DETROIT DAM, LINN &
MARION COUNTIES, OREGON
DETRIOT TRANSFORMER REPLACEMENT PHASE 1
SOLICITATION
W9127N21R0013
PROJECT MANUAL
CODE
(Hour)
PAGE(S)
until 01:00 PM local t ime 16 Aug 2021
X
A X B
C D
EX
X G F 35 - 43
44 - 51 H 52 - 57
ROBBIE.R.NEWLAND@usace.army .mil
RATING PAGE OF PAGES
7. ISSUED BY
(Date)
IMPORTANT - Award will be made on this Form, or on Standard Form 26, or by other authorized official written notice.
Previous Edition is Unusable 33-134 STANDARD FORM 33 (REV. 9-97)
Prescribed by GSA FAR (48 CFR) 53.214(c)
1 57
(If other than Item 7)
15A. NAME 16. NAME AND TITLE OF PERSON AUTHORIZED TO
AND
ADDRESS SIGN OFFER (Type or print)
OF
OFFEROR
AMENDMENT NO. DATE
15B. TELEPHONE NO (Include area code) 17. SIGNATURE15C. CHECK IF REMITTANCE ADDRESS
IS DIFFERENT FROM ABOVE - ENTER
SUCH ADDRESS IN SCHEDULE.
18. OFFER DATE
1. THIS CONTRACT IS A RATED ORDER
UNDER DPAS (15 CFR 700)
2. CONTRACT NO.
W9127N 8. ADDRESS OFFER TO
See Item 7
9. Sealed offers in original and 4 copies for furnishing the supplies or services in the Schedule will be received at the place specified in Item 8, or if handcarried, in the depository located in
CAUTION - LATE Submissions, Modifications, and Withdrawals: See Section L, Provision No. 52.214-7 or 52.215-1. All offers are subject to all terms and
See Block 7 conditions contained in this solicitation.
10. FOR INFORMATION
CALL:
A. NAME (NO COLLECT CALLS)
ROBBIE R NEWLAND 503-808-4634
11. TABLE OF CONTENTS
SOLICITATION/ CONTRACT FORM
SUPPLIES OR SERVICES AND PRICES/ COSTS
2 - 4
X I CONTRACT CLAUSES
DESCRIPTION/ SPECS./ WORK STATEMENT X
PACKAGING AND MARKING
J LIST OF ATTACHMENTS
INSPECTION AND ACCEPTANCE
DELIVERIES OR PERFORMANCE
6 X K REPRESENTATIONS, CERTIFICATIONS AND
OTHER STATEMENTS OF OFFERORS
CONTRACT ADMINISTRATION DATA 7 X
SPECIAL CONTRACT REQUIREMENTS
OFFER (Must be fully completed by offeror) X M
L INSTRS., CONDS., AND NOTICES TO OFFERORS
EVALUATION FACTORS FOR AWARD
NOTE: Item 12 does not apply if the solicitation includes the provisions at 52.214-16, Minimum Bid Acceptance Period.
is inserted by the offeror) from the date for receipt of offers specified above, to furnish any or all items upon which prices are offered at the price set opposite each item, delivered at the designated point(s), within the time specified in the schedule.
13. DISCOUNT FOR PROMPT PAYMENT
(See Section I, Clause No. 52.232-8)
14. ACKNOWLEDGMENT OF AMENDMENTS
(The offeror acknowledges receipt of amendments
AMENDMENT NO. DATE
to the SOLICITATION for offerors and related documents numbered and dated):
FACILITY
12. In compliance with the above, the undersigned agrees, if this offer is accepted within calendar days (60 calendar days unless a different period
SOLICITATION, OFFER AND AWARD
X
(X) SEC. DESCRIPTION (X) SEC. DESCRIPTION PAGE(S)
PART I - THE SCHEDULE
26. NAME OF CONTRACTING OFFICER (Type or print) 27. UNITED STATES OF AMERICA 28. AWARD DATE
EMAIL:TEL: (Signature of Contracting Officer)
CODE CODE
B. TELEPHONE (Include area code) C. E-MAIL ADDRESS
AWARD (To be completed by Government)
19. ACCEPTED AS TO ITEMS NUMBERED 20. AMOUNT 21. ACCOUNTING AND APPROPRIATION
22. AUTHORITY FOR USING OTHER THAN FULL AND OPEN COMPETITION:
10 U.S.C. 2304(c)( ) 41 U.S.C. 253(c)( ) (4 copies unless otherwise specified)
23. SUBMIT INVOICES TO ADDRESS SHOWN IN ITEM
24. ADMINISTERED BY (If other than Item 7) CODE 25. PAYMENT WILL BE MADE BY CODE
PART IV - REPRESENTATIO NS AND INSTRUCTIO NS
PART III - LIST O F DO CUMENTS, EXHIBITS AND O THER ATTACHMENTS
8 - 33
PART II - CO NTRACT CLAUSES
USACE, PORTLAND DISTRICT
333 SW 1ST AVE
PORTLAND OR 97204
FAX:
TEL:
FAX:
TEL:
NOTE: In sealed bid solicitations "offer" and "offeror" mean "bid" and "bidder".
SOLICITATION
6. REQUISITION/PURCHASE NO.
W66QKZ03495776
5. DATE ISSUED
30 Jun 2021
4. TYPE OF SOLICITATION
SEALED BID (IFB)
NEGOTIATED (RFP)
[ X ]
3. SOLICITATION NO.
W9127N21R0013
Section B - Supplies or Services and Prices
ITEM NO SUPPLIES/SERVICES QUANTITY UNIT UNIT PRICE AMOUNT
0001 2 Each
Design, Manufacture and Factory Test
FFP
87,000 kVA; 230 kV high-voltage winding, 13.2 kV low-voltage winding; Class ONAN cooling; three-phase GSU power transformer and accessories.
(Section 48 19 23.04 26)
PROJECT NO.: 452797
FOB: Destination
MILSTRIP: W66QKZ03495776
PURCHASE REQUEST NUMBER: W66QKZ03495776
PSC CD: 6120
NET AMT
ITEM NO SUPPLIES/SERVICES QUANTITY UNIT UNIT PRICE AMOUNT
0002 1 Job
Deliver Transformers
FFP
Deliver the transformer and devices removed for the purposes of shipment from the manufacturing facility complete to the Detroit Dam transformer yard.
(Section 48 20 00.04 26)
PROJECT NO.: 452797
FOB: Destination
PURCHASE REQUEST NUMBER: W66QKZ03495776
PSC CD: 6120
NET AMT
Section B-1
0003 1 Job
Off-load Transformers
FFP
Off-load the transformers and devices removed for shipment at the Detroit Dam power plant transformer yard, perform inspections, perform cleaning, move transformer to its operating location, perform transformer reassembly, furnish transformer oil and perform oil-filling and processing, perform field tests, and provide the of services of an Erecting Engineer and Commissioning Agent.
(Section 48 20 00.04 26)
PROJECT NO.: 452797
FOB: Destination
PURCHASE REQUEST NUMBER: W66QKZ03495776
PSC CD: 6120
NET AMT
ITEM NO SUPPLIES/SERVICES QUANTITY UNIT UNIT PRICE AMOUNT
0004 1 Lot
Furnish Spare Parts
FFP
(Section 48 19 23.04 26, paragraph 2.17)
PROJECT NO.: 452797
FOB: Destination
PURCHASE REQUEST NUMBER: W66QKZ03495776
Section B-2
0005 1 Job OPTION Short-term temporary storage
FFP
Provide short-term temporary storage of the transformer and accessories at the Detroit Dam power plant not to exceed 6 months in duration, including: move transformer to the temporary storage location, off-loading, provision of an oil containment berm and hardwood timber mats, provision of temporary grounding and 120 VAC power connections for cabinet heaters and lights, load and move the transformer to the transformer yard as the location is made available by the separate installations contractor, and provide the services of an Erecting Engineer.
(Section 48 20 01.04 26)
PROJECT NO.: 452797
FOB: Destination
PURCHASE REQUEST NUMBER: W66QKZ03495776
Section B-3
Detroit Transformer Replacement Phase 1
PROJECT TABLE OF CONTENTS
DI VI SI ON 01 - GENERAL REQUI REMENTS
01 10 00.00 25 CONTRACT ADMINISTRATION DATA
01 10 10.00 25 CONTRACTOR'S OPERATIONS AND REQUIREMENTS
01 11 00.00 25 SUMMARY OF WORK
01 22 00.00 25 MEASUREMENT AND PAYMENT
01 32 01.00 25 PROJECT SCHEDULE
01 33 00 SUBMITTAL PROCEDURES
01 35 26.00 25 GOVERNMENTAL SAFETY REQUIREMENTS
01 42 00 SOURCES FOR REFERENCE PUBLICATIONS
01 45 00.00 25 QUALITY CONTROL
01 45 00.15 25 RESIDENT MANAGEMENT SYSTEM CONTRACTOR MODE (RMS CM)
01 57 19.00 25 TEMPORARY ENVIRONMENTAL CONTROLS
01 78 23.00 25 OPERATION AND MAINTENANCE DATA
01 78 39.00 25 AS-BUILT RECORDS AND DRAWINGS
DI VI SI ON 25 - I NTEGRATED AUTOMATI ON
25 05 11.00 26 CYBERSECURITY
DI VI SI ON 26 - ELECTRI CAL
26 05 19.00 26 INSULATED WIRE AND CABLE
26 08 02.04 26 TRANSFORMER COMMISSIONING
DI VI SI ON 48 - ELECTRI CAL POWER GENERATI ON
48 19 23.04 26 CLASS II GSU POWER TRANSFORMERS
48 20 00.04 26 TRANSFORMER SHIPMENT, HAULING AND SITE ASSEMBLY
48 20 01.04 26 TRANSFORMER SHORT-TERM TEMPORARY STORAGE (OPTIONAL)
-- End of Project Table of Contents --
PROJECT TABLE OF CONTENTS Page 1
SECTION TABLE OF CONTENTS
DIVISION 48 - ELECTRICAL POWER GENERATION
SECTION 48 20 00.04 26
TRANSFORMER SHIPMENT, HAULING AND SITE ASSEMBLY
PART 1 GENERAL
1.1 GENERAL INFORMATION
1.2 DESCRIPTION OF WORK
1.3 REFERENCES
1.4 SUBMITTALS
1.5 POINT OF CONTACT FOR SITE ACCESS
1.6 FIELD SUPERVISOR EXPERIENCE AND RESPONSIBILITIES
1.6.1 Field Supervisor Experience
1.6.2 Responsibilities
1.6.3 Daily Reports
1.7 SITE ASSEMBLY CONTRACTOR EXPERIENCE
1.8 ERECTING ENGINEER SERVICES
1.8.1 General
1.8.2 Erecting Engineer's Qualifications
1.8.3 Responsibilities
1.8.4 Specialized Equipment Installation Services
1.8.5 Reporting
PART 2 PRODUCTS
2.1 DRY-AIR
2.1.1 Dry-Air in Cylinders
2.1.2 Air Compressor Dryer
2.2 Nitrogen
PART 3 EXECUTION
3.1 PROTECTION OF MATERIAL AND WORK
3.2 TRANSFORMER SHIPMENT PREPARATION
3.2.1 General
3.2.2 Packaging and Marking for Shipment
3.3 SHIPPING
3.3.1 Preparation for Shipment
3.3.2 Impact Recorders
3.3.3 Shipment
3.3.4 Hauling
3.4 TRANSFORMER MOVEMENT PLAN
3.5 SITE DELIVERY INSPECTIONS
3.5.1 Site Delivery Inspection Procedure and Schedule
3.5.2 Sample Site Delivery Inspection Procedure
3.5.3 Site Delivery Inspection Report
3.6 TRANSFORMER CLEANING
3.7 SITE MOVEMENT AND ASSEMBLY
3.7.1 Transformer Movement and Site Placement
3.7.2 Transformer Site Assembly Procedure
3.8 REQUIREMENTS FOR PERFORMANCE OF WORK WITHIN THE TRANSFORMER TANK
3.8.1 General
3.8.2 Tools and Parts Control and Accountability
3.9 TRANSFORMER OIL-FILLING AND PROCESSING
SECTION 48 20 00.04 26 Page 1
3.9.1 Tank Pressure Test
3.9.2 Vacuum Leak Test
3.9.3 Vacuum Treatment
3.9.4 Transformer Oil for Processing
3.9.5 Vacuum Filling
3.9.6 Oil Containment
3.10 TOUCH-UP PAINTING
3.11 FIELD TESTS
3.11.1 Electrical Tests
3.11.2 Oil Tests
3.12 CONTRACTOR-FURNISHED TRAINING OF GOVERNMENT PERSONNEL
3.12.1 Training General Requirements
3.12.2 Sample Training Outline
3.12.3 Training for Specialized Equipment
-- End of Section Table of Contents --
SECTION 48 20 00.04 26 Page 2
SECTION 48 20 00.04 26
TRANSFORMER SHIPMENT, HAULING AND SITE ASSEMBLY
PART 1 GENERAL
1.1 GENERAL INFORMATION
This Section, in conjunction with Sections 48 19 23.04 26, CLASS II GSU
POWER TRANSFORMERS 01 10 10.00 25, CONTRACTOR'S OPERATIONS AND
REQUIREMENTS and 01 57 19.00 25, TEMPORARY ENVIRONMENTAL CONTROLS covers the Contractor's responsibilities for shipment of the transformers for delivery f.o.b. destination Detroit Dam transformer yard, hauling, off-loading and placement, site assembly, oil-filling, field testing, and provision of Erecting Engineer services.
1.2 DESCRIPTION OF WORK
All site work for removal of the existing transformers, modifications to the power plant for acceptance of the new transformers, interconnection of the new transformers to the power plant, and welding of the transformers' bases to the mounting pads for seismic anchoring will be performed by a separate installations Contractor. Deliver the transformers to the Detroit Dam power plant per the required delivery schedule, and perform the following site work:
a. Perform on-car inspections and testing (as required).
b. Perform transformer cleaning.
c. Off-load and coordinate movement of the transformers with the separate installations Contractor, and locate the transformers on the mounting pads in the positions as indicated by the installations Contractor.
d. Off-load the accessory crates at the location directed by the COR.
e. Perform transformer reassembly, vacuum treatment, oil-filling and processing, all required field tests, and final transformer cleaning and touch-up painting.
f. Provide manufacturer's Erecting Engineer services for witnessing all site movement and work performed, as required in paragraph, "ERECTING ENGINEER SERVICES".
g. Provide Commissioning Agent services as required in Section
26 08 02.04 26, TRANSFORMER COMMISSIONING.
1.3 REFERENCES
The publications listed below form a part of this specification to the extent referenced. The publications are referred to within the text by the basic designation only.
ASTM INTERNATIONAL (ASTM)
ASTM D923 (2007) Standard Practice for Sampling
SECTION 48 20 00.04 26 Page 3
Electrical Insulating Liquids
ASTM D1933 (2003; R 2017) Standard Specification for Nitrogen Gas as an Electrical Insulating Material
ASTM D3283 (1998; R 2020) Standard Specification for Air as an Electrical Insulating Material
ASTM D3487 (2016; E2017) Standard Specification for Mineral Insulating Oil Used in Electrical Apparatus
INSTITUTE OF ELECTRICAL AND ELECTRONICS ENGINEERS (IEEE)
IEEE C57.13 (2016) Requirements for Instrument Transformers
IEEE C57.93 (2019) Guide for Installation and Maintenance of Liquid-Immersed Power Transformers
IEEE C57.149 (2012) Guide for the Application and Interpretation of Frequency Response Analysis for Oil-Immersed Transformers
IEEE C57.152 (2013) Guide for Diagnostic Field Testing of Fluid-Filled Power Transformers, Regulators, and Reactors
1.4 SUBMITTALS
Government approval is required for submittals with a "G" designation;
submittals not having a "G" designation are for information only. When used, a designation following the "G" designation identifies the office that will review the submittal for the Government. Submit the following in accordance with Section 01 33 00, SUBMITTAL PROCEDURES.
SD-01 Preconstruction Submittals
Transformer Movement Plan; G
Submit for approval a transformer movement plan detailing movement of the transformers to the Detroit Dam power plant not later than 60 calendar days prior to delivery of the transformers (see paragraph "TRANSFORMER MOVEMENT PLAN").
Transformer Site Assembly Procedure; G
Submit for approval a transformer site assembly procedure and schedule detailing the reassembly of the transformers, vacuum treatment, heated oil-filling, final field testing, and durations not later than 60 calendar days prior to delivery of the transformers (see paragraph "Transformer Site Assembly Procedure").
Field Supervisor Experience; G
Submit for approval the field supervisor experience qualifications a minimum of 60 calendar days prior to the performance of
SECTION 48 20 00.04 26 Page 4 sitework, if the proposed field supervisor is different than that included with the proposal documents. (see paragraph "Field Supervisor Experience").
Erecting Engineer's Qualifications; G
Submit for approval the manufacturer's Erecting Engineer's qualifications not later than 60 calendar days prior to delivery of the transformers (see paragraph "Erecting Engineer's Qualifications").
Site Assembly Contractor Experience List; G
Submit for approval the site assembly Contractor's experience list not later than 60 calendar days prior to delivery of the transformers (see paragraph "Site Assembly Contractor Experience").
SD-03 Product Data
Submit for approval descriptive data of the following not later than 90 calendar days prior to transformer shipment, to demonstrate fully that all items will conform to the requirements and intent of the specifications.
Insulating Oil Antioxidant Additive; G
Dry-Air; G
Nitrogen; G
SD-06 Test Reports
Delivery Transformer Oil Test Report; G
Submit for approval a transformer oil field test report, showing that the transformer oil meets the requirements of ASTM D3487, Table I, Type II, with an oxidation inhibitor content of between
0.25 and 0.30 percent by mass, not later than 15 working days following taking of the oil samples (see paragraph "Transformer Oil for Processing").
Transformer Field Test Report; G
Submit for approval a transformer field test report for each transformer not later than seven calendar days following completion of the field tests (see paragraph "Electrical Tests").
Oil-Filled Transformer Oil Test Report; G
Submit for approval a transformer oil test report for each transformer after the final transformer oil-filling process has been completed, showing that the transformer oil meets the requirements of TABLE 1, TRANSFORMER INSULATING OIL TEST REQUIREMENTS, Attachment J4, not later than 15 working days following taking of the oil samples (see paragraph "Oil Tests").
Commissioning Oil Sample Test Report; G, HDC
Submit for approval a transformer oil test report after the
SECTION 48 20 00.04 26 Page 5 completion of the loading phase during the commissioning process, showing that the transformer oil meets the requirements of TABLE 1, TRANSFORMER INSULATING OIL TEST REQUIREMENTS, included at the end of this section, not later than 15 working days following taking of the oil samples (see paragraph "Oil Tests").
SD-07 Certificates
Shipping Notices; G
Submit a list of articles shipped with descriptive data within 7 days of the shipment (see paragraph "Packaging and Marking for Shipment").
SD-08 Manufacturer's Instructions
Training Outline; G
Submit for approval a training outline covering the material to be used for performance of the on-site training session, including a schedule, not later than 10 calendar days prior to completion of the transformer field tests (see paragraph "CONTRACTOR-FURNISHED
TRAINING OF GOVERNMENT PERSONNEL").
Site Delivery Inspection Procedure And Schedule
SD-09 Manufacturer's Field Reports
Field Supervisor daily report; G
Provide a copy of the field supervisor's daily report at the end of every working day. (see paragraph "FIELD SUPERVISOR EXPERIENCE
AND RESPONSIBILITIES").
Impact Recorder Summary Report; G
Submit for approval the impact recorder summary report, including a copy of the digital impact recorder log and photos of any impacts greater than 3.0g on any axis for the analog impact recorder trace, within 24 hours after delivery of the transformers (see paragraph "Site Delivery Inspection Procedure and Schedule")
Site Delivery Inspection Report; G
Submit for approval the site delivery inspection report within 48 hours following completion of the site delivery inspection for the transformers (see paragraph "Site Delivery Inspection Report")
Tools and parts control checklist; G
Submit for approval a copy of the tools and parts control checklist at the end of every working shift. (see paragraph "Tools and Parts Control").
1.5 POINT OF CONTACT FOR SITE ACCESS
Coordinate site access no later than 30 business days prior to mobilizing at the Detroit Dam power plant for delivery of the transformers. the point of contact for coordinating site access is as follows:
SECTION 48 20 00.04 26 Page 6
Tim Ernster Detroit Dam Project Manager 40990 Hwy 22, Mill City, OR 97360
(503) 897-2385, ext. 12
1.6 FIELD SUPERVISOR EXPERIENCE AND RESPONSIBILITIES
1.6.1 Field Supervisor Experience
The field supervisor must have been engaged in the field (site) movement, reassembly, oil-filling and testing of similar power transformers as specified herein, with qualifying experience based upon performance of this work at a minimum of five projects within the previous ten years.
Submit for approval the field supervisor experience, which includes a listing of projects performed, scope of the work, and a contact name and phone number. The field supervisor and erecting engineer may be the same person, provided the qualifications for both are met.
1.6.2 Responsibilities
One full-time employee of the Contractor must be available at the worksite anytime other Contractor or subcontractor personnel are working on the site, to supervise and direct the work specified herein, who is fluent in the spoken and written English language. The supervisor must be present at the Detroit Dam power plant during all site work including transformer site movement, reassembly, oil-filling and testing, and must be responsible for following OSHA safe clearance procedures and the Government's Safe Clearance procedures. The supervisor must keep all as-built drawings current and provide copies upon completion of the work.
The field supervisor must be responsible for the performance, oversight and correctness of all site work identified in these specifications, including the following:
a. Compliance with all safety, health and reporting requirements of these specifications, including power plant Safe Clearance procedures, accident prevention, environmental protection, activity hazard analysis, fall protection, and confined space entry.
b. Preparation of all required submittals and documentation.
c. Securing an inventory of all materials entering the transformer to ensure no unintended foreign objects remain in the tank.
1.6.3 Daily Reports
Maintain a Field Supervisor daily report, and provide a copy to the COR at the end of every working day, which includes the following activities, at a minimum:
a. Weather conditions
b. References to Activity Hazard Analysis
c. Inspection activities
d. Detailed description of work performed
e. Photographs
SECTION 48 20 00.04 26 Page 7
f. Tests performed with results
g. Tools and parts control daily checklist
h. Problems noted
1.7 SITE ASSEMBLY CONTRACTOR EXPERIENCE
Submit for approval a site assembly Contractor experience list, if the transformer site assembly Contractor is other than the transformer manufacturer, documenting that the proposed Contractor has been engaged in the site assembly and oil filling of generator step-up transformers, rated greater than or equal to 230 kV and 50 MVA three-phase, self-cooled rating, for the last five (5) or more years.
1.8 ERECTING ENGINEER SERVICES
1.8.1 General
Provide a transformer manufacturer’s erecting engineer on the site of the work continually during the progress of transformer delivery, movement, assembly, oil-filling and testing, who is fluent in the spoken and written English language. The erecting engineer and field supervisor may be the same person, provided the qualifications for both are met.
1.8.2 Erecting Engineer's Qualifications
Provide an erecting engineer who is a permanent employee of the transformer manufacturing facility, or a factory certified representative thereof, who has been engaged in the witnessing of field (site) assembly and installation of similar power transformers, as specified herein, for a minimum of five years, and has performed this work on a minimum of 20 transformers. Submit for approval the Erecting Engineer’s Qualifications, consisting of a listing of this required experience, including a verifying contact, name and phone number for three facilities at which this work was performed. The Erecting Engineer has the authority to make decisions on behalf of the transformer manufacturer.
1.8.3 Responsibilities
The transformer manufacturer's Erecting Engineer is responsible for the transformers, and for the oversight and correctness of instructions given during their reassembly, including the following:
a. Witness and guide off-loading and loading of the transformers at each transloading location (transferring a shipment from one mode of transportation to another) during shipment, and off-loading from the transport truck at the Detroit Dam power plant.
b. Witness and guide movement of the transformers to their final operating location, and coordinate placement on the mounting pad with the separate installations Contractor supervisor.
c. Witness and guide the reassembly of the transformers, including the oil filling process.
d. Witness, guide or perform all transformer inspections and tests, and coordinate with the Commissioning Agent during the commissioning
SECTION 48 20 00.04 26 Page 8 process.
e. Oversee the final installation and setup of the on-line dissolved gas and moisture content monitor by the specific equipment manufacturer.
f. After completion of all transformer site work, conduct training for Government personnel, per the requirements of paragraph
"CONTRACTOR-FURNISHED TRAINING OF GOVERNMENT PERSONNEL".
1.8.4 Specialized Equipment Installation Services
The on-line dissolved gas and moisture content monitor must be installed during the transformer site reassembly process utilizing turnkey installation services by the specific equipment manufacturer.
1.8.5 Reporting
Maintain a record of all data taken during site assembly and installation, including inspection activities, instructions provided, test results, recommendations and observations, and provide this information to the Field Supervisor for inclusion in the daily reports.
PART 2 PRODUCTS
2.1 DRY-AIR
Submit for approval the descriptive data for the proposed Dry-air for use onsite in conformance with the following paragraphs.
2.1.1 Dry-Air in Cylinders
Dry-air provided in cylinders must be in accordance with ASTM D3283, Type I, with the composition and properties as follows:
a. Oxygen, volume: 19.5 percent to 23.5 percent
b. Carbon monoxide, max. volume: 0.0020 percent
c. Carbon dioxide, max. volume: 0.10 percent
d. Nitrogen: predominantly balance
e. Dew point, max.: -58 Degrees Celsius
2.1.2 Air Compressor Dryer
Dry-air supplied by a oil-less compressor must include the following, as a minimum:
a. Desiccant system on the output of the compressor for removal of dirt, water, oil and uncondensed moisture from compressed air lines.
b. Maintain a maximum -40 degrees Fahrenheit dew point, while achieving a 0 percent compressed air humidity.
c. Coalescer that removes oil and sub-micron particles down to 0.01 microns.
SECTION 48 20 00.04 26 Page 9
d. Filter that provides removal of water and contaminants down to 5 microns.
e. Provides a filtration capacity up to 30 CFM @ 175 psi.
f. Replaceable or regenerative desiccant system which provides indication of silica gel saturation.
2.2 Nitrogen
Submit for approval the descriptive data for the nitrogen proposed for use during the transformer reassembly process, and for establishing the nitrogen blanket headspace after the vacuum oil-filling process for each transformer. All nitrogen used must meet the requirements of ASTM D1933, Type III.
PART 3 EXECUTION
3.1 PROTECTION OF MATERIAL AND WORK
At all times prior to delivery and during the assembly and testing process, all materials, supplies, and equipment of every description including property which may be Government-owned and all work performed must be protected and preserved. If, as determined, material, equipment, supplies, and work performed are not adequately protected, such property may be protected by the Government and the cost thereof may be charged to the Contractor or deducted from any payment due. All machinery, materials, and articles in a complete or incomplete state for which payment has been made prior to delivery must be adequately protected from loss and from corrosion and all other forms of damage. The Contractor must also be responsible for, and make good for, any damages due through their fault or negligence occurring during assembly and testing of the equipment at the power plant.
3.2 TRANSFORMER SHIPMENT PREPARATION
3.2.1 General
Supply units of shipping dimensions and weight that allow for transport from the point of manufacture to the power plant, including any beams or cribbing required to distribute loading during shipment. Color any internal shipping blocking or bracing that is to be removed from the transformer at its destination a bright yellow, and specifically address these components and their removal during the reassembly process in the transformer site assembly procedure. Any material to be returned to the vendor after transformer shipment must be returned at the Contractor's expense, and include identification of material ownership and the shipping address. Materials not so marked will be disposed of at the Government's discretion.
3.2.2 Packaging and Marking for Shipment
a. Prepare and load all material and articles for shipment in such manner as to protect them from damage during transit, and include the following at a minimum:
(1) Protect all bushings left installed on the transformer during shipment using covers constructed of either wood or metal, securely fastened.
SECTION 48 20 00.04 26 Page 10
(2) Protect the control cabinet, and all valves located within 48 inches of the base of each transformer tank, using covers constructed of either wood or metal, and securely fastened.
(3) Wrap the entire transformer with a marine/industrial shrink film of 7-mil thickness, with provisions made for the following:
(a) Access to any transformer tank tie-down locations required during shipment.
(b) Exposure of the Lat-Lon impact recorder solar cells.
(c) Access to any testing terminals which require access during shipment.
(d) Access to the shipment dry-air gas cylinder regulator and gauges.
b. The transformer and accessories must not be shipped until after the inspections by Government personnel have been performed with all noted deficiencies corrected (unless inspection of the equipment has been waived in writing), factory acceptance tests have been completed and the test reports approved, and the Transformer Movement Plan has been reviewed and approved with either an Action Code A or B.
c. Prepare all transformer accessories removed for shipment, including spare parts, in crates with integral skids and lifting means for a fork lift. Package and wrap all accessories within the crates so that they are water resistant. Identify each shipping crate with a unique number which corresponds to an overall packing list for each transformer, and a crate contents packing list which is securely affixed within a see-through weatherproof envelope, and includes the following:
(1) Manufacturer
(2) Contract number
(3) Each spare part or accessory identified so that it can be easily matched against with the transformer, its entry on the packing list, and with the transformer layout drawing.
(4) Clearly identify the hardware included for installation of each accessory device, and fasten the hardware securely to the device if possible.
d. Identify all crates containing equipment that should be stored indoors, including electronic devices, bushings, gaskets and spare parts, with 2-inch high lettering indicating "STORE INDOORS".
Identify items that are required to be shipped and stored in a particular arrangement with 2-inch high lettering indicating "THIS
SIDE UP".
e. Submit for approval the shipping notices as soon as each shipment is made, which includes a description of the article furnished, the item number of the contract schedule to which the article applies, the shipping weight of each item, the number of pieces, the total weight, and, if shipped by railroad, the car number.
SECTION 48 20 00.04 26 Page 11
3.3 SHIPPING
3.3.1 Preparation for Shipment
Deliver the transformers with the oil drained from the tanks. Purge the tanks with dry air meeting the requirements of paragraph "DRY AIR", and install a dry air cylinder and pressure regulator set to at least 2.5 psi during shipment, including gauges to indicate both the transformer tank pressure and the cylinder pressure. Attach a shipping marker with the regulator equipment showing the regulator setting, bottle pressure, tank dew point measurements, and date the tank was sealed. Prior to shipment, perform a transformer tank pressure test in the shipping configuration, maintained for a minimum of 24 hours, to verify that there are no leaks and there is no appreciable reduction in bottle pressure. If part of the shipment is by rail, the transformer must be shipped on rail cars equipped with hydraulic draft gear and hydraulic snubbing devices.
3.3.2 Impact Recorders
Provide a 3-axis analog impact recorder for each transformer shipment, and for transportation within North America also provide a digital impact recorder with GPS satellite tracking, such as the Lat-Lon Solar Tracking Unit STU15K. Mount the impact recorders on the tank reinforcing channels, covered with a shield. Calibrate the digital impact recorder to record and transmit impact data greater than 1.0g, and provide timed on-line reports every 30 minutes during transformer movement. The impact recorder "real-time" data must be Internet viewable, and the Contracting Officer must be provided with the "login" and "password" for site access prior to shipment. Provide the impact recorder serial number and corresponding transformer serial number information for each device.
3.3.3 Shipment
Prepare the transformers and ancillary equipment for shipment from the manufacturing facility to the power plant, after completion of factory testing and the transformers have been released for shipment by the COR.
Perform the following at all transformer transloading operations:
a. Inspection and logging of the transformer tank dry air shipping pressure.
b. Inspection for any signs of transformer movement or shipping damage.
c. Take photos of the transformer and transloading movement operations.
3.3.4 Hauling
The dimensions and weight (without oil) of the largest piece as shipped by the Contractor must not exceed that allowed for truck transport and for movement to the Detroit Dam power plant. In the event the shipping dimensions or weight of the largest piece exceed those allowed for truck transport or at the project, the unit must be manufactured such that its weight and dimension can be safely reduced in the field to that allowed for transport. Any limitations affecting transportation must not become the basis for claims or damages, or for extension of time for completion of work.
SECTION 48 20 00.04 26 Page 12
3.4 TRANSFORMER MOVEMENT PLAN
The Contractor must be responsible for the transport and movement of the transformer to the power plant. Government approval of the movement plan does not constitute approval by railroad or transportation authorities.
Submit for approval the transformer movement plan, and approved with either an Action Code A or B prior to transformer shipment, to include the following as a minimum.
a. The method and means of transformer lifting and movement from the manufacturing facility to the power plant, including all transloading locations. Identify the transloading locations with scheduled inspections to be performed during these occurrences.
b. Drawings or detailed maps showing the intended route to be taken by the the transporter to the power plant.
c. Wheel, axle, outrigger, and track loads of the transport truck, as applicable, and their locations along the route. Coordinate the axle loading and road loading limitations with the applicable state and county Departments of Transportation.
d. The method and means of transformer off-loading and handling at the power plant, including equipment, crane operations, loading plans for equipment, and intended route while on Government property at the power plant.
3.5 SITE DELIVERY INSPECTIONS
3.5.1 Site Delivery Inspection Procedure and Schedule
Submit for approval a transformer site delivery inspection procedure and schedule, contain a step-by-step activity listing and a schedule that defines critical path activities and activity dependencies. Include in the procedure the persons on each shift responsible for superintendence and safe clearance, and the activities which are hazardous, affect plant operation, or require participation by Government personnel.
3.5.2 Sample Site Delivery Inspection Procedure
The following outline is based on the expected site delivery inspection and shipping procedure, and is intended to show the scope of the required work. The actual step-by-step procedure submitted must be applicable to the transformer actually furnished, and list methods of repair and/or retesting if unacceptable results of the inspections are obtained.
a. Perform an on car or transporter external inspection of the transformer and associated equipment for shipping damage, including signs of movement and loose or damaged tie rods. Provide photographs of any noted rail or transporter shipping damage, and included in the Site Delivery Inspection Report.
b. Record the transformer tank and bottle gas pressures at the shipping regulator gauges. Tank pressure must be positive. If the tank pressure is found other than positive, contact the transformer manufacturer to determine the necessity for field dry-out procedures, per the requirements of IEEE C57.93 , paragraph 4.9.2, high-vacuum drying, Method 2.
SECTION 48 20 00.04 26 Page 13
c. Perform a dew point check and determine the insulation moisture content, per the methods of IEEE C57.93 , Annex C, paragraph C.2.1.1.
Moisture content, in terms of temperature, pressure and dew point should be essentially the same as when the unit was shipped. If the moisture content is greater than 0.5 percent of the dry weight of insulation, perform field dry-out procedures per the requirements of IEEE C57.93 , paragraph 4.9.2, high-vacuum drying, Method 2.
d. Inspect the impact recorders before removal for tight securement, in position as loaded, protective cover intact, seals in position, and whether the area the device is secured to is intact, loose, or deformed. Any exceptions to the shipment observed must be brought to the attention of the COR. Remove the impact recorder mounting provisions. Inspect the analog impact recorder charts, and the digital GPS data files, in the presence of the COR for any indication of excessive impacts during shipment. Inform the transformer manufacturer of any impacts greater than 3.0g on any axis, and perform inspections and tests as required, below. Submit for approval an Impact Recorder Summary Report for each impact recorder.
e. The Contractor will be responsible for acceptance of all delivered materials and equipment, the condition, and completeness as compared to the manufacturer's shipping packing list.
f. Perform an SFRA test of each transformer in its shipping configuration, as specified in Section 48 19 23.04 26, CLASS II GSU POWER TRANSFORMERS paragraph "Sweep Frequency Response Analysis Tests", and paragraph "FIELD TESTS", below, and compare to the factory SFRA tests as performed with the transformer in its shipping configuration. Wavetrace comparisons are expected to match closely, with little differences between matched scans. Wavetrace comparisons that do not match closely must be explained to the satisfaction of the COR, and may be grounds for transformer rejection, requiring an internal inspection of the transformer by the Contractor to determine the cause of the deviations, or requiring the transformer to be sent back to the manufacturing facility for repair at no expense to the Government.
g. If shipping damage is suspected or impacts greater than 3.0g on any axis was noted on the impact recorder charts, perform an internal inspection of the transformer to check for internal damage such as loose coils, broken lead supports, dislodged end insulation, frayed lead insulation, core grounds, or loose nuts or bolts. During this internal inspection, follow the requirements of paragraph, "REQUIREMENTS FOR PERFORMANCE OF WORK WITHIN THE TRANSFORMER TANK" and include the inspection results, with photos and manufacturer repair and test recommendations, in the site delivery inspection report.
Reseal the transformer after the internal inspection has been completed, perform vacuum treatment, and repressurize the transformer to 2.5 psi with dry-air. Maintain positive pressure during transportation of the transformer to the project, off loading, and until such time that the tank is opened during assembly. Perform an additional dew point check 24 hours after reseal of the transformer.
3.5.3 Site Delivery Inspection Report
Submit for approval a Site Delivery Inspection Report after completion of the transformer site delivery inspections, based upon the approved procedural outline. The Government will not accept delivery of the
SECTION 48 20 00.04 26 Page 14 transformer until a Government review of the report verifies no damage to the transformer has occurred during shipping. The site delivery inspection report must include, but not necessarily be limited to, the following:
a. Records of inspections performed and photos taken for all transloading operations.
b. Record of the tank pressure, cylinder pressure and dew point, including the procedure for diagnosis and correction in the event of loss of positive gas pressure during shipment.
c. Visual inspection log, including photographs of any shipping damage and any evidence of transformer movement during shipment, and the proposed method of repair.
d. Results of internal inspection, if required, including photographs of any shipping damage and the proposed method of repair including any recommended tests.
e. Sweep Frequency Response Analysis test results.
3.6 TRANSFORMER CLEANING
Perform heated water pressure washing and cleaning of each transformer prior to movement to its permanent operating location at the power plant, if determined necessary by the COR. This cleaning process may be performed on the transport truck, at a location approved by the COR.
Avoid the ingress of moisture into any electrical cabinets during the cleaning process. Any cleaning agent used during this process must be biodegradable, and subject to the approval of the COR.
3.7 SITE MOVEMENT AND ASSEMBLY
3.7.1 Transformer Movement and Site Placement
Off-load and move the transformers at the power plant as indicated below.
a. Offload the accessory crates at the staging location, as indicated. Notify the COR of any crates which require indoor storage, and coordinate their storage for future access.
b. Off-load each transformer to its permanent operating location, locating the transformer on the mounting pad in the position as indicated by the installations Contractor.
c. After placement on the mounting pad, perform transformer reassembly, vacuum processing, oil-filling, all required field tests, and final transformer cleaning and touch-up painting.
d. Provide manufacturer's Erecting Engineer services for witnessing all site movement and work performed, as required in paragraph, "ERECTING ENGINEER SERVICES".
3.7.2 Transformer Site Assembly Procedure
The Contractor is responsible for the complete reassembly of the transformers, operational verification of all transformer components, vacuum processing, oil-filling and performance of the final field tests as
SECTION 48 20 00.04 26 Page 15 required in paragraph "FIELD TESTS". Submit for approval a transformer site assembly procedure which includes a step-by-step activity listing and a proposed time line for each specific task, with references to the transformer manufacturer's instructions, as follows. Include any activities which are hazardous, affect plant operation, or require participation by Government personnel.
a. Torque all bolted connections to the manufacturer's recommendations, and indicated with a permanent marker on every connection that the torquing process has been performed.
b. Perform an internal inspection of the transformer during the assembly process, by visual inspection through the manhole and bushing covers, for evidence of shifting components during transportation, condition of high-voltage lead insulation for evidence of abrasion, and verification that no tools or hardware were inadvertently left inside the tank after the manufacturing process. Any discovered anomalies must immediately be brought to the attention of the COR.
Take photos of the inside of the transformer during this inspection process, and included in the field test report.
c. Remove any interior shipping braces. Install and connect the bushings, radiators and accessory devices removed for shipment.
Install new gaskets at gasketed connections for the re-installation of components removed for shipping purposes. Thoroughly clean all gasketed grooves and mating surfaces prior to installation of the new gasket, and apply a high-temperature lubricant designed for transformer gasket applications to the gasket during installation.
The use of Vaseline as a lubricant will not be considered acceptable.
Inspect each gasket during installation to assure no damage exists, and the gasket is properly sized to provide approximately 25 percent compression for filling of the groove when installed, and not oversized causing the gasket to be compressed out of the groove and pinched between the mating surfaces.
d. Pressure test the assembled transformer.
e. Perform a vacuum leak test of the completely assembled transformer, per the requirements of IEEE C57.93 , paragraph 5.7.4, and these specifications.
f. Perform vacuum treatment and hot oil-fill the transformer under vacuum to the normal operating level per the requirements of paragraph "TRANSFORMER OIL-FILLING AND PROCESSING", and the manufacturer's recommendations (whichever is more stringent). Provide a listing of all equipment to be used during the filling process.
g. Perform routine accuracy tests on all bushing current transformers in accordance with IEEE C57.13 , paragraph 6.11. After completion of the tests, verify that all the shorting screws on the bushing current transformer terminal blocks within the control cabinet are installed, and the current transformer are shorted to ground.
h. Perform an inspection and verify the correct installation of the transformer ancillary equipment and devices after reassembly.
i. Verify the tightness of all valve stem packing glands.
j. Completely clean the transformer after completion of the reassembly
SECTION 48 20 00.04 26 Page 16 process, including the insulator sheds on the bushings, and perform touch-up painting.
3.8 REQUIREMENTS FOR PERFORMANCE OF WORK WITHIN THE TRANSFORMER TANK
3.8.1 General
Perform the following when working within, or around an opening of, the transformer tank:
a. Thoroughly clean and vacuum the top of the transformer prior to the removal of any tank man-hole covers, to minimize the possibility of contaminants entering the tank.
b. Monitor the temperature and relative humidity around the transformer during the performance of work, and tank must not be opened if the measured relative humidity is greater than 60 percent, or if there are signs of external condensation on the tank surfaces.
c. Continuously purged the tank with dry air through the lower filter valve, utilizing a dry-air compressor delivering moisture-free air at a maximum dew point of -40 degrees Fahrenheit, any time the transformer tank internals are exposed to the atmosphere.
d. Purge the tank with dry air until analysis of the gas in the transformer indicates at least 19.5 percent oxygen, prior to personnel entry.
e. Provide Tyvek suits, or equivalent, for all personnel entering the transformer tank. Maintain a logbook of all items entering and leaving the transformer tank to assure nothing has inadvertently been left inside (See paragraph "Tools and Parts Control and Accountability Procedure").
f. Cover all openings into the transformer tank whenever possible to prevent any falling objects from entering the tank.
g. Re-seal the tank at the end of each working day, and pressurized with 2.5 psi of dry-air using a dry-air cylinder.
3.8.2 Tools and Parts Control and Accountability
A tool and parts control and accountability program is necessary to ensure that foreign objects are not left within the transformer tank during internal inspections and transformer reassembly work. Personnel must remove all personal items from their person prior to entering the transformer tank. Log all tools and parts taken into the transformer tank, or which are used within the transformer tank, and any personal items which must remain with the Contractor personnel when working within the tank, onto a Tools and Parts Control Checklist. At the end of each shift, and prior to resealing of the transformer tank, account for all tools and parts identified on the checklist, and the interior of the transformer tank inspected for any loose tools or parts. To maintain control of the tools entering the transformer tank, all personal transportable tools will be checked out of a controlled space, such as a tool bin, and checked back during each shift. The Contractor Field Supervisor must be responsible during each shift to assure that inventoried tools for each craftsperson are accounted and signed for, and logged on the Tools and Parts Control Checklist. To control parts
SECTION 48 20 00.04 26 Page 17 entering the transformer tank, the Quality Control manager must inventory and issue the parts during each shift. At the end of each shift, a count will be made of the installed parts to ensure that the quantity checked out matches what was installed. Provide a copy of the Tools and Parts Control Checklist to the COR at the end of each shift for work being performed within the transformer tank,or when the transformer tank is open, and discrepancies in tools or parts must be brought to the attention of the COR.
3.9 TRANSFORMER OIL-FILLING AND PROCESSING
Provide all oil handling and high-vacuum processing equipment for filling of each transformer per the requirements of IEEE C57.93 , paragraph 5.7, or the manufacturer's recommendations, whichever is more stringent. Include the transformer oil-filling and processing procedure in the transformer site assembly procedure. No Government provided power source will be available to the Contractor for this equipment.
3.9.1 Tank Pressure Test
Perform a transformer tank pressure test after each transformer has been fully assembled, but prior to oil-filling. Verify that all bolted connections have been torque-checked for the correct tightness prior to performing the test, and perform testing at a gauge pressure of 4 psi for a minimum of 8 hours. The tank must hold pressure during the test duration without leakage, and any leaks detected resolved prior to proceeding to vacuum treatment.
3.9.2 Vacuum Leak Test
Perform a transformer tank vacuum leak test after each transformer has been fully assembled, but prior to oil-filling. Ensure that all devices which are not suitable for vacuum have been valved off prior to testing.
A vacuum level of 0.25 Torr must be achieved, and during the initial 30 minutes of the test the maximum allowable pressure rise must not exceed
0.15 Torr. If more than 0.15 Torr of vacuum is lost during the first 30 minutes, or if the rate of loss of vacuum increases over time, determine the source of the vacuum leak and take the necessary corrective actions, and re-perform the vacuum leak test until the maximum allowable pressure rise has been achieved.
3.9.3 Vacuum Treatment
After an acceptable leak rate has been achieved, perform vacuum treatment by holding a maximum vacuum of 0.25 Torr for a duration per the manufacturer's recommendations, but must be a minimum of 24 hours. If a vacuum of 0.25 Torr cannot be achieved, check all bolted fittings for tightness, and explain to the satisfaction of the COR. During this period, hot oil at a temperature between 60 - 65 degrees Celsius may be introduced to aid in heating the windings for moisture removal, then drained to allow for moisture removal using vacuum.
3.9.4 Transformer Oil for Processing
Provide insulating transformer oil which meets requirements of Section 48 19 23.04 26, paragraph "INSULATING OIL", delivered in tanker trucks in which the tank interiors were either cleaned prior to delivery or the prior haul was for unused transformer insulating oil. Provide a certificate verifying tank cleanliness upon delivery. Prior to filling, SECTION 48 20 00.04 26 Page 18 take oil samples and test per the requirements of paragraph "Oil Tests".
3.9.5 Vacuum Filling
After vacuum treatment, the oil…