REQUEST FOR QUOTATIONS
(THIS IS NOT AN ORDER) 1
PAGE OF PAGES
1. REQUEST NO. 2. DATE ISSUED RATING
W9123722Q0058 24-Feb-2022 5a. ISSUED BY
8. TO: NAME AND ADDRESS, INCLUDING ZIP CODE
SEE SCHEDULE
IMPORTANT: This is a request for information, and quotations furnished are not offers. If you are unable to quote, please so indicate on this form and return it to the address in Block 5a. This request does not commit the Government to pay any costs incurred in the preparation of the submission of this quotation or to contract for supplies or services. Supplies are of domestic origin unless otherwise indicated by quoter. Any representations and/or certifications attached to this
Request for Quotations must be completed by the quoter.
11. SCHEDULE (Include applicable Federal, State, and local taxes)
ITEM NO.
(a)
SUPPLIES/ SERVICES
(b)
QUANTITY
(c)
UNIT
(d)
UNIT PRICE
(e) (f)
SEE SCHEDULE
AMOUNT
% No. %
NOTE: Additional provisions and representations [ ] are [ ] are not attached.
13. NAME AND ADDRESS OF QUOTER (Street, City, County, State, and ZIP Code)
14. SIGNATURE OF PERSON AUTHORIZED TO
SIGN QUOTATION
15. DATE OF
QUOTATION
16. NAME AND TITLE OF SIGNER (Type or print) (Include area code)
TELEPHONE NO.
AUTHORIZED FOR LOCAL REPRODUCTION STANDARD FORM 18 (REV. 6-95)
PREVIOUS EDITION NOT USABLE Prescribed by GSA FAR (48 CFR) 53.215-1(a)
THIS RFQ X[ ] IS [ ] IS NOT A SMALL BUSINESS SET-ASIDE
6. DELIVER BY (Date)
SEE SCHEDULE
AND/OR DMS REG. 1
UNDER BDSA REG. 2
4. CERT. FOR NAT. DEF.3. REQUISITION/PURCHASE
REQUEST NO.
USACE, CONTRACTING DIVISION
KAREN SIMMONS, 502 8TH STREET
HUNTINGTON WV 25701
9. DESTINATION (Consignee and address, including ZIP Code)
7. DELIVERY
[ ]X FOB
DESTINATION
[ ] OTHER
(See Schedule)
09-Mar-2022(Date)
PLEASE FURNISH QUOTATIONS TO THE ISSUING OFFICE IN BLOCK 5a ON OR BEFORE CLOSE OF BUSINESS:10.
304-399-5182KAREN L SIMMONS
(Name and Telephone no.) (No collect calls)5b. FOR INFORMATION CALL:
d. CALENDAR DAYSc. 30 CALENDAR DAYSb. 20 CALENDAR DAYS12. DISCOUNT FOR PROMPT PAYMENT a. 10 CALENDAR DAYS
W9123722Q0058
Section B - Supplies or Services and Prices
INSTRUCTION TO OFFERORS
SITE VISITS ARE HIGHLY RECOMMENDED PRIOR TO PROVIDING A QUOTE. SEE CLAUSE
52.236-27 FOR ADDITIONAL INFORMATION.
* PLEASE DIRECT ALL QUESTIONS TO THOMAS HARTMAN AT (304) 399-5182 or Karen.l.Simmons@usace.army.mil. ANY INFORMATION RECEIVED AT THE
SITE VISIT WHICH CONFLICTS WITH THIS SOLICITATION SHOULD BE BROUGHT TO THE
ATTENTION OF MR. HARTMAN. THE SOLICITATION AND RESULTING CONTRACT SHALL BE THE
GOVERNING DOCUMENT IN ALL CASES.
**QUOTES CAN ONLY BE E-MAILED TO Karen.L.Simmons@usace.army.mil by the date reference on page 1 of the SF18.
Per FAR 36.204 the estimated price range for this project is between $25,000.00 and $100,000.00.
NOTE: Award will be made to the lowest price offeror who meets the technical requirements of the solicitation and is deemed responsible by the contracting officer.
The intent is to award without discussions.
NOTE: this procurement is 100% Set-Aside for Small Business. For more information see FAR Clause 52.219-6 (Dev).
QUOTATION INSTRUCTIONS (Provide the following with your quote):
Company Name and Address: ______________________________________________ Phone Number:______________________________Fax Number:___________________ Email Address: ____________________________________________________________ Business Size (select all that apply):
Large Business _________ Small Business _________ HUBZONE Business______ 8A__________ Women-Owned ______ Service-Disabled Veteran Owned ________
If subcontractor will used for this work, please provide company name and credentials/qualifications:
IMPORTANT NOTICE: Effective September 26, 2018 and in accordance with FAR Clause 52.204-7, “an Offeror is required to be registered in SAM when submitting an offer or quotation, and shall continue to be registered until time of award, during performance, and through final payment of any contract, basic agreement, basic ordering agreement, or blanket purchasing agreement resulting from this solicitation.”
Vendors are highly encouraged to check their registration status and plan accordingly prior to submitting an offer.
Please note, as of April 2018, GSA's System for Award Management (SAM) system is requiring new registrations and renewals of existing registrations to submit an original signed notarized letter identifying the authorized Entity Administrator. Vendors are encouraged to check their entity's status in SAM.gov and plan accordingly. If the prospective contractor is not registered in the SAM database, the Contracting Officer will follow the procedures at FAR 4.1103. Contact the supporting Federal Service Desk at www.fsd.gov, or by telephone at 866- 606-8220 (toll free) or 334-206-7828 (internationally) Monday through Friday from 8 a.m. to 8 p.m. (EDT), for FREE assistance.
Contractor is registered with SAM: Yes _____ No (/see FAR 52.204-7)
Provide business Unique Entity Identifier number: ________________________________________ (phone 800-333-0505 for Unique Entity Identifier number).
Provide business CAGE code: _____________________________________________________ Provide Tax Identification Number: _________________________________________________
All work under this contract shall be in performance with all local, state, and federal laws, regulations, and codes.
Contractors are not required to submit an Accident Prevention Plan (APP) with their quote. The successful offeror will be required to submit this document upon award. The APP must be accepted by the Government Designated Authority prior to the preconstruction conference. The contractor that receives this award will have 10 calendar days to provide an Accident Prevention Plan (APP). If this deadline is not met, the contractor will be given a cure notice stating that they will have 10 calendar days to submit an APP, otherwise the contract may be terminated for default.
Only the awarded contractor shall provide a copy of their insurance certificate required by State and Local Governments that have been acquired for the time period covered under this contract to the Contracting Officer within 10 business days after award. No further insurance requirements will be imposed by the Corps of Engineers for this contract.
Note: Please ensure that FAR Clause 52.204-24 is completed and returned with your quote.
Per FAR 52.211‐6 ‐ Brand Name or Equal: If quoting an or equal for LUDOWICI Ludoshake, interlocking tile and ridge cap, identify the name and manufacturer of the or equal below. Contractor is responsible for furnishing descriptive literature demonstrating the system identified below meets or exceeds the requirements specified in the solicitation.
Brand Name or Equal-Quoting On: _______________________________________
Manufactured By: ________________________________________
ITEM NO SUPPLIES/SERVICES QUANTITY UNIT UNIT PRICE AMOUNT
0001 Job Replace Roof at ATI Gatehouse.
FFP
Contractor shall provide all necessary labor, equipment, and materials to Atwood Gate House Roof Replacement located at Atwood Dam, Mineral City, OH in accordance with the attached Statement of Work FOB: Destination
PSC CD: Z1KA
NET AMT
PRICE BREAKOUT SCHEDULE
Description of Requirement Qty/Unit of Measure Extended Price
A Reimbursement of actual cost of payment bond for quotes in excess of $35,000.00
JOB $__________
B Labor required for Atwood Dam Gatehouse Roof Replacement, Mineral City, OH, in accordance with attached scope of work.
C Supplies, materials, and equipment required for Atwood Dam Gatehouse Roof Replacement, Mineral City, OH, in accordance with attached scope of work.
Section C - Descriptions and Specifications
STATEMENT OF WORK
SCOPE OF WORK
ATWOOD DAM
Gatehouse Roof Tile Removal/ Shingle Replacement & Chimney Brick work/Tuck point
CONDITIONS:
Contractor shall follow all conditions and material requirements in the contract.
DESIGNATED AREA
The area of work is the Dam Gatehouse roof and surrounding area.
WORK AREA ACCESS
Access to roof will require a crane capable of 170 ft. boom extension, with safe lifting capabilities for personnel and dumpster hopper for tile/brick removal. Hoisting personnel is considered a CRITICAL LIFT per EM 385-1-1 and requires a Certificate of Compliance, Written & Approved Standard Lift plan and Critical Lift plan.
Gatehouse roof is only accessible utilizing a crane and operator certified for lifting/hoisting personnel, has all required equipment for Personnel Fall Arrest systems and Independent Secondary retrieval system IAW EM 385-1-1 and OSHA requirements.
ROOF REPLACEMENT
All work shall be completed by competent roofers, in strict accordance with the plans and specifications in a thorough and workmanlike manner. Contractor shall ensure all equipment used meets or exceeds requirements for lifting personnel IAW U.S. Army Corps of Engineers Safety Manual EM 385-1-1, OSHA standards and Ohio b u i l d i n g codes. All entrances shall be p ro tec te d f rom o ve r he ad fa l l haz a rd s in such a way so as to permit safe foot traffic into the building at all times. Owner agrees to indemnify and hold harmless the Contractor against any claims or damages while Owner's agents or representatives are examining, climbing, or using any of the Contractor 's scaffolding or equipment. Contractor shall carefully remove all existing roofing materials down to exposi ng the roof decking (concrete panels). The removed materials shall be loaded directly into a disposal container and shall be removed from Government property. Contractor shall inspect exiting chimney brickwork, remove all cracked or broken bricks, and replace with new bricks to match existing structure exterior, perform tuckpoint to seal all mortar cracks. Contractor shall cover the entire roof designated area with ¾” thick, treated for exterior exposure, plywood. The plywood shall extend over all existing stainless-steel flashing. The Contractor shall cover the entire designated area with one (1) layer of ice and water self-adhering roofing underlayment membrane, double lapped at peak and ridges, secured with large headed nails or compatible concrete screws.
Membrane meet the following specifications:
Color: Gray-black Thickness Membrane: 40 mil (1.02mm) Tensile Strength, membrane: 250 psi (1720 kN/m2) Elongation, membrane: 250% Low Temperature flexibility: Unaffected @ -20 degrees Fahrenheit (-29 C) Adhesion to plywood: 3.0 lbs/in width (525N/M) Permeance (max): 0.05 Perms (2.9 ng/m2s PA Material weight installed (max) 0.3 lb/ft2 (1.3 kg/m2)
Meets or exceeds the following test methods ASTM D3767, ASTM D412, ASTM1970, ASTMD903,ASTM E96, ASTM D461.
No more roofing shall be removed than can be adequately covered at the end of each working day. This membrane shall be approved by the Project Manager prior to application.
New i nterlocking LUDOWICI Ludoslate or equal clay tiles are to be used on roof.
To be considered equal it must be:
A clay tile conforming to ASTM C-1167 specifications A minimum Grade 1 tile with water absorption less than 2% A minimum 75-year warranty against color fading and manufacturing defects) Slate Red in color Interlocking tile and ridge cap shall be installed in strict accordance with the manufacturer's specifications by experienced workmen.
This product is specified because it has to be in compliance with the Historic Preservation Office as this was the original material on the roof at construction of structure. Shop drawings showing all details and color options shall be submitted to the Government Representative prior to installation.
All areas of the roof requiring sealant for a proper installation shall be filled with a one- part urethane sealant which meets or exceeds the requirements of the following specifications:
ASTM C920 Type S, Grade NS, Class 50, Use NT, T, M, A, O, I U.S. Federal Specification TT-S-00230C, Class A, Type II
CAN/CGSB-19,13-M87
International Code Council (ICC) Section R703.8 Flashing AAMA 714-15 Specification for Liquid-Applied Flashing NFPA 285 Listed Component
All roofing material shall be installed in strict accordance with the manufacturer's specifications by experienced workmen. Shop drawings showing all details and color options shall be submitted to the Project Manager prior to installation. Contractor shall install new stainless steel step flashing, counter flashing, base flashing and drip edge. All flashi ngs shall be installed as recommended by the shingle manufacturer and in regard to good commercial practices.
Contractor shall install two new open-ended gutters, one above the south entrance door (bridge) and one above the north entrance door (stairs). Locations are shown on the attached sketch; more precise locations will be discussed with the Owner’s representative during installation. The gutters shall be 7’ and 16’ in length and constructed of 16-gauge minimum thickness stainless steel. The gutters shall be 6” x 6” x 6” and shall be secured with stainless steel anchors at 18” max spacing. A 2x6 treated wood spacer shall be installed behind the gutters as needed. See attached exhibits.
Care shall be taken so that no roofing material (i.e. nails, felt, shingles, paper, plastic etc.) fall into the lake. Work area shall be clean of excess material at the end of each day. Contractor shall wear Personal Protective Equipment appropriate for the job.
Special Considerations
1. Work shall be performed Monday – Friday 7:30 am thru 4:00 pm, excluding Federal government holidays.
2. Care shall be taken to control public access utilizing barricades and signage during the work and in the evenings, until work is completed.
3. The Contractor shall be held responsible for any and all damages attributable to the actions of the Contractor or its subcontractors outside the limits of construction, shown on the drawings or designated by the Government representative.
Contractor shall furnish all personnel, equipment, transportation, disposal, supplies and materials to perform the work. No government equipment or supplies shall be used for this project. The Contractor shall provide Personal Protection Equipment (PPE) to include fall protection equipment, steel-toed safety boots, hard hat, safety glasses or goggles, hearing protection, sleeved shirts, long pants, gloves, sunscreen and other applicable PPE specified in EM 385-1-1 and Appendix A).
Equipment, Material, and Supply Inspections: All materials shall be inspected upon delivery and or prior to use by government personnel. Materials shall be of high quality, commercial grade and meet or exceed industry standards or otherwise specified by COR and this contract.
Contractor Safety Requirements:
A. General. Contractor shall comply with all Federal, State and Local safety requirements including those specified by the Occupational Safety and Health Act (OSHA) in 29 CRF 1910 General Industry Standard, 1926 Construction Standard and the U.S. Army Corps of Engineers Safety & Health Requirements Manual EM 385-1-1 as currently revised at date of solicitation. Where a conflict exists between safety standards/requirements the contractor shall comply with the more stringent requirement. If the Contractor fails or refuses to promptly comply with safety requirements as specified herein, any project employee may stop all or part of the work until satisfactory corrective action has been taken. No part of the time lost due to any such work stoppage shall be made subject to any claims for extension of time or for excess costs or damages sustained by the Contractor. Also, the Contractor will not be paid for work not performed as a result of the stop order.
B. Contractor Accident Prevention Plan (APP). The Contractor shall prepare a site-specific Accident Prevention Plan as outlined in EM 385-1-1, Appendix A beginning with subparagraph 3.k on page A-10. Contractor must address each element/sub-element in the order they appear in the outline. Any element the contractor feels is not applicable to work under this contract must be listed and a brief explanation provided. Plan must be accepted by the Contracting Officer prior to commencement of any work. Contractors are encouraged to contact the USACE Safety & Occupational Health Office for questions or information regarding the development of contract Accident Prevention Plans. Office hours are Monday-Friday 8:30 a.m. - 4 p.m. at (304)399-5039/5032/5326.
The web address for EM 385-1-1 is:
http://www.publications.usace.army.mil/Portals/76/Publications/EngineerManuals/EM_385-1-1.pdf
C. Contractor Risk Management Process. Contractor may use Job Safety analyses (JSAs), Job Hazard Analyses (JHAs) or Activity Hazard Analysis (AHA) for the purpose of risk assessment. Before beginning each work activity Contractor performing that work activity shall prepare an initial assessment (AHA/JSA/JHA) listing each job step, anticipated hazards, site conditions, equipment, materials, personnel and control measures to be implemented. A Risk Assessment Code (RAC) shall be assigned to each step assessing the level of risk remaining after implementation of controls. Once this process is complete a RAC will be assigned to the activity as a whole (cannot be lower than the highest step RAC). Residual risk must be communicated to the proper authority for acceptance in order to proceed. It is the Contractor's responsibility to prepare the AHA/JSA/JHA. Analysis with RAC shall be accepted by the GDA and discussed with al engaged in the activity including Contractor, subcontractor(s), and on-site government representative prior to commencement of work. Names of Competent Person(s) and Qualified Person(s) required for a particular activity (e.g., excavation, scaffolding, fall protection, or other activities specified by OSHA and/or EM 385-1-1) shall be identified and included in the AHA/JSA/JHA and proof of their competency/qualification.
NOTES:
Work crews of two or more must have two people holding current qualifications in First Aid and CPR from the American Red Cross, American Heart Association or a licensed physician. Training must include a hands-on element and the contractor must maintain appropriate First Aid kit on site. Single individuals working alone must have current certification in First Aid as a minimum.
Contractor shall employee a minimum of one Competent Person at each worksite to function as the Site Safety and Health Officer (SSHO). The SSHO as a minimum must have completed the 30-hour OSHA Construction or General Industry Safety class or it’s equivalent as specified in EM 385-1-1 Section 01.A.17.b and have a minimum of 5 years safety experience relative to the work being completed. The SSHO must be on-site at all times work is being performed. (Note: SSHO qualification requirements may be waived at the discretion of the USACE District Safety & Occupational Health Office for extremely low risk operations.)
Crane operators, riggers and signal persons shall be trained, licensed and meet the physical and drug testing requirements specified in EM 385-1-1 Section 16.
All electrical work must be completed by a Qualified Person with verifiable credentials as specified in EM 385-1-1, Section 11.A.01.c. Electrical work will require contractor to submit a Control of Hazardous Energy Plan (LOTO) in accordance with EM 385-1-1, Section 12.
D. Accident/Mishap Reporting: The Contractor shall report all recordable mishaps to the GDA within 24-hours in accordance with EM 385-1-1 Section 01.D. Accidents shall be investigated to determine causal factors and corrective actions shall be implemented. Accidents resulting in: days away injuries, days away illnesses, restricted/transfer injuries, property damage of $5,000.00 or more shall be investigated and reported to the GDA using the USACE Accident Investigation Report Form ENG 3394 within 24 hours of the occurrence.
(1) Immediate notification to the GDA is required for all serious accidents:
a. Fatal Injury/illness;
b. Permanent totally disabling injury/illness;
c. Permanent partial disabling injury/illness;
d. One (1) or more persons hospitalized as inpatients as a result of a single occurrence;
e. $500,000 or greater accidental property damage;
f. Three (3) or more individuals become ill or have a medical condition suspected to be related to a site condition, or a hazardous or toxic agent on the site;
g. USACE aircraft destroyed or missing;
The Contractor shall maintain an OSHA Log of Work Related Injuries and Illnesses, OSHA Form 300 and comply with all accident reporting and recordkeeping requirements specified in 29 CFR 1904.39.
(2) In addition to the above, any mishap occurring in any of the following high hazard areas shall be reported immediately to the GDA, investigated and corrective actions implemented.
a. Electrical (includes Arc Flash, electrical shock, etc.);
b. Uncontrolled Release of Hazardous Energy (includes electrical and non-electrical);
c. Load Handling Equipment (LHE) or Rigging;
d. Fall-from-Height (any level or other than same surface);
e. Underwater Diving
Site Visit Offerors are encouraged to make a site visit by contacting:
Rick Houze Project Supervisor U. S. Army, Corps of Engineers, Atwood Lake Dam 3434 State Route 212 NE Mineral City, Ohio 44656
(330) 343-5611
Contractor Submittals The successful bidder shall provide as a minimum the following documentation. All contractor submittals must be reviewed and accepted by the contracting officer or government designated authority prior to commencement of any work.
A. Accident Prevention Plan
B. Activity Hazard Analysis
C. Shop drawings showing all details and color options shall be submitted to the Project Manager prior to installation.
D. Invoice as stated on the contract award.
E. Man hour report to project office at completion of work.
DAMAGE REPORTS. All instances where Government materials, supplies, property, and/or equipment are damaged shall be reported immediately to the Project Supervisor at Atwood Dam . When the damage is caused by contract employees, a written report of the incident and extent of such damage shall be submitted to the Project Supervisor, Within 2 work days (less weekends and holidays) of occurrence. For property damage Accidents of $2,000 or more, the Contractor will complete and submit to the Resource Manager a copy of ENG 3394.
CONTRACT EMPLOYEES' CONDUCT AND COMPETENCY.
Employees shall conduct themselves in a proper manner at all times. Since the majority of work shall be performed in the presence of the general public, the conduct of all Employees are critical and will be closely monitored. Use of controlled substances or Consumption of beer or alcoholic beverages by contract employees is strictly prohibited.
The contractor may be required to immediately remove from the work site any employee Of the Contractor who is incompetent or who endangers persons or property or whose Physical or mental condition is such that it would impair the employee's ability to Satisfactorily perform the work.
CONTRACTOR INVOICE. Contractor shall submit their invoice to:
Facility Manager U.S. Army Corps of Engineers Atwood Lake Dam
3434 State 212 NE
330-343-0048
WORKING HOURS. Normal working hours are Monday through Friday, 7:30 a.m. to 4:00 p.m. Work inside Government buildings or other secured areas shall be performed During the above referenced work hours. Eleven Federal holidays observed are as follows:
New Year's Day (January 1st) Martin Luther King Day (3 rd Monday in January) President's Day (3 rd Monday in February) Memorial Day (Last Monday in May) Juneteenth (June 19th) Independence Day (July 4th) Labor Day (1st Monday in September) Columbus Day (2nd Monday in October) Veteran's Day (November 11th) Thanksgiving Day (4th Thursday in November) Christmas Day (December 25th)
When one of the above designated holidays falls on a Sunday, the following Monday is observed as a legal holiday.
When a legal holiday falls on a Saturday, the preceding Friday is observed as a holiday.
Work that interferes with other ongoing functions at the project shall be scheduled around Normal working hours.
Work shall be scheduled around the above listed Federal holidays unless approved in advance.
Work shall be performed during daylight hours and days to be worked will be at the discretion of the Project Supervisor.
DEFICIENCIES. If the Contractor fails to perform, or if performance in any area is judged unsatisfactory, the Government will take corrective action. If any of the work does not conform to contract requirements, the Government may require the Contractor to perform the services again in conformity with contract requirements, at no cost to the Government. When the defect in services cannot be corrected by re-performance, or Cannot be corrected in the specified time frame, the Contractor is required to respond To a Contract Discrepancy Report and deductions will be determined in accordance with Contract Clause entitled "Terms and Conditions-Simplified Acquisitions (Other than Commercial Items), paragraph (d)."
PRE-WORK CONFERENCE. The Contractor shall attend a pre-work conference, prior to the initiation of work under this contract. The Contractor's Accident Prevention Plan and all contractor submittals must be approved prior to this meeting.
SECURITT REQUIREMENTS. All Contractors and subcontractor employee(s) working on this contract who require access in and/or around any Huntington District facilities shall receive authorization to be on site at these facilities based upon a favorable background investigation in accordance with “Homeland Security Presidential Directive 12: Policy for a Common Identification Standard for Federal Employees and Contractors” (HSPD 12).
The Huntington District Security Management Office shall submit contractor(s) personal information to complete the basic background investigation in order to make a recommendation to the Contracting Office of an employee’s suitability for work on Government property. The Procuring Contracting Officer (PCO) has the right to deny any contractor or subcontractor employee from working on the contract based upon the results of the background investigation provided by the Huntington District Security Management Office. The Government, Contractor, and subcontractors shall not permit any employee(s) access to drawings, blueprints, records, photos, sites, or projects until the Huntington District Security Management Office has completed an Operations Security (OPSEC) review of such items and determined they can be released.
FOR ALL CONTRACTS 1-YEAR AND SUBSEQUENT OPTION YEARS:
Contractors shall submit a complete investigation packet for each contractor and subcontractor employee to the Huntington District Security Management office within 10 working days after award of any contract, or prior to the individual being permitted unescorted access in or on District facilities.
The Contractor must also provide the following: (1) Name of the Contract Specialist with whom he/she is working,
(2) Project Name, (3) Contract Number (4) Task Order Number when applicable, and (5) Security Information sheet on each employee working on site must be submitted directly to the Huntington District Security Office.
The Contractor must provide a full legal name, complete SSN#, Date of Birth, Place of Birth (City and State) and Driver’s license number if available. It is the Contractor’s responsibility to ensure the above information is accurate and legible, otherwise delays may occur.
Contractors shall have background checks completed for their employees annually in the case of Contracts with option periods. For instance, if the employee was cleared in May of 2018, they shall be cleared again in May of 2019. It is the Contractor’s responsibility to ensure that each employee’s security is up to date. Failure to comply may lead to possible removal from the project/jobsite.
The Contractor must ensure if new employees are brought in to work on an existing Contract with the U.S. Army Corps of Engineers (USACE), they must process the employee through the Huntington District USACE Security Management Office for background purposes.
FOR CONTRACTORS REQUIRING DOD COMMON ACCESS CARDS (CAC)
The documents listed below are required:
SF 85, Questionnaire for Non-Sensitive Positions (see http://www.opm.gov/forms/ to print form). FD 258, Contractor Fingerprint Card (one card for digital prints, two for ink prints) (NOTE: a trained/qualified individual must take prints, ORI block on the FD 258 must be USOPM000Z) (Contractor Fingerprint Cards (FD-258) may be obtained by Contracting Division by contacting the Huntington District Security Management Office).
Contractor shall report any changes in personnel, or at any time conditions change at least 5 working days prior to individual(s) need to have access to the site. The Contractor shall provide the same information as listed above for all new employees.
Following submission of paperwork, the Huntington District Security Management Office will conduct an initial criminal check based upon the information provided. If there are no issues, the Huntington District Security Management Office will make recommendations to the PCO or their Designated Representative. The Huntington District Security Management Office cannot give approval due to unfavorable report(s). The Huntington District Security Management Office shall coordinate with Office of Counsel and will jointly make recommendations to the PCO and/or the Designated Representative should a background investigation come back with derogatory information. The PCO will make the determination whether to allow the Contractor personnel to work on the site based on Security and Office of Counsel recommendations, and the PCO will advise the Contractor of the decision.
FOREIGN NATIONALS
The Contractor shall provide the package listed above, as well as additional materials noted below for all Foreign Nationals. The Contractor is to expect additional time in the approval process for all Foreign Nationals due to the level of review and elevation of the review to Headquarters staff to complete. All Foreign Nationals must comply with the following paragraph:
In accordance with Engineering Regulation 380-1-18, “Technology Transfer, Disclosure of Information and Contacts with Foreign Representatives” dated 1 August 1996, Section 4, all foreign nationals who work on Corps of Engineers’ contracts shall be approved by the Headquarters US Army Corps of Engineers (HQ USACE) Foreign Disclosure Officer before beginning work on this contract; this regulation includes subcontractor employees. The Contractor shall submit to the Security Management Office, the names of all foreign nationals proposed for performance under this contract, along with documentation to verify legal admittance into the United States. Such documentation shall include at least one of the following: a U.S. passport, Certificate of U.S. Citizenship (INS Form N-560 or N-561), Certificate of Naturalization (INS Form N-550 or N-570), Alien Registration Card with photograph (INS Form I-151 or I-551), Employment Authorization Card (INS Form I-688A), etc.
In order to assure forms are properly completed, and to minimize time delays, the Contractor is encouraged to work closely with the Huntington District Security Management Office. The Government will return for correction incomplete forms, illegible forms, etc. which will delay the contractor / subcontractor from beginning work.
Security requirements are subject to change in accordance with HSPD-12, Office of Personnel Management, regulation or policy changes, etc. The Government shall add any changes to security requirements by modification to the contract.
The Contractor shall contact the Huntington District Security Management Office by phone, letter, or email at the following numbers/addresses:
CELRH-SM
502 Eighth Street Huntington, WV 25701
Stephen R. Curry, phone (304) 399-5695; email stephen.r.curry@usace.army.mil Matthew D. Green, phone (304) 399-5294; email matthew.d.green@usace.army.mil Scott E. Grandon, phone (304) 399-5661; email scott.e.grandon@usace.army.mil
AT/OPSEC REQUIREMENTS
2. Access and General Protection/Security Policy and Procedures. All contractor and all associated sub-contractors employees shall comply with applicable installation, facility and area commander installation/facility access and local security policies and procedures (provided by government representative). The contractor shall also provide all information required for background checks to meet installation/facility access requirements to be accomplished by installation Provost Marshal Office, Director of Emergency Services or Security Office. Contractor workforce must comply with all personal identity verification requirements (FAR clause 52.204-9, Personal Identity Verification of Contractor Personnel) as directed by DOD, HQDA and/or local policy. In addition to the changes otherwise authorized by the changes clause of this contract, should the Force Protection Condition (FPCON) at any installation or facility change, the Government may require changes in contractor security matters or processes.
4. Suspicious Activity Reporting Training (e.g. iWATCH, CorpsWatch, or See Something, Say Something).
The contractor and all associated sub-contractors shall receive a brief/training (provided by the RA) on the local suspicious activity reporting program. This locally developed training will be used to inform employees of the types of behavior to watch for and instruct employees to report suspicious activity to the project manager, security representative or law enforcement entity. This training shall be completed within 30 calendar days of contract award and within 30 calendar days of new employees commencing performance with the results reported to the COR NLT 5 calendar days after the completion of the training.
15. Pre-screen candidates using E-Verify Program. The Contractor must pre-screen Candidates using the E-verify Program (http://www.uscis.gov/e-verify) website to meet the established employment eligibility requirements. The Vendor must ensure that the Candidate has two valid forms of Government issued identification prior to enrollment to ensure the correct information is entered into the E-verify system. An initial list of verified/eligible Candidates must be provided to the COR no later than 3 business days after the initial contract award." *When contracts are with individuals, the individuals will be required to complete a Form I-9, Employment Eligibility Verification, with the designated Government representative. This Form will be provided to the Contracting Officer and shall become part of the official contract file.
APPENDIX A
MINIMUM BASIC OUTLINE FOR ACCIDENT PREVENTION PLANS
An Accident Prevention Plan (APP) is a safety and health policy and program document. The following areas are typically addressed in an APP, but an APP shall be job-specific and shall also address any unusual or unique aspects of the project or activity for which it is written.
The APP shall interface with the employer’s overall safety and health program, and a copy shall be available on the work site. Any portions of the overall safety and health program that are referenced in the APP shall be included as appropriate. ANSI/ASSE A10.38 should be referenced for Programmatic Issues.
> For LIMITED-SCOPE SERVICE, SUPPLY AND R&D CONTRACTS, for example, mowing (only), park attendant, rest room cleaning, the Contracting Officer and SOHO may allow an ABBREVIATED APP (customized APP requirements and waive the more stringent elements of this section). > See 01.A.11 and Appendix a, paragraph 11.
1. SIGNATURE SHEET. Title, signature, and phone number of the following:
a. Plan preparer (Qualified Person, Competent Person, such as corporate safety staff person, QC);
b. Plan must be approved, by company/corporate officers authorized to obligate the company;
c. Plan concurrence (e.g., Chief of Operations, Corporate Chief of Safety, Corporate Industrial Hygienist, project manager or superintendent, project safety professional, project QC). Provide concurrence of other applicable corporate and project personnel (Contractor).
2. BACKGROUND INFORMATION. List the following:
a. Contractor;
b. Contract number;
c. Project name;
d. Brief project description, description of work to be performed, and location; phases of work anticipated (these will require an AHA).
3. STATEMENT OF SAFETY AND HEALTH POLICY. Provide a copy of current corporate/company Safety and Health Policy Statement, detailing commitment to providing a safe and healthful workplace for all employees.
The Contractor’s written safety program goals, objectives, and accident experience goals for this contract should be provided.
4. RESPONSIBILITIES AND LINES OF AUTHORITIES. Provide the following:
a. A statement of the employer’s ultimate responsibility for the implementation of his SOH program;
b. Identification and accountability of personnel responsible for safety at both corporate and project level.
Contracts specifically requiring safety or industrial hygiene personnel shall include a copy of their resumes.
Qualifications shall include the OSHA 30-hour course or equivalent course areas as listed here:
(1) OSH Act/General Duty Clause;
(2) 29 CFR 1904, Recordkeeping;
(3) Subpart C: General Safety and Health Provisions, Competent Person;
(4) Subpart D: Occupational Health and Environmental Controls, Citations and Safety Programs;
(5) Subpart E: PPE, types and requirements for use;
(6) Subpart F: understanding fire protection in the workplace;
(7) Subpart K: Electrical;
(8 Subpart M: Fall Protection;
(9) Rigging, welding and cutting, scaffolding, excavations, concrete and masonry, demolition; health hazards in construction, materials handling, storage and disposal, hand and power tools, motor vehicles, mechanized equipment, marine operations, steel erection, stairways and ladders, confined spaces or any others that are applicable to the work being performed.
c. The names of Competent and/or Qualified Person(s) and proof of competency/qualification to meet specific OSHA Competent/Qualified Person(s) requirements must be attached. The District SOHO will review the qualifications for acceptance;
d. Requirements that no work shall be performed unless a designated competent person are present on the job site;
e. Requirements for pre-task safety and health analysis;
f. Lines of authority;
g. Policies and procedures regarding noncompliance with safety requirements (to include disciplinary actions for violation of safety requirements) should be identified;
h. Provide written company procedures for holding managers and supervisors accountable for safety.
5. SUBCONTRACTORS AND SUPPLIERS. If applicable, provide procedures for coordinating SOH activities with other employers on the job site:
a. Identification of subcontractors and suppliers (if known);
b. Safety responsibilities of subcontractors and suppliers.
6. TRAINING.
a. Requirements for new hire SOH orientation training at the time of initial hire of each new employee.
b. Requirements for mandatory training and certifications that are applicable to this project (e.g., explosive actuated tools, confined space entry, crane operator, diver, vehicle operator, HAZWOPER training and certification, PPE) and any requirements for periodic retraining/recertification.
c. Procedures for periodic safety and health training for supervisors and employees.
d. Requirements for emergency response training. > See paragraph 9.b. below for a list of requirements that may require emergency response training.
7. SAFETY AND HEALTH INSPECTIONS.
a. Specific assignment of responsibilities for a minimum daily job site safety and health inspection during periods of work activity: Who will conduct (e.g., SSHO, PM, safety professional, QC, supervisors, employees – depends on level of technical proficiency needed to perform said inspections), proof of inspector’s training/qualifications, when inspections will be conducted, procedures for documentation, deficiency tracking system, and follow-up procedures;
b. Any external inspections/certifications that may be required (e.g., USCG).
8. ACCIDENT REPORTING. The Contractor shall identify person(s) responsible to provide the following:
a. Exposure data (man-hours worked);
b. Accident investigations, reports, and logs: Report all accidents as soon as possible but not more than 24 hours afterwards to the Contracting Officer/Representative (CO/COR). The contractor shall thoroughly investigate the accident and submit the findings of the investigation along with appropriate corrective actions to the CO/COR in the prescribed format as soon as possible but no later than five (5) working days following the accident. Implement corrective actions as soon as reasonably possible;
c. The following require immediate accident notification:
(1) A fatal injury;
(2) A permanent total disability;
(3) A permanent partial disability;
(4) The hospitalization of three or more people resulting from a single occurrence;
(5) Property damage of $200,000 or more.
9. PLANS (PROGRAMS, PROCEDURES) REQUIRED BY THE SAFETY MANUAL. Based on a risk assessment of contracted activities and on mandatory OSHA compliance programs, the Contractor shall address all applicable occupational risks and compliance plans. Using the EM 385-1-1 as a guide, plans may include but not be limited to:
a. Layout plans (04.A.01);
b. Emergency response plans:
(1) Procedures and tests (01.E.01);
(2) Spill plans (01.E.01, 06.A.02);
(3) Firefighting plan (01.E.01, Section 19);
(4) Posting of emergency telephone numbers (01.E.05);
(5) Man overboard/abandon ship (Section19.A.04);
(6) Medical Support. Outline on-site medical support and off-site medical arrangements including rescue and medical duties for those employees who are to perform them, and the name(s) of on-site Contractor personnel trained in first aid and CPR. A minimum of two employees shall be certified in CPR and first-aid per shift/site (Section 03.A.02; 03.D);
c. Plan for prevention of alcohol and drug abuse (01.C.02);
d. Site sanitation plan (Section 02);
e. Access and haul road plan (4.B);
f. Respiratory protection plan (05.G);
g. Health hazard control program (06.A);
h. Hazard communication program (06.B.01);
i. Process Safety Management Plan (06.B.04);
j. Lead abatement plan (06.B.05 & specifications);
k. Asbestos abatement plan (06.B.05 & specifications);
l. Radiation Safety Program (06.E.03.a);
m. Abrasive blasting (06.H.01);
n. Heat/Cold Stress Monitoring Plan (06.I.02)
o. Crystalline Silica Monitoring Plan (Assessment) (06.M);
p. Night operations lighting plan (07.A.08);
q. Fire Prevention Plan (09.A);
r. Wild Land Fire Management Plan (09.K);
s. Hazardous energy control plan (12.A.01);
t. Critical lift Plan (16.H);
u. Contingency plan for severe weather (19.A.03);
v. Float Plan (19.F.04);
w. Site-Specific Fall Protection & Prevention Plan (21.C);
x. Demolition plan (to include engineering survey) (23.A.01);
y. Excavation/trenching plan (25.A.01);
z. Emergency rescue (tunneling) (26.A.);
Aa. Underground construction fire prevention and protection plan (26.D.01);
Bb. Compressed air plan (26.I.01);
Cc. Formwork and shoring erection and removal plans (27.C);
Dd. PreCast Concrete Plan (27.D);
Ee. Lift slab plans (27.E);
Ff. Steel erection plan (27.F.01);
Gg. Site Safety and Health Plan for HTRW work (28.B);
Hh. Blasting Safety Plan (29.A.01);
ii. Diving plan (30.A.13);
JJ. Confined space Program (34.A).
10. RISK MANAGEMENT PROCESSES. Detailed project-specific hazards and controls shall be provided by an Activity Hazard Analysis (0I.A.13) for each major phase/activity of work.
11. ABBREVIATED APP for LIMITED-SCOPE SERVICE, SUPPLY AND R&D CONTRACTS. If service, supply and R&D contracts with limited scopes are awarded, the contractor may submit an abbreviated Accident Prevention Plan. This APP shall address the following areas at a minimum. If other areas of the EM 385-1-1 are pertinent to the contract, the contractor must assure these areas are addressed as well.
a. Title, signature, and phone number of the plan preparer.
b. Background Information to include: Contractor; Contract number; Project name; Brief project description, description of work to be performed, and location (map); The project description shall provide a means to evaluate the work being done (see AHA requirements in 01.A.13) and associated hazards involved. Contractor’s APP shall address the identified hazards involved and the control measures to be taken.
c. Statement of Safety and Health Policy detailing their commitment to providing a safe and healthful workplace for all employees.
d. Responsibilities and Lines of Authorities – to include a statement of the employer’s ultimate responsibility for the implementation of his SOH program; Identification and accountability of personnel responsible for safety at all levels to include designated site safety and health officer (SSHO) and associated qualifications. The District SOHO will review the qualifications for acceptance.
e. Training - new hire SOH orientation training at the time of initial hire of each new employee and any periodic retraining/recertification requirements.
f. Procedures for job site inspections - assignment of responsibilities and frequency.
g. Procedures for reporting man-hours worked and reporting and investigating any accidents as soon as possible but not more than 24 hours afterwards to the Contracting Officer/Representative (CO/COR). An accident that results in a fatal injury, permanent partial or permanent total disability shall be immediately reported to the Contracting Officer.
h. Emergency Planning. Employees working alone shall be provided an effective means of emergency communication. This may be cellular phone, two-way radio or other acceptable means. The selected means of communication must be readily available and must be in working condition.
i. Drinking Water provisions, toilet and washing facilities.
j. First Aid and CPR training (at least two employees on each shift shall be qualified/certified to administer first aid and CPR) and provision of first aid kit (types/size).
k. Personal Protective Equipment.
(1) Work Clothing - Minimum Requirements. Employees shall wear clothing suitable for the weather however minimum requirements for work shall be short-sleeve shirt, long pants
(Excessively long or baggy pants are prohibited) and leather work shoes. If analysis determines that safety-toed (or other protective) footwear is necessary (i.e., mowing, weedeating, chain saw use, etc), they shall be worn.
(2) Eye and Face Protection. Eye and face protection shall be worn as determined by an analysis of the operations being performed HOWEVER, all involved in chain saw use, chipping, stump grinding, pruning operations, grass mowing, weedeating and blowing operations shall be provided safety eyewear (Z87.1) as a minimum.
(3) Hearing Protection. Hearing protection must be worn by all those exposed to high noise activities (to include grass mowing and trimming, chainsaw operations, tree chipping, stump grinding and pruning).
(4) Head Protection. Hard hats shall comply with ANSI Z89.1 and shall be worn by all workers when a head hazard exists. At a minimum, hard hats shall be worn when performing activities identified in (2) above.
(5) High Visibility Apparel shall comply with ANSI/ISEA 107, Class 2 requirements at a minimum and shall be worn by all workers exposed to vehicular or equipment traffic.
(6) Protective Leg chaps shall be worn by all chainsaw operators.
(7) Gloves of the proper type shall be worn by persons involved in activities that expose the hands to cuts, abrasions, punctures, burns and chemical irritants.
(8) If work is being performed around water and drowning is a hazard, PFDs must be provided and worn as appropriate.
l. Machine Guards and safety devices. Lawn maintenance equipment must have appropriate guards and safety devices in place and operational.
m. Hazardous Substances. When any hazardous substances are procured, used, stored or disposed, a hazard communication program must be in effect and MSDSs shall be available at the worksite. Employees shall have received training in hazardous substances being used. When the eyes or body of any person may be exposed to corrosives, irritants or toxic chemicals, suitable facilities for quick drenching or flushing of the eyes and body shall be provided within 10 seconds of the worksite.
n. Traffic control shall be accomplished in accordance with DOT’s MUTCD.
o. Control of Hazardous Energy (Lockout/Tagout). Before an employee performs any servicing or maintenance on any equipment where the unexpected energizing or startup of the equipment could occur, procedures must be in place to ensure adequate control of this energy.
p. Driving, working on (i.e., working with equipment/mowers) while on slopes, working from/in boats/skiffs, etc shall also be considered and dealt with accordingly
CONTRACTOR SUBMITTALS.
The successful bidder shall provide as a minimum the following documentation:
A. Accident Prevention Plan – In accordance with EM 385-1-1 Appendix A.
B. Activity Hazard Analysis – In accordance with EM 385-1-1 Section 01.A.14.
C. Invoice as stated on the contract award upon completion of work.
D. Material Submittals for Interlocking Clay title, ice and water membrane, and urethane sealant.
E. Man-hour report to project office at completion of work.
For additional information point of contact is:
Rick Houze
Project Supervisor U. S. Army, Corps of Engineers, Atwood Lake Dam 3434 State Route 212 NE
(330) 343-5611
Section H - Special Contract Requirements
DAVIS BACON WAGE RATES
"General Decision Number: OH20220058 02/18/2022
Superseded General Decision Number: OH20210058
State: Ohio
Construction Type: Building
County: Tuscarawas County in Ohio.
BUILDING CONSTRUCTION PROJECTS (does not include single family homes or apartments up to and including 4 stories).
Note: Contracts subject to the Davis-Bacon Act are generally required to pay at least the applicable minimum wage rate required under Executive Order 14026 or Executive Order 13658.
Please note that these Executive Orders apply to covered contracts entered into by the federal government that aresubject to the…
This is the start of the file's text. The full file is on GovTribe.
File details come from the government source that posted it. Updated .