b.SnowPlowSolicitation.pdf

PDF 6 MB Posted

Attached to
Wallowa-Whitman Snow Park Snow Removal IDIQ
Solicitation number
1240BE23Q0003
Issued by

View the file

Other files

File Type Posted
a.SnowPlowQuotersPacket.pdf PDF

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

SOLICITATION/CONTRACT/ORDER FOR COMMERCIAL ITEMS 1. REQUISITION NUMBER

Offeror to complete blocks 12, 17, 23, 24, & 30 1077401 46

2. CONTRACT NO. 3. AWARD/EFFECTIVE DATE 4. ORDER NUMBER 5. SOLICITATION NUMBER 6. SOLICITATION ISSUE DATE

1204R322Q0003 November 10th,

a. NAME 8. OFFER DUE DATE/

LOCAL TIME 4:30 PM 7. FOR SOLICITATION

INFORMATION CALL Andrea Pollock, Contract Specialist John Hollenbeak, COR

(541) 969-3554

(541) 426-5520

November 21st,

9. ISSUED BY (MAIL OFFERS TO) CODE 10. THIS ACQUISITION IS

UNRESTRICTED

11. DELIVERY FOR FOB

DESTINATION UNLESS

BLOCK IS MARKED.

12. DISCOUNT TERMS

USDA FOREST SERVICE SET-ASIDE. 100% FOR SEE SCHEDULE

PPS, Field Procurement Operations SMALL BUSINESS, HUBZONE SMALL BUSINESS

13a. THIS CONTRACT IS A RATED ORDER

NW Zone, CSA 3 8(A) UNDER DPAS (15 CFR 700)

Services and Supplies SOLE SOURCE 13b. RATING

NAICS: 561790 14. METHOD OF SOLICITATION

SIZE STANDARD: $7.0M RFQ IFB RFP

15. DELIVER TO: CODE 16. ADMINISTERED BY CODE

Various locations on the Wallowa Whitman National Forest (see Clause 1. Description of Work for Snow Park Locations)

Same as Block 9

17a. CONTRACTOR/OFFEROR CAGE FACILITY

CODE

18a. PAYMENT WILL BE MADE BY CODE

Invoice Processing Platform www.ipp.gov/index.html

UEI #

Email:

TELEPHONE: TIN: 18b. SUBMIT INVOICES TO ADDRESS SHOWN IN BLOCK 18a UNLESS BLOCK

17b. CHECK IF REMITTANCE IS DIFFERENT AND PUT SUCH ADDRESS IN OFFER IS CHECKED: SEE ADDENDA 19.

ITEM NO,

20.

SCHEDULE OF SUPPLIES/SERVICES

21.

QUANTITY

22.

UNIT

23.

UNIT

PRICE

24.

AMOUNT

Wallowa-Whitman Snow Parks Snow Removal IDIQ

(Use Reverse and/or Attach Additional Sheets as Necessary)

25. ACCOUNTING AND APPROPRIATION DATA 26. TOTAL AWARD AMOUNT (For Govt. Use Only)

27a. SOLICITATION INCORPORATES BY REFERENCE FAR 52.212-1, 52.212-4. FAR 52.212-3 AND 52.212-5 and ADDENDA 27b. CONTRACT/PURCHASE ORDER INCORPORATES BY REFERENCE FAR 52.212-4. FAR 52.212-5 AND ADDENDA ARE

ARE ARE NOT ATTACHED.

ARE NOT ATTACHED.

28. CONTRACTOR IS REQUIRED TO SIGN THIS DOCUMENT AND RETURN ORIGINAL TO ISSUING OFFICE.

CONTRACTOR AGREES TO FURNISH AND DELIVER ALL ITEMS SET FORTH OR OTHERWISE IDENTIFIED

ABOVE AND ON ANY ADDITIONAL SHEETS SUBJECT TO THE TERMS AND CONDITIONS SPECIFIED

HEREIN.

29.

AWARD OF CONTRACT: YOUR OFFER ON SOLICITATION (BLOCK 5), DATED

BLOCK 30c) INCLUDING ANY ADDITIONS OR CHANGES WHICH ARE SET FORTH

HEREIN, IS ACCEPTED AS TO ITEMS:

30a. SIGNATURE OF OFFEROR/CONTRACTOR 31a. UNITED STATES OF AMERICA (SIGNATURE OF CONTRACTING OFFICER)

30b. NAME AND TITLE OF SIGNER (TYPE OR PRINT) 30c. DATE SIGNED 31b. NAME OF CONTRACTING OFFICER 31c. DATE SIGNED

AUTHORIZED FOR LOCAL REPRODUCTION STANDARD FORM 1449 (Rev. 4/2002) PREVIOUS EDITION IS NOT USABLE Prescribed by GSA FAR (48 CFR) 53.212 http://www.ipp.gov/index.html

Solicitation # 1240BE23Q0003 Page 2 of 46

B. SUPPLIES OR SERVICES PRICES/COST

Please Note: Each location may be awarded in a separate contract award and/or may go to different contractors.

19. ITEM NO 20. SCHEDULE OF SUPPLIES/SERVICES 21. QTY 22. UNIT 23. UNIT PRICE 24. AMOUNT

Wallowa-Whitman Snow Park Snow Removal IDIQ 1 Plowing – Salt Creek Summit Snow Park, NFSR 39 and

NFSR 3915, November 2022-April 2023 1 Plow $ $

Option 1a Plowing – Salt Creek Summit Snow Park, NFSR 39 and NFSR 3915, November 2023-April 2024

1 Plow $ $

Option 1b Plowing – Salt Creek Summit Snow Park, NFSR 39 and NFSR 3915, November 2024-April 2025

1 Plow $ $

2 Plowing – Clear Creek Snow Park, November 2022- April 2023

1 Plow $ $

Option 2a Plowing – Clear Creek Snow Park, November 2023-April

1 Plow $ $

Option 2b Plowing – Clear Creek Snow Park, November 2024-April

3 Plowing – Catherine Creek Summit Snow Park, November 2022-April 2023

1 Plow $ $

Option 3a Plowing – Catherine Creek Summit Snow Park, November 2023-April 2024

1 Plow $ $

Option 3b Plowing – Catherine Creek Summit Snow Park, November 2024-April 2025

Please provide a list all equipment including the following information:

year, type, make, model, and any special attachments that may be used.

SEND COMPLETED PACKAGES TO ANDREA POLLOCK,

CONTRACTING OFFICER TO

andrea.pollock@usda.gov.

DUE BY NOVEMBER 21TH, 2022 1630 (PT).

FOR QUESTIONS YOU EMAIL THE ADDRESS ABOVE.

MINIMUM AND MAXIMUM CONTRACT AMOUNTS (FEB 1988)

During the period specified in FAR clause 52.216-18 ORDERING, the Government shall place orders totaling a minimum of $ 2,500 per contract award, but not in excess of $100,000.

32a. QUANTITY IN COLUMN 21 HAS BEEN

RECEIVED INSPECTED ACCEPTED, AND CONFORMS TO THE CONTRACT, EXCEPT AS NOTED:

32b. SIGNATURE OF AUTHORIZED GOVT. REPRESENTATIVE 32c. DATE 32.d PRINTED NAME AND TITLE OF AUTHORIZED GOVERNMENT REPRESENTATIVE

32.e MAILING ADDRESS OF AUTHORIZED GOVERNMENT REPRESENTATIVE 32.f TELEPHONE NUMBER OF AUTHORIZED GOVERNMENT REPRESENTATIVE

32.g E-MAIL OF AUTHORIZED GOVERNMENT REPRESENTATIVE

Solicitation # 1240BE23Q0003 Page 3 of 46

C. DESCRIPTION/SPECIFICATIONS/STATEMENT OF WORK

C.1. DESCRIPTION OF WORK

The work consists of removing snow, in accordance with 2. Maintenance Requirements for Snow Removal, below, from the following three State Snow Parks: Salt Creek Summit, Catherine Creek Summit and Clear Creek. See descriptions and locations below for each project area.

This contract consists of one base year and two optional years for each location. The Forest Service anticipates making multiple awards to different Offeror’s based on each of the Snow Parks.

This work is funded in cooperation with the Oregon Department of Transportation (ODOT) with the U. S.

Forest Service. These snow parks are designated winter recreation parking locations by the State, who provides a limited amount of snow removal funding through the Winter Snow Parking Permit program through ODOT. If ODOT fails to receive funding, appropriations, limitations or other expenditure authority which prohibits ODOT from reimbursing the Forest Service, then this contract may be terminated after minimum guarantees have been met.

Work shall be completed during the Winter Snow Park seasons of November 1st through April 30th each year. Contractor shall regularly check snow depths on the roads and parking areas, and shall plow entire area when average snow depth at the parking area reaches or exceeds a trigger depth of 6” of snow accumulation. The Contractor shall contact COR for authorization prior to conducting maintenance on access roads when 6” snow depth trigger is not reached in parking areas (occurs infrequently; typically due to drifting caused by heavy wind). Snow removal shall typically avoid high traffic periods between 10 a.m.

and 3 p.m.

1. Salt Creek Summit Snow Park:

The snow park is located approximately 12.5 air miles Southeast of Joseph, Oregon. The Salt Creek Summit Snow Park project consists of plowing snow from approximately 5.0 miles of Forest Rd. 39 (double-lane asphalt), 0.10 miles of Forest Rd. 3915 (double-lane asphalt), a 3.0 acre snow park, pedestrian access paths to the restroom facilities (approximately 50 feet), and pedestrian access paths to the Salt Creek Summit multi-purpose building (approximately 20 feet). One complete removal consists of plowing snow through one full width (22’ minimum) and length of the project area. Though not an indicator of future plow needs, this Snow Park was plowed an average of 15 times per season in recent years. The lowest number of plows was 9 and the highest was 23.

2. Clear Creek Snow Park:

The snow park is located approximately 9 miles north of Halfway, Oregon. The Clear Creek Snow Park project consists of plowing snow from a 1.0 acre snow park (road loop and parking area), and from approximately 1.5 miles of NFSR 66 (single lane gravel w/ turnouts). One complete removal consists of plowing snow through one full width (14’minimum plus turnouts) and length of the road, and from approximately 800 feet of the snow park loop road (12’ minimum width) plus the adjacent parking area for the snow park. Though not an indicator of future plow needs, this Snow Park was plowed an average of 7 times per season in recent years. The lowest number of plows was 4 and the highest was 13.

3. Catherine Creek Summit Snow Park:

The snow park is located approximately 20 miles east of Union, Oregon. The Catherine Creek Summit Snow Park project consists of plowing snow from a 2.0 acre snow park (road loop and parking area). One complete removal consists of plowing snow through one full width of the loop road (12’ minimum width) and length of the project area (approximately 1200 ft.), plus the adjacent parking area. Though not an indicator of future plow needs, this Snow Park was plowed an average of 4 times per season in recent years.

The lowest number of plows was 1 and the highest was 11.

Solicitation # 1240BE23Q0003 Page 4 of 46

C.2. MAINTENANCE REQUIREMENTS FOR SNOW REMOVAL

a) Work shall be performed in a manner to preserve and protect roads, appurtenances, to prevent erosion damage to roads, streams, and other Forest values.

b) Banks shall not be undercut nor shall gravel or other surfacing material be bladed off the road.

c) Drainage ditches shall be functional when needed during operations and upon completion of operations.

d) Snow removal shall be controlled to identify the traveled way (the portion of the roadway designated for the movement of vehicles, including curve widening, exclusive of shoulders.) Over-width plowing shall be reshaped as necessary to define the usable width.

e) Contractor shall remove snow from all of the traveled way, including turnouts, for safe and efficient use. Intruding windfalls, debris, or slough and slide material shall be removed for the full width of the traveled way and shall be disposed of out of the drainages at agreed upon locations.

f) Contractor shall: space, construct, and maintain drainage holes in the dike of snow or berm caused by snow removal operations. Drain holes shall be placed to obtain surface drainage without discharging onto erodible fills.

g) Upon written notice by the Forest Service, the Contactor shall replace in kind, within 60 days after the start of operations, any surface material that has been bladed off of the road at no additional expense to the Government. The Contracting Officer or COR will notify the Contractor of the cubic yard equivalent of material to be replaced.

h) Contractor shall erect safety signs when operating any equipment on the roadway. Signs shall meet requirements of the latest edition of the Manual on Uniform Traffic Control Devices.

i) Ice control may be performed by the contactor when approved by the CO in writing. Such approval will include ice control materials, application rates, and any specific requirements of use.

j) Maintain a berm on the outside of the roadway to maintain full width.

k) All blades or plows shall be equipped with shoes or runners to keep the blade a minimum of two (2”) inches above the road surface unless agreed upon in writing by the Contracting Officer. When plowing snow from a paved surface, the blade or plow may come in contact with the paved surface.

l) Contractor shall notify COR within one business day of accomplishing work and shall include a detail of the work accomplished, the dates of each snow removal, equipment used with start and end meter readings of each piece of equipment.

Solicitation # 1240BE23Q0003 Page 5 of 46

D. PACKAGING AND MARKER

{For this Solicitation, there are NO clauses in this section}

Solicitation # 1240BE23Q0003 Page 6 of 46

E. INPSECTION AND ACCEPTANCE

E.1. EQUIPMENT

Contractor may use any type or size of equipment generally used to remove snow, providing the type or use of equipment is not restricted in the current Wallowa-Whitman NF Commercial Road Rules document, and the equipment used to remove snow shall not cause damage to the road. All equipment anticipated to be used in this contract shall be provided and include the following information: year, type, make, model, and any special attachments that may be used.

E.2. PAYMENT

Payment will be made on a per-plow basis. Invoices shall be submitted once a month through the Invoice Processing Platform System (IPP). Invoices shall be itemized separately by snow park and shall include the dates and times of each snow removal. Failure to provide complete information on each invoice will result in delaying the acceptance of work and the processing of the payment.

E.3. 52.216-18 ORDERING (OCT 1995)

(a) Any supplies and services to be furnished under this contract shall be ordered by issuance of delivery orders or task orders by the individuals or activities designated in the Schedule. Such orders may be issued from date of award through November 30th, 2024.

(b) All delivery orders or task orders are subject to the terms and conditions of this contract. In the event of conflict between a delivery order or task order and this contract, the contract shall control.

(c) If mailed, a delivery order or task order is considered “issued” when the Government deposits the order in the mail. Orders may be issued orally, by facsimile, or by electronic commerce methods only if authorized in the Schedule.

E.4. 52.216-19 ORDER LIMITATIONS (OCT 1995)

(a) Minimum order. When the Government requires supplies or services covered by this contract in an amount of less than two plows, the Government is not obligated to purchase, nor is the Contractor obligated to furnish, those supplies or services under the contract.

(b) Maximum order. The Contractor is not obligated to honor—

(1) Any order for a single item in excess of $25,000.00;

(2) Any order for a combination of items in excess of $50.000.00; or

(3) A series of orders from the same ordering office within five days that together call for quantities exceeding the limitation in paragraph (b)(1) or (2) of this section.

(c) If this is a requirements contract (i.e., includes the Requirements clause at subsection 52.216-21 of the Federal Acquisition Regulation (FAR)), the Government is not required to order a part of any one requirement from the Contractor if that requirement exceeds the maximum-order limitations in paragraph (b) of this section.

(d) Notwithstanding paragraphs (b) and (c) of this section, the Contractor shall honor any order exceeding the maximum order limitations in paragraph (b), unless that order (or orders) is returned to the ordering office within five days after issuance, with written notice stating the Contractor’s intent not to ship the item (or items) called for and the reasons. Upon receiving this notice, the Government may acquire the supplies or services from another source.

E.5. 52.216-22 INDEFINITE QUANTITY (OCT 1995)

(a) This is an indefinite-quantity contract for the supplies or services specified and effective for the period stated, in the Schedule. The quantities of supplies and services specified in the Schedule are estimates only and are not purchased by this contract.

(b) Delivery or performance shall be made only as authorized by orders issued in accordance with the Ordering clause. The Contractor shall furnish to the Government, when and if ordered, the supplies or http://www.acquisition.gov/comp/far/current/html/52_216.html#wp1115057

Solicitation # 1240BE23Q0003 Page 7 of 46 services specified in the Schedule up to and including the quantity designated in the Schedule as the “maximum.” The Government shall order at least the quantity of supplies or services designated in the Schedule as the “minimum.”

(c) Except for any limitations on quantities in the Order Limitations clause or in the Schedule, there is no limit on the number of orders that may be issued. The Government may issue orders requiring delivery to multiple destinations or performance at multiple locations.

(d) Any order issued during the effective period of this contract and not completed within that period shall be completed by the Contractor within the time specified in the order. The contract shall govern the Contractor’s and Government’s rights and obligations with respect to that order to the same extent as if the order were completed during the contract’s effective period; provided, that the Contractor shall not be required to make any deliveries under this contract after April 30th, 2025.

E.6. TASK ORDER ISSUANCE

Task orders may be issued verbally, by facsimile, or by electronic commerce methods. Verbal task orders will be backed up by a written order.

Warranted Contracting Officers within the Contracting East AQM Area are authorized to place task orders against this contract within their delegated warrant authority.

Ombudsman Description. In accordance with FAR 16.505(a)(8), no protest under FAR subpart 33.1 is authorized in connection with the issuance or proposed issuance of a TO under this contract, except for a protest on the grounds that a task order increases the scope, period, or maximum value of the contract. The Ombudsman will review complaints from the contractors and ensure that all contractors are afforded a fair opportunity to be considered consistent with the procedures in the contract.

Complaints to the USDA Forest Service Ombudsman must be forwarded to:

Assistant Director for Operations, Acquisition Management, Washington Office Rosslyn Plaza 1621 N Kent Street, Plaza E, Suite 707 Arlington, VA 22209 Phone (703) 605-4665 Facsimile (703) 605-5100

E.7. FINAL CLEANUP

Before final acceptance, all areas occupied by the Contractor in connection with the work shall be cleaned of all contractor’s rubbish, excess materials, temporary structures, and equipment, and all parts of the work area shall be left in a neat and presentable condition.

E.8. APPROVAL OF SUBCONTRACTING

The Contractor shall request approval from the Contracting Officer prior to entering into any subcontract arrangement. The subcontractor shall have the experience and be equipped for such work. The written notification shall include as a minimum:

A. The name, address and telephone number of the subcontractor.

B. The date upon which the subcontract was entered into and its duration C. A detailed description of the work being subcontracted including a listing of contract items, units, etc., as appropriate.

D. Documentation of the subcontractor's representative authority.

Subcontracting any portion of the contract shall not relieve the Prime Contractor of any responsibility under this contract. Any subcontract agreement shall contain all terms and conditions of the prime contract.

Solicitation # 1240BE23Q0003 Page 8 of 46

F. DELIVERIES OR PERFORMANCE

F.1. FAR 52.211-10 COMMENCEMENT, PROSECUTION AND COMPLETION OF

WORK (APR 1984)

The Contractor shall be required to (a) commence work under this contract within 1 calendar day after the date the Contractor receives the notice to proceed, (b) prosecute the work diligently, and (c) complete the entire work ready for use not later than the time specified on the task order. Estimated start date is December 1st, 2022. .

Note: Contract time will be determined and stated on each task order.

Solicitation # 1240BE23Q0003 Page 9 of 46

G. CONTRACT ADMINISTRATION DATA

G.1. DESIGNATION OF CONTRACTING OFFICER’S REPRESENTATIVE

The Contracting Officer designates the Contracting Officer's Representative(s) (COR). The COR is responsible for administering the performance of work under this contract. In no event, however, will any understanding, agreement, modification, change order, or other matter deviating from the terms of this contract be effective or binding upon the Government unless formalized by proper contractual documents executed by the Contracting Officer prior to completion of the contract.

The Contracting Officer should be informed as soon as possible of any actions or inactions by the Contractor or the Government which will change the required delivery or completion times stated in the contract, and the contract will be modified accordingly. (This does not apply to individual task assignments which were issued by the COR provided they do not affect the delivery schedule or performance period stated in the contract.)

On all matters that pertain to the contract terms, the Contractor must communicate with the Contracting Officer. Whenever, in the opinion of the Contractor, the COR requests effort outside the scope of the contract, the Contractor should so advise the COR. If the COR persists and there still exists a disagreement as to proper contractual coverage, the Contracting Officer should be notified immediately, preferably in writing if time permits. Proceeding with work without proper contractual coverage could result in nonpayment or necessitate submittal of a contract claim.

G.2. AGAR 42.215-73 POST AWARD CONFERENCE (NOV 1996)

(a) A post award conference with the successful offeror(s) is required. It will be scheduled within 1 week after the date of contract award. The conference will be held at the Whitman Ranger District Office in Baker City or via Conference Call, unless otherwise changed by mutual agreement.

(b) Contractor designated representative or foreman (whomever the Contractor will have on the site) shall be present at the post award conference.

Solicitation # 1240BE23Q0003 Page 10 of 46

H. SPECIAL CONTRACT REQUIREMENTS

H.1. SAFETY

The following are some safety hazards identified while performing road and bridge construction/reconstruction activities on the National Forest. The contractor shall provide a written, job specific safety plan addressing these hazards at the post award conference.

1. Traffic Hazards

A. Narrow, gravel- or native-surfaced forest roads

1. Recreational traffic 2 Pedestrians, skiers, snowmobiles

3. Foggy/snowy conditions when following or meeting other vehicles

4. Ice/snow covered running surface & slippery conditions

B. Obstructions in Road

1. Livestock and wildlife

2. Rolling rocks

3. Downed timber

2. Heavy Equipment Operation While operating or working adjacent to or near heavy equipment, strict attention should be given to safety procedures. Injury, disability, or death may occur during any of the following:

A. Backing B. Clearance around equipment C. Steep side slopes or soft ground / rollover D. Refueling E. Equipment limitations F. Unsafe equipment / lack of safety equipment

3. Human Factors

A. Operator fatigue B. Potential injury during trailer, bucket, plow, and other connections or retrofitting.

C. Cold/hypothermia

H.2. AGAR 452.236-74 CONTROL OF EROSION, SEDIMENTATION, AND

POLLUTION (NOV 1996)

A. Operations shall be scheduled and conducted to minimize erosion of soils and to prevent silting and muddying of streams, rivers, irrigation systems, and impoundments (lakes, reservoirs, etc.).

B. Pollutants such as fuels, lubricants, bitumen’s, raw sewage, and other harmful materials shall not be discharged on the ground; into or nearby rivers, streams, or impoundments; or into natural or man-made channels. Wash water or waste from concrete or aggregate operations shall not be allowed to enter live streams prior to treatment by filtration, settling, or other means sufficient to reduce the sediment content to not more than that of the stream into which it is discharged.

C. Mechanized equipment shall not be operated in flowing streams without written approval by the Contracting Officer.

Solicitation # 1240BE23Q0003 Page 11 of 46

H.3. LANDSCAPE PRESERVATION

The Contractor shall give attention to the effect of contract operation upon the landscape, shall take care to maintain natural surroundings undamaged, and shall conduct the work at all times in compliance with the following requirements.

a. Prevention of the Landscape Defacement. The Contractor shall not remove, deface, injure, or destroy trees, shrubs, lawns, or other natural features or any other improvements in the work area unless specifically authorized by the Contracting Officer. Unless otherwise provided herein, the Contractor shall confine contract operations to within the areas designated in contract documents.

b. Protection of Streams, Lakes, and Reservoirs. The Contractor shall take sufficient precautions to prevent pollution of streams, lakes, small ponds, and reservoirs with fuels, oils, bitumen’s, calcium chloride, silt, or other harmful materials. Mechanical equipment shall not be operated in live streams without written approval of the Contracting Officer.

Solicitation # 1240BE23Q0003 Page 12 of 46

PART II CONTRACT CLAUSES

I. CONTRACT CLAUSES

I.1. 52.212-4 CONTRACT TERMS AND CONDITIONS—COMMERCIAL ITEMS (NOV

2021)

(a) Inspection/Acceptance. The Contractor shall only tender for acceptance those items that conform to the requirements of this contract. The Government reserves the right to inspect or test any supplies or services that have been tendered for acceptance. The Government may require repair or replacement of nonconforming supplies or reperformance of nonconforming services at no increase in contract price. If repair/replacement or reperformance will not correct the defects or is not possible, the Government may seek an equitable price reduction or adequate consideration for acceptance of nonconforming supplies or services.

The Government must exercise its post-acceptance rights-

(1) Within a reasonable time after the defect was discovered or should have been discovered; and

(2) Before any substantial change occurs in the condition of the item, unless the change is due to the defect in the item.

(b) Assignment. The Contractor or its assignee may assign its rights to receive payment due as a result of performance of this contract to a bank, trust company, or other financing institution, including any Federal lending agency in accordance with the Assignment of Claims Act ( 31 U.S.C. 3727). However, when a third party makes payment (e.g., use of the Governmentwide commercial purchase card), the Contractor may not assign its rights to receive payment under this contract.

(c) Changes. Changes in the terms and conditions of this contract may be made only by written agreement of the parties.

(d) Disputes. This contract is subject to 41 U.S.C. chapter 71, Contract Disputes. Failure of the parties to this contract to reach agreement on any request for equitable adjustment, claim, appeal or action arising under or relating to this contract shall be a dispute to be resolved in accordance with the clause at Federal Acquisition Regulation (FAR) 52.233-1, Disputes, which is incorporated herein by reference. The Contractor shall proceed diligently with performance of this contract, pending final resolution of any dispute arising under the contract.

(e) Definitions. The clause at FAR 52.202-1, Definitions, is incorporated herein by reference.

(f) Excusable delays. The Contractor shall be liable for default unless nonperformance is caused by an occurrence beyond the reasonable control of the Contractor and without its fault or negligence such as, acts of God or the public enemy, acts of the Government in either its sovereign or contractual capacity, fires, floods, epidemics, quarantine restrictions, strikes, unusually severe weather, and delays of common carriers. The Contractor shall notify the Contracting Officer in writing as soon as it is reasonably possible after the commencement of any excusable delay, setting forth the full particulars in connection therewith, shall remedy such occurrence with all reasonable dispatch, and shall promptly give written notice to the Contracting Officer of the cessation of such occurrence.

(g) Invoice. (1) The Contractor shall submit an original invoice and three copies (or electronic invoice, if authorized) to the address designated in the contract to receive invoices. An invoice must include-

(i) Name and address of the Contractor;

(ii) Invoice date and number;

(iii) Contract number, line item number and, if applicable, the order number;

(iv) Description, quantity, unit of measure, unit price and extended price of the items delivered;

(v) Shipping number and date of shipment, including the bill of lading number and weight of

Solicitation # 1240BE23Q0003 Page 13 of 46 shipment if shipped on Government bill of lading;

(vi) Terms of any discount for prompt payment offered;

(vii) Name and address of official to whom payment is to be sent;

(viii) Name, title, and phone number of person to notify in event of defective invoice; and

(ix) Taxpayer Identification Number (TIN). The Contractor shall include its TIN on the invoice only if required elsewhere in this contract.

(x) Electronic funds transfer (EFT) banking information.

(A) The Contractor shall include EFT banking information on the invoice only if required elsewhere in this contract.

(B) If EFT banking information is not required to be on the invoice, in order for the invoice to be a proper invoice, the Contractor shall have submitted correct EFT banking information in accordance with the applicable solicitation provision, contract clause (e.g., 52.232-33, Payment by Electronic Funds Transfer- System for Award Management, or 52.232-34, Payment by Electronic Funds Transfer-Other Than System for Award Management), or applicable agency procedures.

(C) EFT banking information is not required if the Government waived the requirement to pay by EFT.

(2) Invoices will be handled in accordance with the Prompt Payment Act ( 31 U.S.C.3903) and Office of Management and Budget (OMB) prompt payment regulations at 5 CFR Part 1315.

(h) Patent indemnity. The Contractor shall indemnify the Government and its officers, employees and agents against liability, including costs, for actual or alleged direct or contributory infringement of, or inducement to infringe, any United States or foreign patent, trademark or copyright, arising out of the performance of this contract, provided the Contractor is reasonably notified of such claims and proceedings.

(i) Payment.- (1) Items accepted. Payment shall be made for items accepted by the Government that have been delivered to the delivery destinations set forth in this contract.

(2) Prompt payment. The Government will make payment in accordance with the Prompt Payment Act ( 31 U.S.C.3903) and prompt payment regulations at 5 CFR Part 1315.

(3) Electronic Funds Transfer (EFT). If the Government makes payment by EFT, see 52.212-5(b) for the appropriate EFT clause.

(4) Discount. In connection with any discount offered for early payment, time shall be computed from the date of the invoice. For the purpose of computing the discount earned, payment shall be considered to have been made on the date which appears on the payment check or the specified payment date if an electronic funds transfer payment is made.

(5) Overpayments. If the Contractor becomes aware of a duplicate contract financing or invoice payment or that the Government has otherwise overpaid on a contract financing or invoice payment, the Contractor shall-

(i) Remit the overpayment amount to the payment office cited in the contract along with a description of the overpayment including the-

(A) Circumstances of the overpayment (e.g., duplicate payment, erroneous payment, liquidation errors, date(s) of overpayment);

(B) Affected contract number and delivery order number, if applicable;

(C) Affected line item or subline item, if applicable; and

(D) Contractor point of contact.

Solicitation # 1240BE23Q0003 Page 14 of 46

(ii) Provide a copy of the remittance and supporting documentation to the Contracting Officer.

(6) Interest. (i) All amounts that become payable by the Contractor to the Government under this contract shall bear simple interest from the date due until paid unless paid within 30 days of becoming due.

The interest rate shall be the interest rate established by the Secretary of the Treasury as provided in 41 U.S.C. 7109, which is applicable to the period in which the amount becomes due, as provided in (i)(6)(v) of this clause, and then at the rate applicable for each six-month period as fixed by the Secretary until the amount is paid.

(ii) The Government may issue a demand for payment to the Contractor upon finding a debt is due under the contract.

(iii) Final decisions. The Contracting Officer will issue a final decision as required by 33.211 if–

(A) The Contracting Officer and the Contractor are unable to reach agreement on the existence or amount of a debt within 30 days;

(B) The Contractor fails to liquidate a debt previously demanded by the Contracting Officer within the timeline specified in the demand for payment unless the amounts were not repaid because the Contractor has requested an installment payment agreement; or

(C) The Contractor requests a deferment of collection on a debt previously demanded by the Contracting Officer (see 32.607-2).

(iv) If a demand for payment was previously issued for the debt, the demand for payment included in the final decision shall identify the same due date as the original demand for payment.

(v) Amounts shall be due at the earliest of the following dates:

(A) The date fixed under this contract.

(B) The date of the first written demand for payment, including any demand for payment resulting from a default termination.

(vi) The interest charge shall be computed for the actual number of calendar days involved beginning on the due date and ending on-

(A) The date on which the designated office receives payment from the Contractor;

(B) The date of issuance of a Government check to the Contractor from which an amount otherwise payable has been withheld as a credit against the contract debt; or

(C) The date on which an amount withheld and applied to the contract debt would otherwise have become payable to the Contractor.

(vii) The interest charge made under this clause may be reduced under the procedures prescribed in FAR 32.608-2 in effect on the date of this contract.

(j) Risk of loss. Unless the contract specifically provides otherwise, risk of loss or damage to the supplies provided under this contract shall remain with the Contractor until, and shall pass to the Government upon:

(1) Delivery of the supplies to a carrier, if transportation is f.o.b. origin; or

(2) Delivery of the supplies to the Government at the destination specified in the contract, if transportation is f.o.b. destination.

(k) Taxes. The contract price includes all applicable Federal, State, and local taxes and duties.

(l) Termination for the Government’s convenience. The Government reserves the right to terminate this contract, or any part hereof, for its sole convenience. In the event of such termination, the Contractor shall immediately stop all work hereunder and shall immediately cause any and all of its suppliers and subcontractors to cease work. Subject to the terms of this contract, the Contractor shall be paid a percentage of the contract price reflecting the percentage of the work performed prior to the notice of termination, plus

Solicitation # 1240BE23Q0003 Page 15 of 46 reasonable charges the Contractor can demonstrate to the satisfaction of the Government using its standard record keeping system, have resulted from the termination. The Contractor shall not be required to comply with the cost accounting standards or contract cost principles for this purpose. This paragraph does not give the Government any right to audit the Contractor’s records. The Contractor shall not be paid for any work performed or costs incurred which reasonably could have been avoided.

(m) Termination for cause. The Government may terminate this contract, or any part hereof, for cause in the event of any default by the Contractor, or if the Contractor fails to comply with any contract terms and conditions, or fails to provide the Government, upon request, with adequate assurances of future performance.

In the event of termination for cause, the Government shall not be liable to the Contractor for any amount for supplies or services not accepted, and the Contractor shall be liable to the Government for any and all rights and remedies provided by law. If it is determined that the Government improperly terminated this contract for default, such termination shall be deemed a termination for convenience.

(n) Title. Unless specified elsewhere in this contract, title to items furnished under this contract shall pass to the Government upon acceptance, regardless of when or where the Government takes physical possession.

(o) Warranty. The Contractor warrants and implies that the items delivered hereunder are merchantable and fit for use for the particular purpose described in this contract.

(p) Limitation of liability. Except as otherwise provided by an express warranty, the Contractor will not be liable to the Government for consequential damages resulting from any defect or deficiencies in accepted items.

(q) Other compliances. The Contractor shall comply with all applicable Federal, State and local laws, executive orders, rules and regulations applicable to its performance under this contract.

(r) Compliance with laws unique to Government contracts. The Contractor agrees to comply with 31 U.S.C. 1352 relating to limitations on the use of appropriated funds to influence certain Federal contracts; 18 U.S.C. 431 relating to officials not to benefit; 40 U.S.C. chapter 37, Contract Work Hours and Safety Standards; 41 U.S.C. chapter 87, Kickbacks; 41 U.S.C. 4712 and 10 U.S.C. 2409 relating to whistleblower protections; 49 U.S.C. 40118, Fly American; and 41 U.S.C. chapter 21 relating to procurement integrity.

(s) Order of precedence. Any inconsistencies in this solicitation or contract shall be resolved by giving precedence in the following order:

(1) The schedule of supplies/services.

(2) The Assignments, Disputes, Payments, Invoice, Other Compliances, Compliance with Laws Unique to Government Contracts, and Unauthorized Obligations paragraphs of this clause;

(3) The clause at 52.212-5.

(4) Addenda to this solicitation or contract, including any license agreements for computer software.

(5) Solicitation provisions if this is a solicitation.

(6) Other paragraphs of this clause.

(7) The Standard Form 1449.

(8) Other documents, exhibits, and attachments.

(9) The specification.

(t) [Reserved]

(u) Unauthorized Obligations. (1) Except as stated in paragraph (u)(2) of this clause, when any supply or service acquired under this contract is subject to any End User License Agreement (EULA), Terms of Service (TOS), or similar legal instrument or agreement, that includes any clause requiring the Government to indemnify the Contractor or any person or entity for damages, costs, fees, or any other loss or liability that would create an Anti-Deficiency Act violation (31 U.S.C. 1341), the following shall govern:

Solicitation # 1240BE23Q0003 Page 16 of 46

(i) Any such clause is unenforceable against the Government.

(ii) Neither the Government nor any Government authorized end user shall be deemed to have agreed to such clause by virtue of it appearing in the EULA, TOS, or similar legal instrument or agreement. If the EULA, TOS, or similar legal instrument or agreement is invoked through an "I agree" click box or other comparable mechanism (e.g., "click-wrap" or "browse-wrap" agreements), execution does not bind the Government or any Government authorized end user to such clause.

(iii) Any such clause is deemed to be stricken from the EULA, TOS, or similar legal instrument or agreement.

(2) Paragraph (u)(1) of this clause does not apply to indemnification by the Government that is expressly authorized by statute and specifically authorized under applicable agency regulations and procedures.

(v) Incorporation by reference. The Contractor’s representations and certifications, including those completed electronically via the System for Award Management (SAM), are incorporated by reference into the contract.

(End of clause)

I.2 52.212-5 CONTRACT TERMS AND CONDITIONS REQUIRED TO IMPLEMENT

STATUTES OR EXECUTIVE ORDERS--COMMERCIAL ITEMS. (OCT 2022)

(a) The Contractor shall comply with the following Federal Acquisition Regulation (FAR) clauses, which are incorporated in this contract by reference, to implement provisions of law or Executive orders applicable to acquisitions of commercial products and commercial services:

(1) 52.203-19, Prohibition on Requiring Certain Internal Confidentiality Agreements or Statements (JAN 2017) (section 743 of Division E, Title VII, of the Consolidated and Further Continuing Appropriations Act, 2015 (Pub. L. 113-235) and its successor provisions in subsequent appropriations acts (and as extended in continuing resolutions)).

(2) 52.204-23, Prohibition on Contracting for Hardware, Software, and Services Developed or Provided by Kaspersky Lab and Other Covered Entities (NOV 2021) (Section 1634 of Pub. L. 115-91).

(3) 52.204-25, Prohibition on Contracting for Certain Telecommunications and Video Surveillance Services or Equipment. (NOV 2021) (Section 889(a)(1)(A) of Pub. L. 115-232).

(4) 52.209-10, Prohibition on Contracting with Inverted Domestic Corporations (NOV 2015).

(5) 52.233-3, Protest After Award (AUG 1996) ( 31 U.S.C. 3553).

(6) 52.233-4, Applicable Law for Breach of Contract Claim (OCT 2004) (Public Laws 108-77 and 108- 78 ( 19 U.S.C. 3805 note)).

(b) The Contractor shall comply with the FAR clauses in this paragraph (b) that the Contracting Officer has indicated as being incorporated in this contract by reference to implement provisions of law or Executive orders applicable to acquisitions of commercial products and commercial services:

_X_ (1) 52.203-6, Restrictions on Subcontractor Sales to the Government (JUN 2020), with Alternate I (NOV 2021) ( 41 U.S.C. 4704 and 10 U.S.C. 2402).

_X_ (2) 52.203-13, Contractor Code of Business Ethics and Conduct (NOV 2021) ( 41 U.S.C. 3509)).

__ (3) 52.203-15, Whistleblower Protections under the American Recovery and Reinvestment Act of 2009 (JUN 2010) (Section 1553 of Pub. L. 111-5). (Applies to contracts funded by the American Recovery and Reinvestment Act of 2009.)

https://www.acquisition.gov/far/part-52#FAR_52_203_19 https://www.acquisition.gov/far/part-52#FAR_52_204_23 https://www.acquisition.gov/far/part-52#FAR_52_204_25 https://www.acquisition.gov/far/part-52#FAR_52_209_10 https://www.acquisition.gov/far/part-52#FAR_52_233_3 http://uscode.house.gov/browse.xhtml;jsessionid=114A3287C7B3359E597506A31FC855B3 https://www.acquisition.gov/far/part-52#FAR_52_233_4 http://uscode.house.gov/browse.xhtml;jsessionid=114A3287C7B3359E597506A31FC855B3 https://www.acquisition.gov/far/part-52#FAR_52_203_6 http://uscode.house.gov/browse.xhtml;jsessionid=114A3287C7B3359E597506A31FC855B3 http://uscode.house.gov/browse.xhtml;jsessionid=114A3287C7B3359E597506A31FC855B3 https://www.acquisition.gov/far/part-52#FAR_52_203_13 http://uscode.house.gov/browse.xhtml;jsessionid=114A3287C7B3359E597506A31FC855B3 https://www.acquisition.gov/far/part-52#FAR_52_203_15

Solicitation # 1240BE23Q0003 Page 17 of 46

__ (4) 52.204-10, Reporting Executive Compensation and First-Tier Subcontract Awards (JUN 2020) (Pub. L. 109-282) ( 31 U.S.C. 6101 note).

__ (5) [Reserved].

__ (6) 52.204-14, Service Contract Reporting Requirements (OCT 2016) (Pub. L. 111-117, section 743 of Div. C).

_X_ (7) 52.204-15, Service Contract Reporting Requirements for Indefinite-Delivery Contracts (OCT 2016) (Pub. L. 111-117, section 743 of Div. C).

__ (8) 52.209-6, Protecting the Government’s Interest When Subcontracting with Contractors Debarred, Suspended, or Proposed for Debarment. (NOV 2021) ( 31 U.S.C. 6101 note).

_X_ (9) 52.209-9, Updates of Publicly Available Information Regarding Responsibility Matters (OCT 2018) ( 41 U.S.C. 2313).

__ (10) [Reserved].

__ (11) 52.219-3, Notice of HUBZone Set-Aside or Sole-Source Award (OCT 2022) ( 15 U.S.C. 657a).

__ (12) 52.219-4, Notice of Price Evaluation Preference for HUBZone Small Business Concerns (OCT 2022) (if the offeror elects to waive the preference, it shall so indicate in its offer) ( 15 U.S.C. 657a).

__ (13) [Reserved]

_X_ (14) (i) 52.219-6, Notice of Total Small Business Set-Aside (NOV 2020) ( 15 U.S.C. 644).

__ (ii) Alternate I (MAR 2020) of 52.219-6.

__ (15) (i) 52.219-7, Notice of Partial Small Business Set-Aside (NOV 2020) ( 15 U.S.C. 644).

__ (ii) Alternate I (MAR 2020) of 52.219-7.

__ (16) 52.219-8, Utilization of Small Business Concerns (OCT 2022) ( 15 U.S.C. 637(d)(2) and (3)).

__ (17) (i) 52.219-9, Small Business Subcontracting Plan (OCT 2022) ( 15 U.S.C. 637(d)(4)).

__ (ii) Alternate I (NOV 2016) of 52.219-9.

__ (iii) Alternate II (NOV 2016) of 52.219-9.

__ (iv) Alternate III (JUN 2020) of 52.219-9.

__ (v) Alternate IV (SEP 2021) of 52.219-9.

__ (18) (i) 52.219-13, Notice of Set-Aside of Orders (MAR 2020) ( 15 U.S.C. 644(r)).

__ (ii) Alternate I (MAR 2020) of 52.219-13.

_X_ (19) 52.219-14, Limitations on Subcontracting (OCT 2022) ( 15 U.S.C. 637s).

_X_ (20) 52.219-16, Liquidated Damages—Subcontracting Plan (SEP 2021) ( 15 U.S.C. 637(d)(4)(F)(i)).

__ (21) 52.219-27, Notice of Service-Disabled Veteran-Owned Small Business Set-Aside (OCT 2022) ( 15 U.S.C. 657f).

https://www.acquisition.gov/far/part-52#FAR_52_204_10 http://uscode.house.gov/view.xhtml?req=granuleid:USC-prelim-title31-section6101&num=0&edition=prelim https://www.acquisition.gov/far/part-52#FAR_52_204_14 https://www.acquisition.gov/far/part-52#FAR_52_204_15 https://www.acquisition.gov/far/part-52#FAR_52_209_6 http://uscode.house.gov/view.xhtml?req=granuleid:USC-prelim-title31-section6101&num=0&edition=prelim https://www.acquisition.gov/far/part-52#FAR_52_209_9 http://uscode.house.gov/view.xhtml?req=granuleid:USC-prelim-title41-section2313&num=0&edition=prelim https://www.acquisition.gov/far/part-52#FAR_52_219_3 http://uscode.house.gov/view.xhtml?req=granuleid:USC-prelim-title15-section637a&num=0&edition=prelim https://www.acquisition.gov/far/part-52#FAR_52_219_4 http://uscode.house.gov/browse.xhtml;jsessionid=114A3287C7B3359E597506A31FC855B3 https://www.acquisition.gov/far/part-52#FAR_52_219_6 http://uscode.house.gov/browse.xhtml;jsessionid=114A3287C7B3359E597506A31FC855B3 https://www.acquisition.gov/far/part-52#FAR_52_219_6 https://www.acquisition.gov/far/part-52#FAR_52_219_7 http://uscode.house.gov/browse.xhtml;jsessionid=114A3287C7B3359E597506A31FC855B3 https://www.acquisition.gov/far/part-52#FAR_52_219_7 https://www.acquisition.gov/far/part-52#FAR_52_219_8 http://uscode.house.gov/browse.xhtml;jsessionid=114A3287C7B3359E597506A31FC855B3 https://www.acquisition.gov/far/part-52#FAR_52_219_9 http://uscode.house.gov/browse.xhtml;jsessionid=114A3287C7B3359E597506A31FC855B3 https://www.acquisition.gov/far/part-52#FAR_52_219_9 https://www.acquisition.gov/far/part-52#FAR_52_219_9 https://www.acquisition.gov/far/part-52#FAR_52_219_9 https://www.acquisition.gov/far/part-52#FAR_52_219_9 https://www.acquisition.gov/far/part-52#FAR_52_219_13 http://uscode.house.gov/browse.xhtml;jsessionid=114A3287C7B3359E597506A31FC855B3 https://www.acquisition.gov/far/part-52#FAR_52_219_13 https://www.acquisition.gov/far/part-52#FAR_52_219_14 http://uscode.house.gov/browse.xhtml;jsessionid=114A3287C7B3359E597506A31FC855B3 https://www.acquisition.gov/far/part-52#FAR_52_219_16 http://uscode.house.gov/browse.xhtml;jsessionid=114A3287C7B3359E597506A31FC855B3 https://www.acquisition.gov/far/part-52#FAR_52_219_27

Solicitation # 1240BE23Q0003 Page 18 of 46

__ (22)

(i) 52.219-28, Post Award Small Business Program Rerepresentation (OCT 2022) ( 15 U.S.C. 632(a)(2)).

__ (ii) Alternate I (MAR 2020) of 52.219-28.

__ (23) 52.219-29, Notice of Set-Aside for, or Sole-Source Award to, Economically Disadvantaged Women-Owned Small Business Concerns (OCT 2022) ( 15 U.S.C. 637(m)).

__ (24) 52.219-30, Notice of Set-Aside for, or Sole-Source Award to, Women-Owned Small Business Concerns Eligible Under the Women-Owned Small Business Program (OCT 2022) ( 15 U.S.C. 637(m)).

__ (25) 52.219-32, Orders Issued Directly Under Small Business Reserves (MAR 2020) ( 15 U.S.C. 644(r)).

__ (26) 52.219-33, Nonmanufacturer Rule (SEP 2021) ( 15U.S.C. 637(a)(17)).

_X_ (27) 52.222-3, Convict Labor (JUN 2003) (E.O.11755).

_X_ (28) 52.222-19, Child Labor-Cooperation with Authorities and Remedies (JAN 2022) (E.O.13126).

_X_ (29) 52.222-21, Prohibition of Segregated Facilities (APR 2015).

_X_ (30) (i) 52.222-26, Equal Opportunity (SEP 2016) (E.O.11246).

__ (ii) Alternate I (FEB 1999) of 52.222-26.

__ (31) (i) 52.222-35, Equal Opportunity for Veterans (JUN 2020) ( 38 U.S.C. 4212).

__ (ii) Alternate I (JUL 2014) of 52.222-35.

__ (32) (i) 52.222-36, Equal Opportunity for Workers with Disabilities (JUN 2020) ( 29 U.S.C. 793).

__ (ii) Alternate I (JUL 2014) of 52.222-36.

__ (33) 52.222-37, Employment Reports on Veterans (JUN 2020) ( 38 U.S.C. 4212).

__ (34) 52.222-40, Notification of Employee Rights Under the National Labor Relations Act (DEC 2010) (E.O. 13496).

_X_ (35) (i) 52.222-50, Combating Trafficking in Persons (NOV 2021) ( 22 U.S.C. chapter 78 and E.O.

13627).

__ (ii) Alternate I (MAR 2015) of 52.222-50 ( 22 U.S.C. chapter 78 and E.O. 13627).

__ (36) 52.222-54, Employment Eligibility Verification (MAY 2022) (Executive Order 12989). (Not applicable to the acquisition of commercially available off-the-shelf items or certain other types of commercial products or commercial services as prescribed in FAR 22.1803.)

__ (37) (i) 52.223-9, Estimate of Percentage of Recovered Material Content for EPA–Designated Items (May 2008) ( 42 U.S.C. 6962(c)(3)(A)(ii)). (Not applicable to the acquisition of commercially available off-the-shelf items.)

__ (ii) Alternate I (MAY 2008) of 52.223-9 ( 42 U.S.C. 6962(i)(2)(C)). (Not applicable to the acquisition of commercially available off-the-shelf items.)

__ (38) 52.223-11, Ozone-Depleting Substances and High Global Warming Potential Hydrofluorocarbons (Jun 2016) (E.O. 13693).

https://www.acquisition.gov/far/part-52#FAR_52_219_28 http://uscode.house.gov/browse.xhtml;jsessionid=114A3287C7B3359E597506A31FC855B3 https://www.acquisition.gov/far/part-52#FAR_52_219_28 https://www.acquisition.gov/far/part-52#FAR_52_219_29 http://uscode.house.gov/browse.xhtml;jsessionid=114A3287C7B3359E597506A31FC855B3 https://www.acquisition.gov/far/part-52#FAR_52_219_30 http://uscode.house.gov/browse.xhtml;jsessionid=114A3287C7B3359E597506A31FC855B3 https://www.acquisition.gov/far/part-52#FAR_52_219_32 https://www.govinfo.gov/content/pkg/USCODE-2018-title15/html/USCODE-2018-title15-chap14A-sec644.htm https://www.acquisition.gov/far/part-52#FAR_52_219_33 https://www.govinfo.gov/content/pkg/USCODE-2018-title15/html/USCODE-2018-title15-chap14A-sec637.htm https://www.acquisition.gov/far/part-52#FAR_52_222_3…

This is the start of the file's text. The full file is on GovTribe.

File details come from the government source that posted it. Updated .