SRS Title II Application updated Dec 16 2020.docx
DOCX document 87 KB Posted
- Opportunity number
- L21AS00235
About this file
SRS Title II Application updated Dec 16 2020.docx
View the file
Other files
| File | Type | Posted |
|---|---|---|
| Foa_Content_of_L21AS00235 Amended.pdf | ||
| 03 SRS Attachments A & B.docx | DOCX document | |
| Foa_Content_of_L21AS00235 (2).pdf |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Attachment A: Project Proposal SECURE RURAL SCHOOLS – Title II Project Submission Form FY 2017-2020 Elections
SECURE RURAL SCHOOLS AND COMMUNITY SELF DETERMINATION ACT OF 2000, Public Law 106-393 (16 U.S.C. 500) as amended by the “Further Consolidated Appropriations Act, 2020” (Public Law 116-94)
Person Submitting Proposal:
Date:
E-mail :
Phone:
Organization Name:
FOA No.:
FOA Title:
Recipient Project Title:
Estimated Period of Performance:
BLM Contact Name:
BLM Field and District Office:
County Project is Located:
10. Project Location (Attach project area map)
a. 4th Field Watershed Name and HUC #
b. Township
Range
Section(s)
Township
Range
Section(s)
Township
Range
Section(s)
Township
Range
Section(s)
Township
Range
Section(s)
c. BLM District
d. BLM Resource Area
| e. State / Private / Other lands involved? |
| Yes |
No
If yes, specify:
11. Project Goals and Objectives [Sec. 203(b)(1)] * (max. 7 lines)
How your objectives of the project support your mission.
Describe how your objectives of your project meets one or more of the DOI priorities described in this announcement.
Describe your project objectives, goals, and how your mission relates to this announcement.
Describe why this support is being requested.
12. Project Description [Sec. 203(b)(1)] (max. 30 lines.)
Describe the details of the project, the procedures to be used, how data will be collected, analyzed, and interpreted, etc. Proposals must have measurable outcomes.
| 13. Coordination of this project with other related project(s) on adjacent lands? |
| Yes |
No
If yes, then describe (max. 10 lines)
14. How does proposed project meet purposes of the Legislation? [Sec. 203(b)(1)] (check all that apply)
Improves maintenance of existing infrastructure. [Sec. 2 (2)(A)(i)]
Implements stewardship objectives that enhance forest ecosystems. [Sec. 2 (2)(A)(ii)]
Restores and improves land health and water quality. [Sec. 2 (2)(A)(iii)]
Improves cooperative relationships between people that use and care for Federal land and the agencies that manage Federal land [Sec. 2 (3)]
15. Project Type [Sec. 203(b)(1)] (check one)
Road Maintenance [Sec. 2 (2)(C)(i)]
Trail Maintenance [Sec. 2 (2)(C)(i)]
Road Decommission/Obliteration [Sec. 2(2)(C)(i)]
Trail Obliteration [Sec. 2 (2)(C)(i)]
Soil Productivity Improvement [Sec. 2 (2)(C)(ii)]
Forest Health Improvement [Sec. 2 (2)(C)(iii)]
Watershed Restoration & Maintenance.
[Sec. 2 (2)(C)(iv)]
Fish Habitat Restoration [Sec. 2 (2)(C)(v)]
Control of Noxious Weeds [Sec. 2 (2)(C)(vi)]
Wildlife Habitat Restoration [Sec. 2 (2)(C)(v)]
Reestablish Native Species [Sec. 2 (2)(C)(vii)]
Fuels Management/Prevention [Sec. 2 (2)(C)(iii)]
Other Infrastructure Maintenance [Sec. 2 (2)(C)(i)]
Conservation Education [Sec. 2 (3)]
| Other Project Type [Sec. 2 (2)(C)] |
| (Specify) |
16. Measure of Project Accomplishments/Expected Outcomes [Sec. 203(b)(5)]
a. Total Acres
b. Total Miles
c. Number of Structures
d. No. Laborer Days
e. Estimated People Reached (for conservation education projects):
f. Other (specify)
17. Merchantable Material Contracting Pilots [Sec. 204(e)(3)]
| Will the project generate merchantable wood products? (circle one) |
| Yes |
No
18. Proposed Method(s) of Accomplishment (check those that apply
Contract
| Federal Workforce |
| Other (specify below) |
County Workforce
Volunteers
19. Estimated Completion Date [Sec. 203(b)(2)]
20. Anticipated Project Costs [Sec. 203(b)(3)] (Double click on table to enter spreadsheet)
| Column A |
| Column B |
| Column C |
| Column D |
Item Federal Agency Appropriated Contribution [Sec. 203 (b) (4)] Requested Title II Contribution [Sec.
203(b)(4)] Other Contributions [Sec.
203(b)(4)]
Total Available Funds
a. Field Work & Site Surveys
b. NEPA
c. ESA Consultation
d. Permit Acquisition
e. Project design & Engineering
f. Contract/Grant Preparation
g. Contract/Grant Administration
h. Contract/Grant Cost
i. Salaries
j. Materials & Supplies
k. Monitoring
l. Other
| m. Project Sub-Total |
| $0 |
| $0 |
| $0 |
| $0 |
n. Indirect Costs
| o. Total Cost Estimate |
| $0 |
| $0 |
| $0 |
| $0 |
21. Is the Project Scalable?
a. Yes or No (Circle one)
| b. If Yes - What is the minimum amount needed? |
| $ |
c. Explanation about the scaling of the project:
22. Identify Source(s) of Other Funding Identified in Column C Above [Sec. 203 (b)(4)] Explain whether or not they are secured and clarify any other aspects that might be useful in evaluating the application.
23. BLM District Office jurisdiction of your project? Refer to map at https://blm-egis.maps.arcgis.com/apps/webappviewer/index.html?id=a446ec91307c45898cafe57a5f26982e
Check all that apply:
| Northwest Oregon District |
| Roseburg District |
| Coos Bay District |
| Medford District |
| Lakeview District |
(Klamath Falls Field Office)
24. If project was also funded in previous Fiscal Years show amounts below
FY2018
FY2019
FY2020
25. How will cooperative relationships between the people that use federal lands and the agencies that manage them be improved? List known partnerships or collaborative opportunities [Sec. 2 (3)]
26. How is this project in the best interest of the community? [Sec. 203 (b)(7)]
27. How does project benefit O&C or Coos Bay Wagon Road or National Forest lands/resources? The project must show a benefit to O&C, Coos Bay Wagon Road or National Forest lands/resources to be considered for funding.
28. Target Species Benefited (if applicable)
29. Status of Project Planning [Sec. 204 (b)]
a. NEPA Complete?
Yes
No
b. If no, give estimated date of completion
| c. NOAA Fisheries Sec. 7 ESA Consultation Complete? |
| Yes |
No
Not Applicable
| d. USFWS Sec. 7 ESA Consultation Complete? |
| Yes |
No
Not Applicable
| e. DSL/ODFW Permits for In-stream Work Obtained? |
| Yes |
No
Not Applicable
| f. DSL/COE 404 Fill/Removal Permit Obtained? |
| Yes |
No
Not Applicable
| g. SHPO Concurrence Received? |
| Yes |
No
Not Applicable
| h. Project Design(s) Completed? |
| Yes |
No
h. If you answered no to any of the questions above, please describe who will accomplish the work and when it will be complete:
NEPA=National Environment Policy Act, NOAA=National Oceanic and Atmospheric Administration, USFWS=United States Fish and Wildlife Service, DSL = Dept. of State Lands, ODFW = Oregon Department of Fish and Wildlife, COE = Army Corps of Engineers, SHPO = State Historic Preservation Officer
30. Monitoring Plan [Sec. 203(b)(6)]
a. What methods and measures of evaluation will be made to determine whether the proposed project meets or exceeds the desired ecological conditions? [Sec. 203(b)(6)(B)(i)]
Who is responsible for this monitoring item?
b. How will the project be evaluated to determine whether or not the proposed project contributes towards creating local employment and/or training opportunities, including summer youth jobs programs such as the Youth Conservation Corps? [Sec. 203(b)(6)(B)(i)]
Who is responsible for this monitoring item?
c. What methods and measures of evaluation will be established to determine how well the proposed project improves the use of, or added value to, any products removed from federal lands consistent with the purposes of this Act? [Sec. 203(b)(6)(B)(ii) and Sec. 204(e)(3)]
Who is responsible for this monitoring item?
d. Identify total funding needed to carry out specified monitoring tasks (Item k., Column D in Project Costs table)
What are the sources for funding?
31. What are the plans, analyses, legislation, or other supporting documents that support your application? (E.g., a watershed analysis, Oregon Plan for Salmon, Watershed Council plan, Resource Management Plan or another document that provides context within your group or agency)
32. Who are the other key people responsible for the success of this project? (list their names and titles)
List key project personnel and responsibilities, along with their contact information.
Describe the time to be dedicated to the project, how their experience and qualifications are appropriate to the success of the project.
List contractors, sub awards, consultants, if known, and their qualifications
33. Project location map(s) or photo(s):
At a minimum, the map should show the project location, roads, and streams; private versus BLM ownership; all maps should be printed on 8.5 x 11” paper. The photographs should show the project site or a representative portion of it. More than one photograph can be submitted, but they must all fit on an 8.5 x 11” page. Map(s) and photograph(s) must be incorporated/attached this application – do not submit photos and maps as separate documents.
34. All project proposals from nonfederal applicants MUST BE SUBMITTED through the Grants.gov portal and comply with all deadlines and requirements of the Secure Rural Schools, Title II Funding Opportunity Announcement. Internal BLM project must be submitted through SRS Title II SharePoint by February 23, 2021.
image1.png
File details come from the government source that posted it.