B04_Attachment_1_-_SOW.pdf

PDF 2 MB Posted

Attached to
WATER STORAGE TANK CLEANING & INSPECTION - ALASKA
Solicitation number
140P9725Q0041
Issued by

About this file

This Statement of Work (SOW) details water storage tank cleaning and inspection services for up to 8 water tanks across three National Parks in Alaska: Denali (DENA), Katmai (KATM), and Western Arctic Parklands (WEAR). The base bid and optional line items cover tanks ranging from 5,000 to 150,000 gallons, with locations including Front Country, Rock Creek, Savage Campground, King Salmon, and Kotzebue. The contractor must perform comprehensive cleaning and inspection using Remote Operated Vehicle (ROV) equipment, following American Water Works Association (AWWA) standards, and document findings through detailed reports, photographs, and videos.

Key requirements include disinfecting and cleaning tank interiors, removing sediment, monitoring water quality, inspecting structural conditions, and identifying potential repairs. The work is to be completed between June 1, 2025 and July 15, 2026, with inspection reports due within 30 days of each tank's inspection and no later than August 15, 2026. Contractors must have 3 years of prior experience in potable water tank cleaning and inspections, submit comprehensive safety and work plans, and comply with federal, state, and local regulations. Payment will be made through monthly itemized invoices for completed work, with separate line items for the base bid and optional tank groups.

View the file

Other files

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

STATEMENT OF WORK

NATIONAL PARK SERVICE

WATER STORAGE TANK CLEANING and INSPECTION at THREE NATIONAL PARKS in ALASKA

PART 1 – GENERAL

ITEM 1 - DESCRIPTION OF WORK

1.1 Background: The work under this contract consists of cleaning, inspecting, and providing individual reports on multiple potable water tanks and appurtenances for up to three National Parks and 8 tanks in

Alaska. All water systems consist of a treatment facility, storage tanks and distribution piping serving park staff and the public and are considered public water systems (PWS) regulated by the Alaska

Department of Environmental Conservation (ADEC) and the US Public Health Service (USPHS).

1.2 Parks and Tanks Covered by the Contract Documents: The project sites include up to three

National Parks and up to 8 tanks.

Park

Acronym Tank Name

Tank

Material

Volume

(gal.)

Geographic Location

Latitude / Longitude

DENA Front Country Primary Tank Concrete 47,000 Front Country, Denali, Alaska

DENA Front Country Summer Tank Steel 150,000 Front Country, Denali, Alaska

DENA Rock Creek West Reservoir Concrete 50,500 Headquarters, Denali, Alaska

DENA Rock Creek East Reservoir Concrete 50,500 Headquarters, Denali, Alaska

DENA C Camp Tank Steel 70,000 Maintenance Area, Denali, Alaska

DENA Savage Campground Tank Steel 10,000 Savage CG, Denali, Alaska

KATM King Salmon FAA Water Tank Steel 83.000 King Salmon, Alaska

WEAR

N.W. Arctic Heritage Center

Fire Tank Steel 5,000 Kotzebue, Alaska

A. Denali National Park & Preserve (DENA) is approximately a 4.5-hour drive north of Anchorage.

Lodging is generally available just outside of the park from approximately May 15th-Sept.15th.

1. The DENA Front Country Water System has two finished water storage tanks.

a. Front Country Water System Primary Tank: The 47,000-gallon primary tank is for year-round usage that is a below grade concrete tank constructed in approximately 1975 and stores treated potable water. The tank is 34 feet in diameter, 8 feet high, and has a 2’-6” x 2’-0” roof hatch at grade. (63°43'56.87"N / 148°55'41.77"W)

b. Front Country Water System Summer Tank: The 150,000-gallon above ground steel tank is for summer-use only to meet the increased visitor demand and was constructed in approximately 2005 and stores treated potable water. The tank is 46’-6” in diameter, 12 feet tall and has a 2’ x 2’ roof hatch with a un-caged ladder for access to the top of the tank. (63°43'56.74"N / 148°55'43.87"W)

Both tanks are open to the atmosphere and located at the Front Country water treatment building. Both tanks can be individually isolated off-line as necessary during cleaning work.

2. The DENA Rock Creek Water System has two finished water reservoirs and one storage tank.

a. Rock Creek Water System East & West Reservoirs: The two below ground concrete reservoirs are located in the headquarters area and are 50,564 gallons each with a shared common wall, were constructed in approximately 1985 and store treated potable water. Each reservoir is 26’-0” x 26’-0” with a working water depth of approximately 10 feet and each has a 2’-6” x 3’-0” roof hatch at grade. (63°43'22.58"N / 148°58'4.16"W)

b. C Camp Water System: The 70,000-gallon above ground steel tank is located in the park maintenance shop area, was constructed in approximately 2003 and stores treated potable water. The tank is 29’-8.62” in diameter, 14 feet tall, and has a 2’ x 2’ roof hatch with a caged ladder for access to the top of the tank. (63°43'28.90"N / 148°57'38.88"W)

Both reservoirs and the C Camp tank are open to the atmosphere. Only the Rock Creek

East & West Reservoirs and can be individually isolated off-line as necessary during cleaning work. The C Camp tank CANNOT be taken off-line during inspection and cleaning work.

3. The DENA Savage Campground Water System is located approximately 13 miles west on the Denali Park Road from the entrance and has one finished water storage tank.

a. The Savage Campground tank is a summer-use only 10,000-gallon steel tank that was installed in approximately 1970 and stores treated potable water. The tank is 26’-6” long, 8 feet in diameter and lays on its side with approximately 5 feet of the tank exposed above grade. There is a 1’-2” x 2’-0” access hatch and the park can provide a ladder for access. The tank is open to the atmosphere and CANNOT be taken off-line during inspection and cleaning work. (63°43'2.27"N / 149°15'20.27"W)

B. Katmai National Park & Preserve (KATM) inspection site is in King Salmon, 285 air miles southwest of Anchorage. Flights can be difficult to book in the shoulder seasons of May and September. Lodging is generally available in King Salmon. Cellular service may not be available in King Salmon depending on the service provider.

1. The KATM FAA Water System has one finished water storage tank.

a. FAA Water System Tank: The 83,000-gallon tank is an above ground steel tank constructed in approximately 1994 and stores treated potable water. The tank is 21 feet in diameter, 32 feet high, and has a 3’ x 3’ roof hatch with a caged ladder for access to the top of the tank but no railing. The tank is open to the atmosphere and located at the FAA Water Treatment building and can be individually isolated off-line as necessary during cleaning work. (58°41'30.88"N / 156°41'17.99"W)

C. Western Arctic Parklands (WEAR) inspection site is in Kotzebue, 547 air miles northwest of

Anchorage. Lodging is generally available in Kotzebue and cellular service may not be available in town depending on the service provider.

1. The WEAR NWAHC Fire System has one tank that is part of the buildings fire suppression system.

a. NWAHC Fire System Tank: The steel tank measures 12' long 5-1/2' wide and 10' tall or approximately 4,935 gallons. It is located inside the visitor center and was specially fabricated for the building in 2009. The building/fire system water comes from a town municipal supply which exceeds the EPA recommendations for manganese levels.

There is a flanged entry hatch on the side of the tank and an 8” outflow on top. The tank is pressurized under normal operating conditions. The Contractor should pay particular attention to the photographs in Appendix A. (66°53'33.42"N / 162°36'19.29"W)

D. NPS supervisors and/or utility system operators will be available during on-site contract work to answer questions.

E. Period of performance: Field work shall be completed between June 1, 2025 and July 15, 2026 when tanks are expected to be at their fullest. Inspection reports shall be delivered electronically no more than 30 days after the completion of each tank inspection and no later than August 15, 2026.

1.3 Description of Tasks:

A. Water Tank Cleaning:

1. All interior water tank cleaning and inspection work shall be conducted using Remote

Operated Vehicle (ROV) equipment and in accordance with AWWA 652-19, Disinfection of

Water Storage Facilities. ROV equipment shall be disinfected before use in water tank interior. Interior tank diving shall not be allowed.

2. Contractor shall clean the interior of potable water storage tanks prior to tank inspection.

Work must be performed in accordance with the American Water Works Association (AWWA) Manual M-42 Standard for Steel Water- Storage Tanks (1999) and the National Fire Protection Association (NFPA) -25, Sections 9.2 and 9.3. Interior tank cleaning and disinfection shall be conducted in accordance with AWWA C652-02 Section 4.4 disinfection procedures. Contractor shall submit for approval a work plan outlining work procedures, equipment and methods for disinfection and sanitizing equipment a minimum 2 weeks in advance of performing the work.

3. Contractor shall clean underwater surfaces to remove bio-growths, sediments, silt, sand, sludge buildup, etc. and thoroughly remove all accumulated bottom sediment and debris from all potable water storage water reservoirs.

4. All accumulated bottom sediment and debris shall be removed in a manner that does not compromise the tank integrity and/or coating system and shall not cause disruption to the use or quality of the water.

5. The reservoir shall remain in operation while the cleaning is in progress. Where it is necessary to shut down operations, it shall be for a minimal period and Contractor shall coordinate tank isolation/valve operation with Park. C Camp and Savage campground tanks shall remain in operation at all time.

6. Cleaning of the tank floor will be performed with a vacuum pump and rotary bristle brush or equal.

7. Turbidity shall be minimal, preserving water quality.

8. Contractor shall use dechlorination equipment during the cleaning process to allow for the disposal of tank water within the park’s boundaries and in accordance with AWWA C655.

9. Sediment and water removed shall be pumped out of the structure to a Park designated discharge point.

B. Water Quality Monitoring

1. Before entry - the chlorine residual and turbidity of the tank contents shall be measured and recorded by the contractor. Samples should be taken from several depths, if possible. If the chlorine residual is less than 0.5 mg/l, sufficient chlorine solution or granules shall be added to raise the residual to at least 0.5 mg/l but not to exceed 3 mg/l.

2. After entry – the chlorine residual and turbidity of the tank shall be measured and recorded at the same locations and at least one bacteriological sample collected and analyzed for coliform bacteria.

3. Acceptable Water Quality

a. Water returned to the distribution system from a tank which has undergone an underwater inspection or cleaning must meet one of the following criteria:

i. If the tank is isolated: A negative bacteriological analysis (coliform absent) from a certified drinking water lab; and after-entry chlorine residual and turbidity measurements that show no degradation when compared to the before-entry measurements.

ii. If the tank is not isolated: After-entry chlorine residual and turbidity measurements that show no degradation when compared to the before-entry measurements, as determined by the contracting officer’s representative. The contractor shall also collect and submit a sample from the tank for coliform analysis to a certified drinking water laboratory, the results of which (24-48 hrs later) must be negative (coliform absent).

Degradation is defined as a reduction in the chlorine residual by 0.2 mg/l or more, or a turbidity increase of 2 NTU or more.

b. If after the tank entry the water fails to meet these criteria, the contractor shall immediately:

i. Isolate the tank, reestablish the chlorine residual in the water in the tank, and collect subsequent bacteriological samples until the results are negative

(coliform absent); or,

ii. The Government will issue a Boil Water Advisory (BWA) for the distribution area served by the tank. The BWA is to remain in effect until bacteriological samples from the tank and the distribution system are negative (coliform absent).

C. Water Tank Inspection:

1. Contractor shall provide a letter of certification stating the ROV is dedicated to potable water use inspection only.

2. No confined space entry will be permitted without the CO’s or designee’s approval and an approved safety plan.

3. Contractor shall coordinate with Park staff to ensure tanks remain as full as possible during cleaning and inspections.

4. Contractor shall determine condition of the tank interiors and exteriors including:

a. Condition of concrete or steel on the interior including approximate percent of cracking, corrosion, settling, type of failure, and locations of concentrated spalling.

b. Corrosion of any exposed reinforcing materials.

c. For steel tanks, the metal loss due to corrosion such as pitting, layered corrosion or physical damage. Special attention shall be paid to joints, seams, bolts and roof column and support members.

d. Condition of any membrane covers, including flexibility and UV damage.

e. OSHA safety compliance of access ladders, anti-climbing devices, anti-fall devices, rails, roof, safety systems and hatches.

f. Sanitary conditions of tank hatches, vents and other penetrations and interior plumbing.

g. Percentage of coating failure and corrosion on any coated surfaces.

h. Condition of foundation and anchors, visual inspection of obvious defects.

i. Water level sensors and associated wiring.

j. Seams, welds/bolted joints and integrity of previous repairs.

k. All other structural members not mentioned above.

1. Inspection Report: Upon completion of the inspection a final inspection report shall be issued.

The report shall present a description of how the work was prosecuted, and inspection findings including photographs and videos as per Parts D & E below. Contractor shall provide recommendations as to what must be corrected to meet applicable AWWA, NFPA, and OSHA

Standards and to identify corrective actions to correct deficiencies. Deficiencies shall be prioritized by significance with a cost estimate breakdown of each item. The final report must be reviewed and signed off by a AMPP Certified inspector for completeness (www.ampp.org).

D. Photo and Documentation: Contractor must provide existing condition and completion photos in the final reports.

1. All photos shall be in focus, show maximum range of depth of field general image and then close up detail image as needed. Photos shall be in JPEG digital form submitted electronically by email or via downloadable internet link a minimum within 14 days from time of taken or as approved by COR.

2. Maintain organized index for photos with date, description, etc.

3. Additional images as needed when questions or emergency situations occur and shall be submitted within 24 hours.

E. Video Documentation: Contractor shall provide high quality color (DVD) video/digital recording inspection in mp4 format of 100% of all internal surfaces, including the roof, walls, floor, hatches, https://gcc02.safelinks.protection.outlook.com/?url=http%3A%2F%2Fwww.ampp.org%2F&data=05%7C02%7CSusan_Lehmann%40nps.gov%7C27f00fb36e9c42787cbb08dd82997e23%7C0693b5ba4b184d7b9341f32f400a5494%7C0%7C0%7C638810317927847616%7CUnknown%7CTWFpbGZsb3d8eyJFbXB0eU1hcGkiOnRydWUsIlYiOiIwLjAuMDAwMCIsIlAiOiJXaW4zMiIsIkFOIjoiTWFpbCIsIldUIjoyfQ%3D%3D%7C0%7C%7C%7C&sdata=1G1o%2Fc7GdSBBSt68%2BqGKvkADUJZ2beHi5jbgdBTT1ZI%3D&reserved=0 joints, gaskets, etc. through closed circuit TV. Video recording shall have real time imprint. Video shall be taken within a timeframe of very low turbidity so as to get clearest picture.

1. Contractor shall provide adequate lighting to thoroughly document all surfaces with video under all conditions of water and surfaces.

2. The Field Inspector shall be on-site during the inspection and shall witness and narrate the underwater camera video footage.

3. The Field Inspector shall provide, recorded on the inspection video, any professional assessment and evaluation comments about the condition of the tank.

4. Videos shall be in mp4 digital form submitted electronically by email or via downloadable internet link a minimum within 14 days from time of taken or as approved by COR.

F. This Scope of Work includes mobilization for the purpose of cleaning and inspection and a final report for each tank as described below. It is the responsibility of the contractor to verify that all the information provided in this solicitation is accurate.

G. All work is to be completed in accordance with all applicable Codes and Standards. Contractor shall, without additional expense to the Government, be responsible for obtaining necessary licenses and permits, and for complying with any and all applicable federal, state, and borough laws, codes, and regulations pertaining to the performance of the service that is to be rendered.

H. Contractor and Field Inspector must have 3-years of prior experience with potable water tank cleaning and inspections and provide a qualification letter substantiating such experience. Letter should have a minimum of 3 projects with references and list relevant team members for the project including any licensed or certified personnel required.

I. All work shall be performed under a single contract.

ITEM 2 - EXISTING UTILITIES

2.1 Notify CO and COR not less than five business days in advance of proposed site visit and any anticipated utility interruptions.

ITEM 3 - CONTRACTOR’S USE OF PREMISES

3.1 Conduct of Operations: At all times the contractor shall conduct his operations in conformance with the rules and regulations promulgated by the Secretary of the Interior for the National Park Service, and applicable park rules and regulations prescribed by the Park Superintendent.

A. No signs or advertisements (except those specified herein and as required for safety) shall be displayed on the project site or within the park unless approved by the Contracting Officer.

B. Smoking is not permitted within any Federal building or within 25 feet of entrances, operable windows, or outdoor air intakes.

C. Public Use of Site: Contractor shall at all times conduct operations to ensure the least inconvenience to the public.

3.2 On-site work hours: Work shall be generally performed during normal business working hours of 7 a.m. to 5 p.m., Monday through Friday, except when otherwise requested by the Contractor and approved by the CO.

A. Work on Saturdays, Sundays, Federal holidays, early morning, or at night may not be performed without prior consent from the CO and COR. Submit requests for work outside of the stated normal business hours to the CO and COR for approval at least 48 hours in advance of the work.

The following Federal holidays are observed by the National Park Service:

New Year Day

Martin Luther King, Jr’s Birthday

Washington’s Birthday

Memorial Day

Juneteenth National Independence Day

Independence Day

Labor Day

Columbus Day

Veterans Day

Thanksgiving Day

Christmas Day

B. Note: Any of the above holidays falling on a Saturday will be observed on the preceding Friday;

holidays falling on Sunday will be observed on the following Monday. The specific day that each holiday is recognized for each year can be found at the following site: Federal Holidays

(opm.gov).

3.3 Contractor Use of Site:

A. General: Contractor shall have limited use of the site for project operations. Limit use of premises to project area immediately surrounding each tank. Do not disturb portions of Project site beyond areas in which the Work is indicated.

B. Driveways and Entrances: Keep driveways, access roads, and entrances serving premises clear and available to Government, Government's employees, and emergency vehicles at all times.

Park in locations designated by COR or their designated park representative.

C. Limit site disturbance: Discharge wash/flushing water to a location/area designated by the COR or their designated park representative.

D. Utilities

a. General: Cost or use charges for temporary facilities shall be included in the Contract

Sum as required.

b. Water Service: Water from existing water system is available for use without metering and without payment of use charges. Provide connections and extensions of services as required for project operations without any additional permit costs. Use resources wisely and minimize waste of water.

https://www.opm.gov/policy-data-oversight/pay-leave/federal-holidays/#url=2022 https://www.opm.gov/policy-data-oversight/pay-leave/federal-holidays/#url=2022

c. Electric Power Service: 120V Electric power from existing system is available for use without metering and without payment of use charges. Provide connections and extensions of services as required for performance operations without any additional permit costs. Power may or may not meet your power tool requirements, provide generators if questionable. Use power in a resourceful manner and avoid excess power waste.

d. Toilets: Restrooms are available in park administrative buildings as designate by the park representative.

E. Security and Protection on facilities:

a. All tanks are accessible by a standard vehicle but located in restricted access areas. A designated Park employee shall escort contractors’ personnel and be onsite for the duration of the work. Park to secure the site daily.

b. Environmental Protection: Provide protection, operate temporary facilities, and conduct construction in ways and by methods that comply with state and federal environmental regulations and that minimize possible air, waterway, and subsoil contamination or pollution or other undesirable effects.

3.4 Storage - Staging Areas:

A. Establishment of a project camp is not permitted.

B. The contractor is responsible to provide written notification to the Contracting Officer detailing any staging area needs that will be requested from the National Park Service (NPS) in advance of work to allow time for resource coordination.

3.5 Fire and Life Safety:

As a minimum, conduct one weekly 15 minute "toolbox" safety meetings. These meetings shall be conducted by a foreman or supervisor and attended by all project personnel at the worksite. Topics need to coincide with work scheduled for the following week. Document and submit meeting minutes to the CO and COR within one day after the meeting and document the meetings on the daily reports.

A. Store and handle hazardous materials in accordance with manufacturer’s and OSHA 29CFR1926 Subpart D requirements 1926 | Occupational Safety and Health Administration (osha.gov). Maintain readily available, on site, MSDS/Safety Data Sheets (SDS) for each chemical.

i. Immediately report all spills of hazardous materials to the CO, COR and park.

ii. Maintain a spill emergency response kit.

iii. Train employees how to respond to a spill and use the emergency response kit.

B. The contractor shall prosecute the work in accordance with OSHA regulations 1910 and 1926 concerning General Construction safe working procedures.

C. Fall protection safety shall be in accordance with OSHA regulations found in 1926 subpart M.

D. All elevated tank work by the contractor shall be conducted only after a review and approval by the NPS safety officer.

E. Contractor to submit a safety plan 2 weeks in advance of the work.

ITEM 4 – GOVERNMENT FURNISHED ITEMS: None https://www.osha.gov/laws-regs/regulations/standardnumber/1926 https://www.osha.gov/laws-regs/regulations/standardnumber/1926

ITEM 5 - QUALITY ASSURANCE

5.1 The list of abbreviations, standards and organizations which may be used in/referred within the

Project Specifications or Special Provisions, may be found linked from the listed page below. On the home page, follow the link under “Contracting and Procurement” labeled “NPS Reference

Standards.”

https://www.nps.gov/orgs/1671/do-business-with-us.htm

5.2 All materials and methods used for this contract must meet or exceed the current local, state, and federal codes, standards, and regulations applicable to the contract work which includes American Water Works Association (AWWA) standard C652 and Reference

Manual 83A Public Health Protection and Prevention (April 28, 2023).

A. All work performed on this contract shall adhere to the most current standards of the following:

i. American Water Works Association (AWWA);

ii. RM-83A Public Health Protection and Prevention (NPS/PHS)

iii. U.S. Occupational Safety & Health Administration (OSHA);

iv. Association for Materials Protection and Performance (AMPP);

v. American Concrete Institute (ACI);

vi. Environmental Protection Agency (EPA); and,

vii. All State, local, and federal regulations related to the service performed.

ITEM 6 - ACCIDENT PREVENTION

6.1 Description: The work of this section consists of establishing and implementing an effective accident prevention program (APP) and providing a safe environment for all personnel and visitors.

6.2 Submittals:

A. Accident Prevention (Safety) Plan (APP): Submit a site-specific accident prevention (safety) plan. The Plan shall be written to comply with OSHA and project requirements (a generic plan is not acceptable) including but not limited to the following:

1. Name and qualifications of responsible supervisor to carry out the program.

2. First aid and rescue procedures.

3. Training, both initial and continuing.

4. Outline of each phase of the work, the hazards associated with each major phase, and the methods proposed to provide for property protection and safety of the public, National Park

Service personnel, and Contractor's employees. Identify the work included under each phase, with a Job Hazard Analysis (JHA)/Job Safety Analysis (JSA), etc. A sample JHA template may be provided upon request.

6. Contractor to identify nearest location of medical facility for emergencies

7. Recognition that work will be performed in remote areas with limited communication or cell phone coverage if applicable.

8. Supplemental hazard specific plans may be required IAW 29 CFR 1926 or 1910.

https://www.nps.gov/orgs/1671/do-business-with-us.htm

6.3 Qualification of Employees:

A. During the performance of the work, the contractor shall provide adequate professional supervision and quality control to assure the accuracy, quality, completeness and progress of work.

B. Ensure that employees are physically qualified to perform their assigned duties in a safe manner to include operators of vehicles and equipment. Provide operating instructions for all equipment.

C. Do not allow employees to work whose ability or alertness is impaired because of drugs, fatigue, illness, intoxication, or other conditions that may expose themselves or others to injury.

6.4 Accident Reporting: The Contractor shall report all accidents to the CO and COR as soon as safely possible and assist the CO and COR and other officials as required in the investigation of the accident.

6.5 First Aid Facilities: Provide access to facilities for the number of employees and appropriate to the hazards associated with the types of ongoing project work at the site.

6.6 Emergency Instructions: Post telephone numbers and reporting instructions for ambulance, physician, hospital, fire department, and police in conspicuous locations at the work site.

6.7 Personal Protective Equipment (PPE): It is the Contractor's responsibility to require all those working on or visiting the site to wear necessary protective equipment at all times.

A. PPE must meet requirements of applicable ANSI standards. Selection shall conform to OSHA

29CFR 1926 Subpart E.

B. A hard hat use area shall be designated by the Contractor. The hard hat area shall be posted by the Contractor in a manner satisfactory to the Contracting Officer.

C. All PPE shall be serviceable at all times. At a minimum, maintain two sets of extra PPE including hard hats and all other Accident Prevention Plan required equipment.

6.8 Hazardous Materials: It shall be the responsibility of all operators and contractors, functioning within the park to properly cleanup, mitigate and remediate if necessary, all unauthorized discharges of hazardous materials or non-hazardous chemical and biological products released from fleet and/or other support vehicles or stationary sources. Response shall be consistent with guidelines established by federal, state and local regulations, and as outlined within the operator's Safety or Hazardous Materials

Business Plan.

A. If a spill, leak or other release occurs, the operator shall as soon as possible, without impeding cleanup, notify the National Park Service Emergency Dispatch.

ITEM 7 - PRECONSTRUCTION CONFERENCE: If the Contracting Officer decides to conduct a preconstruction conference, the successful offeror will be notified and will be required to attend. The

Contracting Officer’s notification will include specific details regarding the date, time, and location of the conference, any need for attendance by subcontractors, and information regarding the items to be discussed. See Item 9.1C below.

ITEM 8 - SUBMITTALS

8.1 General Submittal Procedures:

A. General: Prepare and submit submittals electronically to the Contracting Officer and COR.

B. Preconstruction Conference Submittal: Satisfactory evidence of liability insurance coverage and workman’s compensation, and any applicable bonds, must be submitted within 10 calendar days of Notice of Award. The following items shall be submitted a minimum of one week prior to the Preconstruction Conference. If all of these documents have not been received one week prior to the scheduled Pre-performance Conference date, the conference will be cancelled, Notice to Proceed may not be issued, and the Contracting Officer will consider other contractual remedies. Work shall not commence until written Notice to Proceed has been issued. Contracting Officer will notify Contractor of tentative date for the Pre-performance Conference:

1. Letter designating Project Superintendent.

2. Tank Inspection Schedule-due 10 days after award

3. Method of performing C Camp & Savage Campground tanks inspections without taking the tanks off-line.

4. Work Plan- Must be approved 2 weeks before start of work.

5. Safety Plan- Must be approved 2 weeks before start of work.

6. Accident Prevention (Safety) Plan (see Section 7 of this document).

7. A list of Subcontractors for this project.

8. Written statements from subcontractors certifying compliance with applicable labor

9. standard clauses (SF1413).

10. Quality Control Plan.

11. Waste Management Plan.

12. If the need for confined space entry is anticipated, Contractor shall submit the identified trained personnels and the means of rescue.

ITEM 9 – TEMPORARY SERVICES

9.1 It is the Contractor’s responsibility to provide temporary services, equipment, tools, and skilled labor as required for the chosen means and methods to perform the work in accomplishing this Contract.

ITEM 10 - PROJECT CLOSEOUT

12.1 CLEANUP

1. Remove all tools, equipment, excess materials, project debris, and trash from the project site. Legally dispose of trash and debris at authorized facilities off Government property.

Restore or refinish any surfaces damaged during performance of the contract work. Leave project site clean and ready for use at the time of final inspection.

2. Legally disposal of all excess and unusable materials at authorized disposal facilities.

10.2 FINAL INSPECTION AND ACCEPTANCE OF WORK

A. When all work including site restoration and cleanup has been completed, the Contractor shall contact the COR to arrange the final inspection. The final inspection should be conducted by the COR within 5 working days after receipt of the Contractor’s request.

B. The Contractor will be notified of any deficiencies found during the final inspection. After all deficiencies have been corrected and all required closeout submittals have been forwarded to the COR, the CO will issue a letter of final acceptance and request the release of claims.

C. Contractor shall supply a “Certificate of Performance” for each reservoir to the CO at the completion of the project. At a minimum, the Certificate will indicate the date of cleaning, the name of the servicing company, areas cleaned, and those area(s) not cleaned.

D. Contractor shall submit four (4) copies of a detailed “Service Report” at the conclusion of the project to the CO (to include fully narrated DVD of the internal inspection). This Report shall indicate, but not be limited to, the following:

1. Job site location and address

2. Date and time of cleaning

3. Type of tank

4. Name and certificate number of the technician(s)

5. Measurements and recording of bottom sediment depth

6. A high resolution, DVD video/digital recording providing a detailed review of structural concrete, steel, landings, etc. of the interior of the structure

7. Digital photos of ladders, piping (above ground), hatches, vents and all other structural/ mechanical components

8. Recommended next service due date

9. Identify any mechanical, accessibility, and safety concerns

10. Identify any tank defects and recommendations for repair or upgrades

11. Identify in detail which component(s) is or/need repair/replacement/upgrade

12. Identify all repairs or upgrades needed to ensure the tank is in proper working order according to AWWA standards

13. A detailed cost estimate for any repair/upgrades found in the inspection/cleaning process.

E. Contractor shall provide a schematic diagram of each tank showing the location of each problem area with corresponding still color image. 6. Contractor will provide detailed information and recommendations to maximize the serviceable life of each tank and provide information for possible modifications to improve operational effectiveness.

ITEM 11 - DEFINITION OF BID ITEMS

A. BASE BID: Cleaning and Inspection of the DENA Front Country Primary & Summer Tanks, 2

Tanks Total - Fixed Lump Sum Price

B. Option Item 1: Cleaning and Inspection of the DENA Rock Creek East & West Reservoirs, 2

Tanks Total - Fixed Lump Sum Price

C. Option Item 2: Cleaning and Inspection of the DENA C Camp & Savage Campground Tanks, 2 Tanks Total - Fixed Lump Sum Price

A. Option Item 3: Cleaning and Inspection of the KATM King Salmon FAA Water Tank, 1 Tank

Total - Fixed Lump Sum Price

B. Option Item 4: Cleaning and Inspection of the WEAR N.W. Arctic Heritage Center Fire Tank, 1 Tank Total - Fixed Lump Sum Price

ITEM 12 - FEE AND PAYMENT

Request for progress payment shall be made on monthly-itemized invoices submitted for completed work.

Invoices shall include a description of the work, the cost for the billing cycle, and the cost to date for each

BASE BID Park and Option Item.

PART 2 – PRODUCTS (NOT USED)

PART 3 – EXCUTION (NOT USED)

END OF SECTION

Appendix A

DENA Front Country Primary Tank, 47,000 gal., Front Country, Denali, Alaska

DENA Front Country Summer Tank, 150,000 gal., Front Country, Denali, Alaska

DENA Rock Creek East & West Reservoirs, 50,500 gal., Headquarters, Denali, Alaska

DENA C Camp Tank, 70,000 gal., Maintenance Area, Denali, Alaska

DENA C Camp Tank, 70,000 gal., Maintenance Area, Denali, Alaska

DENA Savage Campground Tank, 10,000 gal., Savage CG, Denali, Alaska

KATM King Salmon FAA Water Tank, 83.000 gal., King Salmon, Alaska

WEAR N.W. Arctic Heritage Center Fire Tank, 5,000 gal., Kotzebue, Alaska