About this file

This amendment modifies the solicitation for the FTW360 1+1 Barracks project at Fort Wainwright, Alaska. The Army Corps of Engineers seeks to select a design-build contractor through a two-phase selection process. The amendment extends the proposal due date from May 5 to May 12 at 2:00pm Alaska Standard Time. Offerors may submit a maximum of seven past performance examples each for design work and construction work on similar projects completed within the last six years. For design work, no more than three examples may be provided for any individual design firm.

View the file

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT

Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.

15A. NAME AND TITLE OF SIGNER (Type or print)

30-105-04EXCEPTION TO SF 30

APPROVED BY OIRM 11-84

STANDARD FORM 30 (Rev. 10-83)

Prescribed by GSA

FAR (48 CFR) 53.243

FTW360 1 + 1 Barracks, Ft Wainw right, AK

a. The purpose of this amendment is to extend proposal due date from May 5 to May 12 at 2:00pm AST

b. Please see continuation page for detailed changes.

c. Government POC for this action is Yolanda M Ikner, 907-753-2553

1. CONTRACT ID CODE PAGE OF PAGES

1 2

16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)

16C. DATE SIGNED

BY 21-Apr-2022

16B. UNITED STATES OF AMERICA15C. DATE SIGNED15B. CONTRACTOR/OFFEROR

(Signature of Contracting Officer)(Signature of person authorized to sign)

8. NAME AND ADDRESS OF CONTRACTOR (No., Street, County, State and Zip Code) X W911KB22R0019

X 9B. DATED (SEE ITEM 11)

05-Apr-2022

10B. DATED (SEE ITEM 13)

9A. AMENDMENT OF SOLICITATION NO.

11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS

X The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offer X is extended, is not extended.

Offer must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended by one of the following methods:

(a) By completing Items 8 and 15, and returning 1 copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted;

or (c) By separate letter or telegram which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE

RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN

REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by telegram or letter, provided each telegram or letter makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.

12. ACCOUNTING AND APPROPRIATION DATA (If required)

13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS.

IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.

A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE

CONTRACT ORDER NO. IN ITEM 10A.

B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, appropriation date, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(B).

C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:

D. OTHER (Specify type of modification and authority)

E. IMPORTANT: Contractor is not, is required to sign this document and return copies to the issuing office.

14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)

10A. MOD. OF CONTRACT/ORDER NO.

2. AMENDMENT/MODIFICATION NO. 5. PROJECT NO.(If applicable)

6. ISSUED BY

3. EFFECTIVE DATE

22-Apr-2022

CODE

U.S. ARMY ENGINEER DISTRICT, AK

CEPOA-CT (W911KB)

2204 TALLEY AVENUE

JBER AK 99506-0898

W911KB 7. ADMINISTERED BY (If other than item 6)

4. REQUISITION/PURCHASE REQ. NO.

CODE

See Item 6

FACILITY CODECODE

EMAIL:TEL:

Summary of Changes

FTW360– Amendment #1 (AM#01) 21 April 2022

a. The proposal due date has changed from May 5 to May 12 at 2:00pm AST

b. The following drawings are added:

NONE

c. The following drawings are deleted:

NONE

d. The following revised documents/sections are substituted for the superseded documents/sections:

• Section 00 22 10 Phase 1 of 2 Phase Design-Build Selection Procedures.

Paragraph 5.1.1 AM#01***five (5) Seven (7)***AM#01

e. The following sections are added:

NONE

f. The following sections are deleted:

g. Other:

ALL OTHER TERMS AND CONDITIONS SHALL REMAIN THE SAME

(End of Summary of Changes)

Section 00 22 10 Page 3

Section 00 22 10 W911KB22R0019

FTW360

Location Factor Number Description Relative Importance

Tab D Factor 3 Technical Approach 3rd Most Important Factor (slightly less important than Factors 1 and 2)

4.0 TAB A - STANDARD FORM 1442 AND PROPOSAL DATA SHEET

4.1. Submit the SF 1442, completed and signed by a person authorized by the Offeror. Include the completed proposal data sheet (See Attachment 1, provided at the end of this Section). Also include joint venture agreement or

LLC Certificate of Organization, Articles of Organization and the Operating Agreement, if applicable (see Section

00 21 00, paragraph 1.11).

5.0 TAB B – FACTOR 1 - PAST PERFORMANCE (CONFIDENCE ASSESSMENT)

5.1. SUBMISSION REQUIREMENTS

The prime contractor and designer of record design firms for for civil, architectural, structural, mechanical, electrical, telecommunications, and fire protection design shall each demonstrate recent, relevant experience on similar projects.

Design Past Performance Requirements

Submit no more than seven (7) projects* total for the design firms and consultant, if applicable. Of those seven

(7) – no more than three (3) projects for any individual design firm/consultant. Design firms may list projects of prime contractors they have worked for or projects directly contracted with government, private or commercial customers. Projects submitted must be substantially complete**.

Construction Past Performance Requirements

Submit no more than seven (7) projects* for the prime contractor (whether single entity or joint venture) that are substantially complete**. The offeror shall select the design firm(s). If projects were design-build, so identify them.

5.1.1 The offeror shall submit information for Design and Construction past performance that best demonstrates the offeror’s experience on projects that are similar in size, scope, and complexity to this requirement, as described in this solicitation. Note: To be considered, the project must have been completed by the offeror, i.e., not the offeror’s subcontractor. To be evaluated, each project must have been completed or must be substantially complete** by the offeror within six (6) years of the date that proposals are due.

*A maximum of fourteen (14) projects (7 for Design and 7 for Construction) will be evaluated. If an offeror disregards these instructions and submits more than the stated number of projects, only the first

AM#01*** five (5) Seven (7)***AM#01