B01_08_SAM_DRAFT_Summary_of_Work_30AUG24_1.pdf

PDF 82 KB Posted

Attached to
Folsom Right Wing Dam Ditch Bypass Modification
Solicitation number
140R2024R0020
Issued by

About this file

This document is a Summary of Work for the Folsom Right Wing Dam North Fork Ditch Modification project, which is part of the American River Division - Folsom Unit of the Central Valley Project in California. The key components of the work include mobilization, site preparation, excavation, removing concrete structures, installing drainage systems, embankment construction, and site restoration.

The related federal contract opportunity is a pre-solicitation Sources Sought notice for this construction project, with an estimated value between $5 million and $10 million and a 372-calendar day period of performance. The Department of the Interior's Bureau of Reclamation is conducting market research to identify potential sources, focusing on companies with recent experience in similar large-scale civil engineering projects. Interested parties are requested to provide details on their qualifications, capabilities, and intent to submit an offer when the formal solicitation is issued.

View the file

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Folsom Right Wing Dam

North Fork Ditch Modification

American River Division – Folsom Unit – Central Valley Project, California

Summary of Work

01 11 00 - 1

SUMMARY OF WORK

PART 1 GENERAL

1.01 LOCATION

A. Work is located approximately 2 miles north of Folsom, California, in Sacramento and

Placer Counties.

1.02 PRINCIPAL COMPONENTS OF WORK

A. Mobilization and preparatory work.

B. Clearing, grubbing, and topsoil removal.

C. Fencing removal and installation.

D. Establishing site access and installing security measures.

E. Installing and operating temporary unwatering and dewatering systems.

F. Supported excavation to expose abandoned concrete headwall and portions of three abandoned CMP conduits.

G. Removing concrete headwall and downstream end of the abandoned CMP conduits.

H. Installing a filter and drainage zones, backfilling the excavation, and replacing a segment of toe drain pipe.

I. Placing and compacting embankment to create a seepage stability berm.

J. Installing toe drain inspection wells and toe drain pipe cleanouts.

K. Installing gravel surfacing.

L. Installing utilities and instrumentation.

M. Replacing topsoil and seeding.

1.03 SPECIFICATIONS REQUIREMENTS

A. Requirements in Division 1, General Requirements, apply to Divisions 2 through 53.

B. Imperative statements in these specifications are Contractor requirements, unless otherwise stated.

Folsom Right Wing Dam

North Fork Ditch Modification

American River Division – Folsom Unit – Central Valley Project, California

Summary of Work

01 11 00 - 2

C. Where specifications are written in streamlined form, the words “shall be” are included by inference where a colon (:) is used within the sentence or phrase.

1.04 DEFINITIONS

A. When the specifications use a word or term defined in the Federal Acquisition

Regulations (FAR), the definition of the word or term shall be in accordance with FAR sections in effect at the time the solicitation was issued.

1.05 ACRONYMS

A. The following acronyms apply to specifications Divisions 1 through 53:

1. CCAO: Central California Area Office

2. CE: Construction Engineer

3. CO: Contracting Officer

4. COR: Contracting Officer’s Representative

5. SWPPP: Stormwater Pollution Prevention Plan

6. USACE: United States Army Corps of Engineers

7. Reclamation: United States Bureau of Reclamation

B. Some design standards and manuals in this specification have not been updated to changed naming standards and use USBR as the acronym for United States Bureau of

Reclamation.

PART 2 PRODUCTS

Not Used

PART 3 EXECUTION

Not Used

END OF SECTION