B01 Attachment 03 Price Schedule.xlsx
XLSX spreadsheet 15 KB Posted
- Attached to
- Zuni Wastewater Treatment Improvements
- Solicitation number
- 75H70120R00029
About this file
This price schedule and related federal contract opportunity provide details for the Zuni Wastewater Treatment Improvements project. The price schedule outlines 25 line items for the base construction and one optional line item, with descriptions, quantities, units, unit prices, and total prices. It includes two-phase construction to renovate and expand the existing 32.6-acre, six cell lagoon facility to a 49-acre, five cell treatment system. The related federal contract opportunity posted on SAM.gov with solicitation number 75H70120R00029 further describes the requirement for the Contractor to furnish all labor, materials, and equipment for the construction improvements. This acquisition is set aside for Indian Small Business Economic Enterprises in accordance with the Buy Indian Act. The Department of Health and Human Services Indian Health Service is the contracting agency.
View the file
Other files
Show all 24
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
PRICE SCHEDULE
| Zuni Wastewater Treatment Improvements |
| IHS PROJECT No. AL-17-A77 |
| PRICE SCHEDULE |
Contractor: _____________________________________ Date: ________________________________________
BASE CONSTRUCTION SCHEDULE
| ITEM | DESCRIPTION | QTY | UNIT | UNIT PRICE | TOTAL PRICE | |
| 1 | Mobilization/Demobilization | |||||
| (TP-119.D) | 1 | LS | ||||
| 2 | Storm Water Pollution Prevention Plan, Preparation & Implementation | |||||
| (TP-113.E) | 1 | LS | ||||
| 3 | Removal and disposal of existing wire fencing, including posts - approx. length = 7,150 LF | |||||
| (TP-6007.C) | 1 | LS | ||||
| 4 | Removal & disposal of existing piping structures (i.e. transfer, inlet & outlet), including D.I. pipe & concrete supports (TP-4012.I) | |||||
| 8 | EA | |||||
| 5 | Wastewater Lagoon Construction, New Cell 1 - Phase 1 | |||||
| (TP-4012.A) | 1 | LS | ||||
| 6 | Wastewater Lagoon Construction, New Cells 2, 3, 4 & 5 - Phase 2 | |||||
| (TP-4012.A) | 1 | LS | ||||
| 7 | Clearing & Grubbing, Expanded New Cell 1 (Undisturbed) Area | |||||
| (Tp-4012.H) | 17.9 | Acre | ||||
| 8 | Sludge Removal, Blending, & Placement | |||||
| (TP-4012.B) | 1 | LS | ||||
| 9 | Lagoon Liner, HDPE, 60 mil, with gas vents & anchor trenching, New Cell 1 - Phase 1 | |||||
| (TP-4012.F) | 23.5 | Acre | ||||
| 10 | Lagoon Liner, HDPE, 60 mil, with gas vents in New Cells 2, 3, 4, & 5 - Phase 2 | |||||
| (TP-4012.F) | 30.8 | Acre | ||||
| 11 | Geocomposite Gas Venting Layer (GGVL), installation in New Cells 2, 3, 4, & 5 - Phase 2 | |||||
| (TP-4012.G) | 1 | LS | ||||
| 12 | New Transfer Piping Structure, TYPE A, standard length* | |||||
| (TP-4012.C) | 5 | EA | ||||
| 13 | New Transfer Piping Structure, TYPE A, extended length, between new Cells 4 & 5 | |||||
| (TP-4012.C) | 1 | EA | ||||
| 14 | New Transfer Piping Structure, TYPE B, at secondary cell discharge** | |||||
| (TP-4012.C.) | 3 | EA | ||||
| 15 | Gravity Sewer Pipe, 18" PVC | |||||
| (TP-612.A) | 778 | LF | ||||
| 16 | Connection of New Sewer Pipe to Existing 18" PVC Gravity Sewer Main | |||||
| (TP-612.K) | 3 | EA | ||||
| 17 | Discharge Structure & Piping to Lift Station, New Cell 5 - Phase 2 | |||||
| (TP-4012.J) | 1 | LS | ||||
| 18 | Inlet Structure, 24" PVC to New Cell No. 1, Phase 1 | |||||
| (TP-4012.D) | 1 | EA | ||||
| 19 | Inlet Structure, 24" PVC to New Cell No. 4, Phase 2 | |||||
| (TP-4012.D) | 1 | EA | ||||
| 20 | Connection of New Inlet Piping to Existing Flow Diversion Structure | |||||
| (TP-4012.K) | 2 | EA | ||||
| 21 | Chain Link Fencing, 6' Height, Lagoon Perimeter Including 2 double access gates and signage | |||||
| (TP-6007.A) | 7,060 | LF | ||||
| 22 | Rip-rap, lagoon embankement - East Berm Face | |||||
| (TP-4012.L) | 400 | SY | ||||
| 23 | Rip-rap, lagoon embankement - South Berm Face | |||||
| (TP-4012.L) | 2,960 | SY | ||||
| 24 |
Slape, Genna M (IHS/ALB/ASU): Slape, Genna M (IHS/ALB/ASU):
Are these necessary since we have the flow monitoring station
| Dual-Channel Electromagnetic Flow Meter, for Existing Lift Station | ||
| (TP-42.13.C) | 1 | LS |
| 25 | Removal of Flow Meter from Existing Meter Vault | |
| (TP-42.13.D) | 1 | LS |
| Base Price Subtotal = |
| Zuni TERO (5%) = |
| BASE PRICE TOTAL = |
| OPTION PRICING ITEM | ||||||
| ITEM | DESCRIPTION | QTY | UNIT | UNIT PRICE | TOTAL PRICE | |
| 26 | Portable Monitoring Kit | |||||
| (TP-9304) | 1 | LS |
| Option Price Subtotal = |
| Zuni TERO (5%) = |
| Option Price TOTAL = |
TOTAL CONSTRUCTION COST (Base Price + Option No. 1) =
&10PRICE SCHEDULE
Zuni WW Treatment Improvements Project Page &P of &N