PLEASANT HILL LAKE

ROBERT HAWK

36007 STATE ROUTE 715

WARSAW OH 43844

TEL: 419-938-5785 FAX:

W81F8E22075818

REQUEST FOR QUOTATIONS

(THIS IS NOT AN ORDER) 1

PAGE OF PAGES

1. REQUEST NO. 2. DATE ISSUED RATING

W9123722Q0159 24-Aug-2022 5a. ISSUED BY

8. TO: NAME AND ADDRESS, INCLUDING ZIP CODE

IMPORTANT: This is a request for information, and quotations furnished are not offers. If you are unable to quote, please so indicate on this form and return it to the address in Block 5a. This request does not commit the Government to pay any costs incurred in the preparation of the submission of this quotation or to contract for supplies or services. Supplies are of domestic origin unless otherwise indicated by quoter. Any representations and/or certifications attached to this

Request for Quotations must be completed by the quoter.

11. SCHEDULE (Include applicable Federal, State, and local taxes)

ITEM NO.

(a)

SUPPLIES/ SERVICES

(b)

QUANTITY

(c)

UNIT

(d)

UNIT PRICE

(e) (f)

SEE SCHEDULE

AMOUNT

% No. %

NOTE: Additional provisions and representations [ ] are [ ] are not attached.

13. NAME AND ADDRESS OF QUOTER (Street, City, County, State, and ZIP Code)

14. SIGNATURE OF PERSON AUTHORIZED TO

SIGN QUOTATION

15. DATE OF

QUOTATION

16. NAME AND TITLE OF SIGNER (Type or print) (Include area code)

TELEPHONE NO.

AUTHORIZED FOR LOCAL REPRODUCTION STANDARD FORM 18 (REV. 6-95)

PREVIOUS EDITION NOT USABLE Prescribed by GSA FAR (48 CFR) 53.215-1(a)

THIS RFQ X[ ] IS [ ] IS NOT A SMALL BUSINESS SET-ASIDE

6. DELIVER BY (Date)

SEE SCHEDULE

AND/OR DMS REG. 1

UNDER BDSA REG. 2

4. CERT. FOR NAT. DEF.3. REQUISITION/PURCHASE

REQUEST NO.

USACE, CONTRACTING DIVISION

KAREN SIMMONS, 502 8TH STREET

HUNTINGTON WV 25701

9. DESTINATION (Consignee and address, including ZIP Code)

7. DELIVERY

[ ]X FOB

DESTINATION

[ ] OTHER

(See Schedule)

06-Sep-2022(Date)

PLEASE FURNISH QUOTATIONS TO THE ISSUING OFFICE IN BLOCK 5a ON OR BEFORE CLOSE OF BUSINESS:10.

217.373.4569JEFFERY W MORTON

(Name and Telephone no.) (No collect calls)5b. FOR INFORMATION CALL:

d. CALENDAR DAYSc. 30 CALENDAR DAYSb. 20 CALENDAR DAYS12. DISCOUNT FOR PROMPT PAYMENT a. 10 CALENDAR DAYS

W9123722Q0159

Section B - Supplies or Services and Prices

INSTRUCTIONS TO OFFERORS

INSTRUCTION TO OFFERORS

SITE VISITS ARE HIGHLY RECOMMENDED PRIOR TO PROVIDING A

QUOTE. SEE CLAUSE 52.236-27 FOR ADDITIONAL INFORMATION.

PLEASE DIRECT ALL QUESTIONS TO JEFF MORTON AT (304) 399-5888 or jeffery.w.morton@usace.army.mil. ANY INFORMATION RECEIVED AT THE

SITE VISIT WHICH CONFLICTS WITH THIS SOLICITATION SHOULD BE

BROUGHT TO THE ATTENTION OF MR. MORTON. THE SOLICITATION

AND RESULTING CONTRACT SHALL BE THE GOVERNING DOCUMENT IN

ALL CASES.

QUOTES CAN ONLY BE E-MAILED TO JEFF MORTON AT jeffery.w.morton@usace.army.mil by the date referenced on page one of the SF18.

Per FAR 36.204 the estimated price range for this project is between $25,000 and $100,000.

NOTE: Award will be made to the lowest price offeror who meets the technical requirements of the solicitation and is deemed responsible by the contracting officer.

The intent is to award without discussions.

NOTE: this procurement is 100% Total Set-Aside for Small Business. For more information see FAR Clause 52.219-6.

QUOTATION INSTRUCTIONS (Provide the following with your quote):

Company Name and Address:

Phone Number: Fax Number:

Email Address:

Business Size (select all that apply):

Large Business Small Business HUBZone Business 8A

Woman-Owned Service-Disabled Veteran-Owned

If subcontractor will be used for this work, please provide company name and credentials/qualifications:

IMPORTANT NOTICE: Effective September 26, 2018 and in accordance with FAR Clause 52.204- 7, “an Offeror is required to be registered in SAM when submitting an offer or quotation, and shall continue to be registered until time of award, during performance, and through final payment of any contract, basic agreement, basic ordering agreement, or blanket purchasing agreement resulting from this solicitation.” Vendors are highly encouraged to check their registration status and plan accordingly prior to submitting an offer.

Please note, as of April 2018, GSA's System for Award Management (SAM) system is requiring new registrations and renewals of existing registrations to submit an original signed notarized letter identifying the authorized Entity Administrator. Vendors are encouraged to check their entity's status in SAM.gov and plan accordingly. If the prospective contractor is not registered in the SAM database, the Contracting Officer will following the procedures at FAR 4.1103. Contact the supporting Federal Service Desk at www.fsd.gov, or by telephone at 866- 606-8220 (toll free) or 334-206-7828 (internationally) Monday through Friday from 8 a.m. to 8 p.m. (EDT), for FREE assistance.

Contractor is registered with SAM:

YES NO (See FAR 52.204-7)

Provide business Unique Entity Identifier number:

(phone 800-333-0505 for Unique Entity Identifier number).

Provide business CAGE code:

Provide Tax Identification Number:

All work under this contract shall be in performance with all local, state, and federal laws, regulations, and codes.

Only the awarded contractor shall provide a copy of their insurance certificate required by State and Local Governments that has been acquired for the time period covered under this contract to the Contracting Officer within 10 business days after award. No further insurance requirements will be imposed by the Corps of Engineers for this contract.

Contractors are not required to submit an Accident Prevention Plan (APP) with their quote.

The successful offeror will be required to submit this document upon award. The APP must be accepted by the Government Designated Authority prior to the preconstruction conference. The contractor that receives this award will have 10 calendar days to provide an Accident Prevention Plan (APP). If this deadline is not met, the contractor will be given a cure notice stating that they will have 10 calendar days to submit an APP, otherwise the contract may be terminated for default.

Only the awarded contractor shall is required to submit back FAR Clause 52.204-24 with signed award. Please answer the two questions that are within the clause by placing an X in the box for does or does not OR will or will not, whichever applies to you as the contractor.

Please submit back within 10 business days after award.

PRICE BREAKOUT SCHEDULE

Line Item No. Description of Requirement Qty/Unit of Measure Extended Price

0001 Reimbursement of actual cost of payment bond for quotes in excess of $35,000.00

JOB $__________

0002 Mobilization & de-mobilization of equipment required in accordance with the attached Scope of Work.

0003 Labor required for Compound Fence installation in accordance with the attached Scope of Work.

0004 Supplies, materials, and equipment Required for Compound fence installation in Accordance with the attached Scope of Work.

Quote Total $__________

ITEM NO SUPPLIES/SERVICES QUANTITY UNIT UNIT PRICE AMOUNT

0001 1 Job

INSTALLATION OF NEW COMPOUND FENCE

FFP

Contractor shall supply all materials, labor, and supervision required to complete the Installation of a new compound fence and gates at North Branch of Kokosing with the attached Scope of Work.

FOB: Destination

MILSTRIP: W81F8E22075818

PURCHASE REQUEST NUMBER: W81F8E22075818

PSC CD: Y1PZ

NET AMT

Section C - Descriptions and Specifications

STATEMENT OF WORK

SCOPE OF WORK

INSTALL NEW CHAIN LINK COMPOUND FENCE

AROUND MAINTENANCE BUILDING AREA

North Branch of Kokosing Dam 18350 Waterford Rd, Fredericktown, OH 43019

PH:419-938-5785

DESIGNATED AREA:

US Army Corps is requiring the installation of Security Fencing with 2 sliding canter lever gates with one automatic opener with pedestal and pressure sensor, around the North Branch of Kokosing Dam Maintenance Building Area.

GENERAL CONDITIONS:

Contractor shall furnish all necessary labor, material, equipment, permits and insurance to complete the following operations in a first-class workmanlike manner. Prices shall include equipment mobilization & de-mobilization, fuel, labor, all materials and equipment to complete the job.

GENERAL INSTALLATION:

The contractor shall provide all labor and materials necessary to furnish and install a compound 140 feet by 170 feet around the maintenance building and parking area. The chain link fence shall be 8 feet in height with a barbed wire cap. Two 8-foot cantilever gates, 24-feet wide opening with canter lever, shall be installed as indicated on the attached sketch. One automatic gate opener system with pedestal and pressure sensor, sized for gate, shall be installed on the indicated gate with a pedestal mount pin entry system for entry and pressure sensor system for exiting compound. Gate opener shall be wired to existing building electrical panel per manufacture and NEC requirements as required. Fence shall have proper grounding as required by NEC Code. All material provided in the performance of this contract shall be unused and meet the requirements of the specifications. After new fence is installed, the old fence and posts shall be removed and disposed of in accordance with local, state, and federal laws.

The old post sections shall be filled with fill material to ground height. The old slide gate and gate posts shall be removed and be kept at North Branch of Kokosing. See Exhibit 1 and Exhibit 2 for Detail.

REQUIRED SUBMITTALS:

The Contractor shall furnish a drawing showing proposed layout of fence to show proposed alignment of fence and location of all line posts, terminal posts, gates and other details necessary to confirm that the proposed layout is acceptable and meets the requirements of the specifications. The Contractor shall provide Operating and Maintenance Instructions along with a Manufacturers Recommendation for Scheduled Maintenance and tasks.

MATERIAL STORAGE and HANDLING Materials delivered to site shall be in an undamaged condition. Materials shall be stored off the ground to provide protection against oxidation caused by ground contact.

FENCE FABRIC

Provide ASTM A392, Class 1, zinc-coated steel wire with minimum coating weight of 1.2 ounces of zinc per square meter foot of coated surface. Fabricate fence fabric of 9-gauge wire woven in 2-inch mesh conforming to ASTM A116. Set fabric height of 8 feet. Fabric shall be twisted and barbed on the top selvage and knuckled on the bottom selvage. Secure fabric to posts using stretcher bars or ties spaced 15 inches on center, or by integrally weaving to integral fastening loops of end, corner, pull, and gate posts for full length of each post. Install fabric on opposite side of posts from area being secured.

POSTS

Provide Class 1 steel pipe grade A high strength grade 50,000 psi or equivalent pipe conforming to ASTM F 1083 (schedule 40 standard weight) meets or exceeds the requirements for grade A. Steel pipe other than ASTM F 1083 (schedule 40 standard weight) shall meet the outsides dimensions and minimum wall thickness required and shall have minimum yield strength of 50,000 psi. Grade A pipe shall be hot-dipped zinc coated inside and out with an average weight of not less than 1.8 ounces of zinc per square foot of coated surface area. Provide sizes as shown on the drawings. Line posts selected shall be of the same designation throughout the fence. Terminal posts (corner, gate, and pull) selected shall be of the same designation throughout the fence design. Provide gate posts for the gate type specified subject to the limitation specified in ASTM F900 and/or ASTM F1184. Post spacing shall conform to the recommended guidelines as set forth in the CLFMI "Wind Load Guide for the Selection of Line Post Spacing and Size" unless specified to exceed those guidelines.

FS RR-F-191/3 line posts; Class 1, steel pipe, Grade A. End, corner, and pull posts; Class 1, steel pipe, Grade A.

ACCESSORIES

Provide accessories conforming to ASTM F626. Ferrous accessories shall be zinc or coated. Furnish truss rods for each terminal post. Provide truss rods with turnbuckles or other equivalent provisions for adjustment. Provide Barbed wire supporting arms of the single 45 degree (Line Post) and Single 35 Degree (Corner Post) outward angle 3-strand arm type and of the design required for the post furnished. Secure arms by top rail and pin riveted in place.

Provide 9-gauge steel tie wire for attaching fabric to rails, braces, and posts and match the coating of the fence fabric. Tie wires for attaching fabric to tension wire on high security fences shall be 16 gage stainless steel.

Miscellaneous hardware coatings shall conform to ASTM A153/A153M unless modified.

BRACES AND RAILS

ASTM F1083, zinc-coated, Group IA, steel pipe, size NPS 1-5/8(1.660). Braces and rails shall be Group 1A, steel pipe, and size NPS 1-5/8 (1.660). Top rail lengths shall be fitted with 6-inch connectors of the same material as the rail or shall have a 3-inch-long swage on one end for connecting into a continuous run. Suitable fittings shall be provided for securing top rail to each gate, corner, and end posts. Braces shall be provided for gate posts and each terminal post when a top rail is not used. Braces shall be furnished with or without top rail. Braces extending to line post shall be connected back to the base of the brace post by a 5/16-inch minimum outside diameter truss rod and tightener.

BARBED WIRE

Barbed wire shall consist of three 12-1/2-gage twisted line wires with 14-gage round barbs as listed in ASTM A121, Design Number 12-4-5-14R. Barbed wire shall be zinc-coated steel per ASTM F166. All barbs shall consist of four points and spacing of barbs shall be at 5-inch (+1-inch) centers. Zinc-coated steel barbed wire shall have a zinc coating of at least 0.80 ounces per square foot of coated surface area

CONCRETE

ASTM C94/C94M, 3/4-inch maximum size aggregate, and having minimum compressive strength of 3000 psi at 28 days. Grout shall consist of one part Portland cement to three parts clean, well-graded sand and the minimum amount of water to produce a workable mix.

CANTILEVER GATE ASSEMBLY

Provide gate assembly of the same material as the posts. Cantilever gate frames shall consist of 2-1/2" O.D.

horizontal rails, 2" O.D. vertical bracing, and 1-5/8" diagonal bracing; all shall be welded and galvanized for the longest lasting gate. Gates fabric shall be fully stretched, including counterbalance so they do not require modification to automate in the future. Gate fabric shall be as specified for chain link fabric. Gates shall have locking latch mechanisms for keyed locks. Cantilever gate opening shall be open and have no height restrictions when open. See Exhibit 3 Example.

CANTILEVER GATE POST FOOTER

Cantilever post footings shall be sized accordingly for the Cantilever gate by size and weight. The post hole shall be “bell shaped” with the widest point at the bottom of the hole and the concrete level shall be 4” below grade.

CANTILEVER GATE HARDWARE and ACCESSORIES Furnish and install latches, hinges, stops, keepers, rollers, and other hardware items as required for the operation of the gate. Arrange latches for padlocking so that the padlock will be accessible from both sides of the gate. Provide stops for holding the gates in the open position. Each end member of gate frames shall be extended sufficiently above the top member to carry three strands of barbed wire in horizontal alignment with barbed wire strands on the fence.

FENCE INSTALLATION

Perform complete installation conforming to ASTM F567.

LINE and GRADE Install fence to the lines and grades indicated on submitted plan. Space line posts equidistant at intervals not exceeding 10 feet. Terminal (corner, gate, and pull) posts shall be set at abrupt changes in vertical and horizontal alignment. Provide fabric continuous between terminal posts; however, runs between terminal posts shall not exceed 500 feet. Repair any damage to galvanized surfaces, including welding, with paint containing zinc dust in accordance with ASTM A780/A780M.

EXCAVATION

Clear all post holes of loose material. Spread waste material where directed. Eliminate ground surface irregularities along the fence line to the extent necessary to maintain a minimum 1.5 inch and 2.5 maximum clearance between the bottom of the fabric and finish grade.

POST INSTALLATION

Set posts plumb and in alignment. Except where solid rock is encountered, set posts in concrete to the depth of 40 inches. Where solid rock is encountered with no overburden, set posts to a minimum depth of 18 inches in rock.

Where solid rock is covered with an overburden of soil or loose rock, set posts to the minimum depth indicated on the drawing unless a penetration of 18 inches in solid rock is achieved before reaching the indicated depth, in which case terminate depth of penetration. Grout all portions of posts set in rock.

Portions of posts not set in rock shall be set in concrete from the rock to 2 inches below ground level. Posts set in concrete shall be set in holes not less than the diameter shown on the drawings. Make diameters of holes in solid rock at least 1 inch greater than the largest cross section of the post. Thoroughly consolidate concrete and grout around each post, free of voids and finished to form a dome. Allow concrete and grout to cure for 72 hours prior to attachment of any item to the posts.

Test fence post rigidity by applying a 50-pound force on the post, perpendicular to the fabric, at 5 feet above ground.

Post movement measured at the point where the force is applied shall be less than or equal to 3/4 inch from the relaxed position. Test every tenth post for rigidity. When a post fails this test, make further tests on the next four posts on either side of the failed post. All failed posts shall be removed, replaced, and retested at the Contractor's expense.

RAILS, TENSION WIRE and TENSION BANDS Ends for top rail and braces shall be provided when top rail or braces are required. Top rail and brace ends shall be press steel, malleable casting in accordance with ASTM F626. Top rail sleeves shall allow for expansion and contraction of the top rail. Top rail sleeves shall have a minimum length of 6 inches and be of the same material as the top rail. Top rails provided with 3-inch swage ends are acceptable in lieu of top rail sleeves. Brace bands shall be used to secure top rail and brace ends to terminal posts. When tension bars are used, tension bands shall be used for securing chain-link fabric at each terminal post (see 3.4.6). Spacing of tension bands on posts shall be at 15-inch intervals or less. Brace and tension bands shall be steel and shall be 3/4-inch wide by 1/10-inch-thick nominal.

Tension bars for 2-inch mesh shall be no less than 3/16 by 3/4-inch or equivalent cross-sectional area. A tension bar shall be provided where chain-link fabric meets terminal posts. Tension bar shall be steel, of a continuous length compatible with the height of the fence and shall be threaded through the fabric and attached to the post by tension bands. Bottom Tensioner wire shall be interwoven along the bottom row of fabric diamonds. Tension wire shall be zinc coated steel in accordance with ASTM A824. Tension wire shall be manufactured with 7 gage steel wire size.

Steel tension wire shall be marcelled hard tempered carbon steel wire. The tension wire shall have a minimum tensile strength of 75,000 pounds per square inch. Zinc coated steel shall not have less than 1.2 ounces of zinc per square foot of coated surface area. Truss rods shall be steel and have a minimum diameter of 5/16-inch.

FABRIC INSTALLATION

Install chain link fabric on the side of the post indicated. Attach fabric to terminal posts with stretcher bars and tension bands. Space bands at approximately 15-inch intervals. Install fabric and pull taut to provide a smooth and uniform appearance free from sag, without permanently distorting the fabric diamond or reducing the fabric height.

Fasten fabric to line posts at approximately 15-inch intervals and fastened to all rails and tension wires at approximately 24-inch intervals.

Cut fabric by untwisting and removing pickets. Accomplish splicing by weaving a single picket into the ends of the rolls to be joined. The bottom of the installed fabric shall be 2-inch plus or minus 1/2 inch above the ground.

After the fabric installation is complete, exercise the fabric by applying a 50 pound push-pull force at the center of the fabric between posts; the use of a 30 pound pull at the center of the panel shall cause fabric deflection of not more than 2.5 inches when pulling fabric from the post side of the fence; every second fence panel shall meet this requirement; re-secure and retest all failed panels at the Contractor's expense.

SUPPORTING ARMS

Install barbed wire supporting arms and barbed wire as indicated on the drawings and as recommended by the manufacturer. Anchor supporting arms to the posts in a manner to prevent easy removal with hand tools 3/8-inch diameter plain pin rivets or, at the Contractor's option. Studs driven by an explosive-actuated tool shall not be used with gray iron or other material that can be fractured. Pull barbed wire taut and attach to the arms with clips or other means that will prevent easy removal.

GATE INSTALLATION

Install gates at the locations shown. Mount gates to swing as indicated. Install latches, stops, and keepers as required. Install Slide gates as recommended by the manufacturer.

Weld or otherwise secure hinge pins, and hardware assembly to prevent removal.

Submit 1 copies of operating and maintenance instructions. Operating instructions shall outline the step-by-step procedures required for system maintenance schedule. Include the manufacturer's name, model number, service manual, parts list, and brief description of all equipment and their basic operating features. Include in the maintenance instructions routine maintenance procedures, possible breakdowns and repairs, and troubleshooting guide. Also include the general gate layout and equipment layout of the system as installed.

GROUNDING

Ground fencing as indicated on drawings.

Ground fences on each side of both gates, at each corner, at the closest approach to each building located within 50 feet of the fence. Grounding locations shall not exceed 650 feet. Bond each sliding gate with a flexible bond strap to its gate post as to allow the gate to open and close freely.

Provide ground conductor consisting of No. 8 AWG solid copper wire. Grounding electrodes shall be 3/4 inch by 10 foot long copper-clad steel rod. Drive electrodes into the earth so that the top of the electrode is at least 6 inches below the grade. Where driving is impracticable, electrodes shall be buried a minimum of 12 inches deep and radially from the fence. The top of the electrode shall not be less than 2 feet or more than 8 feet from the fence.

Clamp ground conductor to the fence and electrodes with bronze grounding clamps to create electrical continuity between fence posts, fence fabric, and ground rods. Total resistance of the fence to ground shall not be greater than 25 ohms.

CLEANUP

Remove waste fencing materials and other debris from the work site each workday.

PROTECTION OF UTILITIES

The Contractor shall contact OUPS to locate and clearly identify all underground and above ground utility lines, wires, cables, pipes, poles, support lines, and culverts, within the Contractor's work area. The Contractor shall contact the Ohio Utilities Protection Services (800) 362-2764 at least three days prior and no more than 10 working days to beginning any Construction activity. The Contractor shall be responsible for any costs associated with calls to OUPS. The Contractor shall conduct his operations such that the utilities are not damaged or disturbed. Any damage to utilities caused by the Contractor's actions shall be repaired by him at no additional expense to the Government.

REMOVAL OF OLD FENCE AND GATE COMPONENTS

The contractor shall remove he old fence after completion of the new fence. The fence and the posts shall be removed and disposed off site in accordance with local, state, and federal laws The sliding gate, man gate, and associated gate posts shall be removed and left at the North Branch site. The intention of the government is to utilize these components at a nearby project. These items are to be intact and undamaged after removal and stored at North Branch of Kokosing. All removed post holes shall be filled with 304 gravel material to grade.

PROTECTION OF GOVERNMENT PROPERTY

The contractor shall protect all government property during the performance of this contract. All damage to existing government property as a result of the contractors work shall be repaired or replaced to the satisfaction of the Contracting Officer. Work areas shall be cleaned by the contractor after construction is complete. All areas adjacent to the fence line that have been rutted shall be re-graded and smoothed. The Government will re-seed and straw these areas.

All Measurements provided are approximations to assist Contractors in preparing their quotes, Contractors are strongly encouraged to visit the site to take/confirm measurements of the fence area.

ACCESS and SECURITY TO WORK LOCATION:

Access to the work location shall be through the outflow access road of the facility.

Security measures and project security shall be maintained at all time during the construction process. At the end of the work day all secured areas shall be able to be securely shut and locked.

All work shall be completed by competent and qualified tradesman, in strict accordance with the plans and specifications in a thorough and workmanlike manner.

HOURS OF OPERATION

Working Hours: 0730-1530 hours Monday through Friday. Work may continue outside these times only with permission from the onsite government representative or Facility Manager. All work shall be performed during daylight hours. Delay of work may occur during excessive rainfall or wet periods due to access to the site.

PERIOD OF PERFORMANCE: Contractor shall start work within 30 calendar days of issuance of Notice to Proceed (NTP) and complete all work within 45 calendar days from commencement of work.

FEDERAL HOLIDAY

When one of the designated holidays falls on a Sunday the following Monday is observed as a legal holiday. When a legal holiday falls on a Saturday, the preceding Friday is observed as a holiday. Work that interferes with other ongoing functions at the project shall be scheduled around normal working hours to be approved by Project Manager.

Work shall be scheduled around the above listed Federal holidays unless approved in advance.

Ten Federal holidays observed are as follows:

New Year’s Day (January 1st) Martin Luther King Day (3rd Monday in January) President’s Day (3rd Monday in February) Memorial Day (Last Monday in May) Juneteenth Day (June 19th) Independence Day (July 4th) Labor Day (1st Monday in September) Columbus Day (2nd Monday in October) Veterans Day (November) Thanks Giving (November 24th) Christmas Day (December 25th)

SITE VISIT

Offerors are encouraged to make a site visit by contacting:

US Army Corp of Engineers North Branch Kokosing Dam 18350 Waterford Rd Fredericktown, OH 43019 POC: Johnny Grace Phone: 419-938-5785

CONTRACTOR INVOICE

Contractor shall submit their invoice to:

Walhonding Area Office Robert Hawk Walhonding Facility Manager 36007 State Route 715 Warsaw, Ohio 43812 Phone: 740-824-4343

SECURITY REQUIREMENTS

All Contractors and subcontractor employee(s) working on this contract who require access in and/or around any Huntington District facilities shall receive authorization to be on site at these facilities based upon a favorable background investigation in accordance with “Homeland Security Presidential Directive 12: Policy for a Common Identification Standard for Federal Employees and Contractors” (HSPD 12). The Huntington District Security Management Office shall submit contractor(s) personal information to complete the basic background investigation in order to make a recommendation to the Contracting Office of an employee’s suitability for work on Government property. The Procuring Contracting Officer (PCO) has the right to deny any contractor or subcontractor employee from working on the contract based upon the results of the background investigation provided by the Huntington District Security Management Office. The Government, Contractor, and subcontractors shall not permit any employee(s) access to drawings, blueprints, records, photos, sites, or projects until the Huntington District Security Management Office has completed an Operations Security (OPSEC) review of such items and determined they can be released.

FOR CONTRACTS LESS THAN 1 YEAR DURATION/OPTION TO EXTEND CONTRACTS:

Contractors shall submit a complete investigation packet for each contractor and subcontractor employee to the Huntington District Security Management office within 10 working days after award of any contract, or prior to the individual being permitted unescorted access in or on District facilities.

The Contractor must also provide the following: (1) Name of the Contract Specialist with whom he/she is working,

(2) Project Name, (3) Contract Number (4) Task Order Number when applicable, and (5) Security Information sheet on each employee working on site must be submitted directly to the Huntington District Security Office.

The Contractor must provide a full legal name, complete SSN#, Date of Birth, Place of Birth (City and State) and Driver’s license number if available. It is the Contractor’s responsibility to ensure the above information is accurate and legible, otherwise delays may occur.

Contractors shall have background checks completed for their employees annually in the case of Contracts with option periods. For instance, if the employee was cleared in May of 2018, they shall be cleared again in May of 2019. It is the Contractor’s responsibility to ensure that each employee’s security is up to date. Failure to comply may lead to possible removal from the project/jobsite.

The Contractor must ensure if new employees are brought in to work on an existing Contract with the U.S. Army Corps of Engineers (USACE), they must process the employee through the Huntington District USACE Security Management Office for background purposes.

FOR CONTRACTS IN EXCESS OF 1 YEAR DURATION, THE DOCUMENTS LISTED BELOW ARE

REQUIRED:

The documents listed below are required:

SF 85, Questionnaire for Non-Sensitive Positions (see http://www.opm.gov/forms/ to print form). FD 258, Contractor Fingerprint Card (one card for digital prints, two for ink prints) (NOTE: a trained/qualified individual must take prints, ORI block on the FD 258 must be USOPM000Z) (Contractor Fingerprint Cards (FD-258) may be obtained by Contracting Division by contacting the Huntington District Security Management Office).

Contractor shall report any changes in personnel, or at any time conditions change at least 5 working days prior to individual(s) need to have access to the site. The Contractor shall provide the same information as listed above for all new employees.

Following submission of paperwork, the Huntington District Security Management Office will conduct an initial criminal check based upon the information provided. If there are no issues, the Huntington District Security Management Office will make recommendations to the PCO or their Designated Representative. The Huntington District Security Management Office cannot give approval due to unfavorable report(s). The Huntington District Security Management Office shall coordinate with Office of Counsel and will jointly make recommendations to the PCO and/or the Designated Representative should a background investigation come back with derogatory information. The PCO will make the determination whether to allow the Contractor personnel to work on the site based on Security and Office of Counsel recommendations, and the PCO will advise the Contractor of the decision.

FOREIGN NATIONALS

The Contractor shall provide the package listed above, as well as additional materials noted below for all Foreign Nationals. The Contractor is to expect additional time in the approval process for all Foreign Nationals due to the level of review and elevation of the review to Headquarters staff to complete. All Foreign Nationals must comply with the following paragraph:

In accordance with Engineering Regulation 380-1-18, “Technology Transfer, Disclosure of Information and Contacts with Foreign Representatives” dated 1 August 1996, Section 4, all foreign nationals who work on Corps of Engineers’ contracts shall be approved by the Headquarters US Army Corps of Engineers (HQ USACE) Foreign Disclosure Officer before beginning work on this contract; this regulation includes subcontractor employees. The Contractor shall submit to the Security Management Office, the names of all foreign nationals proposed for performance under this contract, along with documentation to verify legal admittance into the United States. Such documentation shall include at least one of the following: a U.S. passport, Certificate of U.S. Citizenship (INS Form N-560 or N-561), Certificate of Naturalization (INS Form N-550 or N-570), Alien Registration Card with photograph (INS Form I-151 or I-551), Employment Authorization Card (INS Form I-688A), etc.

In order to assure forms are properly completed, and to minimize time delays, the Contractor is encouraged to work closely with the Huntington District Security Management Office. The Government will return for correction incomplete forms, illegible forms, etc. which will delay the contractor / subcontractor from beginning work.

Security requirements are subject to change in accordance with HSPD-12, Office of Personnel Management, regulation or policy changes, etc. The Government shall add any changes to security requirements by modification to the contract.

The Contractor shall contact the Huntington District Security Management Office by phone, letter, or email at the following numbers/addresses:

CELRH-SM

502 Eighth Street Huntington, WV 25701

Stephen R. Curry, phone (304) 399-5695; email stephen.r.curry@usace.army.mil Matthew D. Green, phone (304) 399-5294; email matthew.d.green@usace.army.mil Sandra L. Hardwick, phone (304) 399-5612; email sandra.l.hardwick@usace.army.mil

AT/OPSEC REQUIREMENTS

General security requirements and guidance: The security requirements described below apply to all contract personnel (including employees of the prime Contractor (“Contractor”) and all subcontractor employees) supporting the performance requirements of this contract. The Contractor is responsible for compliance with these security requirements. Questions regarding security matters shall be addressed to the designated Government representative (e.g., Contracting Officer Representative (COR), Requiring Activity (RA) representative, or Contracting Officer (if a COR or other RA representative is not appointed)). Contract personnel are critical to the overall security and safety of US Army Corps of Engineers (USACE) installations, facilities and activities, and security awareness training contributes to those efforts. The Department of Defense (DoD) and Army security training requirements specified below, if applicable, are performance requirements; all applicable contract personnel shall complete initial training within 30 days of contract award or the date new contract personnel begin performance on the contract. Within five business days from the completion of training, the Contractor shall provide written documentation (e.g., email or memorandum) to the Government representative. The documentation shall include the names of contract personnel trained and which training they completed; the Contractor shall maintain training records as part of their contract files and be prepared to provide copies of training certificates to the Government representative. Contractor personnel and vehicles are subject to search when entering federal installations. Additionally, all contract personnel shall comply with Force Protection Condition (FPCON) measures, Random Antiterrorism Measures (commonly referred to as “RAMs”), and Health Protection Condition (HPCON) measures. The Contractor is responsible for meeting performance requirements during elevated FPCON and/or HPCON levels in accordance with applicable RA plans and procedures --this includes identifying mission essential and non-mission essential personnel. In addition to the changes otherwise authorized by the changes clause of this contract, should the FPCON or HPCON levels at any individual facility or installation change, the Government may implement security changes that affect contract personnel. The Contractor shall ensure all contract personnel are aware of their security responsibilities, including any site-specific requirements identified in local policies or procedures.

Suspicious Activity Reporting training (e.g. iWATCH, CorpsWatch, or See Something, Say Something): All contract personnel shall receive initial and annual refresher training from the RA representative on the local suspicious activity reporting program. This locally developed training provides contract personnel with general information on suspicious behavior, and guidance on reporting suspicious activity to the project manager, security representative or law enforcement entity.

Pre-screen candidates using E-Verify Program: Contractors shall comply with the requirements set forth in FAR clause 52.222-54 Employment Eligibility Verification and FAR Subpart 22.18 in using the E-Verify Program at (https://www.e-verify.gov/) (website subject to change) to meet the contract employment eligibility requirements.

Contractors are encouraged to cooperate with Federal and State agencies responsible for enforcing labor requirements to include eligibility for employment under United States immigration laws in accordance with FAR 22.102-1(i). An initial list of verified/ eligible candidates shall be provided to the COR no later than three business days after the initial contract award. When contracts are with individuals, the individuals will be

Contractor Accident Prevention Plan (APP).

A. General. Contractor shall comply with all Federal, State and Local safety requirements including those specified by the Occupational Safety and Health Act (OSHA) in 29 CRF 1910 General Industry Standard, 1926 Construction Standard and the U.S. Army Corps of Engineers Safety & Health Requirements Manual EM 385-1-1 as currently revised. Where a conflict exists between safety standards/requirements the contractor shall comply with the more stringent requirement. If the Contractor fails or refuses to promptly comply with safety requirements as specified herein, any project employee may stop all or part of the work until satisfactory corrective action has been taken. No part of the time lost due to any such work stoppage shall be made subject to any claims for extension of time or for excess costs or damages sustained by the Contractor. Also, the Contractor will not be paid for work not performed as a result of the stop order.

B. Contractor Accident Prevention Plan (APP). The Contractor shall prepare a site-specific Accident Prevention Plan following the outline provided in EM 385-1-1, Appendix A as a minimum. The contractor shall address each element and sub-element in the outline in the order they appear in Appendix A. Any item from the outline that does not apply must be listed, in its assigned place and a brief explanation of the reason it is not required provided. The APP shall address any unusual or unique aspects of the project or activity. This plan must be accepted by the Contracting Officer prior to commencement of any work. Contractors are encouraged to contact the USACE Safety & Occupational Health Office for questions or information regarding the development of contract Accident Prevention Plans. Office hours are Monday through Friday 8:00 AM to 3:00 PM at (304)399- 5032/5326/6961.

The web address for EM 385-1-1 is:

http://www.publications.usace.army.mil/Portals/76/Publications/EngineerManuals/EM_385-1-1.pdf

(1) The contractor shall have on site an employee designated as a Site Safety and Health Officer (SSHO) who has completed the OSHA 30-hour Construction Safety training or its equivalent as specified in EM 385-1-1, 01.A.17 and has at least five years safety management experience relative to the work to be performed. No work will be permitted unless the SSHO is present at the work site. Work crews of two or more must have two people holding current certification in First Aid and CPR from the American Red Cross, American Heart Association or a licensed physician.

Training must include a hands-on component that cannot be taken online and the contractor must maintain appropriate First Aid kit on site. Single individuals working alone must have current certification in First Aid as a minimum.

(2) All work that potentially exposes the worker to falls of six feet or more will require the contractor to submit a Site Specific Fall Protection & Prevention Plan in accordance with EM 385-1-1, Section 21.D.

(3) Cranes and hoisting equipment shall be operated only by qualified personnel (operators licensing, physical and drug testing in accordance with EM 385-1-1 Section 16.B). Note: CDL Medical Clearance is not acceptable. Please see attached medical clearance requirements.

(4) Effective November 8, 2010 all “Signalpersons” and “Riggers” shall be qualified. This is a mandatory requirement in accordance with 29 CFR 1926.1400 Regulations. Riggers must be a qualified person for the performance of specified hoisting activities such as during assembly/disassembly, in accordance with OSHA 1926.1404(r)(1) and 1926.1425(c)(3).

(5) Work orders involving potential exposure to Hazardous, Toxic or Radiological Waste shall require development of Site Specific Safety and Health Plan (SSHP) by qualified personnel as specified in EM 385-1-1 Sections 6 and 33.

C. Risk Management Process. The Contractor shall utilize risk management tools such as Activity Hazard Analysis (AHA), Job Hazard Analyses (JSAs) or similar tools to identify, assess, prioritize risks and develop controls to minimize, monitor and control the probability and/or impact of unfortunate events to an acceptable level.

Within each major phase, all activities, tasks or Definable Features of Work (DFOWs) shall be identified that will require an AHA/JSA. For each work activity, task or DFOW contractor shall prepare the initial AHA/JSA. A Risk Assessment Code (RAC) is assigned to each step, to the risk that remains after controls have been applied (residual risk) a final RAC (cannot be lower than the highest step RAC) shall be assigned. See EM 385-1-1 Section 01.A.14.b. for further guidance or contact the SOHO for assistance. The AHA/JSA shall be reviewed and accepted by the proper authority in order to proceed with the activity. All on-site employees shall review the accepted AHA/JSA prior to performing work and during weekly and “Tool Box” safety meetings as appropriate.

(1) AHA/JSA shall define the activities being performed and identify the work sequences, the specific anticipated hazards, site conditions, equipment, materials, and the control measures to be implemented to eliminate or reduce each hazard to an acceptable level of risk. AHA/JSA should indicate compliance with EM 385-1-1 personal protective equipment requirements (safety-toed work boots, safety glasses, gloves, hard hats, etc.), work crews of two or more must have two people currently qualified in first aid and CPR and the appropriate first aid kit on site. Single individuals working alone must have current certification in First Aid only.

(2) The names of the Competent Person(s) and Qualified Person(s) required for a particular activity (e.g., excavation, scaffolding, fall protection, or other activities as specified by OSHA and this manual) shall be identified and included in the AHA, as well as proof of their competency/qualification.

D. Accident/Mishap Reporting. The Contractor shall report all recordable mishaps to the GDA within 24-hours in accordance with EM 385-1-1 Section 01.D. Accidents shall be investigated to determine causal factors and corrective actions shall be implemented. Accidents resulting in: days away injuries, days away illnesses, restricted/transfer injuries, property damage of $5,000.00 or more shall be investigated and reported to the GDA using the USACE Accident Investigation Report Form ENG 3394 within 24 hours of the occurrence.

(1) Immediate notification to the GDA is required for all serious accidents:

a. Fatal Injury/illness;

b. Permanent totally disabling injury/illness;

c. Permanent partial disabling injury/illness;

d. One (1) or more persons hospitalized as inpatients as a result of a single occurrence;

e. $500,000 or greater accidental property damage;

f. Three (3) or more individuals become ill or have a medical condition suspected to be related to a site condition, or a hazardous or toxic agent on the site;

g. USACE aircraft destroyed or missing;

The Contractor shall maintain an OSHA Log of Work Related Injuries and Illnesses, OSHA Form 300 and comply with all accident reporting and recordkeeping requirements specified in 29 CFR 1904.39.

(2) In addition to the above, any mishap occurring in any of the following high hazard areas shall be reported immediately to the GDA, investigated and corrective actions implemented.

a. Electrical (includes Arc Flash, electrical shock, etc.);

b. Uncontrolled Release of Hazardous Energy (includes electrical and non-electrical);

c. Load Handling Equipment (LHE) or Rigging;

d. Fall-from-Height (any level or other than same surface);

e. Underwater Diving

ATTACHMENT 1

APPENDIX A

MINIMUM BASIC OUTLINE FOR ACCIDENT PREVENTION PLANS

An Accident Prevention Plan (APP) is a safety and health policy and program document. The following areas are typically addressed in an APP, but an APP shall be job-specific and shall also address any unusual or unique aspects of the project or activity for which it is written.

The APP shall interface with the employer’s overall safety and health program, and a copy shall be available on the work site. Any portions of the overall safety and health program that are referenced in the APP shall be included as appropriate. ANSI/ASSE A10.38 should be referenced for Programmatic Issues.

> For LIMITED-SCOPE SERVICE, SUPPLY AND R&D CONTRACTS, for example, mowing (only), park attendant, rest room cleaning, the Contracting Officer and SOHO may allow an ABBREVIATED APP (customized APP requirements and waive the more stringent elements of this section). > See 01.A.11, and Appendix A, paragraph 11.

1. SIGNATURE SHEET. Title, signature, and phone number of the following:

a. Plan preparer (Qualified Person, Competent Person, such as corporate safety staff person, QC);

b. Plan must be approved, by company/corporate officers authorized to obligate the company;

c. Plan concurrence (e.g., Chief of Operations, Corporate Chief of Safety, Corporate Industrial Hygienist, project manager or superintendent, project safety professional, project QC). Provide concurrence of other applicable corporate and project personnel (Contractor).

2. BACKGROUND INFORMATION. List the following:

a. Contractor;

b. Contract number;

c. Project name; d. Brief project description, description of work to be performed, and location; phases of work anticipated (these will require an AHA).

3. STATEMENT OF SAFETY AND HEALTH POLICY. Provide a copy of current corporate/company Safety and Health Policy Statement, detailing commitment to providing a safe and healthful workplace for all employees.

The Contractor’s written safety program goals, objectives, and accident experience goals for this contract should be provided.

4. RESPONSIBILITIES AND LINES OF AUTHORITIES. Provide the following:

a. A statement of the employer’s ultimate responsibility for the implementation of his SOH program;

b. Identification and accountability of personnel responsible for safety at both corporate and project level. Contracts specifically requiring safety or industrial hygiene personnel shall include a copy of their resumes. Qualifications shall include the OSHA 30-hour course or equivalent course areas as listed here:

(1) OSH Act/General Duty Clause;

(2) 29 CFR 1904, Recordkeeping;

(3) Subpart C: General Safety and Health Provisions, Competent Person;

(4) Subpart D: Occupational Health and Environmental Controls, Citations and Safety Programs;

(5) Subpart E: PPE, types and requirements for use;

(6) Subpart F: understanding fire protection in the workplace;

(7) Subpart K: Electrical;

(8) Subpart M: Fall Protection;

(9) Rigging, welding and cutting, scaffolding, excavations, concrete and masonry, demolition; health hazards in construction, materials handling, storage and disposal, hand and power tools, motor vehicles, mechanized equipment, marine operations, steel erection, stairways and ladders, confined spaces or any others that are applicable to the work being performed.

c. The names of Competent and/or Qualified Person(s) and proof of competency/qualification to meet specific OSHA Competent/Qualified Person(s) requirements must be attached. The District SOHO will review the qualifications for acceptance;

d. Requirements that no work shall be performed unless a designated competent person is present on the job site;

e. Requirements for pre-task safety and health analysis;

f. Lines of authority; g. Policies and procedures regarding noncompliance with safety requirements (to include disciplinary actions for violation of safety requirements) should be identified;

h. Provide written company procedures for holding managers and supervisors accountable for safety.

4. SUBCONTRACTORS AND SUPPLIERS. If applicable, provide procedures for coordinating SOH activities with other employers on the job site:

a. Identification of subcontractors and suppliers (if known);

b. Safety responsibilities of subcontractors and suppliers.

5. TRAINING. a. Requirements for new hire SOH orientation training at the time of initial hire of each new employee.

b. Requirements for mandatory training and…