B.08 Solicitation - 26QA035 - Willapa Sediment Characterization Service.pdf

PDF 8 MB Posted

Attached to
FY26 Willapa Sediment Characterization Service
Solicitation number
W912DW26QA035
Issued by

About this file

This is a Request for Quote (RFQ) solicitation for sediment characterization services in Willapa Bay, Washington, issued by the U.S. Army Corps of Engineers (USACE) Seattle District. The solicitation number is W912DW26QA035, with a solicitation issue date of March 19, 2026, and an offer due date of April 6, 2026, at 11:00 AM Pacific Standard Time. This is a 100% small business set-aside under NAICS code 541620 (Environmental Consulting Services) with a size standard of $19 million. The contract will be awarded as a firm-fixed-price purchase order to the lowest priced technically acceptable quote.

The contract requires comprehensive sediment characterization services for three federal navigation features in Willapa Bay (Tokeland, Bay Center, and Nahcotta) in Pacific County, Washington, with a nine-month period of performance beginning May 1, 2026. The base scope includes six contract line items: (1) Sampling and Analysis Plan preparation; (2) sample collection and processing of 36 grab samples; (3) physical and chemical analysis of sediment samples for Dredged Material Management Program (DMMP) chemicals of concern; (4) data validation; (5) sediment characterization report; and (6) Environmental Information Management (EIM) data entry. Sixteen optional line items are available for additional sampling, specialized analyses (metals, semivolatiles, pesticides, PCB aroclors, wood waste), reference sediment sampling, and bioassay testing including purging procedures and retests. Quoters must provide complete pricing for all base CLINs and specify unit pricing for optional CLINs. Contractor key personnel required include a Contract Manager, Project Manager, Site Safety and Health Officer, and Quality Control Manager, all to be designated within ten days of award. Analytical laboratories must be accredited by the Washington State Department of Ecology, NELAP, or equivalent certification approved by DMMP. All contractors must be registered in the System for Award Management (SAM) prior to award, and payment will be made by Electronic Funds Transfer (EFT).

View the file

Other files

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

WOMEN-OWNED SMALL

BUSINESS (WOSB)

SOLICITATION/CONTRACT/ORDER FOR COMMERCIAL PRODUCTS AND COMMERCIAL SERVICES

1. REQUISITION NUMBER PAGE 1 OF

2. CONTRACT NUMBER 3. AWARD/EFFECTIVE

DATE

4. ORDER NUMBER 5. SOLICITATION NUMBER 6. SOLICITATION ISSUE

DATE

7. FOR SOLICITATION

INFORMATION CALL:

a. NAME b. TELEPHONE NUMBER (No collect 8. OFFER DUE DATE/

LOCAL TIME

9. ISSUED BY

13b. RATING

14. METHOD OF SOLICITATION

CODE

15. DELIVER TO 16. ADMINISTERED BY CODE

18a. PAYMENT WILL BE MADE BY CODE17a. CONTRACTOR/

OFFEROR

CODE

FACILITY

CODE

CODE

TELEPHONE NUMBER

17b. CHECK IF REMITTANCE IS DIFFERENT AND PUT SUCH ADDRESS IN

OFFER

18b. SUBMIT INVOICES TO ADDRESS SHOWN IN BLOCK 18a UNLESS BLOCK

BELOW IS CHECKED

REQUEST

FOR QUOTE

(RFQ)

INVITATION

FOR BID

(IFB)

REQUEST

FOR

PROPOSAL

(RFP)

SEE ADDENDUM

19.

ITEM NUMBER

20.

SCHEDULE OF SUPPLIES/SERVICES

21.

QUANTITY

22.

UNIT

23.

UNIT PRICE

24.

AMOUNT

(Use Reverse and/or Attach Additional Sheets as Necessary)

25. ACCOUNTING AND APPROPRIATION DATA 26. TOTAL AWARD AMOUNT (For Government Use Only)

28. CONTRACTOR IS REQUIRED TO SIGN THIS DOCUMENT AND RETURN

COPIES TO ISSUING OFFICE. CONTRACTOR AGREES TO FURNISH

AND DELIVER ALL ITEMS SET FORTH OR OTHERWISE IDENTIFIED ABOVE AND

ON ANY ADDITIONAL SHEETS SUBJECT TO THE TERMS AND CONDITIONS

SPECIFIED

29. AWARD OF CONTRACT: REFERENCE OFFER

DATED . . YOUR OFFER ON SOLICITATION

(BLOCK 5), INCLUDING ANY ADDITIONS OR CHANGES WHICH ARE

SET FORTH HEREIN, IS ACCEPTED AS TO ITEMS:

30a. SIGNATURE OF OFFEROR/CONTRACTOR

30b. NAME AND TITLE OF SIGNER (Type or print) 30c. DATE SIGNED

31a. UNITED STATES OF AMERICA (SIGNATURE OF CONTRACTING OFFICER)

31b. NAME OF CONTRACTING OFFICER (Type or print) 31c. DATE SIGNED

AUTHORIZED FOR LOCAL REPRODUCTION

PREVIOUS EDITION IS NOT USABLE

STANDARD FORM 1449 (REV. 11/2021)

Prescribed by GSA - FAR (48 CFR) 53.212

10. THIS ACQUISITION IS UNRESTRICTED OR

NORTH AMERICAN

INDUSTRY CLASSIFICATION

STANDARD (NAICS):

SIZE STANDARD:

13a. THIS CONTRACT IS A

RATED ORDER UNDER

THE DEFENSE PRIORITIES

AND ALLOCATIONS

SYSTEM - DPAS (15 CFR 700)

SET ASIDE: % FOR:

11. DELIVERY FOR FREE ON

BOARD (FOB) DESTINATION

UNLESS BLOCK IS MARKED

SEE SCHEDULE

12. DISCOUNT TERMS

ARE ARE NOT ATTACHED

ARE ARE NOT ATTACHED

27a. SOLICITATION INCORPORATES BY REFERENCE (FEDERAL ACQUISITION REGULATION) FAR 52.212-1, 52.212-4. FAR 52.212-3

AND 52.212-5 ARE ATTACHED. ADDENDA

27b. CONTRACT/PURCHASE ORDER INCORPORATES BY REFERENCE FAR 52.212-4. FAR 52.212-5 IS ATTACHED. ADDENDA

8(A)

ECONOMICALLY

DISADVANTAGED

WOMEN-OWNED SMALL

BUSINESS (EDWOSB)

SERVICE-DISABLED

VETERAN-OWNED

SMALL BUSINESS

(SDVOSB)

HUBZONE SMALL

BUSINESS

SMALL BUSINESS

NOTE: OFFEROR TO COMPLETE BLOCKS 12, 17, 23, 24, AND 30.

calls)

Solicitation/Contract Form Continuation

FY26 Willapa Sediment Characterization ServiceInstrument Name:

QUOTER INSTRUCTIONS

1. The Solicitation (RFQ) Number is: W912DW26QA035 as described in Block 5 of this solicitation (page 1). The title is Willapa Bay Sediment Characterization Service.

2. Per Block 10 of this solicitation (page 1) this is a 100% small business set-aside. The NAICS code for this requirement is 541620 - Environmental Consulting Services with a size standard of $19M. The PSC is B510 - Special Studies / Analysis - Environmental Assessments.

3. See the Purchase Description for a complete description of this requirement.

4. Closing Date and Time Due: 06 April 2026 NLT 1100 PST.

5. Award will be made as a Firm-Fixed Priced Purchase Order to the lowest priced quote whose quote conforms to the requirement of the solicitation and where price has been determined fair and reasonable. The quoter must provide pricing for ALL items in the solicitation for its quote to be acceptable to the Government. Quotes must set forth full, accurate and complete information as required by the RFQ.

Multiple quotes are not accepted for this RFQ. If multiple quotes are received only one quote (as determined by the Contracting Officer) will be evaluated by the Government. The quote shall be determined acceptable based on the date and time received.

The contractor should list any special features or warranty information applicable to the quoted product(s).

6. Quotes shall be emailed to della.s.overton@usace.army.mil with the subject line "RFQ W912DW26QA035". All questions resulting from this RFQ shall be submitted by close of business two (2) days prior to the closing date. For questions email the aforementioned email address. For timely submitted inquiries, responses may be posted as an amendment to the solicitation via Contract Opportunities website at www.sam.gov prior to the RFQ closing date.

Quoters are responsible for review of the Contract Opportunities website for any posted amendments to the RFQ.

7. PROSPECTIVE OFFERORS: Contractors shall be registered in the System for Awards Management (SAM) prior to award of a contract or agreement resulting from solicitations.

"Registered in the System for Award Management (SAM) database" means that -

(1) The Offeror has entered all mandatory information, including the unique entity identifier and the EFT indicator, if applicable, the Commercial and Government Entity (CAGE) code, as well as data required by the Federal Funding Accountability and Transparency Act of 2006 (see subpart 4.14), into the SAM database;

(2) The offeror has completed the Core, Assertions, and Representations and Certification, and Points of contact sections of the registration in the SAM database;

W912DW26QA035

(3) The Government has validated all mandatory data fields, to include validation of the Taxpayer Identification Number (TIN) with the Internal Revenue Service (IRS). The Offeror will be required to provide consent for TIN validation to the Government as a part of the SAM registration process.

(4) The Government has marked the record "Active".

This rule more efficiently implements the Debt Collection Improvement Act of 1996, as it requires contractors to be registered in SAM for consideration of future solicitations, awards, and payment. Registration is required prior to award of any contract, basic agreement, basic ordering agreement, or blanket purchase agreement from a solicitation. LACK OF

REGISTRATION IN THE SAM DATABASE WILL MAKE AN OFFER INELIGIBLE FOR

AWARD. The web site may be accessed at www.sam.gov.

8. ELECTRONIC FUNDS TRANSFER (EFT): Effective 99 Jun 01, the Government will make all payments by EFT (unless the Government VISA credit card is accepted). The only exceptions are: 1) Foreign Vendors, 2) Government Agencies, and 3) One-time payments.

The USACE Finance Center (UFC) has altered their process for obtaining electronic funds transfer (EFT) banking information utilized for vendor contract payment and will no longer accept UFC Form 23 to update EFT banking information for vendors. Banking information for all vendors will be retrieved from SAM.gov and entered into CEFMS II. There are no exceptions to this policy change. All contractors must notify the UFC via e-mail at: cefc-fc-eft@usace.army.mil when banking information has been updated in SAM.gov. Compliance with this requirement will help ensure timely payment to the correct back account.

9. State and Local Taxes

The U.S. Army Corps of Engineers is exempt from paying state and local taxes per Title 4 United States Code 104-107. The U.S. Army Corps of Engineers Tax ID Number is 62-1642142.

Contractors performing services for the U.S. Army Corps of Engineers are not exempt from state and local taxes in transactions with vendors, suppliers or subcontractors.

It is the contractor's responsibility to investigate applicable federal, state, and local taxes, along with any specific exemptions that may exist. This includes any applicable Value-Added Taxes (VAT), sales, use, and excise taxes.

The U.S. Army Corps of Engineers will not accept any invoice with a separate tax line. If there are any appropriate taxes, the contractor my considerer that tax as the cost of doing business and incorporate that cost within the cost of the item or job.

10. Submittals should include: a, c, d, e, and 11 (Failure to complete any of the following tasks renders your quote ineligible)

a) Signed and dated STANDARD FORM 1449 (Solicitation/ Contract/ Order for Commercial Items). See blocks 30a, b, and c.

b) Signed and dated STANDARD FORM 30, if applicable, for any Amendments to the solicitation. See blocks 15a, b, and c.

c) Completed pricing information for all CLIN items.

d) Completed full text clauses that require fill-in information.

e) Required items in #11 below.

11. PLEASE COMPLETE INFORMATION BELOW. The contractor is required to provide the following information with your quote:

Federal Taxpayer's ID Number (EIN): _____________________________________

Unique Entity ID (UEI): ____________________________________________________

Cage Code Number ______________________________________________________

Remit to Address: ________________________________________________________

Company Name: _________________________________________________________

DBA______________________________________________________________________

Address: _________________________________________________________________

City/State/Zip: ____________________________________________________________

Phone & Fax Numbers: __________________________________________________

Point of Contact: ________________________________________________________

E-Mail Address: __________________________________________________________

*** END OF NARRATIVE ***

Continuation of Supplies or Services and Prices/Costs

Additional Information/Notes

Item Supplies/Service Quantity Unit Unit Price

Amount

0001 Sampling and Analysis Plan (SAP).

Detailed requirements for this CLIN are described in the attached PWS.

Pricing Arrangement: Firm Fixed Price

1 Job

0002 Sample Collection and Processing.

Detailed requirements for this CLIN are described in the attached PWS.

Pricing Arrangement: Firm Fixed Price

1 Job

0003 Physical and Chemical Analysis of Sediment Samples. Detailed requirements for this CLIN are described in the attached PWS.

Pricing Arrangement: Firm Fixed Price

1 Job

0004 Data Validation. Detailed requirements for this CLIN are described in the attached PWS.

Pricing Arrangement: Firm Fixed Price

1 Job

0005 Sediment Characterization Report.

Detailed requirements for this CLIN are described in the attached PWS.

Pricing Arrangement: Firm Fixed Price

1 Job

0006 EIM Data Entry. Detailed requirements for this CLIN are described in the attached PWS.

Pricing Arrangement: Firm Fixed Price

1 Job

Option Line Item

Sampling/ Processing of 4 Additional Grab Samples (Option). Detailed requirements for this CLIN are described in the attached PWS.

Pricing Arrangement: Firm Fixed Price

1 Job

Option Line Item

Analysis of Additional Samples - Sediment Conventionals (Option).

Detailed requirements for this CLIN are described in the attached PWS.

Pricing Arrangement: Firm Fixed Price

1 Job

Option Line Item

Analysis of Additional Samples - Standard DMMP COCs (Option).

Detailed requirements for this CLIN are described in the attached PWS.

Pricing Arrangement: Firm Fixed Price

1 Job

Option Line Item

Analysis of Sediment Samples - Metals (Option). Detailed requirements for this CLIN are described in the attached

PWS.

Pricing Arrangement: Firm Fixed Price

1 Job

Option Line Item

Analysis of Sediment Samples - Semivolatiles (Option). Detailed requirements for this CLIN are described in the attached PWS.

Pricing Arrangement: Firm Fixed Price

1 Job

Option Line Item

Analysis of Sediment Samples - PCB Aroclors (Option). Detailed requirements for this CLIN are described in the attached PWS.

Pricing Arrangement: Firm Fixed Price

1 Job

Option Line Item

Analysis of Sediment Samples - Pesticides GC/MS or High-Resolution (Option). Detailed requirements for this CLIN are described in the attached

PWS.

Pricing Arrangement: Firm Fixed Price

1 Job

Option Line Item

Analysis of Sediment Samples - Pesticides (Option). Detailed requirements for this CLIN are described in the attached PWS.

Pricing Arrangement: Firm Fixed Price

1 Job

Option Line Item

Analysis of Sediment Samples - Wood Waste (Option). Detailed requirements for this CLIN are described in the attached PWS.

Pricing Arrangement: Firm Fixed Price

1 Job

Option Line Item

Reference Sediment Sampling (Option).

Detailed requirements for this CLIN are described in the attached PWS.

Pricing Arrangement: Firm Fixed Price

1 Job

Option Line Item

Bioassays with Purging Pretest and Purging for 2 Samples (Option) Pricing Arrangement: Firm Fixed Price

1 Job

Option Line Item

Bioassays, Purging Pretest, and Purging Procedure for Additional Sample (Option). Detailed requirements for this CLIN are described in the attached PWS.

Pricing Arrangement: Firm Fixed Price

1 Job

Option Line Item

Amphipod Retest for One Sample (Option). Detailed requirements for this CLIN are described in the attached

PWS.

Pricing Arrangement: Firm Fixed Price

1 Job

Option Line Item

Larval Retest for One Sample (Option).

Detailed requirements for this CLIN are described in the attached PWS.

Pricing Arrangement: Firm Fixed Price

1 Job

Option Line Item

Neanthes Retest for One Sample (Option). Detailed requirements for this CLIN are described in the attached

PWS.

Pricing Arrangement: Firm Fixed Price

1 Job

W912DW26BAXXX – 1

Performance Work Statement Sediment Characterization

Willapa Bay Pacific County, Washington

November 2025

TABLE OF CONTENTS

PART 1 – GENERAL INFORMATION

1.1 DESCRIPTION OF SERVICES / INTRODUCTION

1.2 BACKGROUND

1.2.1 Previous Sediment Characterizations

1.3 OBJECTIVES

1.4 SCOPE

1.5 PERIOD OF PERFORMANCE (PoP)

1.6 GENERAL INFORMATION

1.6.1 Schedule

1.6.2 Quality Assurance

1.6.3 Government Review

1.6.4 Recognized Holidays

1.6.5 Hours of Operation

1.6.6 Place of Performance

1.6.7 Type of Contract

1.6.8 Security Requirements

1.6.9 Special Qualifications .......................................................Error! Bookmark not defined.

1.6.10 Post Award Conference/Periodic Progress Meetings

1.6.11 USACE Personnel and Billing Procedures

1.6.12 Key Personnel

1.6.13 Pre-screening Requirements for Personnel Candidates

1.6.14 Identification of Contractor Employees

1.6.15 Contractor Travel

1.6.16 Other Direct Costs

1.6.17 Data Rights

1.6.18 Organizational Conflict of Interest

1.6.19 Phase in/Phase out Period ................................................Error! Bookmark not defined.

1.6.20 Laboratory Requirements

1.6.21 Subcontracts

PART 2 - DEFINITIONS AND ACRONYMS

2.1 DEFINITIONS

2.1.1 Contractor

2.1.2 Contracting Officer (KO)

W912DW26BAXXX – 2

2.1.3 Contracting Officer's Representative (COR)

2.1.4 Defective Service

2.1.5 Deliverable

2.1.6 Key Personnel

2.1.7 Physical Security

2.1.8 Quality Assurance

2.1.9 Quality Control

2.1.10 Subcontractor

2.1.11 Work Day

2.1.12 Work Week

2.2 ACRONYMS

PART 3 - GOVERNMENT FURNISHED PROPERTY, EQUIPMENT, AND SERVICES

3.1 SERVICES

3.2 FACILITIES

3.3 UTILITIES

3.4 EQUIPMENT

3.5 MATERIALS

PART 4 - CONTRACTOR FURNISHED ITEMS AND SERVICES

4.1 GENERAL

4.2 SECRET FACILITY CLEARANCE

4.3 MATERIALS

4.4 EQUIPMENT

PART 5 - SPECIFIC TASKS

5.1 BASIC SERVICES

5.2 BASE ITEMS

5.2.1 CLIN 1 - SAP Preparation

5.2.2 CLIN 2 - Sample Collection and Processing

5.2.3 CLIN 3 – Physical and Chemical Analysis of Sediment Samples

5.2.4 CLIN 4 - Data Validation

5.2.5 CLIN 5 – Sediment Characterization Report

5.2.6 CLIN 6 - EIM Data Entry

5.3 OPTION ITEMS

5.3.1 Award of Options

5.3.2 CLIN 7 - Sampling/Processing of 4 Additional Grab Samples (Option)

5.3.3 CLIN 8 - Analysis of Additional Samples – Sediment Conventionals (Option)

5.3.4 CLIN 9 - Analysis of Additional Samples –Standard DMMP COCs (Option)

5.3.5 CLIN 10 - Analysis of Sediment Samples – Dioxins/furans (Option) .......Error! Bookmark not defined.

5.3.6 CLIN 11 - Analysis of Sediment Samples – Metals (Option)

5.3.7 CLIN 12 - Analysis of Sediment Samples – Semivolatiles (Option)

5.3.8 CLIN 13 - Analysis of Sediment Samples – PCB Aroclors (Option)

5.3.9 CLIN 14 – Analysis of Sediment Samples - Pesticides GC/MS or High-Resolution (Option) ... 23

W912DW26BAXXX – 3

5.3.10 CLIN 15 - Analysis of Sediment Samples – Pesticides (Option)

5.3.11 CLIN 16 – Analysis of Sediment Samples - Wood Waste (Option)

5.3.12 CLIN 17 - Reference Sediment Sampling (Option)

5.3.13 CLIN 18 - Bioassays with Purging Pretest and Purging for 2 Samples (Option)

5.3.14 CLIN 19 - Bioassays, Purging Pretest, and Purging Procedure for Additional Sample (Option)

5.3.15 CLIN 20 - Amphipod Retest for One Sample (Option)

5.3.16 CLIN 22 - Larval Retest for One Sample (Option)

5.3.17 CLIN 23 - Neanthes Retest for One Sample (Option)

PART 6 - APPLICABLE PUBLICATIONS PERTAINING TO THIS PWS

PART 7 - ATTACHMENT/TECHNICAL EXHIBIT LISTING

7.1 Attachment 1 – Tables

7.2 Attachment 2 – Figures

7.3 Technical Exhibit 1 - Performance Requirements Summary (PRS)

7.3.1 Performance Objectives

7.4 Technical Exhibit 2 - Deliverables Schedule

7.4.1 Transmission of Submittals

W912DW26BAXXX – 4

PART 1 – GENERAL INFORMATION

This is a non-personnel services contract to provide technical services for a sediment characterization in Willapa Bay, Washington (Figure 1). The U.S. Army Corps of Engineers (USACE) will not exercise any supervision or control over the contract service providers performing the services herein. Such contract service providers will be accountable solely to the Contractor who, in turn, is responsible to the USACE.

1.1 DESCRIPTION OF SERVICES / INTRODUCTION

Provide all personnel, equipment, facilities, transportation, tools, materials, supervision, and other items and non-personal services necessary to perform the tasks for a sediment characterization in Willapa Bay as defined in this Performance Work Statement (PWS) except as specified in Section 3 as USACE-furnished property and services. Perform to the standards in this contract.

1.2 BACKGROUND

As authorized by Congress, the Seattle District, U.S. Army Corps of Engineers (USACE) is responsible for maintenance dredging of the Willapa Bay project components including the entrance channel at Tokeland Marina, the entrance channel and mooring basin access lane at Bay Center, and the entrance channel and mooring basin access lane at Nahcotta, in Pacific County, Washington.

USACE last dredged portions of the Willapa Bay navigation project in 2002. Since then, the Port of Willapa has used a small private cutterhead dredge to maintain portions of the project every two to six years. USACE has continued to evaluate the project, with sediment testing completed in 2007 at Tokeland, 2011 at Bay Center, 2014 at Tokeland, Bay Center, and Nahcotta, and 2020 at Tokeland, Bay Center, and Nahcotta. In the most recent characterization, all dredged material was found to be suitable for open-water disposal (DMMP 2021). Table 1 summarizes details regarding the dimensions of project features and estimated volume above authorized depth. The USACE is responsible for dredging portions of the authorized project as needed to maintain navigation.

1.2.1 Previous Sediment Characterizations

The navigation channel is ranked “low” by the Dredged Material Management Program (DMMP) agencies for concern for potential contamination. Descriptions of the historical characterization efforts follow.

1.2.1.1 Tokeland

• 1991. A single composited dredged material management unit (DMMU) sample representing the marina (including marina area P1) was collected in 1991 and analyzed for DMMP chemicals of concern (COCs). Three COCs (4-methylphenol, phenol, and pyrene) had detected exceedances; non-detect exceedances occurred for an additional number of chemicals. Bioassay testing was conducted, and the DMMP agencies determined that the dredged material was suitable for unconfined open-water disposal (DMMP 1991).

• 1998. Twelve individual grab samples were collected in March 1998 and composited into three DMMUs to represent 76,000 cubic yards (CY) from the entrance channel, marina, and marina area P1. There were no COC detections or non-detect concentrations that exceeded the DMMP screening levels. All material was found suitable for open-water disposal (DMMP 1998a).

• 2006. A total of eleven grab samples were collected from the entrance channel, marina, and marina area P1 in August 2006; the grab samples were composited into three composites to represent the entrance channel, marina, and marina area P1. Based on the two previous sequential testing rounds

W912DW26BAXXX – 5

conducted in 1991 and 1998, the marina and marina area P1 were re-ranked from moderate to low-moderate for testing purposes. No COCs were detected above the DMMP screening levels. Five non-detected chemicals (hexachlorobenzene, dimethylphenol, benzoic acid, N-nitrosodiphenylamine, and alpha-chlordane) had detection limits that exceeded DMMP screening levels in one or all three DMMUs; bioassay testing was thus required for all three DMMUs. The results from the bioassay testing indicated that all of the material was suitable for unconfined open-water disposal (DMMP 2007).

• 2014. Eight cores were collected from the entrance channel, marina, and marina area P1 in September 2014 and composited into four DMMUs (2 surface and 2 subsurface DMMUs). No COCs were detected above DMMP screening levels; three COCs (total chlordane, dieldrin, and heptachlor) were not detected with elevated reporting limits above their respective DMMP screening levels in all four DMMUs. All DMMUs samples were subsequently analyzed for the standard DMMP pesticide COCs using a high resolution method with lower reporting limits; using this method, all pesticides were non-detect with detection limits below the DMMP screening levels. Total dioxin Toxic Equivalencies (TEQs) were below the 15 pptr TEQ and 5 pptr 2,3,7,8-TCDD threshold concentrations for dispersive disposal in Willapa Bay. Total TEQs (U=1/2 reporting limit [RL]) ranged from 1.2 to 2.7 pptr. All material was found suitable for unconfined open-water disposal (DMMP 2015).

• 2020. Nine cores were collected in August 2020. Material from the cores were composited into three DMMUs to represent the entrance channel, marina, and marina area P1. All material was found suitable for unconfined open-water/flow-lane disposal (DMMP 2021).

1.2.1.2 Bay Center

• 1998. Tier 1 no-test for 15,000 CY from Bay Center Entrance Channel, based on a 1993 grain size characterization that showed 99.7% sand from two samples (DMMP 1998b).

• 2001. Vibracore samples characterized 38,000 CY of proposed dredged material. Cores were composited into three DMMUs: two surface and one subsurface DMMUs. Analyses included all routine DMMP COCs (including tributyltin [TBT], but no dioxin) and included special analyses for pesticides carbaryl and glyphosate. All chemicals were either detected or not detected below DMMP screening levels (SLs), and TBT was quantitated at levels well below the screening limit in the porewater of the three DMMUs characterized. All sediments were found suitable for open-water disposal (DMMP 2001).

• 2011. Port of Willapa proposed 18,000 CY of dredging in shoals leading to the Bay Center Marina.

Five individual grab samples were composited into one DMMU. Laboratory analysis was conducted for the standard DMMP COCs plus glyphosate and dioxins. There were no SL exceedances; dioxin TEQ (U=1/2 RL) was 1.36 pptr. All material was found suitable for open-water disposal (DMMP 2011).

• 2015. Eight cores were composited into two surface DMMUs. Porewater TBT was not detected at

0.005 mg/L. Diethyl phthalate initially exceeded the SL in DMMU 2, but further replicated extractions and reanalysis did not replicate this finding. Because diethyl phthalate is a common laboratory contaminant, the DMMP concluded that the original finding was anomalous. Dioxin TEQs (U=1/2 RL) were 1.33 and 0.62 pptr, well below the 15 pptr TEQ threshold for Willapa Bay. All material was found suitable for open-water disposal (DMMP 2015).

W912DW26BAXXX – 6

• 2020. To characterize approximately 72,000 CY, six cores were collected in the Inner Channel and composited into two DMMUs for laboratory analysis of the DMMP COC list. In the Palix River access lane, three grabs were composited for one DMMU analyzing total solids, total organic carbon, and grain size under the Tier 1 no-test exclusionary status. and all material was found suitable for open-water/flow-lane disposal (DMMP 2021).

1.2.1.3 Nahcotta

• 2004. In September 2003, cores were collected from a total of 17 locations and composited into four composite DMMUs to represent 145,000 CY of proposed dredging. Only standard DMMP COCs were analyzed for, and there were no detected or undetected results above screening levels. All material was found suitable for unconfined open-water disposal (DMMP 2004).

• 2015. In September 2014, forty cores were collected and subsequently composited to represent eleven DMMUs, of which one was a subsurface DMMU. No COCs were detected above DMMP screening levels. Two COCs (total chlordane and heptachlor) were undetected with elevated reporting limits above their respective DMMP screening levels in two DMMUs. All DMMU samples were subsequently analyzed for the standard DMMP pesticide COCs using a high-resolution method with lower reporting limits; using this method, no pesticides were detected or not detected above the DMMP screening levels. TBT (porewater) was undetected at 0.005 mg/L. Total dioxin TEQs were below the 15 pptr TEQ and 5 pptr 2,3,7,8-TCDD threshold concentrations for dispersive disposal in Willapa Bay. Total TEQs (U=1/2 RL) ranged from 1.2 to 3.7 pptr. All material was found to be suitable for unconfined open-water disposal (DMMP 2015).

• 2020. Sixteen cores were collected in the entrance channel and boat basin to characterize three surface and two subsurface DMMUs. Sampling was conducted in August 2020. The standard DMMP COC list was analyzed and no COCs were detected above DMMP screening levels. All material was found suitable for open-water/flow-lane disposal (DMMP 2021).

1.3 OBJECTIVES

The objectives for this contract are as follows:

• to prepare a sampling and analysis plan (SAP) that shall be suitable for submission to the DMMP agencies for approval;

• to sample and characterize the sediments in the proposed dredging area as described in the SAP; and

• to prepare a report to document characterization results that can then be used by DMMP to make a suitability determination. This PWS includes preparation of the SAP; sampling and testing of dredged material; data collection and analysis; and report preparation.

1.4 SCOPE

Perform a sediment characterization in Willapa Bay. The services provided under this contract are detailed in Part 5 – Specific Tasks.

1.5 PERIOD OF PERFORMANCE (POP)

The Period of Performance shall be for nine (9) months (270 days) from time of award to contract completion.

W912DW26BAXXX – 7

1.6 GENERAL INFORMATION

1.6.1 Quality Control Plan

Quality control procedures are addressed under Part 5 Specific Tasks, CLIN 1.

1.6.2 Quality Assurance

The USACE will evaluate the Contractor’s performance under this contract in accordance with the Performance Requirements Summary (See Section 7.3). This plan is primarily focused on what the USACE must do to ensure that the Contractor has performed in accordance with the performance standards. It defines how the performance standards will be applied, the frequency of surveillance, and the minimum acceptable defect rate(s).

On the request of the Contracting Officer’s Representative (COR) or any inspector, provide the use of boats, boatmen, laborers, and material forming a part of the ordinary and usual equipment of the sampling team as may be reasonably necessary to inspect the sampling work.

1.6.3 Schedule

Submit a project schedule within ten (10) business days after the date of award. The schedule should target sampling with sufficient time for completion of option CLINs, if required. Update the project schedule, at minimum, monthly. Include an updated schedule in all Pay Requests.

1.6.3.1 Government Review

Include two (2) weeks for Government review of any and all contract deliverables.

1.6.3.2 Recognized Holidays

The Contractor is not required to work on Federal Holidays:

New Year’s Day Martin Luther King Jr.’s Birthday President’s Day Memorial Day Independence Day Juneteenth Labor Day Indigenous Peoples Day (Columbus Day) Veterans Day Thanksgiving Day Christmas Day

1.6.3.3 Hours of Operation

The Contractor is responsible for being responsive to communication from USACE between the hours of 8:00 a.m. and 4:00 p.m. Pacific Time, Monday thru Friday, except Federal holidays or when the USACE facility is closed due to local or national emergencies, administrative closings, or similar USACE-directed facility closings.

1.6.4 Place of Performance

The services described in this PWS will be performed in Willapa Bay and at the Contractor’s offices.

1.6.5 Type of Contract

The USACE will award a performance-based Firm Fixed Price Contact.

W912DW26BAXXX – 8

1.6.6 Security Requirements

There are no special security requirements. Work will not be conducted at a federal facility of any kind;

will not involve the use of government equipment or vessels; and will not require access to government automated information systems. Refer to Section 1.6.11 for required pre-screening procedures for Contractor key personnel.

1.6.7 Post Award Conference/Periodic Progress Meetings

The Contractor agrees to attend any post award conference convened by the contracting activity or contract administration office in accordance with Federal Acquisition Regulation Subpart 42.5. The Contracting Officer (KO), COR, and other Government personnel, as appropriate, may meet periodically with the Contractor to review the Contractor's performance. At these meetings the KO will apprise the Contractor of how the government views the Contractor's performance and the Contractor will apprise the Government of problems, if any, being experienced. Appropriate action shall be taken to resolve outstanding issues. These meetings shall be at no additional cost to the government.

Attend a virtual initial coordination meeting with the COR and Quality Assurance Representative (QAR) within two (2) weeks of contract award. The purpose of this meeting will be to familiarize the Contractor with the project and discuss any issues with planning, project personnel, and necessary materials and equipment to assure that the study goes forward as planned.

1.6.8 USACE Personnel

1.6.8.1 Contracting Officer (KO)

Refer to Part 2 of this PWS for the definition of a Contracting Officer (KO).

1.6.8.2 Contracting Officer’s Representative (COR)

Refer to Part 2 of this PWS for the definition of a COR. As determined by the Contracting Officer, a COR will be appointed and identified by letter of designation, a copy of which will be provided to the Contractor by the Contracting Officer. The designation letter states the responsibilities and limitations of the COR, especially with regard to changes in cost or price, estimates, or changes in delivery dates. The COR is not authorized to change any of the terms and conditions of the resulting order. The COR monitors all technical aspects of the contract and assists in contract administration. The COR is not authorized to obligate the Government. If the work is not written in the contract, the COR is not authorized to request new work.

The COR is authorized to perform the following functions: assure that the Contractor performs the technical requirements of the contract, perform inspections necessary in connection with contract performance, maintain written and oral communications with the Contractor concerning technical aspects of the contract, issue written interpretations of technical requirements, including Government drawings, designs, specifications, monitor Contractor's performance and notifies both the Contracting Officer and Contractor of any deficiencies, coordinate availability of Government property, and coordinate site entry of Contractor personnel.

1.6.8.3 Quality Assurance Representative (QAR)

The QAR monitors technical aspects of the contract and assists in contract administration. The QAR assures that the Contractor performs the technical requirements of the contract, performs inspections necessary in connection with contract performance, maintains written and oral communications with the Contractor concerning technical aspects of the contract, monitors Contractor performance and

W912DW26BAXXX – 9

notifies both the Contracting Officer and Contractor of any deficiencies. The QAR is not authorized to change any of the terms and conditions of the resulting order.

1.6.9 Billing Procedures

Submit invoices electronically to the QAR and COR in accordance with the progress schedule for work performed under this contract. The COR will review the invoice for acceptance and processing.

1.6.10 Contractor Key Personnel

Designate the following key personnel within ten (10) days of contract award except as otherwise indicated:

1.6.10.1 Contract Manager

The Contract Manager is responsible for the overall management and administration of the contract.

Designate in writing to the KO at the time of award, and in the SAP, the name of this person, and an alternate who will act for the Contractor when the Contract Manager is absent.

1.6.10.2 Project Manager

The Project Manager is responsible for the execution and coordination of all technical aspects of the project; assures timely completion of tasks, adherence to the statement of work, and maintenance of quality; communicates directly with the QAR as needed for resolution of technical issues; and notifies the COR, QAR and Contract Manager of any substantive changes needed in the PWS.

The Project Manager is responsible for developing work plans, coordinating and assisting the field collection team, and ensuring that laboratory data from the project meets the program requirements.

The Project Manager oversees the interpretation and reporting of the project results.

1.6.10.3 Site Safety and Health Officer

The Site Safety and Health Officer (SSHO) is responsible for overseeing and ensuring implementation of the Contractor’s Safety and Occupational Health (SOH) program in accordance with the latest version of the USACE Safety and Occupational Health (SOH) Requirements Manual (EM 385-1-1). The SSHO must have the authority to shut down the site work if/when Health and Safety becomes an issue. The SSHO may enlist the support of safety and occupational health professionals with appropriate education and experience when working on sites with multiple (chemical, biological, and physical) hazards.

Designate the SSHO in the Sampling and Analysis Plan submittal.

1.6.10.4 Quality Control Manager

The Quality Control (QC) Manager is responsible for overall management of Contractor Quality Control (CQC) and has the authority to act in all CQC matters. The QC Manager is responsible for ensuring compliance with the requirements identified in the Performance Work Statement and the Contractor Quality Control procedures.

Designate the QC Manager in the Sampling and Analysis Plan submittal.

1.6.11 Pre-screening Requirements for Personnel Candidates

The following are prescreening requirements for key Contractor personnel required by USACE:

Pre-screen Candidates using the E-Verify Program (http://www.uscis.gov/e-verify) website to meet the established employment eligibility requirements. The Contractor must ensure that the Candidate has two valid forms of Government issued identification prior to enrollment to ensure the correct information is entered into the E-Verify system. Provide an initial list of verified/eligible Candidates to http://www.dhs.gov/E-Verify

W912DW26BAXXX – 10

the COR no later than 3 business days after the initial contract award. When contracts are with individuals, the individuals will be required to complete a Form I-9 Employment Eligibility Verification, with the designated Government representative. This Form will be provided to the KO and become part of the official contract file.

1.6.12 Identification of Contractor Employees

All contract personnel attending meetings and working in other situations where their Contractor status is not obvious to third parties are required to identify themselves as such to avoid creating an impression in the minds of members of the public that they are USACE officials. They must also ensure that all documents or reports produced by Contractors are suitably marked as Contractor products or that Contractor participation is appropriately disclosed.

1.6.13 Contractor Travel

Contractor will be required to travel to Pacific County, Washington for the survey. Contractor will be authorized travel expenses consistent with the substantive provisions of the Joint Travel Regulation (JTR) and the limitation of funds specified in this contract. All travel requires Government approval/authorization and notification to the COR. Travel expenses must be included in the proposal submitted in response to the request for proposals.

1.6.14 Other Direct Costs

This category includes travel (outlined in 1.6.13), sampling vessels, sampling equipment and supplies, report reproduction, and shipping expenses.

1.6.15 Data Rights

The Government has unlimited rights to all documents/material produced under this contract. All documents and materials produced under this contract will be Government owned and are the property of the Government with all rights and privileges of ownership/copyright belonging exclusively to the Government. These documents and materials may not be used or sold by the Contractor without written permission from the KO. All materials supplied to the Government will be the sole property of the Government and may not be used for any other purpose. This right does not abrogate any other Government rights.

1.6.16 Organizational Conflict of Interest

Contractor and subcontractor personnel performing work under this contract may receive, have access to or participate in the development of proprietary or source selection information (e.g., cost or pricing information, budget information or analyses, specifications or work statements, etc.) or perform evaluation services which may create a current or subsequent Organizational Conflict of Interests (OCI) as defined in FAR Subpart 9.5. Notify the KO immediately whenever it becomes aware that such access or participation may result in any actual or potential OCI and promptly submit a plan to the KO to avoid or mitigate any such OCI. The Contractor’s mitigation plan will be determined to be acceptable solely at the discretion of the KO and in the event the KO unilaterally determines that any such OCI cannot be satisfactorily avoided or mitigated, the KO may affect other remedies as he or she deems necessary, including prohibiting the Contractor from participation in subsequent contracted requirements which may be affected by the OCI.

1.6.17 Laboratory Requirements

Certification, accreditation, and/or license documentation will be required as part of the proposal. This documentation includes the name and location of the prime laboratories and any other laboratory(ies)

W912DW26BAXXX – 11

to be used. The state(s) in which the laboratory is certified/accredited or licensed (if no certification/accreditation is available/required) will be provided in the documentation. If any laboratory fails to meet project specific requirements at any time, the KO will direct the contractor to procure services from a laboratory which meets project specific requirements.

1.6.17.1 Analytical (Chemical) Testing

The laboratory to be used must be accredited by the Washington State Department of Ecology, the National Environmental Laboratory Accreditation Program (NELAP), or equivalent certification approved by the DMMP. Accreditation must be held for all analytes required to be reported and for the analytical methods proposed in the sampling and analysis plan.

1.6.17.2 Bioassay and Geotechnical Testing

The laboratory must be accredited by the NELAP.

1.6.18 Subcontracts

The Contractor shall not subcontract any portion of this contract to any party other than those identified in the proposal submitted in response to this RFQ without written notification to and written authorization from the KO.

W912DW26BAXXX – 12

PART 2 - DEFINITIONS AND ACRONYMS

2.1 DEFINITIONS

2.1.1 Contractor

A supplier or vendor awarded a contract to provide specific supplies or service to the USACE. The term used in this contract refers to the prime.

2.1.2 Contracting Officer (KO)

A person with authority to enter into, administer, and or terminate contracts, and make related determinations and findings on behalf of the USACE. The KO is the only individual who can legally bind the USACE.

2.1.3 Contracting Officer's Representative (COR)

The COR is an individual designated and authorized in writing by the KO to perform specific technical or administrative functions. This individual has authority to provide technical direction to the Contractor as long as that direction is within the scope of the contract, does not constitute a change, and has no funding implications. This individual does NOT have authority to change the terms and conditions of the contract.

2.1.4 Defective Service

A service output that does not meet the standard of performance associated with the PWS.

2.1.5 Deliverable

Anything that can be physically delivered but may include non-manufactured things such as meeting minutes or reports.

2.1.6 Key Personnel

Contractor personnel that are evaluated in a source selection process and that may be required to be used in the performance of a contract by the Key Personnel listed in the PWS. When key personnel are used as an evaluation factor in best value procurement, an offer can be rejected if it does not have a firm commitment from the persons that are listed in the proposal.

2.1.7 Physical Security

Actions that prevent the loss or damage of USACE property.

2.1.8 Quality Assurance

The USACE procedures to verify that services being performed by the Contractor are performed according to acceptable standards.

2.1.9 Quality Control

All necessary measures taken by the Contractor to assure that the quality of an end product or service will meet contract requirements.

2.1.10 Subcontractor

One that enters into a contract with the prime Contractor. USACE does not have privity of contract with the subcontractor.

W912DW26BAXXX – 13

2.1.11 Work Day

The number of hours per day the Contractor provides services in accordance with the contract.

2.1.12 Work Week

Monday through Friday, unless specified otherwise.

2.2 ACRONYMS

CLIN Contract Line-Item Number COC Chemical of Concern COR Contracting Officer Representative CY Cubic Yards DMMO Dredged Material Management Office DMMP Dredged Material Management Program DMMU Dredged Material Management Unit DOD Department of Defense EIM Environmental Information Management EPA Environmental Protection Agency FAR Federal Acquisition Regulation GIS Geographic Information System JTR Joint Travel Regulation KO Contracting Officer MLLW Mean Lower Low Water OCI Organizational Conflict of Interest PRS Performance Requirements Summary PWS Performance Work Statement QA Quality Assurance QAR Quality Assurance Representative QC Quality Control RL Reporting Limit SAP Sampling and Analysis Plan SCR Sediment Characterization Report SL Screening Level SMARM Sediment Management Annual Review Meeting TBT Tributyltin TE Technical Exhibit TEQ Toxic Equivalency USACE United States Army Corps of Engineers

W912DW26BAXXX – 14

PART 3 - GOVERNMENT FURNISHED PROPERTY, EQUIPMENT, AND SERVICES

3.1 SERVICES

The QAR will coordinate review of the SAP and sediment characterization report with the DMMP agencies and provide combined agency comments to the Contractor on these documents. The QAR will also coordinate with the DMMP agencies and provide guidance on any technical issues that arise.

3.2 FACILITIES

Not applicable.

3.3 UTILITIES

Not applicable.

3.4 EQUIPMENT

Not applicable.

3.5 MATERIALS

USACE will provide the following electronic information:

• The most recent hydrosurvey data for Willapa Bay Federal features (Tokeland, Bay Center, and Nahcotta) in .xyz format. Data is available online on the eHydro website:

http://navigation.usace.army.mil/Survey/Hydro#state=WA

• GIS shapefile or HYPACK files delineating the project footprint to be characterized.

http://navigation.usace.army.mil/Survey/Hydro#state=WA

W912DW26BAXXX – 15

PART 4 - CONTRACTOR FURNISHED ITEMS AND SERVICES

4.1 GENERAL

Furnish all supplies, equipment, facilities and services required to perform work under this contract that are not listed under Section 3 of this PWS.

4.2 SECRET FACILITY CLEARANCE

Not Applicable.

4.3 MATERIALS

Provide all applicable materials necessary for the successful completion of this contract including but not limited to sampling supplies, shipping supplies, lab supplies, and report publishing materials and expenses.

4.4 EQUIPMENT

Provide all needed equipment to meet the requirements under this PWS, including but not limited to, sampling vessels, navigation equipment, sampling equipment, data analysis software, and computers.

W912DW26BAXXX – 16

PART 5 - SPECIFIC TASKS

5.1 BASIC SERVICES

Provide all management, personnel, equipment, supplies, facilities, transportation, tools, materials, supervision, and applicable licenses and permits necessary to perform the services described in this

PWS.

5.2 BASE ITEMS

5.2.1 CLIN 1 – SAP Preparation

Develop and submit a Sampling and Analysis Plan (SAP) that follows the guidance found in the most recent DMMP User Manual (DMMP 2025); updates to DMMP implemented via the sediment management annual review meeting (SMARM) process; and the specific requirements in this PWS. The purpose of the SAP is to provide a clear detailed description of how the project will be executed.

Detailed requirements for this CLIN are described in the following subsections.

5.2.1.1 Submittal Procedures

Submit the draft SAP to the QAR for review. Revise and re-submit in response to comments received until all comments have been addressed.

Between the time that the SAP is approved by USACE, and the commencement of work outlined in the SAP, a pre-sampling conference call may be held at the request of USACE.

No sampling activities may occur until the QAR has approved the SAP. The SAP must be approved at least seven (7) days before sampling is scheduled to occur.

5.2.1.2 Project Description

Provide a general project description; description of the project organization, including a chart showing roles, responsibilities, lines of authority, and key project personnel, including proposed subcontractors;

and contact information.

Describe the means and methods to complete the required work. Prepare supporting figures and tables.

The SAP must contain the information outlined in Section 6 of the DMMP User Manual in sufficient detail to allow the agencies to evaluate the adequacy of the sampling and analysis program.

5.2.1.3 Characterization volumes

The Government estimated characterization volumes are estimated based on the bathymetric survey conducted in March 2025 bathymetric survey data (Table 1).

Recalculate the volumes in all sections (to include side slopes) to verify that the original estimates are sufficient and to guide sample placement. Use the project footprints and characterization depths as shown in Table 1. Include 2H:1V side slopes in volume calculations.

The Government may exercise options for additional sampling collection if needed based on the Contractor’s proposed sampling design.

5.2.1.4 Determine the number of required DMMUs and Minimum Samples

All material will be considered homogenous for the purposes of this contract. The DMMP project ranking for all sub-areas is Low.

No subsurface DMMUs will be used for this project. Grab samples will be used to characterize all DMMUs. In low ranked areas, the DMMP minimum sampling requirement for homogenous sediment is

W912DW26BAXXX – 17

one field sample for every 8,000 CY. The DMMU volume limit for low-ranked homogenous material is 60,000 CY. Due to a majority of the COCs being non-detected at all Willapa Bay sites in 2020, the DMMP is not requiring the field sampling frequency of one sample per 8,000 CY or the maximum volume of a DMMU of 60,000 CY as outlined in the DMMP User Manual.

Table 1 summarizes the project details, required DMMU subdivisions, and estimated anticipated number of grab samples and DMMUs required. For pricing purposes, eight (8) DMMUs are included in the base program. Contract options may be exercised to accommodate additional DMMUs in the approved SAP.

5.2.1.5 Target sampling stations

Place target sampling stations within each DMMU to provide an adequate spatial and volumetric representation of the dredging prism. Target sampling stations on shoals shallower than the operational depth, not the characterization depth. Provide figures and tables that provide the following information:

• DMMU locations and IDs

• Target sampling locations with sampling coordinates, an anticipated mudline elevation (ft

MLLW), and sampling methodology.

5.2.1.6 Quality Control Procedures

Develop and maintain Quality Control procedures to ensure services are performed in accordance with this PWS and to identify, prevent, and ensure non-recurrence of defective services. Include with the SAP, at a minimum:

• A description of the quality control organization, including a chart showing key personnel, roles, and lines of authority. The chart can be combined with the main project organization chart detailed in Section 5.2.1.2.

• Description of the quality control procedures and methods to complete the required work.

• Procedures for identifying, tracking, and correcting deficiencies.

5.2.1.7 Site-Specific Health and Safety Plan

Prepare a brief, site-specific Health and Safety Plan, in accordance with the USACE Safety and Health Requirements Manual (EM 385-1-1, current version) that addresses health and safety issues relevant to field activities associated with this project.

5.2.1.8 Other Elements and Requirements to be included in the SAP

In addition, please note the following:

• Sample volume must provide sufficient material for all potential testing in the base CLINs and options, including testing of the full suite of bioassays, additional ammonia/sulfides testing, and potential purging prior to conducting bioassays.

• Description of bioassays and associated QA/QC requirements must include both termination protocols (standard and re-suspension) for the larval test, along with the…

This is the start of the file's text. The full file is on GovTribe.

File details come from the government source that posted it. Updated .