This document outlines technical provisions for trench excavation and backfill for pipelines and appurtenant structures. It specifies requirements for excavation, safety, shoring and sheeting systems, road and railroad crossings, work within rights-of-way, drainage, excavation methods and materials, backfilling, compaction testing, disposal of excess materials, cleanup, trench maintenance, stormwater pollution prevention, lines and grades, clearing and grubbing, seeding, frost protection, repairs to damaged utilities, as-built drawings, and measurement and payment terms. The solicitation seeks bids for trench excavation and backfill work associated with the Tesuque Lagoon Improvements project for the Department of Health and Human Services Indian Health Service. Contractors must comply with technical requirements for excavation, backfilling, compaction, safety protocols, erosion control, as-built documentation, and addressing damaged infrastructure as specified in the document.

View the file

Other files for this federal contract opportunity

Show all 13

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

TECHNICAL PROVISIONS- SECTION 01 - Page 1 of 18

April 2021

TECHNICAL PROVISIONS

SECTION 01 - TRENCH EXCAVATION & BACKFILL FOR PIPELINES AND

APPURTENANT STRUCTURES

TP-101 SCOPE:

Excavation, as used in these specifications refers to all construction activities necessary to install subsurface utilities in accordance with the plans and specifications. Such activities include, but are not limited to:

All necessary clearing, grubbing and site preparation; removal of all materials that may interfere with construction activities (except existing pipe work, conduits, utility structures or other items to be left in place) to the lines and grades indicated on the plans and otherwise described herein. The Contractor shall remove all construction trash from the site and transport to a legal disposal site.

Removal and/or storage of subsurface materials from trench and construction excavation areas to allow installation of designated utilities or structures. All suitable material removed from excavations shall be used, insofar as practicable, in the formation of embankments, fills and backfilling.

Preparation of sub-grades and backfilling of trench and construction areas upon completion of utility or structure construction.

All necessary bracing, shoring and protection (but not including tight sheeting in trenches and structure excavation ordered left in place by the Owner or Owner’s

Representative).

Final grading, dressing and cleanup of the construction site.

TP-102 SAFETY:

All trench excavation shall be coordinated in strict accordance with current OSHA requirements found in the Occupational Safety and Health Standards - Construction

Standards for Excavations (29 CFR 1926, Subpart P).

Trenches shall be properly sheeted, shored, or sloped in accordance with the current

OSHA standards. Trench excavation shall not proceed more than 500 feet in advance of pipeline work without the Owner or Owner’s Representative's approval. All trenches shall be completely backfilled at the end of each working day, unless otherwise approved by the Owner or Owner’s Representative. No excavation shall be left open without proper barricades and warning lights. Such devices shall conform to the Manual of Uniform Traffic Control Devices (ANSI D6.1) or such permits as are appended to these specifications.

The contractor shall be responsible for safety on the job site and shall designate a trained “competent person” knowledgeable in trench safety to supervise the work.

TECHNICAL PROVISIONS- SECTION 01 - Page 2 of 18

TP-103 SHORING AND SHEETING SYSTEMS:

Protection of employees in excavations shall conform to applicable OSHA Standards.

Any trench protection and modification to trenching safety plans shall be submitted to the Owner or Owner’s Representative in writing to be maintained as part of the record.

The Contractor shall install all shoring and sheeting systems required to prevent cave-ins and protect his employees and adjacent property and structures in accordance with current OSHA standards. No extra payment will be made for these items, the cost thereof being merged with and considered a part of the cost for the related excavation.

Before sheeting is withdrawn, or trench boxes moved forward, they shall be raised, in place, just above the pipe crown to safely allow the Contractor to completely fill any voids left in the pipe zone.

TP-104 ROAD, RAILROAD AND SPECIAL UTILITY CROSSINGS (IF

REQUIRED):

The Contractor shall be responsible for compliance with all requirements of special crossing permits applicable to this project. Copies of such permits shall be included in the Appendix of these specifications. If no special crossing permits are appended, and such crossings are indicated on the plans, crossings will comply with all applicable provisions of Section 11 of the Technical Provisions in addition to those indicated under other provisions of this Section. At least two days notice shall be given to the Owner or Owner’s Representative before work is done on any crossing.

TP-105 WORK WITHIN RIGHT-OF-WAYS & TRAFFIC CONTROL

When performing any work within the right-of-way of roads or railroads, the

Contractor shall comply with the right-of-way permit for the installation including all of the requirements for traffic control and compaction. All work within the right-of-way of roads shall be performed in accordance with the “Standard Specifications for

Construction of Roads and Bridges on Federal Highway Projects FP-03 U.S.

Customary Units – Section 614.” All work within the right-of-way of roads shall be performed in accordance with the latest edition of the Manual on Uniformed Traffic

Control Devices (MUTCD).” In addition, the Contractor shall submit a traffic control plan to the project engineer for review and approval prior to any work within the right-of-way of any roads or railroads.

TECHNICAL PROVISIONS- SECTION 01 - Page 3 of 18

TP-106 DRAINAGE:

The Contractor shall control the grading in the vicinity of the excavation so that the ground surface is properly sloped to prevent water from running into the excavated areas. Water that has accumulated in the excavation from rainfall and/or surface runoff, or from any other cause which might have been prevented by proper care and foresight, shall be removed and the subgrade restored to its proper bearing capacity, all at the Contractor's expense.

TP-107 EXCAVATION:

A. General: All excavation, other than by drilling and blasting, undertaken with the excavation equipment commonly used in the industry for this type of excavated material shall be classified as common excavation.

All excavation shall be made by open cut method except as approved or specified.

During excavation, materials suitable for backfill shall be neatly piled no closer than

24-inches from the edge of the excavation. All materials not required or not suitable for backfill shall be removed and wasted at locations designated by the Owner or

Owner’s Representative.

1. Width: The sides of all trenches for the installation of utility piping systems shall be as nearly vertical as soil conditions will permit from ground level to the pipe.

Except for the trenching of 1-inch water service lines, the width of the trench shall not be less than 16-inches nor more than 24-inches wider than the outside diameter of the pipe barrel. Trench excavation shall be centered on pipe alignment such that a minimum clear space of 8-inches is provided on each side of the pipe. Trench width above the level of the top of the pipe may be as wide as necessary for shoring or sheathing and for proper installation of the work.

2. Depth: The trench shall be excavated to the depth that permits pipe to be laid at the elevations shown on the engineering drawings or with the required depth of cover specified by the Owner or Owner’s Representative. Depth of cover shall be measured from the finished grade or the surface of the permanent improvement to the top of the pipe barrel.

3. Preparation: The bottom of the trenches shall be accurately shaped to line and grade and shall provide uniform bearing and support for each section of the pipe on specifically placed bedding material at every point along its entire length. Bell holes and depressions for joints shall be dug after the trench bottom has been graded and shall be only of such length, depth and width as required for properly making the particular type joint. Care shall be taken not to excavate below the depths indicated.

Unauthorized over depths shall be backfilled with suitable bedding material at the

Contractor's expense.

TECHNICAL PROVISIONS- SECTION 01 - Page 4 of 18

4. Previous Excavation: If the trench passes over a sewer or other previous excavation, the trench bottom shall (1) be compacted to provide support equal to that of the undisturbed native soil or (2) conform to the specific regulatory requirements that preclude damage to the existing installed facility.

5. Unstable Subgrade: Where soft, spongy or otherwise unsuitable material is encountered, which will not provide a firm foundation for pipe, the Owner will direct the extent to which removal and replacement shall be made with suitable material.

Special pipe foundation material is NOT anticipated. However, if required, a price shall be negotiated between the Owner and Contractor for special pipe foundation material.

6. Underground Obstructions: The Contractor shall preserve intact any underground pipes, culverts or other utilities encountered during construction (except as hereinafter permitted) provided their location is such that they do not interfere with new pipelines or structures being installed. The Contractor shall notify all appropriate utility authorities of his construction schedule so they may be at the site to locate and protect their property. If any utilities or structures are accidentally broken or disturbed, they shall be replaced immediately to a condition at least equal to that in which they were found, all at the Contractor's expense. Couplings used to repair water service lines shall be brass compression couplings and couplings used to repair sewer service lines shall be solid sleeve couplings that provide a rigid connection between pipes. The repair work shall be done in a manner acceptable to the Owner or Owner’s

Representative and the utility company. Any existing water or sewer services that will intersect or interfere with the new pipelines or structures shall be rerouted by the

Contractor in the manner indicated by the Owner or Owner’s Representative. Existing water or sewer services from the mains to private property that interfere with trenching operations may be cut and replaced at the Contractor's option and expense, provided that users of such services are notified at least 2 hours in advance and that the use of such service shall in no case be interrupted for more than 4 hours and/or beyond the workday, unless specifically permitted in writing by the owner. Materials and construction for these items shall be as provided in other sections of these specifications. All new and existing water and sewer mains and water and sewer services shall be protected from freezing at all times during construction.

B. Rock: The inclusion of a bid item and estimated quantity for rock excavation in the bid schedule indicates that rock excavation is probable. However, the exclusion of this item from the bid schedule does not preclude the possibility that rock will be encountered; it merely indicates that it is not anticipated. If unanticipated rock is encountered, the Owner or Owner’s Representative will negotiate a price for rock excavation with the contractor. The following paragraphs define solid rock and loose rock excavation.

Solid rock shall be defined as large masses of igneous, metamorphic, or sedimentary rock that, in the opinion of the Owner or Owner’s Representative, cannot be

TECHNICAL PROVISIONS- SECTION 01 - Page 5 of 18 excavated without drilling, blasting, or the use of rippers or other specialized equipment. Any material excavated without the use of blasting or specialized ripping equipment shall not be considered rock.

Solid rock excavation shall be measured in cubic yards from the top of the rock to a point 4-inches below the invert of the installed pipe and an assumed 24-inches trench width, regardless of the actual trench width and depth excavated. For structures, the rock shall be profiled 12-inches outside the perimeter of the structure and computed based on a product of the profile of the rock and an assumed 24-inches outside the structure's perimeter and 6-inches below the structure's footing. The rock volume will be computed as the product of the profiled rock area, as measured by the Owner or

Owner’s Representative. The measurements shall be within the nearest 0.1-feet from the surface and no less than every 10-feet by one of the following methods:

1. Excavating and exposing the rock profile for measurement. This shall be the responsibility of the contractor and no additional payment shall be made for this excavation.

2. Rock profile determined by drilling without excavating and measurements taken prior to any blasting.

3. Rock profile measured after blasting and excavation. A 20% deduction shall be made in rock determination when this method is used to allow for expansion in ledge due to blasting.

Loose rock shall be defined as boulders and other detached stones each having a volume of 1 cubic yard or more. Loose rock shall be removed from the excavation in such a way that a clear distance of at least 4-inches exists between the rock and the bottom of the pipe and 6-inches exist between the rock and the bottom structure.

Loose rock shall not be used for backfill. Loose rock excavation shall be measured in cubic yards, including the total volume of only those rocks or boulders that are individually over 1 cubic yard in volume.

Trench in which rock is encountered shall be excavated at least 4-inches deeper than the pipe invert and refilled to the required elevation with sand , gravel, or crushed rock passing a 3/4-inch mesh screen. Bedding material shall extend upward at least

12-inches above the pipe. Payment for this fill material shall be considered incidental to the rock excavation and no additional payment shall be made.

Should rock excavation be encountered, it shall be the responsibility of the Contractor to have an experienced powderman handle all blasting and be able to furnish proof of his/her credentials. The Contractor shall also inform all residents in the vicinity of proposed blasting activities and shall be responsible for any damage to persons or property as covered in the General Provisions.

C. Removal of Water: The contractor shall remove and dispose of all water entering the trenches and shall keep the trenches water free until the facilities are in

TECHNICAL PROVISIONS- SECTION 01 - Page 6 of 18 place and sealed against the entrance of water. Use of a trash pump for removal of nuisance water shall be at no extra cost and shall not be considered dewatering. In no case shall water, earth, or any foreign materials be allowed to enter the water main or sewer lines.

The removal of nuisance water is determined by pumping the water out of the trench with a heavy-duty 4” construction trash pump with a strainer for a minimum of 1 hour. The strainer shall be placed in a bed of pea gravel or a slotted PVC pipe in order to screen the debris.

All water removed from trenches shall be conveyed to natural drainage channels, storm sewers, or proper reservoirs as approved by Owner or Owner’s Representative.

Such removal of water shall be in a manner that prevents property damage, erosion, or sedimentation.

The inclusion of a bid item and estimated quantity for dewatering in the bid schedule indicates that dewatering is probable. However, the exclusion of this item from the bid schedule does not preclude the possibility that water will not be encountered, it merely indicates that it is not anticipated.

If continuous pumping with well points is required to maintain a satisfactory trench, and the contractor is so directed by the Owner or Owner’s Representative, this work shall be considered as dewatering. Well points shall be set separately for each trench being dewatered. Dewatering shall be based on the actual number of lineal feet of trench dewatered and paid for at the negotiated price between the contractor and

Owner or Owner’s Representative.

D. Structural Excavation: Excavation for structures shall extend a sufficient distance from walls and footings to provide for forming, except where concrete for walls or footings is authorized to be deposited directly against excavated surfaces.

Care shall be taken to avoid excavating below the depths indicated in the plans.

Over-excavation shall be restored to proper elevation by filling with suitable granular bedding material at the Contractor's expense.

TP-108 BACKFILLING:

A. General: Trenches shall not be backfilled until the Owner or Owner’s

Representative has inspected and approved the pipe installation and jointing as being in compliance with the requirements of plans and specifications.

Bedding and backfill materials to a depth of 12-inches above the pipe shall be carefully deposited in layers not more than 6-inches thick, loose measurements, wetted to optimum moisture content and hand or mechanically compacted to at least

95% of the reference density for this material as described in the specification titled

“Compaction Requirements, Methods and Testing. From 12 inches above the pipe to

TECHNICAL PROVISIONS- SECTION 01 - Page 7 of 18 ground surface, the excavation material shall be placed in layers not to exceed 12-inches, mounded and left in a uniform, neat condition.

Wherever trenches have not been properly filled, or if settlement occurs, they shall be reopened to the depth required for proper compaction and refilled and re-compacted as specified above and approved by the Owner or Owner’s Representative.

Compaction methods and equipment may utilize hand and mechanical tampers and rollers. The equipment and procedures proposed by the Contractor shall be subject to the approval of the Owner or Owner’s Representative.

B. Materials: All backfill material shall be approved in advance of installation by the Owner or Owner’s Representative. Materials shall be obtained from areas approved by the Owner or Owner’s Representative.

Backfill material will not be paid for separately, but shall be considered as subsidiary to and a part of the cost for the applicable contract bid item.

1. Embedment: Embedment is that material from the bottom of the trench to twelve inches above the pipe, and includes the pipe bedding material (upon which pipe is layed), haunching material (extending from pipe bottom to pipe centerline), and initial backfill material (extending from pipe centerline to 12 inches above pipe).

Native soil used for embedment must be free from clods of earth or stones larger than

1 inch in any dimension, organic refuse, debris, frozen soil, and other objectionable material. If the native soil does not meet these criteria, the Contractor shall screen it

(as applicable) or import special bedding material.

2. Imported Special Bedding Material: If required, special bedding material shall consist of sand, sandy gravel, or other suitable granular material having a maximum plasticity index of 6, with 100% of the bedding material smaller than 3/4-inches, and no more than 5% passing a No. 200 sieve.

3. Stabilization: Granular stabilization material shall be used to replace soft, spongy, or other unsuitable material, including rock encountered in excavation, to the depths necessary to support the pipe or structure. Stabilization materials shall be underlay bedding material (as applicable) and shall consist of suitable hard, durable granular material having a maximum size of 6-inches, graded so that a maximum of 20% passes a No. 4 sieve. Granular stabilization is not anticipated. If required, a price for granular stabilization shall be negotiated between the Contractor and the Owner.

4. Final Backfill: In general, final backfill will be that material originally excavated from the trench and will extend from 12 inches above the pipe to surface grade. Final backfill material shall be the same as that around the pipe except that the inclusion of a limited amount of stones up to 6-inches in diameter will be permitted.

C. Placement:

TECHNICAL PROVISIONS- SECTION 01 - Page 8 of 18

1. Embedment: Embedment shall be placed in 6-inch loose lifts and compacted as described herein. If over-excavation is required, bedding material is to be compacted to 95% of the maximum dry density as determined by the Standard

Proctor density test (ASTM D-698). Haunching material shall be placed by hand and worked under the pipe haunch to provide adequate side support for the pipe.

Haunching and initial backfill material shall be compacted to 95% of the maximum dry density as determined by the Standard Proctor density test (ASTM D-698).

2. Final Backfill: Final backfill shall not be placed until the embedment material is placed and compacted, and the Owner or Owners Representative have inspected and approved the installation. Final backfill shall be placed in lifts not to exceed 12-inches unless otherwise approved by the Owner or Owners Representative.

Compaction shall be as defined in the Compaction Requirements, Methods, and

Testing section.

3. Backfill for Road Subgrade: Under existing and proposed roadways, to a distance of 10-feet on either side of the road, bedding and backfill materials shall be carefully deposited in layers not more than 6-inches thick, loose measurements, wetted to optimum moisture content and mechanically compacted as described in the

Compaction Requirements, Methods, and Testing section.

4. In areas where pavement is to be replaced, or in roads that are to be paved, no rocks or stones that will interfere with subgrade preparation shall be included in the backfill within 12-inches of the finished subgrade elevation. The upper 12-inch layer, forming the subgrade for pavements, shall be compacted to a density of at least 95%

(ASTM D-698 - Modified Proctor Test). See Section 11 of the Technical Provisions where this is required.

5. Cement slurry can be substituted for compacted native backfill and subgrade if approved by Owner or Owner’s Representative. The cement slurry shall consist of one sack of cement to one cubic yard of concrete sand and shall be placed from the concrete truck at a slump of 6 to 8 inches. Steel plates 5/8” thick are to be placed over the trench with at least 6 inches overlap on each side and edged with asphalt to prevent traffic movement. The backfill shall be allowed to set for a minimum of 12 hours before completing the asphalt patch. Slurry can typically be installed from the trench bottom to ground surface and no intermediary subgrade material is required for placement of asphalt patch.

6. Where trenches cross roads, streets, or driveways, backfilling shall be completed immediately following excavation and inspection. No trenches across roads shall remain open overnight. All crossings shall be backfilled, compacted and open to traffic at the end of each day's work. Major road crossings shall be excavated and backfilled in half widths of the traveled way so that at least one-half of the roadway is open to controlled traffic at all times during the work.

TECHNICAL PROVISIONS- SECTION 01 - Page 9 of 18

7. Backfill Around Structures: Backfill around structures shall conform to the same requirements as those for backfill around piping in unpaved areas, unless more stringent requirements are indicated in other sections of these specifications.

TP-109 COMPACTION REQUIREMENTS, METHODS, AND TESTING:

A. Minimum Density: Unless otherwise specified by applicable permits initial and final backfill and gravel resurfacing shall be compacted to the following minimum requirements. The minimum acceptable percent of compaction is the in place dry density divided by the reference density times 100. Compacted soil shall also be at plus or minus 2% of optimum moisture content.

TYPE LOCATION REQUIRED

COMPACTION

I Under any existing or proposed pavement, curb

Gutter, sidewalk, roadway, shoulder, alley, slab, Footing, canal embankment, or when within 2 feet of above.

95%

II Within any gas, electric, or telephone utility easement, Or within any street or road right-of-way outside the limits defined above as Type I.

90%

III All other locations not defined above as Type I or

Type II.

80% (or 100% of adjacent natural ground)

B. Reference Densities/Baseline Testing: The Contractor, at his expense, shall provide the reference densities for the various bedding and backfill materials used.

All tests shall be performed by a certified soils testing laboratory approved by the

Owner or Owner’s Representative. If reference to natural ground is used, a nuclear gauge may be used to measure the density of the natural ground. The reference densities for compaction tests shall be established in accordance with ASTM D-698, Modified Proctor Test. The Contractor shall submit for approval a testing plan identifying proposed testing locations prior to the start of any excavation work.

TECHNICAL PROVISIONS- SECTION 01 - Page 10 of 18

Contractor shall provide copies of the Modified Proctor Tests with 5 point minimum moisture vs. density curves.

The contractor shall coordinate the collection of soil samples for proctor testing with the IHS construction inspector such that both parties are on-site during the collection of soil samples. This will ensure that enough samples are collected to provide for accurate density testing during construction by providing reference density for differing soil conditions within the project area.

C. Methods: Mechanical compaction is permitted. Water jetting methods are not permitted. The backfill shall be uniformly moistened to plus or minus 2% of optimum moisture content, placed in sufficiently thin layers to obtain the specified results, and compacted with hand and/or pneumatic tamp, roller, hydrohammer, or other device which will obtain the specified density without injury to the pipe or related structures.

D. Density Tests: Backfill density tests shall be performed in accordance with the latest versions of ASTM D-1556 (Sand Cone Method), ASTM D-2167 (Rubber

Balloon Method), ASTM D-2216 (Moisture Content), ASTM D-2922 (Nuclear

Density), and ASTM D-3017 (Nuclear Moisture Content). The Contractor will perform initial field density tests for each location listed in the next paragraph at the expense of the Contractor. Any additional tests due to failure of initial tests shall be at the expense of the Contractor.

The Contractor will perform at least one (1) compaction test every other lift at each two hundred and fifty (250) linear feet of Type I location. One compaction test will be performed every other lift on each five hundred (500) linear feet of trench at Type

II or III locations. A minimum of one (1) compaction test shall be performed under each lift station base and a minimum of four (4) compaction tests shall be performed on each lift of material under proposed foundations or tanks. The exact test locations shall be specified by the Owner or Owner’s Representative. The Owner may perform additional tests. If the results of any of the compaction tests indicate insufficient compaction, the area in question shall be reopened to a depth required for proper compacting, then refilled, compacted and retested, at the expense of the Contractor, until the compaction tests indicate that the necessary compaction requirements have been met. Two copies of the test results of any retesting performed by the Contractor shall be provided to the Owner, for approval, prior to any permanent surfacing. Any improperly placed backfill, or locations where settlement occurs, shall be reopened to the depth required for proper compaction, then refilled and compacted at the expense of the Contractor. The surface shall be restored and resurfaced, if necessary to the required grade.

TECHNICAL PROVISIONS- SECTION 01 - Page 11 of 18

TP-110 DISPOSAL OF EXCESS MATERIAL:

Excess material, including rock, broken concrete, bituminous materials, debris or other materials not suitable for backfill, shall be removed from the site and wasted in the disposal areas selected by the Contractor and approved by the Owner or Owner’s

Representative.

The disposal of such excess materials will not be paid for separately, but shall be considered as incidental to and a part of the cost for the applicable contract bid item.

TP-111 CLEANUP:

Upon completion of the work, the entire site shall be cleared of all debris, and ground surfaces shall be finished to smooth, uniform slopes and shall present neat and workmanlike appearance. All slopes shall be trimmed and dressed, and all surfaces graded such that effective drainage is assured.

Unpaved streets shall be graded smooth to the satisfaction of the Owner or Owner’s

Representative.

TP-112 TRENCH MAINTENANCE:

The Contractor shall, for a period of one year after completion and final acceptance of the work, maintain and repair any trench settlement that may occur and shall make suitable repairs to any pipe, pavement, or other structures that may become damaged as a result of backfill settlement.

TP-113 STORM WATER POLLUTION PREVENTION PLAN (SWPPP):

The Contractor shall prepare a Storm Water Pollution Prevention Plan (SWPPP) in accordance with the latest requirements of the Environmental Protection Agency’s

(EPA) National Pollutant Discharge Elimination System (NPDES) General Permit for

Discharges from Large and Small Construction Activities. The SWPPP must be prepared in accordance with good engineering practices and must 1) Identify all potential sources of pollution which may reasonably be expected to affect the quality of storm water discharges from the construction site; 2) Describe practices to be used to reduce pollutants in storm water discharges from construction site; 3) Assure compliance with the terms and conditions of the NPDES General Permit.

If the Contractor is not experienced in the preparation of SWPPP, the contractor shall retain the services of an environmental firm regularly engaged in the preparation of

TECHNICAL PROVISIONS- SECTION 01 - Page 12 of 18

SWPPP to perform said service. The completed SWPPP must be approved by the

Owner or Owner’s Representative at least 14 calendar days before the start of construction so that a Notice of Intent can be sent to EPA.

The Contractor shall fully implement the SWPPP from the commencement of construction until final stabilization, as defined in the NPDES General Permit is achieved.

The Contractor shall maintain and update the SWPPP, as required in the NPDES

General Permit, for the life of the project. Updates shall include amendments required as a result of the ineffective controls discovered through the course of inspections or investigations conducted by the Owner or Owner’s Representative, site staff, or by local, state, tribal or federal officials. The Contractor shall submit a

Notice of Intent to EPA to obtain permit coverage, modify the coverage as necessary, and terminate permit coverage once final stabilization is achieved.

TP-114 LINES AND GRADES:

The Engineer will give all lines, grades and building locations on the plans and will supply the contractor with the AutoCAD drawing to stake out the facilities to be installed. The CONTRACTOR shall be responsible for staking out pipeline centerlines with a lath every 200 feet or line-of-sight whichever is less. Bends, intersections, manholes, lift station centers and fence corners shall be staked by the

CONTRACTOR and provided with two offsets for alignment. Elevation references will be provided as shown on the plans, at lift station and for sewer manholes. The

Contractor shall be responsible for the preservation of the location and line and grade stakes when set, and if disturbed, shall have such stakes replaced.

TP-115 CLEARING & GRUBBING:

It is the contractor’s responsibility to clear and grub the site prior to or during construction. The contractor shall remove all trees along the water and sewer main alignments. Trees may either be chipped with a woodchipper and placed over the trench for erosion control or disposed of at the Contractor’s expense. Clearing and grubbing shall be done at the contractor’s expense.

TP-116 SEEDING:

All disturbed areas shall be returned to their pre-construction vegetative state. The contractor shall submit a seed mix that is equivalent to the native vegetation in the

TECHNICAL PROVISIONS- SECTION 01 - Page 13 of 18 area of construction. The contractor shall protect the seed after it is placed with hay mulch, straw mulch, wood cellulose mulch, or as approved by the project engineer. A minimum of 20 pounds of seed per acre shall be placed. Seed shall be placed by either drill seeding at a depth of approximately 1 inch or broadcast seeding. If broadcast seeding is utilized, the contractor shall apply twice the minimum seeding rate (40 pounds of seed per acre). The contractor shall perform maintenance as needed to ensure that adequate vegetative growth and stabilization has taken place to minimize erosion after construction is completed.

TP-117 FROST PROTECTION:

A. Materials: The insulation shall be rigid extruded polystyrene insulation board, having a minimum compressive strength of 25 psi. The width shall be 2 feet for mains, service lines and effluent discharge lines less than 6-inches (nominal diameter). The thickness shall be 2-inches.

B. Placement: When indicated on the drawings and in the bid schedule, insulation shall be placed in areas where water lines, sewer lines, or effluent discharge lines are susceptible to freezing. The insulation shall be centered over the main with no more than 6 inches of compacted fill between the pipe and insulation. The

Contractor shall grade fill so insulation lays flat and maintain a straight alignment of insulation. The Contractor shall lap insulation by 6 inches or stagger by 6 inches if composed or two layers. The thickness for the first lift of backfill over the insulation shall be a minimum of 8 inches. The Contractor shall not operate construction equipment directly on insulation and not compact the first lift with the backhoe-mounted compactor, or any other large compaction equipment. The remaining backfill shall be compacted using normal construction practices.

TP-118 REPAIRS TO DAMAGED UTILITIES

The contractor is responsible for repairing any utilities that they damage during construction at no cost to the Owner. Repairs shall be made in accordance with the requirements of each utility. Below are the requirements for making repairs to damaged water and sewer utilities.

Water Mains: If the damage is small a small crack or hole in the water main, the contractor shall install a stainless steel repair coupling equal to a Romac SS1, SS2, SS3 or Ford Style F1. If the damage is too large to repair with a repair coupling, the

Contractor shall install new water main to replace the damaged water main. The repair must result in a watertight water main that does not leak. The new water main shall be DR-18, Class 235, C900 PVC water main per TP-4. The new water main shall be connected to the existing water main using restrained joint solid sleeve

TECHNICAL PROVISIONS- SECTION 01 - Page 14 of 18 couplings equal to Romac Alpha series restrained couplings.

Water Service Lines: If the damage is small a small crack or hole in the water service line, the contractor shall install a stainless steel repair coupling equal to a Ford Small

Repair Clamp with Full Wrap Gasket FSC. If the damage is too large to repair with a repair coupling, the Contractor shall install new water service line to replace the damaged water service line. The repair must result in a watertight water service line that does not leak. The new water service line shall be 200 psi rated polyethylene water service line meeting TP-5 requirements. The new water service line shall be connected to the existing water service line using stab joint, compression joint, or pack joint brass fittings as specified in TP-5.

Sewer Mains & Service Lines: If the damage is small a small crack or hole in the sewer main or service line, the contractor shall install a stainless steel repair coupling equal to a Romac LSS1, LSS2, or LSS3. If the damage is too large to repair with a repair coupling, the Contractor shall install new sewer main or service line to replace the damaged sewer main. The repair must result in a watertight sewer main or service line that does not leak. The new sewer main shall be SDR-35 PVC sewer main meeting TP-6 requirements and the new sewer service line shall be SDR-35 PVC sewer service line meet TP-7 requirements. The new sewer main or service line shall be connected to the existing sewer main using solid sleeve couplings equal to Romac

501 sewer couplings.

TP-119 AS-BUILT DRAWINGS:

A. General: The as-constructed drawings shall be a record of the construction as installed and completed by the Contractor. They shall include all the information shown on the Contractor's set of drawings and a record of all deviations, modifications or changes from those drawings, however minor, which were incorporated in the work, all additional work not appearing on the contract drawings and all changes which are made after final inspection of the contract work.

B. As-Built Drawings: The Contractor shall mark up one set of paper prints to show the As-Built Drawing information. These Asbuilt Drawing prints shall be kept current and available on the job site at all times. All changes from the contract plans which are made in the work or additional information which might be uncovered in the course of construction shall be accurately and neatly recorded as they occur by means of details and notes. No construction work shall be concealed until the necessary record data has been recorded.

The Asbuilt Drawing marked prints will be jointly inspected for accuracy and completeness by the Owner and a responsible representative of the construction Contractor prior to submission of each partial payment, as evidenced by the issuance of a receipt by the Owner indicating the adequacy of the information. Failure to keep the as-constructed marked prints on a

TECHNICAL PROVISIONS- SECTION 01 - Page 15 of 18 current basis shall be sufficient justification to withhold approval of request for payment or suspend pay estimates. The drawings shall show the following information, but not limited thereto.

1. The location and description of any utility lines or other installations of any kind or description known to exist within the construction area. The location includes dimensions to permanent features.

2. The location and dimensions of any changes from the contract drawings.

3. Changes in details of design or additional information obtained from working drawings specified to be prepared and/or furnished by the

Contractor including but not limited to fabrication, erection, installation plans, and placing details, pipe sized, insulation materials, dimensions of equipment foundations, etc.

4. All changes or modifications which result from the final inspection.

5. All information as required in the technical provisions.

C. Electronic/Surveyed As-built Drawings: The contractor shall obtain the services of a surveyor licensed in the State of New Mexico to survey in the locations of all sanitation facilities installed by the project being constructed.

The number and location of surveyed points must be sufficient to provide enough detail to accurately identify the location of the installed sanitation facilities. Points to be surveyed shall include, but not be limited to:

Water Mains & Services: gate valves, fire hydrants, flush hydrants, water meters, air/vacuum release valves, water/sewer crossings, water main bends, water service line connection, water main intersections, casing pipe, water main reducers, and other water main components installed under this project.

Other Water Facilities: wells, booster pumps, valve vaults, building corners, fence corners, water tanks (including base and overflow elevations), and other water main components installed under this project.

Sewer Mains & Services: manholes (including rim elevation, invert in elevation, and invert out elevation), terminal sewer main cleanout rim and invert, sewer service cleanout, new sewer service line connection, and other sewer components installed under this project.

Other Sewer Facilities: lift stations (including base elevation, rim elevation, invert in elevation, lead/lag pump on elevation, all pump off elevation, and high/low alarm elevation), valve vaults, gate or plug valves, air/vacuum valves, building corners, fence corners, treatment tanks (including rim elevations, invert in elevations, and

TECHNICAL PROVISIONS- SECTION 01 - Page 16 of 18 invert out elevations), treatment units, lagoons (including floor elevation, top of berm elevation, and invert elevations of all piping in transfer structures), and other sewer components installed under this project.

The contractor shall furnish the Owner with electronic asbuilts of the facilities installed on this project in ACAD format (dwg file). The project engineer will furnish the contractor with an electronic copy of the contract drawings in

ACAD format and will provide control points for use by the contractor to draft the electronic asbuilt drawings. The labeling, linework, and format of the electronic asbuilts shall be similar to that of the contract drawings.

D. Review and Approval: One set of the preliminary As-built Drawings marked prints shall be delivered to the Owner before final inspection for his review and approval. The review by the Owner will be expedited; however, the

Owner cannot guarantee to review more than one complex mechanical or electrical Record drawing sheet per working day. Upon disapproval of the

As-built Drawings one set of marked prints will be returned to the Contractor for further work and resubmitted to the Owner.

E. Other: All costs incurred by the Contractor in the preparation and furnishing

As-built Drawings shall be included in the contract price and no separate payment will be made for this work.

TP-119 MEASUREMENT AND PAYMENT:

A. General: Except for the following items, the cost of all work done by the

Contractor as required under Section 01 of the Technical Provisions shall be merged with the pay items defined within the Measurement and Payment portions of other

Sections of this contract.

B. Rock Excavation: Payment for rock excavation shall be at the unit price listed in the Bid Schedule based on the computed number of cubic yards removed. No differentiation payment will be made between solid or loose rock excavations.

C. Dewatering: Dewatering shall be based on the actual number of lineal feet completed. Payment for dewatering shall be at the contract unit price shown in the

Bid Schedule. This price shall be full compensation for furnishing all labor, equipment, materials, and incidentals required for a complete dewatering installation.

D. Mobilization/Demobilization: Payment for mobilization/demobilization shall be at the unit price listed in the bid schedule. 60% of this line item may be requested upon complete mobilization to the job site and the remainder may be requested upon demobilization from the job site.

TECHNICAL PROVISIONS- SECTION 01 - Page 17 of 18

E. Storm Water Pollution Prevention Plan: Payment for the preparation and implementation of the SWPPP shall be paid on a lump sum basis as shown on the Bid

Schedule. Payment shall be full compensation for plan preparation including required revisions for Owner’s acceptance, updates to the SWPPP for the life of the project, permit application, inspections, installation and maintenance of controls, modification of controls as determined by inspections, removal of pollutants due to failed controls, and permit termination.

F. Seeding: Seeding shall be paid for on a lump sum basis to seed the site in accordance with these specifications. Payment for seeding shall be at the contract unit price shown in the Bid Schedule. This price shall be full compensation for furnishing all labor, equipment, materials, and incidentals required for complete installation.

G. Exploratory Time: Exploratory time shall be measured on an hourly basis for an actual period spent on locating the existing utility line exceeding two hours.

Contractor shall follow these steps:

1. Call the representative from the operating Utility and make every effort to locate the existing utility line prior to excavation.

2. Locate the existing utility line for two hours at the Contractor’s expense.

3. If the Contractor is unable to locate the existing utility line within two hours, the Contractor shall notify the Owner or Owner’s Representative and both agree upon a start time. The start time shall be recorded. When the Contractor locates the existing utility line, the end time shall be recorded.

If the Contractor fails to notify the Owner or Owner’s Representative when the

Contractor will start locating the existing utility line, the Contractor will not be compensated. Payment for exploratory time shall be at the contract unit price shown in the Bid Schedule. This price shall be full compensation for furnishing all labor, equipment, materials, and incidentals required for locating the existing utility line.

H. Frost Protection: Payment for frost protection shall be based on the actual number of lineal feet completed. Payment for frost protection shall be at the contract unit price shown in the Bid Schedule. This price shall be full compensation for furnishing all labor, equipment, materials, and incidentals required for a complete installation.

TP-120 APPROVALS:

A. Stabilization material, if required

B. Bedding material, if required

TECHNICAL PROVISIONS- SECTION 01 - Page 18 of 18

C. Rock excavation method, if required

D. Dewatering procedures, if required

E. Baseline Proctor density test results (5 point moisture density curves)

F. Baseline testing location plan

G. Soil Testing Lab Certification

H. Stormwater Pollution Prevention Plan, if required

I. Blasting contractor and credentials, if required

J. Seed Mix

K. Insulation, if required

L. Traffic control plan, if required