B05 Amendment 10 SF30.pdf

PDF 358 KB Posted

Attached to
Zuni Wastewater Treatment Improvements
Solicitation number
75H70120R00029
Issued by

About this file

This document contains questions and answers related to a federal solicitation for wastewater treatment improvements. The solicitation seeks a contractor to renovate and expand an existing 32.6-acre, six cell wastewater lagoon facility located on tribal lands into a 49-acre, five cell treatment system. Through a two-phase construction approach, the contractor will furnish all labor, materials and equipment to upgrade the facility. The solicitation is set aside for Indian Small Business Economic Enterprises in accordance with the Buy Indian Act and is issued by the Department of Health and Human Services Indian Health Service. The questions and answers provide clarification on issues such as the estimated volume of sludge removal, material sourcing, construction measurement and payment terms, wastewater management during construction, and licensing requirements.

View the file

Other files

Show all 24

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Offers must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended, by one of the following methods:

(a) By completing items 8 and 15, and returning or (c) By separate letter or electronic communication which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by letter or electronic communication, provided each letter or electronic communication makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.

E. IMPORTANT: Contractor is not is required to sign this document and return copies to the issuing office.

AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT 1. CONTRACT ID CODE

2. AMENDMENT/MODIFICATION NUMBER 3. 4. REQUISITION/PURCHASE REQUISITION NUMBER 5. PROJECT NUMBER (If applicable)

7. ADMINISTERED BY (If other than Item 6) CODE

STANDARD FORM 30 (REV. 11/2016)

Prescribed by GSA FAR (48 CFR) 53.243

FACILITY CODE

10A. MODIFICATION OF CONTRACT/ORDER NUMBER

10B. DATED (SEE ITEM 13)

11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS

The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offers is extended. is not extended.

12. ACCOUNTING AND APPROPRIATION DATA (If required) copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted;

13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS.

IT MODIFIES THE CONTRACT/ORDER NUMBER AS DESCRIBED IN ITEM 14.

CHECK ONE A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE CONTRACT ORDER

NUMBER IN ITEM 10A.

B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, appropriation data, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(b).

C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:

D. OTHER (Specify type of modification and authority)

Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.

15C. DATE SIGNED

15A. NAME AND TITLE OF SIGNER (Type or print)

16C. DATE SIGNED

16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)

14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)

PAGE OF PAGES

6. ISSUED BY CODE

8. NAME AND ADDRESS OF CONTRACTOR (Number, street, county, State and ZIP Code) (X)

CODE

15B. CONTRACTOR/OFFEROR

(Signature of person authorized to sign)

16B. UNITED STATES OF AMERICA

(Signature of Contracting Officer)

Previous edition unusable

The reason for amendment 10 to this solicitation is to provide the final list of answers and questions for this project.

See attached list of Questions and Answers.

Indian Health Service - DES 701 5th Avenue, Suite 1650 Seattle, WA 98104

9A. AMENDMENT OF SOLICITATION NUMBER

75H70120R00029

1 3

EFFECTIVE DATE

5/12/2020

9B. DATED (SEE ITEM 11)

03/24/2020

AL-17-A77

X

QUESTIONS AND ANSWERS

Q1. During the pre-bid meeting it was stated that there approximately 1” of sludge to be removed in the existing ponds. Question #9 in amendment #5 stated that “it is the responsibility of the contractors’ to estimate quantity of sludge in the existing cells.” Can the IHS estimate the cubic yards that will need to be removed and the sludge removal be changed to a surveyed cubic yard price so both the IHS and contractor are protected should quantities vary?

A1. IHS will not be reporting an estimated volume of the sludge. As indicated by the lump sum measurement & payment approach for Price Item No. 8 (See Attachment 3, Price Schedule), it is the responsibility of the Contractor to estimate the amount of sludge that he/she will be responsible for handling.

Q2. Can the location and the available quantities of the gravel and 6” riprap from the Zuni Tribe, listed in resolution no. M70-2002-B045 be provided?

A2. It is recommended that contractor’s consider acquiring necessary gravel and base coarse material from alternate sources, rather than locally from the Pueblo of Zuni. After consulting with the Pueblo of

Zuni, it seems that the Pueblo will not be able to offer base coarse to the Contractor, the Pueblo also reported that the availability of gravel is limited.

Q3. Can the wastewater lagoon construction bid items be changed to cubic yard bid items? This again is to ensure bids are comparable and protect the IHS and contractor should quantities vary.

A3. IHS will not be reporting estimated cut and fill volumes. As indicated by the lump sum measurement and payment approach for Price Items 5 & 6 detailed in TP-4012.A, it is the responsibility of the

Contactor to estimate the volume of earthwork that will be required to construction the lagoon cells. A

DXF file containing the existing versus design contours were made available to support bidders with determining the efforts required to complete the work prescribed by Price Items 5 and 6.

Q4. Can any of the existing cells 1,2,3,5 and 6 be drawn down prior to the completion of phase 1, in order to prevent a delay in starting phase 2?

A4. Potentially one or two (max) may be drawn down prior to the completion of phase 1 work. Please note this response does not constitute as an absolute approval. Such approval would be based upon: (1.)

the successful Contractor presenting a proposed approach for draining the cells while adequately managing the incoming wastewater flows, and (2.) the proposed approach meeting the collective satisfaction of the Zuni Utility Department and IHS.

Q5. How will the limits of sludge removal be determined?

A5. The specifications were developed to ensure the land application (stockpiling) of the anticipated sludge will be executed in accordance with presiding environmental guidelines, therefore IHS is not concerned be applied to quantify the volume of sludge removed.

Q6. If water from the lagoons were treated with a proper amount of bleach, could it be used to moisture condition embankment material?

A6. No. The existing lagoon facility is severely undersized and is therefore providing little to no biological treatment of the wastewater it receives and is currently retaining. The effluent from the existing lagoons is essentially raw (untreated) sewage water due to the lack of biological treatment.

Bleach additive is not a sufficient wastewater treatment solution that will ensure the wastewater effluent is safe to be utilized as construction water and subsequently introduced into the environment in an uncontrolled manner.

Q7. On Drawing Sheets 8 and 9, reference is made to the 536 lf of 18-inch diameter transfer piping running along the berm between Cell 1 and Cell 4. Could we get a cross section of that portion of the term in order to know location & depths within the berm?

A7. It is not clear which section of pipe this question is referring to as this contract does not prescribe new transfer piping to be installed between New Cells 1 and 4. Neither is there an existing section of transfer piping between existing Cells 1 and 4 that is 536 feet in length, as indicated by the question. If contractor is inquiring about the 536 linear feet of new 18-inch transferring piping to be installed between

New Cells 3 and 4, they should refer to the details provided for the “Transfer Piping Structure Between

Treatment Cells – TYPE A” on Sheet 14 to determine the pipe depths for the transfer piping to be installed between New Cells 3 and 4.

Q8. Question #5 in amendment #5 discusses anchor trenches. There appear to be two types of anchor trenches, perimeter and center anchor trenches. Are perimeter anchor trenches (as shown on the bottom left detail of sheet 16) required for all the liners?

A8. Correct, there are two types of anchor trenching for the HDPE liner that is to be installed under this

Contract. Please refer to Detail 40A on Sheet 14 to view the installation of the perimeter anchor trenching that is to be installed at the top of berm (perimeter of HDPE liner).

Q9. Do any of the areas require re-seeding?

A9. No.

Q10. In regards to the liner system, are we to assume that we are placing a complete layer of geocomposite under the liner in all the ponds1-5, then placing an added GGVL of 10' wide strips on 50' centers in cells 2,3,4,5? Or is there no underlying geocomposite layer in the ponds except for the GGVL

10' wide strips in cells 2 through 5?

A10. After reviewing the details within the construction documents (specifications and drawings) concerning the prescribed HDPE liner and GGVL system, please refer to sections TP-4008 - HDPE Liner, TP-4009 - GGVL System, and Sheets 8, 9 10, 14 & 16 of the construction plans, as the provided documentation illustrates a clear technical illustration of the required design.

Q11. Would consideration be made for a bidder with an out of state Contractor’s license if a New Mexico

Contractor’s license is currently in the application process, and would be finalized after award?

A11. After further review, it has been determined that a New Mexico Contractor’s license is not required for this project as it is being performed on Federal/Tribal lands and is not a requirement for this contract.

Please disregard Answer #4 in Amendment 02.