnel and issue credentialed (picture) identification for all construction personnel on the job site.

2. All visitors or short-term subcontractors may be issued a visitor’s pass and shall be accompanied by a credentialed Contractor employee.

1.11 FIELD VERIFICATION

A. Field verify all existing dimensions and conditions affecting the work of this contract before ordering products.

1.12 CONTRACTOR-FURNISHED ITEMS

A. All materials shall be new and Contractor-furnished from outside the site.

1.13 GOVERNMENT-FURNISHED ITEMS

A. The Government will furnish lights, power, and water from existing services in the building for the Contractor’s use. The BLM will not permit wasteful or unauthorized use of Government furnished utilities.

1.14 SOILS INVESTIGATION REPORT

A. Not Used.

1.15 SPECIFICATION FORMATS AND CONVENTIONS

A. Specification Format: The Specifications are organized into Divisions and Sections using the CSI/CSC “MasterFormat 95” 16-division system and "MasterFormat" numbering system.

1. Division 1: Sections in Division 1 govern the execution of the Work of all Sections in the Specifications.

B. Specification Content: The Specifications use certain conventions for the style of language and the intended meaning of certain terms, words, and phrases when used in particular situations.

These conventions are as follows:

1. Abbreviated Language: Language used in the Specifications and other Contract Documents is abbreviated. Words and meanings shall be interpreted as appropriate.

Words implied, but not stated, shall be inferred as the sense requires. Singular words

HVAC SYSTEM IMPROVEMENTS 01010-11

shall be interpreted as plural, and plural words shall be interpreted as singular where applicable as the context of the Contract Documents indicates.

2. Imperative mood and streamlined language are generally used in the Specifications.

Requirements expressed in the imperative mood are to be performed by Contractor.

Occasionally, the indicative or subjunctive mood may be used in the Section Text for clarity to describe responsibilities that must be fulfilled indirectly by Contractor or by others when so noted.

a. The words "shall," "shall be," or "shall comply with," depending on the context, are implied where a colon (:) is used within a sentence or phrase.

C. Terminology: In Division 2 through 16 specification sections, any references to “Owner” shall be replaced with the term “Government” or “Contracting Officer” (when referring to the person acting for the Government). Any references to “Architect” shall be replaced with the term “Contracting Officer”.

PART 2 - PRODUCTS (Not Used)

PART 3 - EXECUTION (Not Used)

END OF SECTION

FARMINGTON DISTRICT OFFICE DEFINITION OF BID ITEMS

HVAC SYSTEM IMPROVEMENTS 01200-1

SECTION 01200 – DEFINITION OF BID ITEMS

PART 1 - GENERAL

1.1 SUMMARY

A. The intent of this section is to explain, in general, what is and what is not included in a contract bid item, and the limits or cut off points where one bid item ends and another begins.

B. If no contract bid item exists for a portion of the work, include the costs in a related bid item.

PART 2 - PRODUCTS (Not Used)

PART 3 - EXECUTION

3.1 LIST OF CONTRACT BID ITEMS

A. Bid Item No. 1 – HVAC System Demolition:

1. This bid item consists of all work required for removal of the existing mechanical systems and equipment in the building to accommodate the new mechanical systems.

2. Measurement of quantities for payment will be based on Contractor’s schedule of values.

3. Payment will be made at the contract lump sum price.

B. Bid Item No. 2 – Electrical System Demolition:

1. This bid item consists of all work required for removal of the existing electrical systems and equipment in the building as necessary to accommodate the new mechanical systems.

2. Measurement of quantities for payment will be based on Contractor’s schedule of values.

3. Payment will be made at the contract lump sum price.

C. Bid Item No. 3 – HVAC System Improvements:

1. This bid item consists of all work required for installation of new HVAC systems consisting of variable refrigerant flow (VRF) systems for heating and cooling the building, energy recovery ventilators (ERVs) for ventilating the building, a new HVAC control system, and all ductwork, piping, roof curb adapters, and appurtenances necessary for a complete and operable HVAC system. This bid item also includes all related work required for cutting, patching, spotting, taping, sanding, painting, access doors, installation of new domestic water heaters, ancillary plumbing work, etc.

2. Measurement of quantities for payment will be based on Contractor’s schedule of values.

3. Payment will be made at the contract lump sum price.

D. Bid Item No. 4 – Electrical System Improvements:

FARMINGTON DISTRICT OFFICE DEFINITION OF BID ITEMS

HVAC SYSTEM IMPROVEMENTS 01200-2

1. This bid item consists of all work required for modification and expansion of the existing electrical systems as necessary to power all new HVAC systems, equipment, and controls. This bid item also includes installation of electrical submeters.

2. Measurement of quantities for payment will be based on Contractor’s schedule of values.

3. Payment will be made at the contract lump sum price.

FARMINGTON DISTRICT OFFICE PROJECT MANAGEMENT

HVAC SYSTEM IMPROVEMENTS 01310-1

SECTION 01310 - PROJECT MANAGEMENT

PART 1 - GENERAL

1.1 SUMMARY

A. This Section includes administrative provisions for coordinating construction operations on the Project including, but not limited to, the following:

1. Project meetings.

2. Requests for Interpretation (RFIs).

1.2 DEFINITIONS

A. RFI: Request from Contractor seeking interpretation or clarification of the Contract Documents.

1.3 PROJECT MEETINGS

A. General: Schedule and conduct meetings and conferences at the Project site, unless otherwise indicated.

1. Attendees: Inform participants and others involved, and individuals whose presence is required, of date and time of each meeting. Notify Contracting Officer of scheduled meeting dates and times.

2. Agenda: Prepare the meeting agenda. Distribute the agenda to all invited attendees.

B. Pre-Work Conference: The Contracting Officer will schedule and conduct a Pre-Work Conference before start of construction. The conference will review responsibilities and personnel assignments, review required work, project drawings, specifications, construction schedules, payroll, payments, and administrative provisions of the Contract. Be prepared to summarize and explain procedures planned for the project and present specified pre-work submittals.

1. Attendees: Authorized representatives of the Government and their consultants;

Contractor and Contractor’s superintendent; major subcontractors; suppliers; and other concerned parties shall attend the conference. All participants at the conference shall be familiar with Project and shall be authorized to conclude matters relating to the Work. The mechanical and electrical subcontractor’s attendance will be required.

2. Agenda: Discuss items of significance that could affect progress, including the following:

a. Tentative construction schedule.

b. Phasing.

c. Critical work sequencing and long-lead items.

d. Designation of key personnel and their duties.

HVAC SYSTEM IMPROVEMENTS 01310-2

e. Procedures for processing field decisions and Change Orders.

f. Procedures for RFIs.

g. Procedures for testing and inspecting.

h. Procedures for processing Applications for Payment.

i. Distribution of the Contract Documents.

j. Submittal procedures.

k. Preparation of Record Documents.

l. Use of the premises.

m. Work restrictions.

n. Government occupancy requirements.

o. Responsibility for temporary facilities and controls.

p. Construction waste management and recycling.

q. Parking availability.

r. Office, work, and storage areas.

s. Equipment deliveries and priorities.

t. First aid.

u. Security.

v. Progress cleaning.

w. Working hours.

3. Minutes: The Contracting Officer will record and distribute meeting minutes.

C. Preinstallation Conferences: Conduct a preinstallation conference at Project site before each construction activity that requires coordination with other construction.

1. Attendees: Installer and representatives of manufacturers and fabricators involved in or affected by the installation and its coordination or integration with other materials and installations that have preceded or will follow, shall attend the meeting. Advise Contracting Officer of scheduled meeting dates.

2. Agenda: Review progress of other construction activities and preparations for the particular activity under consideration, including requirements for the following:

a. The Contract Documents.

b. Options.

c. Related RFIs.

d. Related Change Orders.

e. Purchases.

f. Deliveries.

g. Submittals.

h. Review of mockups.

i. Possible conflicts.

j. Compatibility problems.

k. Time schedules.

l. Weather limitations.

m. Manufacturer's written recommendations.

n. Warranty requirements.

o. Compatibility of materials.

p. Acceptability of substrates.

q. Temporary facilities and controls.

r. Space and access limitations.

HVAC SYSTEM IMPROVEMENTS 01310-3

s. Regulations of authorities having jurisdiction.

t. Testing and inspecting requirements.

u. Installation procedures.

v. Coordination with other work.

w. Required performance results.

x. Protection of adjacent work.

y. Protection of construction and personnel.

3. Record significant conference discussions, agreements, and disagreements, including required corrective measures and actions.

4. Reporting: Distribute minutes of the meeting to each party present and to parties who should have been present.

5. Do not proceed with installation if the conference cannot be successfully concluded.

Initiate whatever actions are necessary to resolve impediments to performance of the Work and reconvene the conference at earliest feasible date.

D. Progress Meetings: Conduct progress meetings once a month. Hold the meetings at the project site. Coordinate dates of meetings with preparation of payment requests. Additional progress meetings may be requested by either the Contracting Officer or Contractor.

1. Attendees: In addition to representatives of Government, each contractor, subcontractor, supplier, and other entity concerned with current progress or involved in planning, coordination, or performance of future activities shall be represented at these meetings.

All participants at the conference shall be familiar with the Project and authorized to conclude matters relating to the Work.

2. Agenda: Review, and correct or approve minutes of previous progress meeting. Review other items of significance that could affect progress. Include topics for discussion as appropriate to status of Project.

a. Contractor's Construction Schedule: Review progress since the last meeting.

Determine whether each activity is on time, ahead of schedule, or behind schedule, in relation to Contractor's Construction Schedule. Determine how construction behind schedule will be expedited; secure commitments from parties involved to do so. Discuss whether schedule revisions are required to ensure that current and subsequent activities will be completed within the Contract Time.

1) Review schedule for next period.

b. Review present and future needs of each entity present, including the following:

1) Interface requirements.

2) Sequence of operations.

3) Status of submittals.

4) Deliveries.

5) Off-site fabrication.

6) Access.

7) Site utilization.

8) Temporary facilities and controls.

9) Work hours.

10) Hazards and risks.

HVAC SYSTEM IMPROVEMENTS 01310-4

11) Progress cleaning.

12) Quality and work standards.

13) Status of correction of deficient items.

14) Field observations.

15) RFIs.

16) Status of proposal requests.

17) Pending changes.

18) Status of Change Orders.

19) Pending claims and disputes.

20) Documentation of information for payment requests.

3. Minutes: Record the meeting minutes.

4. Reporting: Distribute minutes of the meeting to each party present and to parties who should have been present.

a. Schedule Updating: Revise Contractor's Construction Schedule after each progress meeting where revisions to the schedule have been made or recognized. Issue revised schedule concurrently with the report of each meeting.

1.4 REQUESTS FOR INTERPRETATION (RFIs)

A. Procedure: Immediately on discovery of the need for interpretation of the Contract Documents, and if not possible to request interpretation at Project meeting, prepare and submit an RFI in the form specified.

1. RFIs shall originate with the Contractor. RFIs submitted by entities other than the Contractor will be returned with no response.

2. Coordinate and submit RFIs in a prompt manner so as to avoid delays in the Contractor's work or work of subcontractors.

B. Content of the RFI: Include a detailed, legible description of item needing interpretation and the following:

1. Project name.

2. Contract number.

3. Date.

4. Name of Contractor.

5. Name of Contracting Officer.

6. RFI number, numbered sequentially.

7. Specification Section number and title and related paragraphs, as appropriate.

8. Drawing number and detail references, as appropriate.

9. Field dimensions and conditions, as appropriate.

10. Contractor's suggested solution(s). If Contractor's solution(s) impact the Contract Time or the Contract Sum, Contractor shall state impact in the RFI.

11. Contractor's signature.

12. Attachments: Include drawings, descriptions, measurements, photos, Product Data, Shop

Drawings, and other information necessary to fully describe items needing interpretation.

C. Hard-Copy RFIs:

HVAC SYSTEM IMPROVEMENTS 01310-5

1. Identify each page of attachments with the RFI number and sequential page number.

D. Contracting Officer's Action: Contracting Officer will review each RFI, determine action required, and return it. Allow 10 calendar days for Contracting Officer's response for each RFI.

RFIs received after 1:00 p.m. will be considered as received the following working day.

1. The following RFIs will be responded to without action:

a. Requests for approval of submittals.

b. Requests for approval of substitutions.

c. Requests for coordination information already indicated in the Contract

Documents.

d. Requests for adjustments in the Contract Time or the Contract Sum.

e. Requests for interpretation of Contracting Officer's actions on submittals.

f. Incomplete RFIs or RFIs with numerous errors.

2. Contracting Officer's action may include a request for additional information, in which case the Contracting Officer's time for response will start again.

E. On receipt of Contracting Officer's action, update the RFI log and immediately distribute the RFI response to affected parties. Review response and notify the Contracting Officer within seven days if Contractor disagrees with response.

F. RFI Log: Prepare, maintain, and submit a tabular log of RFIs organized by the RFI number.

Submit log at each progress meeting, and include the following:

1. Project name.

2. Name and address of Contractor.

3. Name and address of Contracting Officer.

4. RFI number including RFIs that were dropped and not submitted.

5. RFI description.

6. Date the RFI was submitted.

7. Date Contracting Officer's response was received.

8. Identification of related bilateral or unilateral modifications, extensions, and changes in scope, as appropriate.

PART 2 - PRODUCTS (Not Used)

PART 3 - EXECUTION (Not Used)

FARMINGTON DISTRICT OFFICE CONSTRUCTION SCHEDULE

HVAC SYSTEM IMPROVEMENTS 01320-1

SECTION 01320 – CONSTRUCTION SCHEDULE

PART 1 - GENERAL

1.1 SUMMARY

A. This Section consists of Construction Schedule requirements including but not limited to the following:

1. Schedule of Values

2. Construction Schedule Requirements.

3. Construction Schedule Updates.

4. Time Impact Analysis.

B. Purpose: The purpose of the Construction Schedule is to ensure adequate planning, coordination, scheduling, and reporting during execution of the work by the Contractor. The Construction Schedule will assist the Contractor and Contracting Officer in monitoring the progress of the work, evaluating proposed changes, and processing the Contractor's monthly progress payment.

1.2 DEFINITIONS

A. Activity: A discrete part of a project that can be identified for planning, scheduling, monitoring, and controlling the construction project. Activities included in a construction schedule consume time and resources.

1. Critical activities are activities on the critical path. They must start and finish on the planned early start and finish times.

2. Predecessor Activity: An activity that precedes another activity in the network.

3. Successor Activity: An activity that follows another activity in the network.

B. Cost Loading: The allocation of the Schedule of Values for the completion of an activity as scheduled. The sum of costs for all activities must equal the total Contract Sum, unless otherwise approved by the Contracting Officer.

C. CPM: Critical path method, which is a method of planning and scheduling a construction project where activities are arranged based on activity relationships. Network calculations determine when activities can be performed and the critical path of the Project.

D. Critical Path: The longest connected chain of interdependent activities through the network schedule that establishes the minimum overall Project duration and contains no float.

E. Float: The measure of leeway in starting and completing an activity.

1. Float: Float is not for the exclusive use or benefit of either the Government or the Contractor but is jointly owned.

HVAC SYSTEM IMPROVEMENTS 01320-2

2. Free float is the amount of time an activity can be delayed without adversely affecting the early start of the successor activity.

3. Total float is the measure of leeway in starting or completing an activity without adversely affecting the planned Project completion date.

F. Resource Loading: The allocation of manpower and equipment necessary for the completion of an activity as scheduled.

G. Fragnet: A partial or fragmentary network that breaks down activities into smaller activities for greater detail.

1.3 SUBMITTALS

A. Electronic Copies: All schedules and reports submitted shall be posted on the Contractor’s FTP (or cloud storage such as Google Drive, OneDrive, etc.) website, provided in the native electronic file format. It is the intent of the Government to limit the number of printed reports to only those reports determined by the project team to be essential.

B. Schedule of Values: After contract award and before the Pre-Construction conference submit a schedule of dollar values based on the Contract Price Schedule.

C. Construction Baseline Schedule: After contract award and before the Pre-Construction conference, submit a copy of the baseline schedule, complete to show entire schedule for entire construction period.

D. CPM Reports: Concurrent with CPM schedule, submit copies of each of the following computer-generated reports. Format for each activity in reports shall contain activity number, activity description, resource loading, original duration, remaining duration, early start date, early finish date, late start date, late finish date, and total float in calendar days.

1. Activity Report: List of all activities sorted by activity number and then early start date, or actual start date if known.

2. Logic Report: List of predecessor and successor tasks for all activities, sorted in ascending order by activity number and then early start date, or actual start date if known.

3. Total Float Report: List of all activities sorted in ascending order of total float.

E. Construction Schedule Updates: On or before the 7th day preceding the progress payment request date, submit copies of estimates of the percent completion of each schedule activity and necessary supporting data.

F. Construction Schedule Revisions and Time Impact Analysis: For each Construction Schedule revision submit a copy of a Time Impact Analysis. Each Time Impact Analysis shall include a Fragmentary Network (Fragnet), incorporated into the currently accepted Construction Schedule, demonstrating how the Contractor proposes to incorporate a modification, change, delay, or Contractor request.

HVAC SYSTEM IMPROVEMENTS 01320-3

1.4 QUALITY ASSURANCE

A. The Contractor shall meet with the Contracting Officer on the day of the preconstruction conference to go over the following:

1. Review software limitations, content and format for reports.

2. Verify availability of qualified personnel needed to develop and update schedule.

3. Discuss constraints, including phasing, work stages, work area separations, interim milestones, partial Government occupancy, and temporary relocation of Government personnel.

4. Review schedule for work of separate and concurrent Government contracts.

5.…