GRAYSON LAKE

FRANK JEFFREY

50 LAUNCH RAMP ROAD

GRAYSON KY 41143-9612

TEL: 606-474-5107 EXT8800 FAX:

W81F8E93455480

REQUEST FOR QUOTATIONS

(THIS IS NOT AN ORDER) 1

PAGE OF PAGES

1. REQUEST NO. 2. DATE ISSUED RATING

W9123721Q0081 09-Jun-2021 5a. ISSUED BY

8. TO: NAME AND ADDRESS, INCLUDING ZIP CODE

IMPORTANT: This is a request for information, and quotations furnished are not offers. If you are unable to quote, please so indicate on this form and return it to the address in Block 5a. This request does not commit the Government to pay any costs incurred in the preparation of the submission of this quotation or to contract for supplies or services. Supplies are of domestic origin unless otherwise indicated by quoter. Any representations and/or certifications attached to this

Request for Quotations must be completed by the quoter.

11. SCHEDULE (Include applicable Federal, State, and local taxes)

ITEM NO.

(a)

SUPPLIES/ SERVICES

(b)

QUANTITY

(c)

UNIT

(d)

UNIT PRICE

(e) (f)

SEE SCHEDULE

AMOUNT

% No. %

NOTE: Additional provisions and representations [ ] are [ ] are not attached.

13. NAME AND ADDRESS OF QUOTER (Street, City, County, State, and ZIP Code)

14. SIGNATURE OF PERSON AUTHORIZED TO

SIGN QUOTATION

15. DATE OF

QUOTATION

16. NAME AND TITLE OF SIGNER (Type or print) (Include area code)

TELEPHONE NO.

AUTHORIZED FOR LOCAL REPRODUCTION STANDARD FORM 18 (REV. 6-95)

PREVIOUS EDITION NOT USABLE Prescribed by GSA FAR (48 CFR) 53.215-1(a)

THIS RFQ X[ ] IS [ ] IS NOT A SMALL BUSINESS SET-ASIDE

6. DELIVER BY (Date)

SEE SCHEDULE

AND/OR DMS REG. 1

UNDER BDSA REG. 2

4. CERT. FOR NAT. DEF.3. REQUISITION/PURCHASE

REQUEST NO.

USACE, CONTRACTING DIVISION

JEREMIAH STAFFORD, 502 8TH STREET

HUNTINGTON WV 25701

9. DESTINATION (Consignee and address, including ZIP Code)

7. DELIVERY

[ ]X FOB

DESTINATION

[ ] OTHER

(See Schedule)

22-Jun-2021(Date)

PLEASE FURNISH QUOTATIONS TO THE ISSUING OFFICE IN BLOCK 5a ON OR BEFORE CLOSE OF BUSINESS:10.

304-399-5949JEREMIAH S STAFFORD

(Name and Telephone no.) (No collect calls)5b. FOR INFORMATION CALL:

d. CALENDAR DAYSc. 30 CALENDAR DAYSb. 20 CALENDAR DAYS12. DISCOUNT FOR PROMPT PAYMENT a. 10 CALENDAR DAYS

Section B - Supplies or Services and Prices

ITEM NO SUPPLIES/SERVICES QUANTITY UNIT UNIT PRICE AMOUNT

0001 1 Job Grayson Lake Intake Structure Roof Repla

FFP

Contractor shall furnish all personnel, equipment, supplies and material necessary to remove and reinstall a new 50 mil pvc roof to include insulation, drains, flashing, vents and other existing components in accordance with the attached Statement of Work.

FOB: Destination

MILSTRIP: W81F8E93455480

PURCHASE REQUEST NUMBER: W81F8E93455480

PSC CD: Y1PZ

NET AMT

PRICE BREAKOUT SCHEDULE

TOTAL$

SPECIAL CONTRACT REQUIREMENTS

Line Item No. Description of Requirement Qty/Unit of Measure Extended Price

Reimbursement of actual cost of payment bond for quotes in excess of $35,000.00

JOB

Mobilization & de-mobilization of equipment required in accordance with the attached Statement of Work.

Labor for Roof replacement at Grayson Lake in accordance with the attached Statement of Work.

Materials and Supplies for Roof replacement at Grayson Lake in accordance with the attached Statement of Work.

*SITE VISITS ARE HIGHLY RECOMMENDED PRIOR TO PROVIDING A

QUOTE. SEE CLAUSE 52.236-27 FOR ADDITIONAL INFORMATION.

*PLEASE DIRECT ALL QUESTIONS TO JEREMIAH STAFFORD AT (304) 399-5949 or Jeremiah.s.stafford@usace.army.mil. ANY INFORMATION RECEIVED AT THE

SITE VISIT WHICH CONFLICTS WITH THIS SOLICITATION SHOULD BE

BROUGHT TO THE ATTENTION OF MR. STAFFORD. THE SOLICITATION

AND RESULTING CONTRACT SHALL BE THE GOVERNING DOCUMENT IN

ALL CASES.

**QUOTES CAN ONLY BE FAXED OR PREFERABLY BE E-MAILED TO JEREMIAH

STAFFORD AT Jeremiah.s.stafford@usace.army.mil or faxed to (304) 399-5281 by the date reference on page 1 of the SF18.

Per FAR 36.204 the estimated price range for this project is between $25,000.00 and $100,000.00.

NOTE: Award will be made to the lowest price offeror who meets the technical requirements of the solicitation and is deemed responsible by the contracting officer.

The intent is to award without discussions.

NOTE: this procurement is 100% Set-Aside for Small Business. For more information see FAR Clause 52.219-6 (Dev).

QUOTATION INSTRUCTIONS (Provide the following with your quote):

Company Name and Address:

Phone Number: Fax Number:

Email Address:

Business Size (select all that apply):

Large Business Small Business HUBZone Business 8A

Woman-Owned Service-Disabled Veteran-Owned

If subcontractor will be used for this work, please provide company name and credentials/qualifications:

IMPORTANT NOTICE: Effective September 26, 2018 and in accordance with FAR Clause 52.204- 7, “an Offeror is required to be registered in SAM when submitting an offer or quotation, and shall continue to be registered until time of award, during performance, and through final payment of any contract, basic agreement, basic ordering agreement, or blanket purchasing agreement resulting from this solicitation.” Vendors are highly encouraged to check their registration status and plan accordingly prior to submitting an offer.

Please note, as of April 2018, GSA's System for Award Management (SAM) system is requiring new registrations and renewals of existing registrations to submit an original signed notarized letter identifying the authorized Entity Administrator. Vendors are encouraged to check their entity's status in SAM.gov and plan accordingly. If the prospective contractor is not registered in the SAM database, the Contracting Officer will following the procedures at FAR 4.1103. Contact the supporting Federal Service Desk at www.fsd.gov, or by telephone at 866- 606-8220 (toll free) or 334-206-7828 (internationally) Monday through Friday from 8 a.m. to 8 p.m. (EDT), for FREE assistance.

Contractor is registered with SAM:

YES NO (See FAR 52.204-7)

Provide business Unique Entity Identifier number:

(phone 800-333-0505 for Unique Entity Identifier number).

Provide business CAGE code:

Provide Tax Identification Number:

All work under this contract shall be in performance with all local, state, and federal laws, regulations, and codes.

Contractors are not required to submit an Accident Prevention Plan (APP) with their quote.

The successful offeror will be required to submit this document upon award. The APP must be accepted by the Government Designated Authority prior to the preconstruction conference. The contractor that receives this award will have 10 calendar days to provide an Accident Prevention Plan (APP). If this deadline is not met, the contractor will be given a cure notice stating that they will have 10 calendar days to submit an APP, otherwise the contract may be terminated for default.

Only the awarded contractor shall provide a copy of their insurance certificate required by State and Local Governments that has been acquired for the time period covered under this contract to the Contracting Officer within 10 business days after award. No further insurance requirements will be imposed by the Corps of Engineers for this contract.

Section C - Descriptions and Specifications

STATMENT OF WORK

DESCRIPTION/SPECIFICATIONS 3-17-2021

Removal and replacement of flat PVC membrane roof 40’x40’. – Grayson Lake Intake Structure, Grayson, KY

1. General: Contractor shall furnish all personnel, equipment, supplies and material necessary to remove and reinstall a new 50 mil pvc roof to include insulation, drains, flashing, vents and other existing components. Photos of existing roof and the asbestos report are included as attachment 1 and attachment 2 respectively. All the material removed from the government property shall be disposed of in accordance with state, local, and federal laws.

2. Scope of Work and Information:

A. All construction shall be in accordance to USACE Safety and Health Requirements

Manual (EM385-1-1), the scope of work herein and to current industry standards.

B. Contractor shall prepare to access roof by aerial lift only. All personnel and materials shall be lifted approximately 45 feet to the top of the roof. This shall be the only way to access the roof.

C. Contractor shall ensure a method of fall protection will be implemented as a fall hazard exist while atop of the roof. Methods of restraints or some form of tie off shall be used.

D. Ballast, pvc membrane, vents, insulation previous fastening device, sealant, ect, shall be removed from the roof and disposed of complying with local and state laws. Once removed contractor shall inspect bare metal decking and report any issues prior to installing new pvc roof system.

E. New materials, components and equipment shall be of high quality, free from defects and imperfections, of recent manufacture, unused and shall ne suitable for the intended use. Care shall be taken to provide materials and equipment with long life, liberal factors of safety, and suitable operating characteristics for the conditions where there will be used.

F. Workmanship shall be in accordance with the best modern standard practice in the manufacture and installation. The job shall be completed in a professional style and to professional industry standards. When work is completed, disposal and clean up of all debris that results from installation shall be removed from the project by the contractor.

G. Mechanically fasten two layers of 2” ISO insulation using coated fasteners and three-inch plates. All insulation joints to be staggered per manufactures specs.

H. Install 50 mil membrane that is mechanically fastened per manufactures recommendations for wind uplift. Fasteners shall be of sufficient length to penetrate roof deck.

I. All membrane laps are to be welded using an automatic hot air welder or hand welder to industry standards. All flashing shall be hand welded.

J. Membrane flashing shall be installed along parapet walls roof curbs, pipe penetrations, hatches and drains.

K. Terminations bars shall be used at the roof edges allowing for the pvc to rise a minimum of 8 inches and uniformly terminating below the affixed lightning rod system.

L. Apply new flashing on all roof penetrations and install new counter flashing at all applicable flashing details.

M. Contractor shall ensure water does not stand on roof and is directed toward roof drains. At no place on the roof should the water “stand or pool.”

N. All labor and material supplied by the contractor for the roof will have a 5-year warranty from completion date. This includes but not limited to workmanship, cracking, bubbling, flaking or leaking.

Additionally, the pvc roof system will be rated for a 50-year life span.

O. Asbestos test was conducted on 31 March 2021 by an independent contractor. No asbestos was detected.

See Attachment 1 for asbestos testing report.

P. Attachment existing roof photos

3. Site Inspection:

A site inspection by the offerers prior to the submission of offers is strongly recommended. Appointments for site inspections should be made with the Resource Manager by calling (606) 474-5815, Monday – Friday, 0730 –

1600 EST.

4. Completion Date:

Work is to begin within 14 Calender days of Notice to Proceed. All work is to be completed within 28 Calendar days of Notice to Proceed. Work Schedule shall be approved by Resource Manager prior to on-site work activities. Work activities are to be scheduled for least impact to daily Corps’ employee activities.

5. Payments:

Upon completion the contractor shall submit an invoice within 3 Calender days to the project supervisor for the total amount due. Invoice shall be sent to:

US Army Corps of Engineers Grayson Lake 50 Launch Ramp RD Grayson Ky 41143

Or emailed to: Francis.S.Jeffrey2@usace.army.mil

6. Point of Contact:

US Army Corps of Engineers Grayson Lake Attn: Frank Jefferey 50 Launch Ramp Rd Grayson Kentucky, 41143 Phone: 6064745815 Fax: 606-474-20893.

Contractor Safety Requirements

3.1 General. Contractor shall comply with all Federal, State and Local safety requirements including those specified by the Occupational Safety and Health Act (OSHA) in 29 CRF 1910 General Industry Standard, 1926 Construction Standard and the U.S. Army Corps of Engineers Safety & Health Requirements Manual EM 385-1- 1 as currently revised. Where a conflict exists between safety standards/requirements the contractor shall comply with the more stringent requirement. If the Contractor fails or refuses to promptly comply with safety requirements as specified herein, any project employee may stop all or part of the work until satisfactory corrective action has been taken. No part of the time lost due to any such work stoppage shall be made subject to any claims for extension of time or for excess costs or damages sustained by the Contractor. Also, the Contractor will not be paid for work not performed as a result of the stop order.

3.2 Contractor Accident Prevention Plan (APP). The Contractor shall prepare a site-specific Accident Prevention Plan following the outline provided in EM 385-1-1, Appendix A as a minimum. The contractor shall address each element and sub- element in the outline in the order they appear in Appendix A. Any item from the outline that does not apply must be listed, in its assigned place and a brief explanation of the reason it is not required provided. The APP shall address any unusual or unique aspects of the project or activity. This plan must be accepted by the Contracting Officer prior to commencement of any work. Contractors are encouraged to contact the USACE Safety & Occupational Health Office for questions or information regarding the development of contract Accident Prevention Plans. Office hours are Monday-Friday 8:30 a.m. - 4 p.m. at (304)399- 5039/5032/5326. The web address for EM 385-1-1 is:

http://www.publications.usace.army.mil/Portals/76/Publications/EngineerManuals/EM_385-1-1.pdf

(1) The contractor shall have on site an employee designated as a Site Safety and Health Officer (SSHO) who has completed the OSHA 30-hour Construction Safety training or its equivalent as specified in EM 385-1-1, 01.A.17 and has at least five years safety management experience relative to the work to be performed. No work will be permitted unless the SSHO is present at the work site. Work crews of two or more must have two people holding current certification in First Aid and CPR from the American Red Cross, American Heart Association or a licensed physician. Training must include a hands-on component that cannot be taken online and the contractor must maintain appropriate First Aid kit on site. Single individuals working alone must have current certification in First Aid as a minimum.

(2) All work that potentially exposes the worker to falls of six feet or more will require the contractor to submit a Site Specific Fall Protection & Prevention Plan in accordance with EM 385-1-1, Section 21.D.

(3) Cranes and hoisting equipment shall be operated only by qualified personnel (operators licensing, physical and drug testing in accordance with EM 385-1-1 Section 16.B). Note: CDL Medical Clearance is not acceptable. Please see attached medical clearance requirements.

(4) Effective November 8, 2010 all “Signalpersons” and “Riggers” shall be qualified. This is a mandatory requirement in accordance with 29 CFR 1926.1400 Regulations. Riggers must be a qualified person for the performance of specified hoisting activities such as during assembly/disassembly, in accordance with OSHA 1926.1404(r)(1) and 1926.1425(c)(3).

(5) Work orders involving potential exposure to Hazardous, Toxic or Radiological Waste shall require development of Site Specific Safety and Health Plan (SSHP) by qualified personnel as specified in EM 385-1-1 Sections 6 and 33.

3.3 Risk Management Process. The Contractor shall utilize risk management tools such as Activity Hazard Analysis (AHA), Job Hazard Analyses (JSAs) or similar tools to identify, assess, prioritize risks and develop controls to minimize, monitor and control the probability and/or impact of unfortunate events to an acceptable level. Within each major phase, all activities, tasks or Definable Features of Work (DFOWs) shall be identified that will require an AHA/JSA. For each work activity, task or DFOW contractor shall prepare the initial AHA/JSA. A Risk Assessment Code (RAC) is assigned to each step, to the risk that remains after controls have been applied (residual risk) a final RAC (cannot be lower than the highest step RAC) shall be assigned. See EM 385-1-1 Section 01.A.14.b. for further guidance or contact the SOHO for assistance. The AHA/JSA shall be reviewed and accepted by the proper authority in order to proceed with the activity. All on-site employees shall review the accepted AHA/JSA prior to performing work and during weekly and “Tool Box” safety meetings as appropriate.

1. AHA/JSA shall define the activities being performed and identify the work sequences, the specific anticipated hazards, site conditions, equipment, materials, and the control measures to be implemented to eliminate or reduce each hazard to an acceptable level of risk. AHA/JSA should indicate compliance with EM 385-1-1 personal protective equipment requirements (safety-toed work boots, safety glasses, gloves, hard hats, etc.), work crews of two or more must have two people currently qualified in first aid and CPR and the appropriate first aid kit on site. Single individuals working alone must have current certification in First Aid only.

2. The names of the Competent Person(s) and Qualified Person(s) required for a particular activity (e.g., excavation, scaffolding, fall protection, or other activities as specified by OSHA and this manual) shall be identified and included in the AHA, as well as proof of their competency/qualification.

D. Accident/Mishap Reporting: The Contractor shall report all recordable mishaps to the GDA within 24-hours in accordance with EM 385-1-1 Section 01.D. Accidents shall be investigated to determine causal factors and corrective actions shall be implemented. Accidents resulting in: days away injuries, days away illnesses, restricted/transfer injuries, property damage of $5,000.00 or more shall be investigated and reported to the GDA using the USACE Accident Investigation Report Form ENG 3394 within 24 hours of the occurrence.

(1) Immediate notification to the GDA is required for all serious accidents:

a. Fatal Injury/illness;

b. Permanent totally disabling injury/illness;

c. Permanent partial disabling injury/illness;

d. One (1) or more persons hospitalized as inpatients as a result of a single occurrence;

e. $500,000 or greater accidental property damage;

f. Three (3) or more individuals become ill or have a medical condition suspected to be related to a site condition, or a hazardous or toxic agent on the site;

g. USACE aircraft destroyed or missing;

The Contractor shall maintain an OSHA Log of Work Related Injuries and Illnesses, OSHA Form 300 and comply with all accident reporting and recordkeeping requirements specified in 29 CFR 1904.39.

(2) In addition to the above, any mishap occurring in any of the following high hazard areas shall be reported immediately to the GDA, investigated and corrective actions implemented.

a. Electrical (includes Arc Flash, electrical shock, etc.);

b. Uncontrolled Release of Hazardous Energy (includes electrical and non-electrical);

c. Load Handling Equipment (LHE) or Rigging;

d. Fall-from-Height (any level or other than same surface);

e. Underwater Diving

3.6 Damage Reports.

All instances where Government materials supplies, property, and/or equipment are damaged shall be reported immediately to the Resource Manager.

3.7 Minimum Personal Protective Equipment.

Long pants, safety toe shoes/boots, and shirts with minimum 4 inch sleeves, hard hat, hearing protection as needed, and safety eyewear. Additional Personal Protective Equipment may be needed and should be determined using the Activity Hazard Analysis.

3.8 Pre-Construction Conference.

The Contractor shall attend a pre-Construction conference, prior to the initiation of installation work under this contract. The Contractors Safety Plan must be accepted prior to this meeting.

3.9 Security Requirements - All Contractor and subcontractor employees working on this contract who require access in or around Huntington District facilities (i.e. flood control dams plants, navigation locks, etc.) shall receive a favorable background investigation in accordance with “Homeland Security Presidential Directive 12: Policy for a Common Identification Standard for Federal Employees and Contractors” (HSPD-12). The Huntington District Security Management Office (SMO) will complete the background investigation and make the final determination of an employee’s suitability for work on Government property. The SMO and has the right to deny any contractor or subcontractor employee from working on a contract based on results of the background investigation. The Government, Contractor, and sub-contractors shall not permit any employee access to drawings, records, photos, sites, or projects until the Huntington District Security Management Office has approved them. The Contractor is responsible for meeting this requirement. Contractor’s failure to adhere to this can result in penalties, fines, or sanctions up to and including contract termination and or forfeiture of future contract consideration.

Contractors shall submit a complete investigation package for each contractor and subcontractor employee to the Huntington District Security Management Office within ten (10) working days after award of any contract, OR prior to the individual being permitted unescorted access in or around all District facilities. The documents listed below are required:

SF-85, Questionnaire for Non-sensitive Positions (See http://www.opm.gov/forms/ to print form) FD-258, Contractor Fingerprint Card (one card for digital prints, 2 for ink prints) (Note: a trained/qualified individual must take prints; ORI block on FD-258 must be USOPM000Z) (Contractor Fingerprint Cards (FD-258) may be obtained by contacting the Huntington District Security Management Office)

Contractor shall report any change(s) in personnel at least 5 working days prior to individual(s) needing access to the site. The Contractor shall provide the same information as listed above for any new employees.

Following submission of paperwork the Huntington District Security Management Office will conduct an initial criminal check based on the information provided. If there are no issues, SMO will provide approval via email to the Contractor and the Contracting Officer or their Designated Representative. If the SMO cannot give approval due to unfavorable report(s), it will notify the Contracting Officer and the Designated Representative; the KO will contact the Contractor. The Government will not provide a reason for disapproval; it will be up to the

Contractor and or its employee to investigate the employee’s background information.

3.9.1 Foreign Nationals

The Contractor shall provide the package listed above, as well as additional materials noted below, for all non- U.S. citizens who have lived in the United States for at least three years. The Contractor is to expect additional time in the approval process for all foreign nationals due to the level of review and elevation of the review to Headquarters Staff to accomplish. All non-U.S. citizens, including permanent residents, must comply with the following paragraph:

In accordance with Engineering Regulation 380-1-18, “Technology Transfer, Disclosure of Information and Contacts with Foreign Representatives” dated 1 August 1996, Section 4, all foreign nationals who work on Corps of Engineers’ contracts shall be approved by the Headquarters US Army Corps of Engineers (HQ USACE) Foreign Disclosure Officer before beginning work on this contract; this regulation includes subcontractor employees. The Contractor shall submit to the Huntington District Security Management Office, the names of all foreign nationals proposed for performance under this contract, along with documentation to verify legal admittance into the United States, and has authority to work and/or attend school in the U.S. Such documentation shall include at least one of the following a U.S. passport, Certificate of U.S. Citizenship (INS Form N-560 or N-561), Certificate of Naturalization (INS Form N-550 or N-570), Alien Registration Card with photograph (INS Form I-151 or I-551), Employment Authorization Card (INS Form I-688A), etc. A cleared federal employee shall escort foreign nationals at all times unless otherwise approved in writing by the Huntington District Security Management Office.

In order to assure forms are properly completed, and to minimize time delays, Contractor is encouraged to work closely with the Huntington District Security Management Office. The Government will return for correction incomplete forms, illegible forms, etc. which will delay the contractor/subcontractor from beginning work. No subcontractor shall submit forms directly to the Huntington District Security Management Office;

these documents shall come through the Prime Contractor.

Security requirements are subject to change in accordance with HSPD-12, Office of Personnel Management, regulation or policy changes, etc. The Government shall add any changes to security requirements by modification to the contract.

The Contractor shall contact the Huntington District Security Management Office by phone, letter, or email at the following numbers/addresses:

CELRH-SM

502 Eighth Street Huntington, WV 25701

Sandra L. Hardwick, phone (304) 399-5612; email sandra.l.hardwick@usace.army.mil Matthew D. Green, phone (304) 399-5294; email matthew.d.green@usace.army.mil 3.9.2E-Verify Program The Contractor must pre-screen Candidates using the E-verify Program (http://www.uscis.gov/e-verify) website to meet the established employment eligibility requirements. The Vendor must ensure that the Candidate has two valid forms of Government issued identification prior to enrollment to ensure the correct information is entered into the E-verify system. An initial list of verified/eligible Candidates must be provided to the COR no later than 3 business days after the initial contract award."

*When contracts are withindividuals, the individuals will be required to complete a Form I-9, Employment Eligibility Verification, with the designated Government representative. This Form will be provided to the Contracting Officer and shall become part of the official contract file.

C.3.9.3.1 All contractor employees, to include subcontractor employees, requiring access to Army installations, facilities and

C. 3.9.3 OPERATIONAL SECURITY AND ANTI TERRORISM

The following shall be accomplished by the contractor before any task order will be issued:

controlled access areas shall complete AT Level I awareness training within thirty (30) calendar days after contract start date or effective date of incorporation of this requirement into the contract, whichever is applicable.

The contractor shall submit certificates of completion for each affected contractor employee and subcontractor employee, to the COR or to the contracting officer, if a COR is not assigned, within five (5) calendar days after completion of training by all employees and subcontractor personnel. AT Level I awareness training is available at the following website: https://atlevel1.dtic.mil/at.

C.3.9.3.2 All Contractor and all associated sub‐contractors employees shall comply with applicable installation, facility, and area commander installation/facility access and local security policies and procedures (provided by government representative). The contractor shall also provide all information required for background checks to meet installation access requirements to be accomplished by installation Provost Marshal Office, Director of Emergency Services, or Security Office. Contractor workforce must comply with all personal identity verification requirements as directed by DOD, HQDA and/or local policy. In addition to the changes otherwise authorized by the changes clause of this contract, should the Force Protection Condition (FPCON) at any individual facility or installation change, the Government may require changes in contractor security matters or processes.

C.3.9.3.3 The Contractor and all associated subcontractors shall brief all employees on the local iWATCH, Corps Watch, or “See Something, Say Something” program (training standards provided by the requiring activity ATO). This locally developed training shall be used to inform employees of the types of behavior to watch for and instruct employees to report suspicious activity to the COR and project resource manager. This training shall be completed within thirty (30) calendar days of contract award and within 30 calendar days of new employees commencing performance with the results reported to the COR, as evidenced by a course certificate, no later than five (5) calendar days after course completion.

C.3.9.3.4 All contractor employees shall complete annual OPSEC awareness training, as evidenced by a completed course certificate. New contractor employees shall submit to the COR completed course certificates of Level I OPSEC training within thirty (30) calendar days of their reporting for duty.

3.10 Contractor Submittals

The successful contractor shall provide, the following documentation:

a. Accident Prevention Plan – in accordance with EM 385-1-1 Appendix A.

APPENDIX A

MINIMUM BASIC OUTLINE FOR ACCIDENT

PREVENTION PLANS

An Accident Prevention Plan (APP) is a safety and health policy and program document. The following areas are typically addressed in an APP, but an APP shall be job-specific and shall also address any unusual or unique aspects of the project or activity for which it is written.

ABBREVIATED APP for LIMITED-SCOPE SERVICE, SUPPLY AND R&D CONTRACTS. If service, supply and R&D contracts with limited scopes are awarded, the contractor may submit an abbreviated Accident Prevention Plan. This APP shall address the following areas at a minimum. If other areas of the EM 385-1-1 are pertinent to the contract, the contractor must assure these areas are addressed as well.

a. Title, signature, and phone number of the plan preparer.

b. Background Information to include: Contractor; Contract number; Project name; Brief project description, description of work to be performed, and location (map); The project description shall provide a means to evaluate the work being done (see AHA requirements in 01.A.13) and associated hazards involved. Contractor’s APP shall address the identified hazards involved and the control measures to be taken.

c. Statement of Safety and Health Policy detailing their commitment to providing a safe and healthful workplace for all employees.

d. Responsibilities and Lines of Authorities – to include a statement of the employer’s ultimate responsibility for the implementation of his SOH program; Identification and accountability of personnel responsible for safety at all levels to include designated site safety and health officer (SSHO) and associated qualifications. The District SOHO will review the qualifications for acceptance.

e. Training - new hire SOH orientation training at the time of initial hire of each new employee and any periodic retraining/recertification requirements.

f. Procedures for job site inspections - assignment of responsibilities and frequency.

g. Procedures for reporting man-hours worked and reporting and investigating any accidents as soon as possible but not more than 24 hours afterwards to the Contracting Officer/Representative (CO/COR). An accident that results in a fatal injury, permanent partial or permanent total disability shall be immediately reported to the Contracting Officer.

h. Emergency Planning. Employees working alone shall be provided an effective means of emergency communication.

This may be cellular phone, two-way radio or other acceptable means. The selected means of communication must be readily available and must be in working condition.

i. Drinking Water provisions, toilet and washing facilities.

j. First Aid and CPR training (at least two employees on each shift shall be qualified/certified to administer first aid and CPR) and provision of first aid kit (types/size).

k. Personal Protective Equipment.

(1) WORK CLOTHING - Minimum Requirements. Employees shall wear clothing suitable for the weather however minimum requirements for work shall be short-sleeve shirt, long pants (excessively long or baggy pants are prohibited) and leather work shoes. If analysis determines that safety-toed (or other protective) footwear is necessary (i.e., mowing, weedeating, chain saw use, etc), they shall be worn.

(2) Eye and Face Protection. Eye and face protection shall be worn as determined by an analysis of the operations being performed HOWEVER, all involved in chain saw use, chipping, stump grinding, pruning operations, grass mowing, weedeating and blowing operations shall be provided safety eyewear (Z87.1) as a minimum.

(3) Hearing Protection. Hearing protection must be worn by all those exposed to high noise activities (to include grass mowing and trimming, chainsaw operations, tree chipping, stump grinding and pruning).

(4) Head Protection. Hard hats shall comply with ANSI Z89.1 and shall be worn by all workers when a head hazard exists. At a minimum, hard hats shall be worn when performing activities identified in (2) above.

(5) High Visibility Apparel shall comply with ANSI/ISEA 107, Class 2 requirements at a minimum and shall be worn by all workers exposed to vehicular or equipment traffic.

(6) Protective Leg chaps shall be worn by all chainsaw operators.

(7) Gloves of the proper type shall be worn by persons involved in activities that expose the hands to cuts, abrasions, punctures, burns and chemical irritants.

(8) If work is being performed around water and drowning is a hazard, PFDs must be provided and worn as appropriate.

l. Machine Guards and safety devices. Lawn maintenance equipment must have appropriate guards and safety devices in place and operational.

m. Hazardous Substances. When any hazardous substances are procured, used, stored or disposed, a hazard communication program must be in effect and MSDSs shall be available at the worksite. Employees shall have received training in hazardous substances being used. When the eyes or body of any person may be exposed to corrosives, irritants or toxic chemicals, suitable facilities for quick drenching or flushing of the eyes and body shall be provided within 10 seconds of the worksite.

n. Traffic control shall be accomplished in accordance with DOT’s MUTCD.

o. Control of Hazardous Energy (Lockout/Tagout). Before an employee performs any servicing or maintenance on any equipment where the unexpected energizing or startup of the equipment could occur, procedures must be in place to ensure adequate control of this energy.

p. Driving, working on (i.e., working with equipment/mowers) while on slopes, working from/in boats/skiffs, etc shall also be considered and dealt with accordingly.

APPENDIX A

MINIMUM BASIC OUTLINE FOR ACCIDENT PREVENTION PLANS

An Accident Prevention Plan (APP) is a safety and health policy and program document. The following areas are typically addressed in an APP, but an APP shall be job-specific and shall also address any unusual or unique aspects of the project or activity for which it is written.

The APP shall interface with the employer’s overall safety and health program, and a copy shall be available on the work site. Any portions of the overall safety and health program that are referenced in the APP shall be included as appropriate. ANSI/ASSE A10.38 should be referenced for Programmatic Issues.

> For LIMITED-SCOPE SERVICE, SUPPLY AND R&D CONTRACTS, for example, mowing (only), park attendant, rest room cleaning, the Contracting Officer and SOHO may allow an ABBREVIATED APP (customized APP requirements and waive the more stringent elements of this section). > See 01.A.11, and Appendix A, paragraph 11.

11. ABBREVIATED APP for LIMITED-SCOPE SERVICE, SUPPLY AND R&D CONTRACTS. If service, supply and R&D contracts with limited scopes are awarded, the contractor may submit an abbreviated Accident Prevention Plan. This APP shall address the following areas at a minimum. If other areas of the EM 385-1-1 are pertinent to the contract, the contractor must assure these areas are addressed as well.

a. Title, signature, and phone number of the plan preparer.

b. Background Information to include: Contractor; Contract number; Project name; Brief project description, description of work to be performed, and location (map); The project description shall provide a means to evaluate the work being done (see AHA requirements in 01.A.13) and associated hazards involved.

Contractor’s APP shall address the identified hazards involved and the control measures to be taken.

c. Statement of Safety and Health Policy detailing their commitment to providing a safe and healthful workplace for all employees.

d. Responsibilities and Lines of Authorities – to include a statement of the employer’s ultimate responsibility for the implementation of his SOH program; Identification and accountability of personnel responsible for safety at all levels to include designated site safety and health officer (SSHO) and associated qualifications. The District SOHO will review the qualifications for acceptance.

e. Training - new hire SOH orientation training at the time of initial hire of each new employee and any periodic retraining/recertification requirements.

f. Procedures for job site inspections - assignment of responsibilities and frequency.

g. Procedures for reporting man-hours worked and reporting and investigating any accidents as soon as possible but not more than 24 hours afterwards to the Contracting Officer/Representative (CO/COR). An accident that results in a fatal injury, permanent partial or permanent total disability shall be immediately reported to the Contracting Officer.

h. Emergency Planning. Employees working alone shall be provided an effective means of emergency communication. This may be cellular phone, two-way radio or other acceptable means. The selected means of communication must be readily available and must be in working condition.

i. Drinking Water provisions, toilet and washing facilities.

j. First Aid and CPR training (at least two employees on each shift shall be qualified/certified to administer first aid and CPR) and provision of first aid kit (types/size).

k. Personal Protective Equipment.

(1) Work Clothing - Minimum Requirements. Employees shall wear clothing suitable for the weather however minimum requirements for work shall be short-sleeve shirt, long pants (excessively long or baggy pants are prohibited) and leather work shoes. If analysis determines that safety-toed (or other protective) footwear is necessary (i.e., mowing, weed eating, chain saw use, etc), they shall be worn

(2) Eye and Face Protection. Eye and face protection shall be worn as determined by an analysis of the operations being performed HOWEVER, all involved in chain saw use, chipping, stump grinding, pruning operations, grass mowing, weed eating and blowing operations shall be provided safety eyewear (Z87.1) as a minimum.

(3) Hearing Protection. Hearing protection must be worn by all those exposed to high noise activities (to include grass mowing and trimming, chainsaw operations, tree chipping, stump grinding and pruning).

(4) Head Protection. Hard hats shall comply with ANSI Z89.1 and shall be worn by all workers when a head hazard exists. At a minimum, hard hats shall be worn when performing activities identified in (2) above.

(5) High Visibility Apparel shall comply with ANSI/ISEA 107, Class 2 requirements at a minimum and shall be worn by all workers exposed to vehicular or equipment traffic.

(6) Protective Leg chaps shall be worn by all chainsaw operators.

(7) Gloves of the proper type shall be worn by persons involved in activities that expose the hands to cuts, abrasions, punctures, burns and chemical irritants.

(8) If work is being performed around water and drowning is a hazard, PFDs must be provided and worn as appropriate.

l. Machine Guards and safety devices. Lawn maintenance equipment must have appropriate guards and safety devices in place and operational.

m. Hazardous Substances. When any hazardous substances are procured, used, stored or disposed, a hazard communication program must be in effect and MSDSs shall be available at the worksite. Employees shall have received training in hazardous substances being used. When the eyes or body of any person may be exposed to corrosives, irritants or toxic chemicals, suitable facilities for quick drenching or flushing of the eyes and body shall be provided within 10 seconds of the worksite.

W9123721Q0081

n. Traffic control shall be accomplished in accordance with DOT’s MUTCD.

o. Control of Hazardous Energy (Lockout/Tag Out). Before an employee performs any servicing or maintenance on any equipment where the unexpected energizing or startup of the equipment could occur, procedures must be in place to ensure adequate control of this energy.

p. Driving, working on (i.e., working with equipment/mowers) while on slopes, working from/in boats/skiffs, etc shall also be considered and dealt with accordingly.

Section I - Contract Clauses

CLAUSES INCORPORATED BY REFERENCE

52.204-9 Personal Identity Verification of Contractor Personnel JAN 2011 52.204-10 Reporting Executive Compensation and First-Tier

Subcontract Awards

JUN 2020

52.204-13 System for Award Management Maintenance OCT 2018 52.204-22 Alternative Line Item Proposal JAN 2017 52.204-23 Prohibition on Contracting for Hardware, Software, and

Services Developed or Provided by Kaspersky Lab and Other Covered Entities.

JUL 2018

52.204-25 Prohibition on Contracting for Certain Telecommunications and Video Surveillance Services or Equipment.

AUG 2020

52.209-6 Protecting the Government's Interest When Subcontracting With Contractors Debarred, Suspended, or Proposed for Debarment

JUN 2020

52.209-10 Prohibition on Contracting With Inverted Domestic Corporations

NOV 2015

52.219-6 (Dev) Notice of Total Small Business Set-Aside (DEVIATION 2020-O0008).

NOV 2020

52.222-3 Convict Labor JUN 2003 52.222-4 Contract Work Hours and Safety Standards - Overtime

Compensation

MAY 2018

52.222-6 Construction Wage Rate Requirements AUG 2018 52.222-7 Withholding of Funds MAY 2014 52.222-8 Payrolls and Basic Records AUG 2018 52.222-9 Apprentices and Trainees JUL 2005 52.222-10 Compliance with Copeland Act Requirements FEB 1988 52.222-11 Subcontracts (Labor Standards) MAY 2014 52.222-12 Contract Termination-Debarment MAY 2014 52.222-13 Compliance With Construction Wage Rate Requirements and

Related Regulations

MAY 2014

52.222-14 Disputes Concerning Labor Standards FEB 1988 52.222-15 Certification of Eligibility MAY 2014 52.222-21 Prohibition Of Segregated Facilities APR 2015 52.222-26 Equal Opportunity SEP 2016 52.222-27 Affirmative Action Compliance Requirements for

Construction

APR 2015

52.222-50 Combating Trafficking in Persons OCT 2020 52.222-55 Minimum Wages Under Executive Order 13658 NOV 2020 52.222-62 Paid Sick Leave Under Executive Order 13706 JAN 2017 52.223-2 Affirmative Procurement of Biobased Products Under Service and Construction Contracts

SEP 2013

52.223-5 Pollution Prevention and Right-to-Know Information MAY 2011 52.223-6 Drug-Free Workplace MAY 2001 52.223-17 Affirmative Procurement of EPA-Designated Items in Service and Construction Contracts

AUG 2018

52.223-18 Encouraging Contractor Policies To Ban Text Messaging While Driving

JUN 2020

52.223-19 Compliance with Environmental Management Systems MAY 2011 52.227-4 Patent Indemnity-Construction Contracts DEC 2007 52.227-4 Patent Indemnity-Construction Contracts DEC 2007 52.228-2 Additional Bond Security OCT 1997 52.228-11 (Dev) Individual Surety--Pledge of Assets (DEVIATION 2020-

O0016)

FEB 2021

52.228-13 Alternative Payment Protections JUL 2000 52.232-5 Payments under Fixed-Price Construction Contracts MAY 2014 52.232-23 Assignment Of Claims MAY 2014 52.232-27 Prompt Payment for Construction Contracts JAN 2017 52.232-33 Payment by Electronic Funds Transfer--System for Award

Management

OCT 2018

52.232-39 Unenforceability of Unauthorized Obligations JUN 2013 52.232-40 Providing Accelerated Payments to Small Business

Subcontractors

DEC 2013

52.233-1 Disputes MAY 2014 52.233-3 Protest After Award AUG 1996 52.233-4 Applicable Law for Breach of Contract Claim OCT 2004 52.236-2 Differing Site Conditions APR 1984 52.236-3 Site Investigation and Conditions Affecting the Work APR 1984 52.236-5 Material and Workmanship APR 1984 52.236-6 Superintendence by the Contractor APR 1984 52.236-7 Permits and Responsibilities NOV 1991 52.236-8 Other Contracts APR 1984 52.236-9 Protection of Existing Vegetation, Structures, Equipment, Utilities, and Improvements

APR 1984

52.236-10 Operations and Storage Areas APR 1984 52.236-11 Use and Possession Prior to Completion APR 1984 52.236-12 Cleaning Up APR 1984 52.236-13 Accident Prevention NOV 1991 52.236-14 Availability and Use of Utility Services APR 1984 52.236-26 Preconstruction Conference FEB 1995 52.242-14 Suspension of Work APR 1984 52.243-5 Changes and Changed Conditions APR 1984 52.244-6 Subcontracts for Commercial Items NOV 2020 52.246-12 Inspection of Construction AUG 1996 52.246-21 Warranty of Construction MAR 1994 52.249-1 Termination For Convenience Of The Government (Fixed

Price) (Short Form)

APR 1984

52.249-10 Default (Fixed-Price Construction) APR 1984 52.253-1 Computer Generated Forms JAN 1991 252.203-7000 Requirements Relating to Compensation of Former DoD

Officials

SEP 2011

252.203-7002 Requirement to Inform Employees of Whistleblower Rights SEP 2013 252.204-7000 Disclosure Of Information OCT 2016 252.204-7003 Control Of Government Personnel Work Product APR 1992 252.204-7004 Antiterrorism Awareness Training for Contractors. FEB 2019 252.204-7012 Safeguarding Covered Defense Information and Cyber

Incident Reporting

DEC 2019

252.204-7015 Notice of Authorized Disclosure of Information for Litigation Support

MAY 2016

252.204-7018 Prohibition on the Acquisition of Covered Defense Telecommunications Equipment or Services

JAN 2021

252.215-7013 Supplies and Services Provided by Nontraditional Defense Contractors.

JAN 2018

252.223-7006 Prohibition On Storage, Treatment, and Disposal of Toxic or Hazardous Materials

SEP 2014

252.223-7008 Prohibition of Hexavalent Chromium JUN 2013 252.225-7048 Export-Controlled Items JUN 2013 252.232-7003 Electronic Submission of Payment Requests and Receiving

Reports

DEC 2018

252.232-7010 Levies on Contract Payments DEC 2006 252.232-7017 Accelerating Payments to Small Business Subcontractors--

Prohibition on Fees and Consideration

APR 2020

252.236-7000 Modification Proposals-Price Breakdown DEC 1991 252.243-7001 Pricing Of Contract Modifications DEC 1991 252.247-7023 Transportation of Supplies by Sea FEB 2019

CLAUSES INCORPORATED BY FULL TEXT

52.204-21 BASIC SAFEGUARDING OF COVERED CONTRACTOR INFORMATION SYSTEMS (JUN 2016)

(a) Definitions. As used in this clause--

Covered contractor information system means an information system that is owned or operated by a contractor that processes, stores, or transmits Federal contract information.

Federal contract information means information, not intended for public release, that is provided by or generated for the Government under a contract to develop or deliver a product or service to the Government, but not including information provided by the Government to the public (such as on public Web sites) or simple transactional information, such as necessary to process payments.

Information means any communication or representation of knowledge such as facts, data, or opinions, in any medium or form, including textual, numerical, graphic, cartographic, narrative, or audiovisual (Committee on National Security Systems Instruction (CNSSI) 4009).

Information system means a discrete set of information resources organized for the collection, processing, maintenance, use, sharing, dissemination, or disposition of information (44 U.S.C. 3502).

Safeguarding means measures or controls that are prescribed to protect information systems.

(b) Safeguarding requirements and procedures.

(1) The Contractor shall apply the following basic safeguarding requirements and procedures to protect covered contractor information systems. Requirements and procedures for basic safeguarding of covered contractor information systems shall include, at a minimum, the following security controls:

(i) Limit information system access to authorized users, processes acting on behalf of authorized users, or devices (including other information systems).

(ii) Limit information system access to the types of transactions and functions that authorized users are permitted to execute.

(iii) Verify and control/limit connections to and use of external information systems.

(iv) Control information posted or processed on publicly accessible information systems.

(v) Identify information system users, processes acting on behalf of users, or devices.

(vi) Authenticate (or verify) the identities of those users, processes, or devices, as a prerequisite to allowing access to organizational information systems.

(vii) Sanitize or destroy information system media containing Federal Contract Information before disposal or release for reuse.

(viii) Limit physical access to organizational information systems, equipment, and the respective operating environments to authorized individuals.

(ix) Escort visitors and monitor visitor activity; maintain audit logs of physical access; and control and manage physical access devices.

(x) Monitor, control, and protect organizational communications (i.e., information transmitted or received by organizational information systems) at the external boundaries and key internal boundaries of the information systems.

(xi) Implement subnetworks for publicly accessible system components that are physically or logically separated from internal networks.

(xii) Identify, report, and correct information and information system flaws in a timely manner.

(xiii) Provide protection from malicious code…