This is a sealed bid Invitation for Bid (IFB) solicitation for construction work on the Mississippi River levee system near Magna Vista-Brunswick, Mississippi. The contract requires furnishing all plant, labor, materials, and equipment to construct MRL Item 465-L Slide Repair and Levee Enlargement and Berms in Issaquena County, Mississippi. Principal features include mobilization and demobilization, clearing and grubbing, removal of existing surfacing, excavation and stockpiling of existing levee material, semi-compacted and fully compacted levee embankment, stability berm embankment, crushed stone surfacing, ramp construction, mowing, turfing, storm water pollution prevention, and environmental protection. The estimated project price range is between $5,000,000 and $10,000,000. Sealed bids are due by 2:00 PM local time on March 20, 2026, at the U.S. Army Corps of Engineers, Vicksburg District, 4155 Clay Street, Vicksburg, MS 39183-3435. The contract completion deadline is 275 calendar days after the contractor receives the Notice to Proceed. Performance and payment bonds equal to 100 percent of the original contract price are required. Liquidated damages are assessed at $1,529.00 per calendar day of delay.

This procurement is a 100 percent set-aside for small business concerns under NAICS Code 237990 and is restricted exclusively to FY 25 MATOC contract holders for Mississippi River Levees Construction of Levee Enlargements and Berms. Only the four listed MATOC contract holders—Affolter Contracting Company, Inc.; B&K Construction Company, LLC; Circle, LLC; and Tarpan Construction, LLC—are eligible to submit proposals. No other offers will be considered. The contractor must comply with small business subcontracting requirements under FAR 52.219-14, maintaining at least 15 percent of adjusted contract value for similarly situated small business entities on general construction work. Plans, specifications, and drawings are available at www.sam.gov and www.projnet.org. Technical inquiries must be submitted via ProjNet using the provided bidder inquiry key. The contractor must register in SAM.gov, acknowledge receipt of all amendments, submit representations and certifications, and provide a completed bid schedule with unit and total prices for all line items.

View the file

Other files

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

SOLICITATION No. W912EE26RA009

DATE: 19 FEBRUARY 2026

SPECIFICATIONS

FOR

MR&T, EAST BANK MISSISSIPPI RIVER LEVEES,

MAGNA VISTA-BRUNSWICK, MISSISSIPPI LEVEE

ENLARGEMENT AND BERMS

MRL 465-L SLIDE REPAIR

THIS PROCUREMENT IS SET-ASIDE FOR THE

MISSISSIPPI RIVER LEVEES, CONSTRUCTION OF

LEVEE ENLARGEMENTS AND BERMS, MATOC

CONTRACT HOLDERS.

Building Strong®

Serving the Army Serving the Nation

VICKSBURG DISTRICT

4155 CLAY STREET

VICKSBURG, MS 39183-3435 CEMVK-CT-C

INQUIRIES

REGARDING THIS SOLICITATION SHOULD

BE MADE TO THE FOLLOWING:

https://www.projnet.org

Plans and specifications will be available on the Web Page at:

https://www.sam.gov/

(See ).

SOLICITATION, OFFER,

AND AWARD

(Construction, Alteration, or Repair)

IMPORTANT - The "offer" section on the reverse must be fully completed by offeror.

9. FOR

INFORMATION CALL:

NOTE: In sealed bid solicitations "offer" and "offeror" mean "bid and "bidder".

SOLICITATION

1. SOLICITATION NUMBER

5. REQUISITION/PURCHASE REQUEST NUMBER

CODE

6. PROJECT NUMBER

8. ADDRESS OFFER TO

4. CONTRACT NUMBER

7. ISSUED BY

11. The contractor shall begin performance within

12a. THE CONTRACTOR MUST FURNISH ANY REQUIRED PERFORMANCE AND PAYMENT BONDS?

(If "YES", indicate within how many calendar days after award in Item 12b.)

13. ADDITIONAL SOLICITATION REQUIREMENTS:

a. Sealed offers in original and

b. An offer guarantee

c. All offers are subject to the (1) work requirements, and (2) other provisions and clauses incorporated in the solicitation in full text or by reference.

d. Offers providing less than

STANDARD FORM 1442 (REV. 12/2022)

Prescribed by GSA - FAR (48 CFR) 53.236-1(d) calendar days for Government acceptance after the date offers are due will not be considered and will be rejected.

is, is not required.

local time containing offers shall be marked to show the offeror's name and address, the solicitation number, and the date and time offers are due.

(date). If this is a sealed bid solicitation, offers will be publicly opened at that time. Sealed envelopes copies to perform the work required are due at the place specified in Item 8 by (hour) award, YES NO notice to proceed. This performance period is mandatory negotiable.

calendar days and complete it within calendar days after receiving

a. NAME b. TELEPHONE NUMBER (Include area code) (NO COLLECT CALLS)

12b. CALENDAR DAYS

2. TYPE OF SOLICITATION

SEALED BID (IFB)

INVITATION FOR BID

NEGOTIATED (RFP)

REQUEST FOR PROPOSAL

3. DATE ISSUED PAGE OF PAGES

W912EE26RA009 1 48

PAN 026130

W07V ENDIST VICKSBURG

KO CONTRACTING DIVISION, 4155 CLAY STREET

VICKSBURG, MS 39183-3435

UNITED STATES

AMY STARKS, EMAIL: AMY.L.STARKS@USACE.ARMY.MIL TELEPHONE: 601-631-

W912EE

AMY STARKS 601-631-5693

10. THE GOVERNMENT REQUIRES PERFORMANCE OF THE WORK DESCRIBED IN THESE DOCUMENTS (Title, identifying number, date)

PROJECT TITLE: MR&T, EAST BANK MISSISSIPPI RIVER LEVEES, MAGNA VISTA-BRUNSWICK, MISSISSIPPI LEVEE ENLARGEMENT AND BERMS MRL ITEM 465-L SLIDE

REPAIR

PROJECT LOCATION: JACKSON, MISSISSIPPI

MR&T, EAST BANK MISSISSIPPI RIVER LEVEES

MAGNA VISTA - BRUNSWICK, MISSISSIPPI

LEVEE ENLARGEMENT AND BERMS

MRL ITEM 465-L SLIDE REPAIR

THE WORK CONSISTS OF FURNISHING ALL PLANT, LABOR, MATERIALS AND EQUIPMENT, AND CONSTRUCTING MRL ITEM 465-L SLIDE REPAIR AND LEVEE ENLARGEMENT, STABILITY BERMS, AND RAMP IN ISSAQUENA COUNTY, MISSISSIPPI. PRINCIPAL FEATURES OF WORK INCLUDE MOBILIZATION AND DEMOBILIZATION, CLEARING AND GRUBBING, REMOVING OF EXISTING SURFACING, EXCAVATING AND STOCKPILING EXISTING LEVEE MATERIAL, SEMI- COMPACTED LEVEE EMBANKMENT, SEMI-COMPACTED STABILITY BERM EMBANKMENT, FULLY COMPACTED LEVEE EMBANKMENT, PLACING CRUSHED STONE SURFACING, RAMP CONSTRUCTION, MOWING, TURFING, STORM WATER POLLUTION PREVENTION, ENVIRONMENTAL PROTECTION, AND ALL OTHER WORK

THERETO.

IN ACCORDANCE WITH FAR 36.101-3 DISCLOSURE OF THE MAGNITUDE OF CONSTRUCTION PROJECTS, THE ESTIMATED PRICE RANGE OF THIS PROJECT IS $5,000,000.00

BETWEEN $10,000,000.

10 275

FAR 52.211-10

02:00 PM

20 MAR 2026

19 FEBRUARY 2026

AWARD (To be completed by Government)

17. The offeror agrees to perform the work required at the prices specified below in strict accordance with the terms of this solicitation, if this offer is accepted calendar days after the date offers are due. (Insert any number equal to or greater than the minimum requirement by the Government in writing within stated in Item 13d. Failure to insert any number means the offeror accepts the minimum in Item 13d.)

OFFER (Must be fully completed by offeror)

AMOUNTS

18. The offeror agrees to furnish any required performance and payment bonds.

19. ACKNOWLEDGMENT OF AMENDMENTS

(The offeror acknowledges receipt of amendments to the solicitation -- give number and date of each)

AMENDMENT

NUMBER

DATE

CONTRACTING OFFICER WILL COMPLETE ITEM 28 OR 29 AS APPLICABLE

14. NAME AND ADDRESS OF OFFEROR (Include ZIP Code)

CODE FACILITY CODE

15. TELEPHONE NUMBER (Include area code)

16. REMITTANCE ADDRESS (Include only if different than Item 14.)

20a. NAME AND TITLE OF PERSON AUTHORIZED TO SIGN OFFER (Type or print)

21. ITEMS ACCEPTED:

22. AMOUNT

26. ADMINISTERED BY

30a. NAME AND TITLE OF CONTRACTOR OR PERSON AUTHORIZED TO SIGN (Type or print)

31c. DATE

STANDARD FORM 1442 (REV. 12/2022) BACK

31b. UNITED STATES OF AMERICA

BY

31a. NAME OF CONTRACTING OFFICER (Type or print)

29. AWARD (Contractor is not required to sign this document.) Your offer on this solicitation is hereby accepted as to the items listed. This award consummates the contract, which consists of (a) the Government solicitation and your offer, and (b) this contract award. No further contractual document is necessary.

30b. SIGNATURE 30c. DATE

28. NEGOTIATED AGREEMENT (Contractor is required to sign this document and return and deliver all items or perform all work requirements identified on this form and any continuation sheets for the consideration stated in this contract. The rights and obligations of the parties to this contract shall be governed by (a) this contract award, (b) the solicitation, and (c) the clauses, representations, certifications, and specifications incorporated by reference in or attached to this contract.

copies to issuing office.) Contractor agrees to furnish

24. SUBMIT INVOICES TO ADDRESS SHOWN IN

(4 copies unless otherwise specified)

23. ACCOUNTING AND APPROPRIATION DATA

ITEM

25. OTHER THAN FULL AND OPEN COMPETITION PURSUANT TO THE UNITED STATES

CODE AT

27. PAYMENT WILL BE MADE BY

10 U.S.C. 3204(a) ( ) 41 U.S.C. 3304(a) ( )

20b. SIGNATURE 20c. OFFER DATE

W912EE26RA009

Section 00 00 00 - Procurement and Contracting Requirements Instrument Name: MRL ITEM 465-L SLIDE REPAIR

MR&T, EAST BANK MISSISSIPPI RIVER LEVEES MAGNA VISTA – BRUNSWICK,

MISSISSIPPI LEVEE ENLARGEMENT AND BERMS MRL ITEM 465-L SLIDE REPAIR The work consists of furnishing all plant, labor, materials and equipment, and constructing MRL Item 465-L slide repair and levee enlargement, stability berms, and ramp in Issaquena County, Mississippi. Principal features of work include mobilization and demobilization, clearing and grubbing, removing of existing surfacing, excavating and stockpiling existing levee material, semi-compacted levee embankment, semi-compacted stability berm embankment, fully compacted levee embankment, placing crushed stone surfacing, ramp construction, mowing, turfing, storm water pollution prevention, environmental protection, and all other work thereto.

IN ACCORDANCE WITH FAR 36.101-3 DISCLOSURE OF THE MAGNITUDE OF

CONSTRUCTION PROJECTS, THE ESTIMATED PRICE RANGE OF THIS PROJECT IS

BETWEEN $5,000,000.00 and $10,000,000.

MR&T, East Bank Mississippi River Levees, Magna Vista-Brunswick, Mississippi Levee Enlargement and Berms MRL ITEM 465-L Slide Repair

Proposal Package Requirements

Offerors Shall Submit with their Proposal Package:

1) A Complete and Signed SF-1442 with Amendments Acknowledged.

2) A Complete Bid Schedule, with the Offerors Unit Price, and Total Line Item Bid $ Amounts.

3) An accurately completed copy of the Offerors Representations and Certifications (Ref.

FAR Clause 4.203 System for Award Management).

In lieu of the completed FAR 4.203 System for Award Management, the bidder may certify in their proposal package that their Online Representations and Certifications are available electronically at www.sam.gov. (Ref. FAR Clause 52.204-7 System for Award Management).

*** END OF NARRATIVE 1 ***

http://www.sam.gov/

Section 00 01 15 - List of Drawing Sheets

Identifier Document Name

Document Description

Reference Identifier

Date Line Item

Page Numbers

Document Type

Provided Under Separate Cover

0001 Statement of Work (S OW)final

Statement of Work

Feb

203 Attachment No

0002 MRL Item 4 65-L Drawi ngs

Drawings 17 Feb

37 Attachment No

0003 Wage Deter mination M S20260002

Wage Determination

Feb

5 Attachment No

ITEM DESCRIPTION

EST

QTY U/M

UNIT

PRICE AMOUNT

MOBILIZATION AND

DEMOBILIZATION 1 JOB FOR $

CLEARING AND GRUBBING

1 JOB FOR $

REMOVAL OF EXISTING

SURFACING 1 JOB FOR $

0004 TURFING AND MOWING 1 JOB FOR $

ENVIRONMENTAL PROTECTION

FEATURES 1 JOB FOR $

EXCAVATION AND STOCKPILE

OF EXISTING LEVEE MATERIAL

1 JOB FOR $

LEVEE EMBANKMENT,

SEMICOMPACTED 194,900 CY $ $

BERM EMBANKMENT,

SEMICOMPACTED 52,700 CY $ $

LEVEE EMBANKMENT, FULLY

COMPACTED 10,900 CY $ $

*0010

LEVEE SURFACING, CRUSHED

STONE 2,330 TN $ $

*0011

RAMP 1 JOB $ $

*0012

TURFING AND MOWING, LEVEE

AND LEVEE/BERM Sta.

8200+00 TO Sta. 8300+00 1 JOB $

BIDDING SCHEDULE:

MR&T, EAST BANK MISSISSIPPI RIVER LEVEES,

MAGNA VISTA-BRUNSWICK, MISSISSIPPI LEVEE ENLARGEMENT AND BERMS

MRL 465-L SLIDE REPAIR

TOTAL

Section 00 21 00 - Instructions

Instructions to Offerors or Bidders:

NOTES:

(A) In accordance with DFARS 240.370-5 the following provisions and clauses are required in all solicitations except for solicitations/contracts solely for the acquisition of commercially available off-the-shelf (COTS) items:

Provision - 252.204-7008, Compliance with Safeguarding Covered Defense Information Control.

Clause - 252.204-7009, Limitations on the Use or Disclosure of Third- Party Contractor Reported Cyber Incident Information.

Clause - 252.204-7012, Safeguarding Covered Defense Information and Cyber Incident Reporting

Clause - 252.204-7997, NIST SP 800-171 DoD Assessment Requirements.

(B) In the case of solicitation W912EE26RA009, implementation of a NIST SP 800-171 assessment is not a requirement since there is no covered defense information provided by the Government in the release of the solicitation, and the solicitation contains no controlled technical information. All information related to this project has been posted for full public view at www.sam.gov.

(C) Reference Limitations on Subcontracting FAR 52.219-14. This procurement is 100% Set-aside under NACIS Code 237990-Other Heavy and Civil Engineering Construction, for Total Small Business. The small business size standard is $45,000,000. THIS PROCUREMENT IS SET-ASIDE FOR THE MISSISSIPPI

RIVER LEVEES, CONSTRUCTION OF LEVEE ENLARGEMENTS AND BERMS, MATOC CONTRACT

HOLDERS. NO OTHER OFFERS WILL BE CONSIDERED. The awardee of this contract shall comply with all requirements up to and including the following:

Services (except construction): Contractor will not pay more than 50 percent of the amount paid by the Government for contract performance to subcontractors that are not similarly situated entities. Any work that a similarly situated entity further subcontracts will count towards the prime contractor's 50 percent subcontract amount that cannot be exceeded. When a contract includes both services and supplies, the 50 percent limitation shall apply only to the service portion of the contract.

Supplies (other than procurement from a nonmanufacturer of such supplies): Contractor will not pay more than 50 percent of the amount paid by the Government for contract performance, excluding the cost of materials, to subcontractors that are not similarly situated entities. Any work that a similarly situated entity further subcontracts will count towards the prime contractor's 50 percent subcontract amount that cannot be exceeded. When a contract includes both supplies and services, the 50 percent limitation shall apply only to the supply portion of the contract.

General construction: Contractor will not pay more than 85 percent of the amount paid by the Government for contract performance, excluding the cost of materials, to subcontractors that are not similarly situated entities. Any work that a similarly situated entity further subcontracts will count towards the prime contractor's 85 percent subcontract amount that cannot be exceeded.

Construction by special trade contractors: Contractor will not pay more than 75 percent of the amount paid by the Government for contract performance, excluding the cost of materials, to subcontractors that are not similarly situated entities. Any work that a similarly situated entity further subcontracts will count towards the prime contractor's 75 percent subcontract amount that cannot be exceeded.

Upon the Contracting Officer's request, the Contractor shall submit a report to the Contracting Officer documenting compliance with FAR 52.2l9-l4. If the Contractor is using Similarly Situated Entities, it must be clearly identifiable in the submitted reports. If the required percentage is not being met the Contractor shall also include, with the semiannual report, a plan to meet the required percentage before the contract end date.

The below calculation for FAR 52.219-14 is for example only and not representative of this solicitation or any contract that may be awarded as a result of this solicitation.

1. Total value of contract award = $5,000,000.00

2. Cost of materials = $3,000,000.00

3. Adjusted amount (contract award value less cost of materials): $2,000,000.00 ($5,000,000.00 - $3,000,000.00)

4. 85% of $2,000,000.00 may be paid to non-similarly situated entities ($1,700,000.00)

5. 15% of $2,000,000.00 must be paid to a similarity situated entity ($300,000.00)

What is similarly situated and what does it mean for the prime?

i. 1st tier subcontractor that has the same small business program status of the qualified prime contractor (i.e.

HUBZone prime contractor, any HUBZone subcontractor is similarly situated).

ii. Any 1st tier subcontracts to similarly situated entities can count towards the prime contractor's self-performance requirements.

iii. Example: HUBZone Set-Aside Contract, 1st Tier is a HUBZone Small Business subcontractor. This meets the similarly situated requirement and the work performed by the HUBZone subcontractor will count towards the HUBZone prime contractor's self-performance requirement.

iv. Example: SDVOSB Set Aside Contract, 1st Tier is a WOSB subcontractor only, this does not meet the "similarly situated" requirement and the WOSB subcontractor performance does not count towards the SDVOSB prime contractor's self-performance requirement.

Partnering With Us, https://www.usace.army.mil/Business-With-Us/Partnering/, in all solicitation notices posted at the Governmentwide point of entry for construction contracts anticipated to be awarded to a small business pursuant to FAR Part 19 to be in compliance with FAR 36.211(b).

(D) All technical inquiries and questions relating to this solicitation are to be submitted via bidder inquiry in ProjNet at https://www.projnet.org/project. See special notices to bidder's page entitled "Technical Inquiries and Questions"

(E) Offerors or Bidders shall furnish unit prices for all items listed on the schedule of bid items which require unit prices. If the bidder fails to insert a unit price in the appropriate blank for required items, but does furnish an extended total or an estimated amount for such items, the Government will deem the unit price to be the quotient obtained by dividing the extended estimated amount for that line item by the quantity. IF THE

BIDDER OMITS BOTH THE UNIT PRICE AND THE EXTENDED ESTIMATED AMOUNT FOR ANY ITEM,

THE BID WILL BE DECLARED NONRESPONSIVE.

https://www.usace.army.mil/Business-With-Us/Partnering/ https://www.projnet.org/project

(F) All quantities shown on the BIDDING SCHEDULE are estimated quantities except when the unit of measure is shown as "job" or "each".

(G) If a bid or modification to a bid based on unit price is submitted which provides for a lump sum adjustment to the total estimated cost, the application of the lump sum adjustment to the unit price in the schedule must be stated. If it is not stated, the bidder agrees that the lump sum adjustment shall be applied on a pro rata basis to the unit price in the Bid Schedule.

(H) All extensions of the unit price shown will be subject to verification by the Government. In case of variation between the unit price and the extension, the unit price will be considered to be the bid.

(I) Award will be made, as a whole to the lowest responsive, responsible bidder as may be in the best interest of the Government.

(J) The contractor should be aware of the additional surveying requirements for this contract. See Section 01 00 00.00 09 for more information.

(K) THE NOTICE TO PROCEED (NTP): The successful bidder is advised that performance and payment bonds shall be submitted in accordance with the time frame in block 12B of SF1442. The NTP will be issued immediately after verification of acceptable performance and payment bonds. Within seven (7) calendar days after issuance of the NTP, the Contractor shall initiate a meeting to discuss the submittals process with the Administrative Contracting Officer (ACO), or the Contracting Officer's Representative (COR), or their authorized representative. Physical work cannot start until the Accident Prevention Plan, Contractor Quality Control Plan, and other submittals which may be required, have been submitted and approved and all preliminary meetings called for under the contract, have been conducted. The contract performance duration has been determined as stated in the specifications and includes sufficient time for the preparation, submittal and approval of all pre-work documents and all Pre-Construction conferences required prior to commencement of work on site.

(L) Lack of registration in the WWW.SAM.gov database will make an offeror ineligible for award. See contract clause 52.204-7 entitled, "system for award management".

(M) The SF-1442, Bidding Schedule, and Bidder Representations and Certifications must be accurately completed and returned with your bid, or it may be rejected as nonresponsive. An offeror may also submit, in lieu of the completed FAR Clause 4.203 System for Award Management, certifications with their bid package that their online Representations and Certifications from www.sam.gov. See FAR Clauses 52.204-7 is available.

(N) All work under these specifications shall be performed in accordance with the most recent provisions of EM 385-1-1 "Corps of Engineers Safety and Health Requirements Manual", dated 15-March-2024.

(O) The government reserves the right, as the interests of the government may require, to postpone or delay the date and/or time set for opening bids. Revisions or amendments to the bid opening date and/or time, if any, will be announced by amendment or amendments to this invitation for bids.

GENERAL NOTICES:

1. AUTHORITY & APPROPRIATION INFORMATION PROGRAM DATA

AUTHORITY: Flood Control Acts of 1928, 1936, 1941, 1944, 1946, 1950, 1954, 1962, 1965, 1968, River Basin Monetary Authorization Act of 1971, WRDA 1992, SEC 103, WRDA 2000, Section 508

APPROPRIATION: Consolidated Appropriations Act, 2023/PL 117-328

FUNDING CITATION: Operation and Maintenance, 96 X 3112

2. BID, PERFORMANCE AND PAYMENT BONDS.

A bid guarantee/bond is NOT required for this procurement. Performance and payment bonds with be required after award. See Section 00700, Contract Clauses 52.228-1, BID GUARANTEE and 52.228-15, PERFORMANCE AND PAYMENT BONDS -- CONSTRUCTION

3. AMENDMENTS PRIOR TO DATE SET FOR OPENING BIDS.

The right is reserved, as the interest of the Government may require, to revise or amend the specifications and/or drawings prior to the date set for opening bids. Such revisions or amendments, if any, will be announced by amendment or amendments to this Invitation for Bids. Copies of such amendments as may be issued will be furnished to all prospective bidders. If the revision or amendments are of a nature which require material changes in quantities or prices bid or both, the date set for opening bids may be postponed by such number of days as in the opinion of the District Engineer will enable bidders to revise their bids. In such case, the amendments will include an announcement of the new date for opening bids.

4. BUSINESS INTEGRITY.

Successful offerors as a condition for award of any contract resulting from this Request for Proposal (RFP) may be required to execute a certificate related to Business Integrity.

5. CONDITIONS AFFECTING THE WORK.

Offerors or Bidders should visit the site and take such other steps as may be reasonably necessary to ascertain the nature and location of the work, and the general and local conditions which can affect the work or the cost thereof. Failure to do so will not relieve bidders from responsibility for estimating properly the difficulty or cost of successfully performing the work. The Government will assume no responsibility for any understanding or representations concerning conditions made by any of its officers or agents prior to the execution of the contract, unless included in the Invitation for Bids, the specifications, or related documents.

6. SITE OF THE WORK.

Offerors or Bidders are advised that for purpose of applicability of the Davis-Bacon Act and other contract labor standard provisions, "the site of the work" under the contract to be awarded pursuant to this Invitation may not be limited to the physical place(s) where the construction called for in the contract will remain when work on it has been completed. The "site of the work" may include other adjacent or nearby property used by the Contractor or Subcontractors during such construction. For example, fabrication plants, mobile factories, batch plants, borrow pits, job headquarters, tool yards, etc., will be considered part of the site of the work provided they are dedicated exclusively or nearly so to performance on the contract and are so located in proximity to the actual construction location that it would be reasonable to include them.

7. INFORMATION REGARDING BIDDING MATERIAL, BID GUARANTEE, AND BONDS.

a. Specifications, Bidding Schedule, Pre-award Information/Description of Work/Bid Evaluation, Equipment Schedule, Construction Contract Clauses, and Wage Determination Decisions of the Secretary of Labor, are parts of this Invitation for bids.

b. (1) An offeror (bidder) electing to use individual sureties for either bid guarantees or performance and payment bonds must submit, concurrently with the bonds and required affidavits, a statement of both the business and personal names of the persons and financial institution through whom the bonds or the guarantees are held, together with the address and telephone number of the persons and/or financial institution authorized to commit the surety.

(2) Offerors or bidders should note that some individual sureties have been debarred or suspended from offering themselves or others as sureties to the Government. Offerors or bidders are responsible for ascertaining the current status of their sureties.

(3) Failure to provide the required information or the submission of bid guarantees obtained from debarred or suspended sureties or brokers may cause rejection of the offer (bid).

8. DEFINITIONS

(a) The term "head of the agency" or "Secretary" as used herein means the Secretary of the Army; and the term "his duly authorized representative" means the Chief of Engineers, Department of the Army, or an individual or board designated by him.

(b) "Contracting Officer" means a person with the authority to enter into, administer, and/or terminate contracts and make related determinations and findings. The term includes certain authorized representatives of the Contracting Officer acting within the limits of their authority as delegated by the Contracting Officer.

(c) The agency board of contract appeals having jurisdiction over all appeals from final decisions of the Contracting Officer under the Contract Disputes Act of l978 is the Armed Services Board of Contract Appeals, addressed as follows: Recorder, Armed Services Board of Contract Appeals, Skyline 6, 7th Floor, 5109 Leesburg Pike, Falls Church, Virginia 22041-3208.

(d) "Small business concern" means a concern including its affiliates, that is independently owned and operated, not dominant in the field of operation in which it is bidding on Government contracts, and qualified as a small business under the criteria and size standards in 13 CFR 121.

9. Size Standards for Construction and Special Trades.

(a) Construction. A concern is small if its average annual receipts for its preceding 3 fiscal years did not exceed $45 million.

SPECIAL NOTICES:

1. Proposals shall only be sent Electronically to Amy L. Starks at Amy.L.Starks@usace.army .mil and copy Robert Ellis Screws at Ellis.Sccrews@usace.army.mil. Proposals must be received prior to the exact time set for Proposals Due Time.

mailto:Amy.L.Starks@usace.army mailto:Ellis.Sccrews@usace.army.mil

Offerors must provide full, accurate, and complete information as required by the solicitation and its attachments. The penalty for making false statements in proposals is prescribed in 18 U.

S.C. 1001. (FAR 52.214-4 APR 1984)

2. Proposals for the work described herein will be received until date and time of the proposal due date.

3. Your attention is directed to section 00100-bid schedule/instructions to bidders' clause 52.214-5 entitled "submission of bids". It is the bidder's responsibility to ensure that bids sent by commercial carrier are clearly identified as containing a sealed bid on the outermost envelope. This includes, but is not limited to, bids sent via: Federal Express, Express Mail - U.S. Postal Service, or United Parcel Service.

4. Note the affirmative action requirement of the equal opportunity clause which may apply to the contract resulting from this solicitation.

5. See section 00 80 00.00 09, special contract requirements, clause entitled "commencement, prosecution, and completion of work".

6. See section 01 00 00.00 09, general contract requirements clause, entitled, "payment invoices" which will apply to the contract resulting from this solicitation. The federal acquisition regulation requires that the "remit to" address of the invoice match the "remit to" address on the contract or a proper notice of assignment.

7. In accordance with FAR 42.1102(e), Agencies must prepare past performance evaluations for each construction contract of $900,000 or more, and for each construction contract terminated for default regardless of contract value. Past performance evaluations may also be prepared for construction contracts below $900,000. Past performance evaluations will be prepared by the MVK at least annually and at the time the work under a contract or order is completed and will be entered into the Contractor Performance Assessment Reporting System (CPARS), the Governmentwide evaluation reporting tool for all past performance reports on contracts located at http://www.cpars.gov/

8. Electronic Funds Transfer (EFT)

All vendor direct deposit and Electronic Funds Transfer (EFT) information must be entered/maintained in the System for Award Management (SAM) located at www.SAM.gov. UFC Form 23, previously required for direct deposits/EFT payments by the Vicksburg District (MVK) is obsolete. To receive direct deposits/EFT payments, routing and banking information must be entered and maintained in the SAM. Failure to update /maintain this information in the SAM will result in vendors receiving payments via Treasury checks distributed by U.S. mail. The below links are provided for your information.

How do I update the banking information on my Sam.gov entity registration?

https://www.fsd.gov/gsafsd_sp?id=gsafsd_kb_articles&sys_id=003e5979dbe1259494439f95f39619cd

What is an Electronic Funds Transfer (EFT) indicator and how do I create one?

https://www.fsd.gov/gsafsd_sp?id=gsafsd_kb_articles&sys_id=83629ecadb69e99494439f95f3961958

If you have further questions, please visit the Federal Service Desk (FSD) at www.FSD.gov.

http://www.cpars.gov/ http://www.sam.gov/ https://www.fsd.gov/gsafsd_sp?id=gsafsd_kb_articles&sys_id=003e5979dbe1259494439f95f39619cd https://www.fsd.gov/gsafsd_sp?id=gsafsd_kb_articles&sys_id=83629ecadb69e99494439f95f3961958 http://www.fsd.gov/

9. Proposals will not be accepted, nor shall proposals be withdrawn electronically or by telephone.

Prior to proposal due date, in accordance with federal acquisition regulation part 15.107(d) modification or withdrawal of bids, "Proposals may be withdrawn by written notice at any time before award."

10. All Technical inquiries and questions related to this solicitation shall be submitted via ProjNet.

Technical inquiries and questions relating to this solicitation are to be submitted via bidder inquiry in ProjNet at (https://www.projnet.org). Bidders or Offerors are encouraged to submit questions 5 days prior to bid opening to ensure adequate time is allotted to form an appropriate response and amend the solicitation, if necessary. To submit and review inquiry items, prospective vendors will need to use the bidder inquiry key presented below and follow the instructions listed below the key for access. A prospective vendor who submits a comment /question will receive an acknowledgement of their comment/question via email, followed by an answer to the comment/question after it has been processed by our technical team.

All timely questions and approved answers will be made available through ProjNet.

The solicitation number is: W912EE26RA009

The bidder inquiry key is: Z8H54A-YPCKDV

Specific instructions for ProjNet bid inquiry access:

1. From the ProjNet home page linked above, click on quick add on the upper right side of the screen.

2. Identify the agency. This should be marked as USACE.

3. Key. Enter the bidder inquiry key listed above.

4. Email. Enter the email address you would like to use for communication.

5. Click continue. A page will then open saying that a user account was not found and will ask you to create one using the provided form.

6. Enter your first name, last name, company, city, state, phone, email, secret question, secret answer, and time zone. Make sure to remember your secret question and answer as they will be used from this point on to access the ProjNet system.

7. Click add user. Once this is completed you are now registered within ProjNet and are currently logged into the system.

Specific instructions for future ProjNet bid inquiry access:

1. For future access to ProjNet, you will not be emailed any type of password. You will utilize your secret question and secret answer to log in.

2. From the ProjNet home page linked above, click on quick add on the upper right side of the screen.

3. Identify the agency. This should be marked as USACE.

4. Key. Enter the bidder inquiry key listed above.

5. Email. Enter the email address you used to register previously in ProjNet.

6. Click continue. A page will then open asking you to enter the answer to your secret question.

7. Enter your secret answer and click login. Once this is completed you are now logged into the system.

11. Tax on Foreign Purchases FAR provision 52.229-11 and FAR clause 52.229-12 FAR provision 52.229-11 and FAR clause 52.229-12 are included in this solicitation. This provision and clause concern the imposition of a 2 percent Federal excise tax withholding on any resultant contract award or payment request. This rule applies to Federal Government contracts for goods or services that are awarded to foreign persons - such as foreign contractors. It implements the Department of the Treasury's final regulations published in the Federal Register at 81 FR 55133 on August 18, 2016, under section 5000C https://www.projnet.org/ of the Internal Revenue Code relating to the 2 percent tax on payments made by the U.S. Government to foreign persons pursuant to certain contracts. Pursuant to the FAR 52.229-3 Federal, State, and Local Taxes, taxes imposed under 26 U.S.C. 5000 C may not be included in the contract price or reimbursed.

Exemptions from this excise tax must be claimed by an Offeror when it submits, with its offer, a U.S.

Department of Treasury Internal Revenue Service (IRS) Form W-14, Certificate of Foreign Contracting Party Receiving Federal Procurement Payments, available via the internet at www.irs.gov/W14. If not submitted with the offer, exemptions will not be applied to any resulting contract and the Government will withhold a full 2 percent on each contract payment. Failure to submit an IRS Form W-14 with each payment request will also result in an automatic withholding of 2 percent from the payment request.

When filling out the IRS Form W-14 the following information may be used to complete Part I, Lines 6 and 7.

Line 6 Contract/reference number: [W912EE26RA009]

Line 7 "Name and address of the acquiring agency": [USACE, Vicksburg District, 4155 Clay Street, Vicksburg

MS. 39183]

Any exemption claimed and self-certified is subject to audit by the IRS. Any disputes concerning this tax are adjudicated by the IRS because the Section 5000C tax is a tax matter not a contract issue.

Offerors are encouraged to seek guidance from their own tax professionals for advice concerning the provision, clause, and exclusions exclusion/submission of IRS Form W-14. Additional information is also available at:

Notwithstanding the above, the USACE does not have a means of withholding this excise tax at this time. As a result, contractors are expected to comply with the instructions above and to properly complete and return the W-14 at proposal submission, and with each pay application. Whether the contractor sets the money aside for future payment to the IRS, or makes payment to the IRS, is the contractor's discretion, based on its analysis of the regulations regarding the excise tax. In the event that USACE is able to withhold during contract performance, it will notify the contractor and make such a withholding (including any catch up withholdings); no advance notice is required to the contractor prior to the withholding. Under no circumstances is USACE liable for any tax not paid by the contractor. The contractor is liable for the tax, to the extent required by law, regardless of whether USACE makes a withholding.

FAR 29.204 expressly states that "[a]gencies merely withhold the tax (section 5000C tax) for the Internal Revenue Service (IRS). All substantive issues regarding the underlying section 5000C tax, e.g., the imposition of, and exemption from the tax, are matters under the jurisdiction of the IRS." Therefore, we cannot help you determine how the tax law applies to you. We strongly recommend that you contact the IRS and/or a tax professional should you have any questions of this nature. To be clear, this information does not constitute tax advice or a representation of your tax liability. Furnishing this information does not create liability for the USACE for any Federal, state, or local taxes applicable to the above-referenced contract or any other contract.

For submission requirements and basis of evaluation:

Executed FAR Provision 52.229-11.

Completed IRS Form W-14, Certificate of Foreign Contracting Party Receiving Federal Procurement Payments, if applicable. If not submitted with the offer, exemptions will not be applied to any resulting contract and the Government will withhold a full 2 percent on each payment.

http://www.irs.gov/W14

Veterans Employment Emphasis for U.S. Army Corps of Engineers Contracts:

In addition to complying with the requirements outlined in FAR Part 22.13, Subpart 5122.13, FAR Clause 52.222-35, FAR Clause 52.222-37, DFARS 222.13 and Department of Labor regulations, U.S. Army Corps of Engineers (USACE) contractors and subcontractors at all tiers are encouraged to promote the training and employment of U.S. veterans while performing under a USACE contract. While no set-aside, evaluation preference, or incentive applies to the solicitation or performance under the resultant contract, USACE contractors are encouraged to seek out highly qualified veterans to perform services under this contract.

The following resources are available to assist USACE contractors in their outreach efforts:

- U.S. Department of Labor Veterans' Employment and Training Service (VETS):

https://www.dol.gov/vets/

- Federal Veteran Employment Information: https://www.fedshirevets.gov/

- Veterans Opportunity to Work (VOW) Program: https://www.benefits.va.gov/vow/

- U.S. Army Warrior Transition Command Employment Index:

https://wct.army.mil/modules/employers/index.html

- Hiring Our Heroes: https://www.uschamberfoundation.org/hiring-our-heroes

Army Contract Writing System (ACWS) Transition Information for Contractors.

a. The Department of the Army is in the process of deploying a new solicitation and contract writing software application to Army contracting offices worldwide. Known as the Army Contract Writing System (ACWS), this modern software application will replace most existing Army contract writing systems, including the system used to create and release this Contract.

b. During this transition period, Contractors are hereby advised:

1. The Contracting Office may use any combination of contract writing systems to generate distributable copies of this contract during its period of performance, as well as any subsequent modifications or orders (if applicable). As a result https://www.dol.gov/vets/ https://www.fedshirevets.gov/ https://www.benefits.va.gov/vow/ https://wct.army.mil/modules/employers/index.html https://www.uschamberfoundation.org/hiring-our-heroes

i. Subsequent documents you receive may appear noticeably different than the original award or previous contractual documents from the same Contracting Office.

ii. A change between contract writing systems may cause important information concerning contract terms and conditions to take on different formatting or appear in different parts of later documents issued.

iii. Contractors shall ensure Customer Relationship Management (CRM) systems and personnel interacting with this contract are prepared to identify and respond appropriately to differences between document versions.

2. The Government does not intend to use the shift between contract writing systems to effect any changes to Contract terms and conditions. Therefore:

i. Contractors should view changes to terms or conditions between document versions as system-generated and potentially erroneous unless accompanied by narrative(s) designating such changes as deliberate and desired.

ii. Contractors shall inform the Contracting Officer listed on the first page of the most recent document issued for guidance regarding any suspected or observed inadvertent or system-generated changes (i.e., noticing something missing in a new conformed copy).

iii. The Government will correct any inadvertent or system-generated changes, additions, or omissions discovered by either party, via bilateral modification, at no cost to the Contractor.

iv. The terms and conditions contained in the latest document reflecting deliberate action by the Contracting Officer (i.e., the last conformed copy of the award not affected by the observed issue) will take precedence until the problems are corrected.

3. In the unlikely event award information is corrupted or mutilated during system migration and replacement or re-issuance of this contract is necessary for continued contract administration, the Contracting Officer will:

i. Issue a continuation contract in accordance with DFARS PGI 204.1601(c), carrying over all terms and conditions from the last-known version of this contract to accurately reflect mutual agreement of the parties.

ii. Incorporate the last-known version of this contract to accurately reflect mutual agreement of the parties as an attachment to the replacement or continuation contract for future reference.

iii. Ensure any such reissuance or continuance is properly reported to preserve the integrity of Contractor performance measurement data, if any (i.e., FAPIIS, CPARS).

Commencement, Prosecution, and Completion of Work - Construction (Apr 1984)

The Contractor shall be required to (a) commence work under this contract within 10 calendar days after the date the Contractor receives the notice to proceed, (b) prosecute the work diligently, and (c) complete the entire work ready for use not later than 275.* The time stated for completion shall include final cleanup of the premises.

* The Contracting Officer shall specify either a number of days after the date the contractor receives the notice to proceed, or a calendar date.

(End of condition)

Site Visit (Construction) (Feb 1995)

(a) The conditions, Differing Site Conditions, and Site Investigations and Conditions Affecting the Work, will be included in any contract awarded as a result of this solicitation. Accordingly, offerors or quoters are urged and expected to inspect the site where the work will be performed.

(b) Site visits may be arranged during normal duty hours by contacting:

Name: Greenwood Area Office

Address: 100 Moore Street, Greenwood, MS 38930-4512

Telephone: 662-453-5531

(End of Condition)

*** END OF NARRATIVE 1 ***

Section 00 45 00 - Representations and Certifications

FAR Provisions Incorporated by Full Text

Number Title Effective Date

Alternate Deviation

Variation Effective Date

52.223-4 Recovered Material Certification.

2008-05

Recovered Material Certification (May 2008)

As required by the Resource Conservation and Recovery Act of 1976 (42 U.S.C. 6962(c)(3) (A)(i)), the offeror certifies, by signing this offer, that the percentage of recovered materials content for EPA-designated items to be delivered or used in the performance of the contract will be at least the amount required by the applicable contract specifications or other contractual requirements.

(End of provision)

52.229-12 Tax on Certain Foreign Procurements.

2021-02

Tax on Certain Foreign Procurements-Notice and Representation (Feb 2021)

(a) Definitions. As used in this clause-

Foreign person means any person other than a United States person.

United States person, as defined in 26 U.S.C. 7701(a)(30), means-

(1) A citizen or resident of the United States;

(2) A domestic partnership;

(3) A domestic corporation;

(4) Any estate (other than a foreign estate, within the meaning of 26 U.S.C. 7701(a)(31));

and

(5) Any trust if-

(i) A court within the United States is able to exercise primary supervision over the administration of the trust; and

(ii) One or more United States persons have the authority to control all substantial decisions of the trust.

(b) This clause applies only to foreign persons. It implements 26 U.S.C. 5000C and its implementing regulations at 26 CFR 1.5000C-1 through 1.5000C-7.

(c)

(1) If the Contractor is a foreign person and has only a partial or no exemption to the withholding, the Contractor shall include the Department of the Treasury Internal Revenue Service Form W-14, Certificate of Foreign Contracting Party Receiving Federal Procurement Payments, with each voucher or invoice submitted under this contract throughout the period in which this status is applicable. The excise tax withholding is applied at the payment level, not at the contract level. The Contractor should revise each IRS Form W-14 submission to reflect the exemption (if any) that applies to that particular invoice, such as a different exemption applying. In the absence of a completed IRS Form W-14 accompanying a payment request, the default withholding percentage is 2 percent for the section 5000C withholding for that payment request. Information about IRS Form W-14 and its separate instructions is available via the internet at www.irs.gov/w14.

(2) If the Contractor is a foreign person and has indicated in its offer in the provision 52.229- 11, Tax on Certain Foreign Procurements-Notice and Representation, that it is fully exempt from the withholding, and certified the full exemption on the IRS Form W-14, and if that full exemption no longer applies due to a change in circumstances during the performance of the contract that causes the Contractor to become subject to the withholding for the 2 percent excise tax then the Contractor shall-http://www.irs.gov/w14

(i) Notify the Contracting Officer within 30 days of a change in circumstances that causes the Contractor to be subject to the excise tax withholding under 26 U.S.C. 5000C; and

(ii) Comply with paragraph (c)(1) of this clause.

(d) The Government will withhold a full 2 percent of each payment unless the Contractor claims an exemption. If the Contractor enters a ratio in Line 12 of the IRS Form W-14, the result of Line 11 divided by Line 10, the Government will withhold from each payment an amount equal to 2 percent multiplied by the contract ratio. If the Contractor marks box 9 of the IRS Form W-14 (rather than completes Lines 10 through 12), the Contractor must identify and enter the specific exempt and nonexempt amounts in Line 15 of the IRS Form W- 14; the Government will then withhold 2 percent only from the nonexempt amount. See the IRS Form W-14 and its instructions.

(e) Exemptions from the withholding under this clause are described at 26 CFR 1.5000C-1 (d)(5) through (7). Any exemption claimed and self-certified on the IRS Form W-14 is subject to audit by the IRS. Any disputes regarding the imposition and collection of the 26 U.S.C.

5000C tax are adjudicated by the IRS as the 26 U.S.C. 5000C tax is a tax matter, not a contract issue.

(f) Taxes imposed under 26 U.S.C. 5000C may not be-

(1) Included in the contract price; nor

(2) Reimbursed.

(g) A taxpayer may, for a fee, seek advice from the Internal Revenue Service (IRS) as to the proper tax treatment of a transaction. This is called a private letter ruling. Also, the IRS may publish a revenue ruling, which is an official interpretation by the IRS of the Internal Revenue Code, related statutes, tax treaties, and regulations. A revenue ruling is the conclusion of the IRS on how the law is applied to a specific set of facts. For questions relating to the interpretation of the IRS regulations go to https://www.irs.gov/help/tax-law-questions.

(End of clause)

DFARS Provisions Incorporated by Full Text

Number Title Effective Alternate Variation https://www.irs.gov/help/tax-law-questions

Date Deviation Effective

252.204-7008 Compliance with Safeguarding Covered Defense Information Controls.

2016-10

COMPLIANCE WITH SAFEGUARDING COVERED DEFENSE INFORMATION CONTROLS

(OCT 2016)

(a) Definitions. As used in this provision-

"Controlled technical information," "covered contractor information system," "covered defense information," "cyber incident," "information system," and "technical information" are defined in clause 252.204-7012, Safeguarding Covered Defense Information and Cyber Incident Reporting.

(b) The security requirements required by contract clause 252.204-7012, shall be implemented for all covered defense information on all covered contractor information systems that support the performance of this contract.

(c) For covered contractor information systems that are not part of an information technology service or system operated on behalf of the Government (see 252.204-7012(b)(2)

(1) By submission of this offer, the Offeror represents that it will implement the security requirements specified by National Institute of Standards and Technology (NIST) Special Publication (SP) 800-171 "Protecting Controlled Unclassified Information in Nonfederal Information Systems and Organizations" (see http://dx.doi.org/10.6028/NIST.SP.800-171) that are in effect at the time the solicitation is issued or as authorized by the contracting officer not later than December 31, 2017.

(2)(i) If the Offeror proposes to vary from any of the security requirements specified by NIST SP 800-171 that are in effect at the time the solicitation is issued or as authorized by the Contracting Officer, the Offeror shall submit to the Contracting Officer, for consideration by the DoD Chief Information Officer (CIO), a written explanation of-

(A) Why a particular security requirement is not applicable; or

(B) How an alternative but equally effective, security measure is used to compensate for the inability to satisfy a particular requirement and achieve equivalent protection.

http://dx.doi.org/10.6028/NIST.SP.800-171)

(ii) An authorized representative of the DoD CIO will adjudicate offeror requests to vary from NIST SP 800-171 requirements in writing prior to contract award. Any accepted variance from NIST SP 800-171 shall be incorporated into the resulting contract.

Section 00 72 00 - General Conditions

FAR Clauses Incorporated by Full Text

Number Title Effective

Alternate Deviation

Variation Effective

52.211-12 Liquidated Damages-Construction. 2000-09

Liquidated Damages-Construction (Sept 2000)

(a) If the Contractor fails to complete the work within the time specified in the contract, the Contractor shall pay liquidated damages to the Government in the amount of $1,529.00 [Contracting Officer insert amount] for each calendar day of delay until the work is completed or accepted.

(b) If the Government terminates the Contractor's right to proceed, liquidated damages will continue to accrue until the work is completed. These liquidated damages are in addition to excess costs of repurchase under the Termination clause.

52.228-15 Performance and Payment Bonds- Construction.

2020-06

Performance and Payment Bonds-Construction (Jun 2020)

(a) Definitions. As used in this clause-

Original contract price means the award price of the contract; or, for requirements contracts, the price payable for the estimated total quantity; or, for indefinite-quantity contracts, the price payable for the specified minimum quantity. Original contract price does not include the price of any options, except those options exercised at the time of contract award.

(b) Amount of required bonds. Unless the resulting contract price is valued at or below the threshold specified in Federal Acquisition Regulation 28.102-1(a) on the date of…