B01 RFQ Parking Lot Improvements Lower Brule.pdf
PDF 1 MB Posted
- Attached to
- Parking Lot Improvements Lower Brule Federal contract opportunity
- Solicitation number
- 75H70123Q00003
About this file
This federal solicitation requests proposals for a parking lot improvement project at the Lower Brule Health Center in Lower Brule, South Dakota. Key details include:
-
The project scope involves replacing the existing non-compliant concrete entrance ramp, upgrading ADA parking spaces, repairing damaged pavement, and replacing failing entry doors.
-
The estimated project value is between $100,000 and $250,000.
-
The solicitation is set aside for HUBZone small businesses.
-
Proposals are due no later than March 15, 2023 by 5:00 PM EST and shall be submitted electronically.
-
The applicable Davis-Bacon wage determination is SD20230022 dated January 6, 2023.
-
The period of performance is 365 calendar days from notice to proceed.
View the file
Other files for this federal contract opportunity
| File | Type | Posted |
|---|---|---|
| B05-A02 Attachment SOW PLILB Edited 3Mar2023.pdf | ||
| B01 Attachment 3 GP21LB500C06-Maps and closest towns.pdf | ||
| B01 Attachment 2 LB Parking Lot Drawings.pdf | ||
| B01 Attachment 4 Self Performed Calculation Sheet (Construction).docx | DOCX document | |
| B01 Attachment 1 Wage Det SD20230022 6Jan2023.pdf |
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
75H70123Q00003 Parking Lot Improvements Lower Brule
INDIAN HEALTH SERVICE
DIVISIONOF ENGINEERING SERVICES
Solicitation Number: 75H70123Q00003
Parking Lot Improvements Lower Brule, GP21LB500C6
PROPOSAL DUE DATE:
no later than 03/15/2023, 5:00 PM EST
PROJECT TABLE OF CONTENTS:
Section Taxonomy
Section A Standard Form 1442, Solicitation, Offer, and Award
Section B Schedule of Items / Price Schedule
Section C Description and Specification (Statement of Work)
Section D Packaging and Markings
Section E Inspection and Acceptance
Section F Deliveries or Performance
Section G Contract Administration Data
Section H Special Contract Requirements
Section I Contract Clauses
Section J List of Documents, Exhibits
Section K Representations and Certifications
Section L Instruction, Conditions andNotices
Section M Evaluation Factors for Award
Proposals must set forth full, accurate, and complete information as required by this request for proposal (including attachments). The penalty for making false statements in proposals is prescribed in 18 U.S.C. 1001.
(See ).
SOLICITATION, OFFER,
AND AWARD
(Construction, Alteration, or Repair) IMPORTANT - The "offer" section on the reverse must be fully completed by offeror.
9. FOR INFORMATION
CALL:
NOTE: In sealed bid solicitations "offer" and "offeror" mean "bid and "bidder".
SOLICITATION
1. SOLICITATION NUMBER
5. REQUISITION/PURCHASE REQUEST NUMBER
CODE
6. PROJECT NUMBER
8. ADDRESS OFFER TO
4. CONTRACT NUMBER
7. ISSUED BY
11. The contractor shall begin performance within
12a. THE CONTRACTOR MUST FURNISH ANY REQUIRED PERFORMANCE AND PAYMENT BONDS?
(If "YES", indicate within how many calendar days after award in Item 12b.)
13. ADDITIONAL SOLICITATION REQUIREMENTS:
a. Sealed offers in original and
b. An offer guarantee
c. All offers are subject to the (1) work requirements, and (2) other provisions and clauses incorporated in the solicitation in full text or by reference.
d. Offers providing less than
STANDARD FORM 1442 (REV. 8/2014)
Prescribed by GSA - FAR (48 CFR) 53.236-1(d) calendar days for Government acceptance after the date offers are due will not be considered and will be rejected.
is, is not required.
local time containing offers shall be marked to show the offeror's name and address, the solicitation number, and the date and time offers are due.
(date). If this is a sealed bid solicitation, offers will be publicly opened at that time. Sealed envelopes copies to perform the work required are due at the place specified in Item 8 by (hour) award, YES NO notice to proceed. This performance period is mandatory negotiable.
calendar days and complete it within calendar days after receiving
a. NAME b. TELEPHONE NUMBER (Include area code) (NO COLLECT CALLS)
12b. CALENDAR DAYS
2. TYPE OF SOLICITATION
SEALED BID (IFB)
NEGOTIATED (RFP)
3. DATE ISSUED PAGE OF PAGES
75H70123Q00003
Indian Health Service (IHS) Division of Engineering Services (DES) - Seattle 701 5th Ave, Suite 1650 Seattle, WA 98104 daniel.cotto@ihs.gov; Andrew.Hart@ihs.gov
10. THE GOVERNMENT REQUIRES PERFORMANCE OF THE WORK DESCRIBED IN THESE DOCUMENTS (Title, identifying number, date)
This RFQ is being issued as 100% HUBZone Small Business Set-Aside under NAICS 238990 All Other Specialty Trade Contractors. The Size Standard is $19 million TITLE: Parking Lot Improvements Lower Brule.
ESTIMATED MAGNITUDE OF CONSTRUCTION (APR 1985) (FAR 36.204): The estimated magnitude of the proposed construction is between $100,000.00 - $250,000.00.
Proposals are due no later than 03/15/2023, 5:00 PM EST via email to daniel.cotto@ihs.gov and Andrew.Hart@ihs.gov.
U.S. Department of Labor Wage Determination: SD20230022, dated 1/6/2023 is applicable to this solicitation.
Site Visit: See FAR 52.236-27, Site Visit Construction.
TERO office - (605) 473‐5800 ext. 48171.
Indian Health Service (IHS) Division of Engineering Services (DES) - Seattle 701 5th Ave, Suite 1650 Seattle, WA 98104 daniel.cotto@ihs.gov; Andrew.Hart@ihs.gov
Daniel Cotto, daniel.cotto@ihs.gov 206-615-2790
GP21LB500C6
1 5202/13/2023
1 2:00 PM
03/08/2023
17. The offeror agrees to perform the work required at the prices specified below in strict accordance with the terms of this solicitation, if this offer is accepted calendar days after the date offers are due. (Insert any number equal to or greater than the minimum requirement by the Government in writing within stated in Item 13d. Failure to insert any number means the offeror accepts the minimum in Item 13d.)
OFFER (Must be fully completed by offeror)
AMOUNTS
18. The offeror agrees to furnish any required performance and payment bonds.
19. ACKNOWLEDGMENT OF AMENDMENTS
(The offeror acknowledges receipt of amendments to the solicitation -- give number and date of each)
AMENDMENT
NUMBER
DATE.
AWARD (To be completed by Government)
CONTRACTING OFFICER WILL COMPLETE ITEM 28 OR 29 AS APPLICABLE
14. NAME AND ADDRESS OF OFFEROR (Include ZIP Code)
CODE FACILITY CODE
15. TELEPHONE NUMBER (Include area code)
16. REMITTANCE ADDRESS (Include only if different than Item 14.)
20a. NAME AND TITLE OF PERSON AUTHORIZED TO SIGN OFFER (Type or print)
21. ITEMS ACCEPTED:
22. AMOUNT
26. ADMINISTERED BY
30a. NAME AND TITLE OF CONTRACTOR OR PERSON AUTHORIZED TO SIGN (Type or print)
31c. DATE
STANDARD FORM 1442 (REV. 8/2014) BACK
31b. UNITED STATES OF AMERICA
BY
31a. NAME OF CONTRACTING OFFICER (Type or print)
29. AWARD (Contractor is not required to sign this document.) Your offer on this solicitation is hereby accepted as to the items listed. This award consummates the contract, which consists of (a) the Government solicitation and your offer, and (b) this contract award. No further contractual document is necessary.
30b. SIGNATURE 30c. DATE
28. NEGOTIATED AGREEMENT (Contractor is required to sign this document and return and deliver all items or perform all work requirements identified on this form and any continuation sheets for the consideration stated in this contract. The rights and obligations of the parties to this contract shall be governed by (a) this contract award, (b) the solicitation, and (c) the clauses, representations, certifications, and specifications incorporated by reference in or attached to this contract.
copies to issuing office.) Contractor agrees to furnish
24. SUBMIT INVOICES TO ADDRESS SHOWN IN
(4 copies unless otherwise specified)
23. ACCOUNTING AND APPROPRIATION DATA
ITEM 25. OTHER THAN FULL AND OPEN COMPETITION PURSUANT TO
27. PAYMENT WILL BE MADE BY
10 U.S.C. 2304(c) ( ) 41 U.S.C. 3304(a) ( )
20b. SIGNATURE 20c. OFFER DATE
IHS GREATPLAINS AREA
Great Plains Area IHS
115 4TH AVENUE SE
Aberdeen SD 57401-4301
Indian Health Service (IHS) Division of Engineering Services (DES) - Seattle 701 5th Ave, Suite 1650 Seattle, WA 98104
Section B Price Schedule
DESCRIPTION SCOPE SECTION QUANTITY UNIT UNIT PRICE EXTENDED PRICE
Demolition 2A 1 LS
Electrical 2B 1 LS
Concrete 2C 1 LS
Metals 2D 1 LS
Openings 2E 1 LS
Exterior Improvements 2G 1 LS
General
Requirements/Conditions, Taxes, TERO, Etc.
6C 1
TOTAL
LS
NOTES :
Price Schedule .
Quantities . Price Schedule includes items that are priced by the unit (LS, LF, HR, etc.), these are not-to-exceed quantities.
Unit Prices . The stated unit prices are fully-loaded.
Total Prices . The stated total prices are the "price ceiling" that shall not be exceeded without prior approval from the Contracting Officer.
As a reminder, all offerors are responsible for allowing for all applicable state, local and tribal (where applicable) taxes and fees within their offer and to perform their own due diligence in ascertaining them. The Contractor is responsible to pay all applicable tribal fees and/or taxes, or applicable requirements that may be incurred as a result of this project. Failure on the part of the successful offeror not to account for these fees or the appropriate impacts will not constitute a request for an equitable adjustment to the contract price.
B.1 Incidental Payment Items : The intent of the contract is to provide for the complete work of the project described in the contract. Unless otherwise provided, the contractor shall furnish all labor, materials, equipment, tools, transportation, and supplies, taxes and fees requirements and perform all work required to complete the project in accordance with the drawings, specifications, and provisions of the contract. Payment for contract work will be made for and under those pay items included in the Schedule of Items (which is one lump sum price for the contract). All other work and materials will be considered as incidental to and included in the payment for items shown.
B.2. Estimated Quantities : Estimated quantities are provided in the price schedule for evaluation purposes only. The Government is not obligated to order the estimated amounts specified in the schedule. The estimates provided do not establish any minimum purchase limit for which the Government is obligated. The contractor shall not furnish quantities in excess of the specified amount without prior written consent from the Contracting Officer.
B.3. Wage Determination : Davis-Bacon wages shall be paid for all applicable labor categories for each price schedule line item and should be included in all pricing in accordance with FAR 52.222-6, Construction Wage Rate Requirements. The applicable Wage Determination is included in Section J, Attachments 1.
B.4 Invoices : HHSAR clause 352.232-71 Electronic submission of payment requests is included, so invoices will be processed through www.ipp.gov.
IMPORTANT INFORMATION : Under no circumstances will any oral statements made be binding upon the Government unless such statements or agreements are issued in writing by the Contracting Officer.
Only a warranted Contracting Officer acting within their delegated limits has the authority to issue modifications or otherwise change the terms and conditions of this contract. If an individual other than the Contracting Officer attempts to make changes to the terms and conditions of this contract, you shall not proceed within the change and shall immediately notify the Contracting Officer.
B.5. TERO : TERO is applicable. Refer to Section C.4
END OF SECTION
STATEMENT OF WORK
PARKING LOT IMPROVEMENTS
LOWER BRULE HEALTH CENTER
LOWER BRULE, SD
1. Project Description
A. Title: PARKING LOT IMPROVEMENTS
B. Location: This project is at the LOWER BRULE HEALTH CENTER, in LOWER BRULE, SD.
C. Period of Performance: 365 calendar days from Notice to Proceed.
D. Description: The project defined within this Scope of Work is the replacement of the concrete ramp at the entrance of the Health Center, along with the railing and wind barrier. Replacement of a portion of the asphalt parking lot where the handicapped parking spots are located. Replacement of the entrance door and the delivery entrance door. Installation of pipe bollards and curb stops for parking spots, and pavement markings for the parking lot.
E. Background: The work to be accomplished by this project will replace an ADA non‐compliant ramp entrance to the Health Center. It will also improve the handicap access to the building by supplying a new wider ramp and a door with ADA compliant push button opening. It will improve the safety of the parking lot by installing bollards to protect the ramp and building from a vehicle accidentally driving into those areas.
The project will also reconfigure the entrance into the basement of the Health Center, where a majority of the deliveries are received. It will create a dedicated parking area for the delivery vehicles to use, and a more convenient ramp and new door for the entrance.
F. Related Documents
1. This SOW and any other standard government or IHS documents are included and considered a part of this contract.
2. IHS Architecture and Engineering Design Manual – 2019
3. FGI 2018 – Healthcare Facility Design Guide
4. NFPA 101 Life Safety Code – 2012
5. NFPA 70 National Electric Code (NEC)
6. ASHRAE 170
7. ASHRAE Fundamentals Handbook 2017
8. NFPA 99 Healthcare Facilities Codebook, 2012
G. Common Acronyms or Definitions
1. IHS – Indian Health Service
2. CMS – Centers for Medicare & Medicaid Services
3. LB – Lower Brule
4. BAS – Building Automation System
5. Metasys – Name of the existing BAS
Section C
Statement of Work
PARKING LOT IMPROVEMENTS/GP21LB500C06
November 2022
6. CO – Contracting Officer
7. COR – Contracting Officer’s Representative
8. PM – Project Manager
9. IGCE – Independent Government Cost Estimate
10. BIM – Building Information Model
11. LOD – Level of Design
12. CAD – Computer Aided Design
13. RFI – Request For Information
2. Scope of Work (SOW) The contractor shall provide all plant, labor, materials, transportation, drawings etc. and supplies as needed for all demo, new installation, and clean‐up of the products described below. All electrical installation shall be done by an electrician licensed in the state of South Dakota.
Construction shall comply with industry‐recognized standards for building construction.
All construction shall be in accordance with the most recent publications of the National Electric Code, National Fire Codes, AIA Guidelines for Construction and Equipment of Hospital and Medical Facilities, IBC, and shall be in accordance with Industry Standards.
The facility shall remain fully functional for patient care with minimal interruption during construction.
The contractor shall provide a construction schedule for completing the work and identify how the work will be completed to minimize impact to facility operations.
The Contractor shall restore all areas disturbed by construction, both interior and exterior, to condition at least equal to that existing prior to construction. Contractor shall take necessary precautions to minimize any dust, dirt, or tracking throughout the health center and surrounding areas during the construction process, and shall be responsible for any required clean‐up or damage related to the construction activity. The Contractor shall dispose of all excess construction materials and rubbish in an EPA‐approved landfill.
The Contractor shall be responsible for obtaining all permits, insurance and fees, federal and tribal, required of a general contractor working on the Lower Brule Indian Reservation, TERO ordinance will apply.
The contractor shall coordinate all work activities with Facility Manager prior to commencing work and on a daily basis after beginning work. All meausrements are for estimating purposes, and should be verified prior to ordering any materials.
The contractor shall provide all engineering, design, material, labor, equipment and supervision required to accomplish the following:
A. Demolition: Contractor shall remove the existing concrete ramp, railing, wind barrier, and retaining wall. Remove a 2600 square feet section in the parking lot and the ramp. Remove both the entrance doors in the area. Remove the light on the building above the ramp.
November 2022
The existing pavement section, including the existing concrete ramp, will be removed down to the subgrade material. Any subgrade water damaged areas will be repaired as necessary and the entire subgrade will be moisture conditioned and re‐compacted to a firm uniform density prior to base course and pavement placement.
B. Electrical: Install three new LED light fixtures to properly light the new ramp and the delivery entrance. Lights should be Halo White LED Single Head Outdoor Security Flood Light Model Number FSL303TW 2900 Lumens, or equivalent. Install ADA compliant push button door openers on the main entrance. Install camera and door opener ouside on delivery door, and door opnener switch and minitor downstairs in the office space below the delivery door, same as or equivalent to AIPHONE Video Intercom Station Kit: 17 in Ht, 10 1/2 in Wd, 3 1/2 in Dp, 17 in Door Station Ht.
C. Concrete: Placement of 52’x50’ subgrade, structural steel, and concrete shall follow SD DOT 2015 Standards, part B and D, and any other applicable section. Prepare subgrade 6” with density 95% of standard proctor. #3 rebar every 12” in parallel, and every 36” perpendicularly. 6” concrete for full dimensions poured to 4,000 psi. Space joints at 10‐12 feet, Joiner molded on squares.
Place 8” concrete filled pipe bollards between sidewalk and parking lot, at 56” high. Spacing should be 3‐5’ apart, and approved through a submittal. Bollards will be finished with a rust resistant paint, and then a plastic cover. Provide 4 extra bollard covers.
D. Metals: Provide aluminum ramp with railings and canopy as shown in drawing titled Floor Plan. Door is approximately 4.5’ above ground. New ramp shall be designed and constructed in accordance with ADA accessibility guidelines for ramps and International Building Code for ramps. All ramp sections, platforms, steps, legs, and guardrails are to be constructed of mill finish aluminum extrusions and mill finish aluminum sheet. Extrusion are either 6061‐T6, 6063‐T52, or 6005‐T5 aluminum alloy and all aluminum sheet is 5052‐H32. Ramp shall be aluminum ramp as manufactured by Upside Innovations or equal.
E. Openings: Replace entrance door and the delivery entrance door. Both doors are 3' 6" wide, 80" tall (measurements need to be verified) and are single metal entry doors. The entrance into the Health Center will have ADA compliant push button opening, and an automatic closure. The delivery door will need to have an push botton electric lock and automatic door closure. Ensure doors are operating and sealed properly. Any addition material for a proper operation or seal will be responsibility of contractor.
F. Fire Suppression: Any existing fire suppression in the ceiling or walls will need to stay in place, and be incorporated into the new construction.
G. Exterior Improvements: Replace any exterior wall paneling that is not present due to current ramp, having it match the existing appearance.
If any item is damaged in the removal of the concrete ramp, it will need to be replaced back to original appearance, at contractor’s expense.
Paint parking lot area per plans using specifications from South Dakota DOT 2015 Standard Specifications.
H. Warranty: Provide a 1‐year labor and material warranty at no additional cost to the government which provides for the repair of all work and equipment that was provided under this scope of work.
I. Clean Up: Jobsite shall be cleaned daily and must comply with the Infection Control & Safety Officer’s requirements given with the ICRA and PRCA. The construction areas involved shall be free of
November 2022 any debris, rubbish and left over material scraps upon completion of the project. Trash receptacles used for the collection of this debris and their removal from the project site shall be provided by the contractor. The site will be inspected by the engineer prior to final payment to ensure the sites return to their original condition prior to construction.
J. Site Restoration: The construction site shall be free of any materials, debris and/or rubbish. The contractor will be responsible for the removal of this debris and must restore the site to its original condition as approved by the project engineer. Photo are to be taken before construction begins for documentation the sites original condition by the contractor.
K. Addition Facility Requirements: Contractor shall comply with the requirements of the hospital’s Facility Manager, Infection Control Officer and Safety Officer. These requirement will be laid out during the pre‐construction meeting. Other permits and requirements will be given after the pre‐ construction meeting and the ICRA and PRCA assessments are completed.
3. Period of Performance.
A. Time of the Essence: All time limits for Milestones, if any, Substantial Completion, and completion and readiness for final payment as stated in the Contract Documents are of the essence of the Contract.
B. The Work will be substantially completed within Three Hundred Sixty‐Five (365) calendar days after the date when the Contract Times commence to run.
4. Submittals
A. Submittals or shop drawings shall be submitted for the following items and shall be delivered electronically to the COR or designated PM for final approval before ordering any new material or equipment.
1. Materials and finishes.
2. Electrical components, Exterior Lights
3. New ramp and canopy
4. Paints and parking spot placements
5. New doors and door openers
6. Subgrade Material
7. Concrete
8. Any other items with options available
5. Schedule/Meetings
A. The general contractor shall submit a detailed schedule to the COR for approval within (14) calendar days of the award.
B. Pre‐Construction Meeting: One Pre‐Construction meeting shall be conducted prior to the start of the construction of the contract.
C. Progress Meetings: Progress meetings shall be conducted at regular intervals as merited by the progress of the work.
November 2022
D. Substantial Completion: One substantial completion meeting shall be held following notification of the Project Officer by the General Contractor that the project is Substantially Complete.
E. Final Completion: One final completion meeting shall be held following determination that the project is complete.
6. Miscellaneous
A. Correspondence. All correspondence shall be addressed to the COR. Each letter, document, etc., shall contain the following information:
1. Date
2. Project Numbers, Contract Number, Delivery Order Number and Service Unit Name/Location.
3. Name of those who were sent copies.
B. Superintendent. The prime contractor shall have an onsite superintendent for this project while any and all work is being performed unless prior approval is grant from the COR.
C. Tribal Requirements.
1. The Contractor and all subcontractors engaging in work on the Lower Brule Sioux Indian
Reservation will be required to comply with the Indian preference and Indian preference program requirements administered by the Lower Brule Sioux Tribe Tribal Employment Rights
Office (TERO).
2. Before commencing work, contractors and sub‐contractors are required to submit an acceptable
“Compliance Agreement” to the TERO office. Copies of this form can be obtained from the
TERO office. Typical requirements of TERO include a fee of 4% on the total contract price, and submission of weekly certified payroll reports to TERO.
3. Additionally, the rules and regulations of the TERO Ordinance require that no person who is not a local Indian shall be employed by a covered employer until a work permit has been obtained for them from TERO.
4. Contractors are strongly encouraged to contact the TERO office at (605) 473‐5800 ext. 48171 for an explanation of tribal requirements. Other fees may apply.
D. Construction Materials and Storage
1. All materials shall be stored and handled according the manufacturers’ recommendations.
2. All materials shall be submitted to the COR prior to ordering, for approval by the project engineer.
3. The contractor(s) shall be present and on site to receive all construction material, equipment, or products. IHS staff will not be present, responsible, nor receive, or provide any type of offloading equipment for construction materials, products, or equipment. It is solely the contractor(s) responsibility to properly receive any and all construction equipment, products, and materials on site.
4. The contractor(s) shall provide their own means of storing any and all construction materials, products, or equipment required for installation. IHS staff will not be responsible or provide any means of storing construction material, products, or equipment before or during construction.
November 2022
All material, products, or equipment remain the contractor(s) property until the project has been deemed substantially completed by all parties.
E. Hours Of Operation
1. The project shall start after award and receipt of the Notice to Proceed
2. The work hours shall be 8:00am – 5:00pm, Monday – Friday. Weekends and after hours work may be available upon request.
7. Payments to the Contractor
1. The Government will pay the Contractor a fixed price, as indicted below, which will constitute full compensation for all Contractor professional and incidental services, travel expenses, and materials necessary to furnish complete project as required and specified in this SOW.
2. Progress payments will be paid following acceptance by the Government of that particular schedule item and a properly submitted and approved invoice. Refer to Section G, Item 4.
8. Project Officer
Korry Burkhead will be designated as the Contracting Officer’s Representative (COR) for this Order. His address and telephone are:
Korry Burkhead Great Plains Area Indian Health Service Division of Facilities Management & Engineering 420 S. Garfield Ave Pierre, SD 57501 Office: 605‐945‐5437 Korry.burkhead@ihs.gov
Any change in COR designation will be documented by the Contracting Officer in writing.
9. Reserved.
10. Closeout Documents
The Contractor shall submit one hard copy set of all final, installed submittal items, accessories, and all installation/operation/maintenance documents to the facility manager/engineer. The final installed submittal package and O&M shall also be sent electronically to the COR and/or PM.
End of Section
Section D Packaging And Marking
D.1 PACKAGING AND MARKING
(a) All shipments of materials, equipment and/or supplies to the project site shall be addressed to the Contractor and not the Indian Health Service. Preservation, packaging and packing shall be in accordance with industry standard packaging appropriate for the item(s) involved. The Indian Health Service is not responsible in any manner for deliveries intended for the project that are not generated by the Indian Health Service.
(b) Equipment and materials provided by the Contractor shall be new and, where appropriate, shall arrive onsite sealed in original manufacturer’s containers. The Government reserves the right to refuse any items deemed to not meet this requirement.
(c) Material shall be stored in an enclosed and dry area protected from damage and soiling. The contractor shall coordinate a suitable storage area with the COR.
Section E Inspection And Acceptance E.1. Inspection And Acceptance All work under this contract is subject to inspection and final acceptance by the Contracting Officer or the duly authorized representative of the government.
The Government’s Contracting Officer’s Representative (COR) is a duly authorized representative of the government and is responsible for inspection and acceptance of all items to be delivered under this order.
E.2. Provisions Incorporated by Reference :
52.246-12 Inspection of Construction. (Aug 1996)
Section F. Deliveries Of Performance F.1. SUPERINTENDENT ON SITE . The contractor shall ensure that the Project Superintendent is on site at all times work is being performed by the contractor or subcontractor(s). They shall directly oversee all apprentice and subcontractor work. The Project Superintendent is also responsible to ensure all labor and safety requirements are complied with; and ensure that the worksite is cleaned up at the end of each work day.
All communications between the IHS and contractor concerning the day-to-day workmanship on the project will be handled through the Project Superintendent and they MUST have the authority to act on behalf of the Contractor in all contractual matters.
F.2. REMOVAL OF PERSONNEL . The Contracting Officer may require the contractor to remove from the job any employee who endanger persons or property; those who manufacture, distribute, dispense, possess or use controlled substances at the worksite (FAR 52.223-6, Drug-Free Workplace); and those whose continued employment under this contract is inconsistent with the interest of security or for any and all other reasons as determined by the Contracting Officer as objectionable.
F.3. Clauses Incorporated by Reference :
52.242-14 Suspension of Work. (Apr 1984) 52.236-15 Schedules for Construction Contracts.
52.236-6 Superintendence by the Contractor (Apr 1984).
F.4. Clauses incorporated in full text .
52.211-10 Commencement, Prosecution, and Completion of Work. (Apr 1984) The Contractor shall be required to (a) commence work under this contract within 10 calendar days after the date the Contractor receives the notice to proceed, (b) prosecute the work diligently, and (c) complete the entire work ready for use not later than 365 calendar days .
* The time stated for completion shall include final cleanup of the premises.
(End of clause)
Section G Contract Administration Data G.1. Contracting Officer’s Authority . The Contracting Officer is the only person authorized to make or approve any changes in any of the requirements of this contract, and, notwithstanding any provisions contained elsewhere in this contract, the said authority remains solely in the Contracting Officer. In the event the contractor makes any changes at the direction of any person other than the Contracting Officer, the change will be considered to have been made without authority and no adjustment will be made in the contract terms and conditions, including price.
G.2. Contracting Officer’s Representative .
(a) [TO BE ASSIGNED BY SEPARATE LETTER AT CONTRACT AWARD] is hereby designated as the Contracting Officer’s Representative (COR). The COR may be changed at any time by the Government without prior notice to the Contractor by a unilateral modification to the contract. The COR is located at: see separate letter at contract award
(b) The responsibilities and limitations of the COR are as follows:
(1) The COR is responsible for the technical aspects of the contract and serves as technical liaison with the contractor. The COR is also responsible for the final inspection and acceptance of all deliverables and such other responsibilities as may be specified in the contract.
The COR is not authorized to make any commitments or otherwise obligate the Government or authorize any changes which affect the contract price, terms or conditions. Any contractor request for changes shall be referred to the Contracting Officer directly or through the COR. No such changes shall be made without the express written prior authorization of the Contracting Officer. The Contracting Officer may designate assistant or alternate COR(s) to act for the COR by naming such assistant/alternate(s) in writing and transmitting a copy of such designation to the Contractor.
G.3. CERTIFICATION OF PAYMENTS – RELEASE OF CLAIMS (ROC)
The Contractor, when submitting final payment under this contract, shall submit to the Contracting Officer:
(a) A certification that the Contractor has made payment from proceeds of prior payments, or that he will make timely payment from the proceeds of the progress or final payment then due him, to any subcontractors and suppliers in accordance with established contractual arrangements; and
(b) A properly executed Contractor's Release. The Release of Claims form is available from the Contracting Officer.
Failure to submit this completed release will result in a delay of final payment .
G.4. PAYMENT PROCESS
(a) FAR 52.232 5, Payments Under Fixed Price Construction Contracts, requires that before the first progress payment under the contract is submitted, the contractor shall prepare a Schedule of Values including each principal category of the work which when added together equal the total contract price.
A sample format is available from the Contracting Officer. The following is the detail required by the
Contracting Officer:
(1) The principle categories of work shall be broken into line items of sufficient detail to allow meaningful measurement of the work on a monthly basis as determined by the COR. Units of measure appropriate to the type of work shall be used. “Lump sum” pricing of line items shall be avoided except where payment for that line item is to be requested based on 100% completion of that line item or where there is no other practical unit of measure.
(2) The cost of preparatory work (e.g., shop drawings or product submittals), field and home office overhead, profit, insurance, taxes, warranties, as built drawings, etc., shall be pro rated into items of physical work and not listed as separate line items. Cost of Performance and
Payment Bonds may be listed as a single line item and not pro rated. Also, cost of mobilization and demobilization relating to transportation or installation costs associated with such items as site trailers, heavy equipment, temporary batch plants, temporary on site manufacturing and assembly facilities, temporary on site quarter’s facilities, temporary sanitation facilities, temporary utility connections, and/or temporary secured storage facilities may be listed as line items and not pro rated. If mobilization is listed separately, a line item for demobilization must be listed separately. A detailed listing of the items included and the individual cost for each item shall be provided in support of proposed amounts for mobilization and demobilization.
(b) Material stored on site may be included in earned progress if the Contractor furnishes satisfactory evidence that it has acquired title to such material and that the material will be used to perform in contract.
(c) The following are instructions for submitting pay requests:
(1) Requests are to be submitted with signature for the Contractor certification statement
(scanned signature okay) to the Designated Billing Office. Use of a format that complies with all of the requirements of the “Payments” clause of the contract is mandatory. The “Contractor
Payment Application” form will be provided at the Pre‐Construction meeting.
(2) The Contractor is responsible for delivery of each request for payment electronically using the Department of Treasury Invoice Processing Platform (IPP) www.ipp.gov or successor system.
Hand delivery to the COR in the field does not constitute delivery to the billing office.
(3) If the contractor wishes to inquire concerning the status of any pay request, the contractor should contact the Contracting Officer.
(4) A completed Release of Claims that complies with the requirements of the “Payments” clause must be submitted with the request for final payment. A sample format is available from the
Contracting Officer.
(d) The final payment request will be rejected and returned to the contractor if all items required under the contract have not been completed, submitted, approved, and accepted prior to the receipt of the request; e.g., deficient work items, as built, payrolls, reports, O&M manuals, warranties, delivery of extra stock material, etc.
G.4. Invoice Requirements (cont.)
(e) Invoices must be prepared and submitted and will be paid in accordance with the following FAR clauses:
52.232-5 Payments under Fixed-Price Construction Contracts. (May 2014) 52.232-27 Prompt Payment for Construction Contracts. (Jan 2017) 52.232-33 Payment by Electronic Funds Transfer-System for Award Management (Oct 2018) 52.232-40 Providing Accelerated Payments to Small Business Subcontractors (Nov 2021) HHSAR 352.232-71 Electronic submission of payment requests
The final invoice must be marked “Final” and be accompanied by a Release of Claims form, which states the final payment as outstanding, in the Remarks field. The Release of Claims form is available from the CO. Final payment will be made within 30 Calendar days upon receipt of a properly executed invoice.
G.5. Address For Correspondence It is the intent of the Government to use electronic means as much as possible while administering this contract. Correspondence must be sent via email directly to the Contracting Specialist and the
COR.
G.6. Identification Of Contractor Employees Identification (ID) Badges. The contractor shall provide each employee with an ID badge on contract start date or on employment start date. The ID badge shall be made of non-metallic material. The badge shall be easily readable and include the employee's name, the contractor's name, functional area of assignment, and a color photograph. The Contracting Officer or their designee will approve the ID badge template before the contract start date.
Display of ID Badges. Contractor personnel shall wear the ID badge at all times when performing work under this contract on site and when attending Government meetings and conferences off-site. Unless otherwise specified, each contractor employee shall wear the ID badge in a conspicuous place on the front of exterior clothing and above the waist except when safety or health reasons prohibit such placement.
Utilizing Electronic Mail (e-mail). When prime contractor or subcontractor personnel send e-mail messages as part of contract performance or otherwise relating to contract matters, each sender shall include his/her name (both first and last names), e-mail address and the name of the individual’s employer.
G.7. Test Results The contractor must submit all results of test(s) required by the contract to the COR/Project Manager for review.
G.8. Permits And Certificates The contractor must submit a copy of all permits and certificates as required by the contract to the COR/Project Manager.
Incorporated by Reference:
Section H Special Contract Requirements
H.1. SUBCONTRACTS
(a) Nothing contained in the contract shall be construed as creating any contractual relationship between any subcontractor and the Government. The divisions or sections of the specifications are not intended to control the contractor in dividing the work among subcontractors, or to limit the work performed by any trade.
(b) The contractor shall be responsible to the Government for acts and omissions of his own employees, and of subcontractors and their employees. He shall also be responsible for the coordination of the work of the trades, subcontractors, and suppliers.
(c) The Government will not undertake to settle any differences between or among the contractor and his subcontractors or suppliers.
(d) The contractor shall, without additional expense to the Government employ specialty subcontractors where required by the specifications. “Specialty Subcontractors,” when specified as a requirement, means a subcontractor regularly engaged in the manufacture or installation of the contract items. The specialty subcontractor shall select and combine the materials involved, maintain and have available for the purpose, workmen skilled in the specified work. The specialty subcontractor shall be the manufacturer, be licensed by the manufacturer as an installer, or work under direct supervision of the manufacturer.
H.2. SUBCONTRACTING
(a) In connection with the performance of work under this contract, the contractor shall not subcontract with any subcontractor who, at the time of subcontract award, is listed as an excluded party within the System for Award Management (SAM) unless otherwise authorized by the Government in accordance with Subpart 9.4 of the Federal Acquisition Regulations.
(b) The List of Parties Excluded from Procurement and Non-Procurement Programs is available at: https://www.sam.gov/SAM/
(c) In the event of the contractor’s noncompliance with the foregoing requirements, the Government may terminate this contract for default or take other appropriate action, including, but not limited to, requiring the contractor to terminate any such subcontract and substitute an eligible subcontractor in lieu thereof, at no increase in the contract price or time for performance.
(d) The term “subcontractor,” as used in this clause, shall mean the individual or firm with whom the contractor proposes to enter into a subcontract for manufacturing, fabricating, installing, or otherwise performing work under this contract.
(e) Within ten days after contract award, the contractor shall furnish to the Contracting Officer in writing a list of all subcontractors scheduled to perform work under the contract on Form
SF-1413.
(f) The contractor shall include the provisions of paragraphs a., b., and d. of this clause in every subcontract hereunder.
H.3. STANDARD REFERENCES
(a) Any materials, equipment, or workmanship specified by reference to the number, symbol, or title of any specific standard shall comply with the latest edition or revision thereof, and any amendment or supplement thereto, in effect on the date of the solicitation, except as limited to type, class or grade, or modified in the specifications.
(b) Standards referred to in the plans and specifications, except as modified, shall have full force and effect as though printed in the plans and specifications.
(c) The contractor shall maintain on the site, a complete current set of manufacturers’ and standards referenced from work under the contract.
H.4. WORK HOURS AND ACTIVE GOVERNMENT OPERATIONS
Normal work days and hours are Monday through Friday, 7:00 am to 5:00pm excluding federal holidays for occupied facilities and no set times or days for unoccupied spaces. The contractor shall notify the COR a minimum of 72 hours in advance of arriving on site to complete work and check in with the COR upon arrival. A minimum of 48 hours of advance notice is required for special requests to work outside of normal work hours.
H.5. MATERIALS ON SITE
Unless otherwise provided in the specifications or drawings, materials removed and not reused under the contract shall become the property of the contractor. The contractor shall remove the materials from the work site. Storage or sale of the materials on the site will not be permitted.
H.6. OPERATION AND STORAGE AREAS
Reference FAR 52.236-10 Operations and Storage Areas. The contractor shall coordinate its operations and storage with the COR.
H.7. ACCIDENT PREVENTION
Reference FAR 52.236-13 Accident Prevention. The contractor shall submit for approval a written Safety and Accident Prevention Plan showing how they will comply with FAR 52-236-13.
The contractor shall also designate in writing the individual who is responsible for identifying and correcting safety hazards or violations on the job site.
H.8. AVAILABILITY OF UTILITY SERVICES
Reference FAR 52.236-14 Availability and Use of Utility Services. The Government anticipates that the proposed work will place a small demand on available utility services and therefore will not charge the contractor for their use.
H.9. PRECONSTRUCTION CONFERENCE
Reference FAR 52.236-26 Preconstruction Conference. The Contracting Officer will conduct a preconstruction conference. Location is TBD upon award, but will most likely be at the site. The Contracting Officer, COR, and contractor are required to participate. The Contracting Officer may designate required attendance for subcontractors. The Contracting Officer and COR may attend the conference via conference or video call.
H.10. TRUCKING
(a) All trucks, bringing to or removing from the site, earth, loose materials, or debris shall be loaded in a manner to prevent dropping of materials on streets.
(b) At all points, where trucks leave the project site and enter adjacent paved streets, the contractor shall maintain an installation and crew to prevent any mud from being carried onto such adjacent paved streets.
(c) Earth, loose materials, or debris deposited on the streets due to contract trucking activities shall be removed daily.
H.11. SALVAGE
The Government does not assume responsibility for any loss or damage to materials removed and not reused under the contract that become the property of the contractor.
H.12. NEW WORK
Unless otherwise noted on drawings or specified, new work in extension of existing conditions shall correspond in all respects to similar existing conditions, in material, workmanship and finish.
H.13. EXISTING WORK
(a) Existing work shall be cut, drilled, altered, removed or temporarily removed and replaced for performance of work under the contract. Work replaced shall match similar existing work.
Structural members shall not be cut or altered, except as shown, without authorization of the Contracting Officer. Work remaining in place damaged or defaced during this contract shall be restored to the condition at time of award of contract.
(b) Discolored or unfinished surfaces exposed by removal of existing work and indicated to be the final exposed surfaces shall be refinished or the material shall be replaced to be uniform and harmonious with contiguous work. Work out of alignment, where exposed by removal of existing work, shall be called to the Contracting Officer’s attention. Corrective work, directed by the Contracting Officer will be subject to adjustment of the contract in accordance with FAR 52.236 2, “Differing Site Conditions.”
H.14. WARRANTY OF CONSTRUCTION
Reference FAR 52.246-21 Warranty of Construction. All warranties the contractor receives from subcontractors, manufacturers and suppliers shall be executed in writing for the benefit of the Government. The contractor shall provide the COR with copies of all warranties obtained.
H.15. AS BUILT DRAWINGS
The contractor shall maintain during the progress of the work one (1) set of completed and up to date blue line drawings, which shall be available for inspection by the Contracting Officer at any time. These drawings shall be marked up to record all changes in the work as they occur, and the exact location of all exposed and concealed pipe runs, valves, plugged outlets, cleanouts and other control points including, but not limited to, electrical conduits, and ducts, mechanical valves, shut-off switches, etc., in such a manner as will provide a complete, accurate as built record. The location of pipes or control points concealed underground, under concrete, in chases or above hung ceilings shall be dimensioned. In progress as-built documentation will be reviewed with each progress payment request as a required element. The completed set of as built paper reproducible drawings shall be delivered to the Contracting Officer, in a condition satisfactory to him. As built shall be submitted for review/approval as a condition precedent to the request for final inspection of the work.
H.16. EQUITABLE ADJUSTMENTS DUE TO CHANGES
(a) The contractor shall submit a proposal for all changes in the work within 15 days from the effective date of the change order or request for proposal. With each proposal for a change involving an increase or decrease in the amount of the contract, the contractor shall submit separately an itemized breakdown that will include, but not be limited to, the following:
(1) Material quantities and unit price (separated into trades)
(2) Labor costs (separate into labor classifications and hourly rates)
(3) Construction equipment
(4) Workmen’s compensation
(5) Overhead
(6) Profit
(7) Employment taxes under FICA, FUTA and SUTA
(8) Bond (prime contractor only)
(9) Sales Tax
(10) Direct Performance Time of Change
(11) Impact on Schedule, if any
(12) Impact Costs, if any
(b) In considering proposals for changes involving added work, omitted work, or any combination thereof, estimates will be checked in detail by the Contracting Officer, utilizing unit prices where specified or agreed upon, with the view of arriving at equitable adjustments.
(c) When the necessity to proceed with a change does not allow sufficient time to properly check a proposal, or because of failure to reach an agreement, the Contracting Officer may direct the contractor to proceed immediately with the work.
(d) Proposals and breakdown should be submitted as promptly as possible but in no event later than 30 days.
(e) Should a proposal cost exceed the certified cost or pricing data threshold or is required for a lesser amount at the direction of the Contracting Officer for a change, certified cost or pricing data should be submitted in a format which satisfies the requirements of FAR 15.4. When certified cost or pricing data are required, the Contractor shall submit an executed Certificate of Current Cost or Pricing Data (FAR 15.406-2) as soon as practicable after price agreement is reached.
(f) Allowable overhead, profit, and percentages are given below. These percentages shall be limited to three tiers only and shall be considered to include, but not limited to, all insurance other than FICA, FUTA, SUTA and Workmen’s Compensation, field and office supervisors, assistants, and clerical personnel, use of small tools, incidental job burdens, and general office expense. Incidental job burdens include, but are not limited to, review and coordination, and estimating and expediting relative to contract changes that are associated with field and office supervision.
No percentages for overhead and profit shall be allowed on FICA, FUTA, or SUTA.
The percentages of overhead to be allowed by the Contracting Officer will be 10% for all contract changes performed by the Prime Contractor personnel and 5% for all contract change work performed by subcontractor personnel.
The percentage for profit to be allowed by IHS will vary according to the nature, risk, extent, and complexity of work involved, but in no case shall exceed 10%. Percentages for overhead and profit will be as follows:
Overhead Profit
To subcontractors and/or to the contractor for work performed with its own forces
10% 1% - 10%
To subcontractors and/or to the Contractor on work performed by other than its own forces:
5% 1% - 5%
The percentage of profit is to be negotiated. The burden is on the Contractor to propose and justify to the Government the percentage of profit to be paid on each modification to the contract.
On proposals involving both increases and decreases in the amount of the contract, overhead and profit will be allowed on the net increases only. On net decreases, corresponding overhead and profit will be deducted.
(g) Time Extension: when the contractor submits a change proposal without including a corresponding Time Impact Analysis meeting the requirements of the pertinent Specification Section, the Contractor acknowledges that the particular change order, modifications, delay or contract request does not require an extension of the contract time (or milestone) and the Contractor shall not thereafter be entitled to request or receive any such extension(s).
(h) Delay and Impact Costs: Any proposal for delay and impact costs that is not submitted within 60 days after completion of the work identified in the change will not be considered.