B.08.02 Technical Specifications 20R0007.pdf
PDF 2 MB Posted
- Attached to
- Dworshak Regulating Outlet Valve Upgrade Federal contract opportunity
- Solicitation number
- W912EF20R0007
About this file
This federal contract opportunity document solicits proposals for construction services for upgrades to three regulating outlet valves at Dworshak Dam in Idaho. The work includes replacing hydraulic cylinders, position sensors, wall and eccentric bearings, seals and fasteners for the valves. It also requires replacing valve controls, hydraulic power units, a grease lubrication system, and performing concrete patching and crack sealing on the spillway. For one valve, a new access shaft must be cut. The estimated contract value is between $5-10 million. Proposals are due by July 21, 2020. The selection process will use best value tradeoff and require performance and payment bonds. The competition is set aside for small businesses. The site must be visited to propose, and the visit is recommended, with only one offered on July 7. The contractor must develop safety, quality control, and construction management plans adhering to Corps requirements. Work shall follow Corps safety manual EM 385-1-1.
View the file
Other files for this federal contract opportunity
| File | Type | Posted |
|---|---|---|
| B.08.03 W912EF20R0007 Amendment 04 Technical Specifications.pdf | ||
| B.08.03 W912EF20R0007 Amendment 04 Resource Plans.pdf | ||
| B.08.03 W912EF20R0007 Amendment 04 Plans.pdf | ||
| B.08.03 20R0007 Solicitation Amendment 04.pdf | ||
| B.08.03 20R0007 Solicitation Amendment 03.pdf | ||
| B.08.03 Amendment 03 Technical Specifications.pdf | ||
| B.08.03 20R0007 Solicitation Amendment 02.pdf | ||
| B.08.03 W12EF20R0007 Solicitation Amendment 01.pdf | ||
| B.07.01 W912EF20R0007 Site Visit Attendees.pdf | ||
| B.08.02 OFFEROR EXPERIENCE FORM.pdf | ||
| B.08.02 Solicitation W912EF20R0007.pdf | ||
| B.08.02 Plans 20R0007.pdf | ||
| B.08.02 Resource_Plans 20R0007.pdf |
Show all 13
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Dworshak RO Valves Upgrade W912EF20R0007
PROJECT TABLE OF CONTENTS
DIVISION 00 - PROCUREMENT AND CONTRACTING REQUIREMENTS
00 01 15.00 28 LIST OF DRAWINGS
DIVISION 01 - GENERAL REQUIREMENTS
01 00 00.00 28 GENERAL REQUIREMENTS
01 11 01.00 28 SUPPLEMENTARY REQUIREMENTS
01 14 00.10 28 PROJECT SITE RESTRICTIONS
01 14 00.90 28 INTEGRATING ANTITERRORISM (AT) AND OPERATIONS SECURITY
(OPSEC)
01 22 00.00 28 MEASUREMENT AND PAYMENT
01 32 01.00 28 PROJECT SCHEDULE
01 33 00 SUBMITTAL PROCEDURES
01 35 29.10 28 GOVERNMENTAL SAFETY REQUIREMENTS
01 42 00 SOURCES FOR REFERENCE PUBLICATIONS
01 45 01.00 28 RESIDENT MANAGEMENT SYSTEM CONTRACTOR MODE (RMS CM)
01 45 04.00 28 CONTRACTOR QUALITY CONTROL
01 51 00.00 28 TEMPORARY UTILITIES
01 55 10.00 28 CONTRACTOR WORK, ACCESS AND STORAGE AREAS
01 57 20.00 28 ENVIRONMENTAL PROTECTION
01 78 00.00 28 CLOSEOUT SUBMITTALS
01 78 23.00 28 OPERATION AND MAINTENANCE DATA
DIVISION 02 - EXISTING CONDITIONS
02 41 00.00 28 DEMOLITION
02 83 33.13 28 TOXIC METALS BASED PAINT REMOVAL AND DISPOSAL
DIVISION 03 - CONCRETE
03 01 32 CONCRETE REHABILITATION FOR CIVIL WORKS
03 30 10.01 28 MISCELLANEOUS CONCRETE
03 60 00 CEMENTITIOUS GROUT
DIVISION 05 - METALS
05 50 15 CIVIL WORKS FABRICATIONS
DIVISION 09 - FINISHES
09 97 02 PAINTING: HYDRAULIC STRUCTURES
DIVISION 25 - INTEGRATED AUTOMATION
25 05 11.00 28 CYBERSECURITY
DIVISION 26 - ELECTRICAL
26 00 00.00 20 BASIC ELECTRICAL MATERIALS AND METHODS
26 05 00.00 40 COMMON WORK RESULTS FOR ELECTRICAL
26 05 19.00 10 INSULATED WIRE AND CABLE
26 24 16.00 40 PANELBOARDS
DIVISION 27 - COMMUNICATIONS
27 13 23.00 40 COMMUNICATIONS OPTICAL BACKBONE CABLING
PROJECT TABLE OF CONTENTS Page 1
DIVISION 35 - WATERWAY AND MARINE CONSTRUCTION
35 05 40.14 10 HYDRAULIC POWER SYSTEMS FOR CIVIL WORKS STRUCTURES
35 20 20 ELECTRICAL EQUIPMENT FOR HYDRAULIC POWER SYSTEMS
DIVISION 40 - PROCESS INTERCONNECTIONS
40 95 00 PROCESS CONTROL EQUIPMENT
-- End of Project Table of Contents --
PROJECT TABLE OF CONTENTS Page 2
SECTION TABLE OF CONTENTS
DIVISION 00 - PROCUREMENT AND CONTRACTING REQUIREMENTS
SECTION 00 01 15.00 28
LIST OF DRAWINGS
PART 1 GENERAL
1.1 SUMMARY
1.2 CONTRACT DRAWINGS
1.2.1 Use Of Government Prepared Contract CAD Electronic Files
1.3 RESOURCE DRAWINGS (R)
-- End of Section Table of Contents --
DOCUMENT 00 01 15.00 28 Page 1
SECTION 00 01 15.00 28
LIST OF DRAWINGS
PART 1 GENERAL
1.1 SUMMARY
This section lists the drawings for the project pursuant to contract clause "DFARS 252.236-7001, Contract Drawings, Maps and Specifications."
1.2 CONTRACT DRAWINGS
Contract drawings are as follows:
SHEET
NUMBER
FILE NUMBER DESCRIPTION Revision Number
Date
GENERAL
G-001 DWG-1-0-1/474 COVER SHEET AND LOCATION MAPS
G-002 DWG-1-0-1/475 INDEX TO DRAWINGS
G-003 DWG-1-0-1/476 STANDARD SYMBOLS, STANDARD
ABBREVIATIONS
G-004 DWG-1-0-1/477 OVERALL ARRANGEMENT AND WORK
ELEMENTS
STRUCTURAL
S-100 DWD-1-5-17/41 EXISTING KEY PLAN AND OVERALL
PLAN AT OUTLET WORKS
S-101 DWD-1-5-17/42 EXISTING OVERALL SECTION THRU
RO #2
S-102 DWD-1-5-17/43 EXISTING GATE CHAMBER GENERAL
ARRANGEMENT
S-103 DWD-1-5-17/44 TYPICAL EMERGENCY GATE
LEAKAGE PHOTOS
S-104 DWD-1-5-17/45 RO VALVE EMBEDDED SEALING
SURFACE REPAIRS PLAN AND
SECTION
S-105 DWD-1-5-17/46 RO VALVE EMBEDDED SEALING
SURFACE REPAIRS SECTIONS AND
DETAILS 1
S-106 DWD-1-5-17/47 RO VLAVE EMBEDDED SEALING
SURFACE REPAIRS SECTIONS AND
DETAILS 2
S-107 DWD-1-5-17/48 EXISTING RO CONDUIT CONCRETE
REPAIR GENERAL ARRANGEMENT
DOCUMENT 00 01 15.00 28 Page 2
S-108 DWD-1-5-17/49 RO CONDUIT CONCRETE REPAIR
SCHEDULES
S-109 DWD-1-5-17/50 RO CONDUIT CONCRETE REPAIR
DETAILS SHT 1 OF 2
S-110 DWD-1-5-17/51 RO CONDUIT CONCRETE REPAIR
DETAILS SHT 2 OF 2
S-111 DWD-1-5-17/52 MONOLITHS 17 THROUGH 20 PLAN
AND SECTIONS
MECHANICAL
M-001 DWD-1-3-17/18 HYDRAULIC SYSTEM MECHANICAL
EQUIPMENT SCHEDULE
MD-101DWD-1-3-17/19 MACHINERY ROOM DEMOLITION PLAN
MD-102DWD-1-3-17/20 GATE CHAMBER DEMOLITION PLAN
M-100 DWD-1-3-17/21 HYDRAULIC SYSTEM GENERAL
ARRANGEMENT
M-101 DWD-1-3-17/22 HYDRAULIC SCHEMATIC
M-102 DWD-1-3-17/23 HYDRAULIC PIPING PLAN
M-103 DWD-1-3-17/24 STANDARD MECHANICAL DETAILS
M-104 DWD-1-3-17/25 HYDRAULIC PIPING SECTIONS
M-105 DWD-1-3-17/26 VALVE OPERATING CYLINDER PLAN
M-106 DWD-1-3-17/27 VALVE OPERATING CYLINDER
CONNECTION DETAILS
M-107 DWD-1-3-17/28 ECCENTRIC CYLINDER PLAN
M-108 DWD-1-3-17/29 ECCENTRIC SHAFT AND BEARINGS
PLAN 1
M-109 DWD-1-3-17/30 ECCENTRIC SHAFT AND BEARINGS
PLAN 2
M-110 DWD-1-3-17/31 OPERATING CYCLINDER SUPPORT
FRAME MODIFICATIONS
M-111 DWD-1-3-17/32 ECCENTRIC CYLINDER SUPPORT
ELECTRICAL
E-001 DWD-1-6-17/1 ELECTRICAL ABBREVIATIONS AND
SYMBOLS
E-101 DWD-1-6-17/2 ELECTRICAL PLAN
E-102 DWD-1-6-17/3 DAM ELECTRICAL ROOM
ELECTRICAL PLAN
E-103 DWD-1-6-17/4 POWERHOUSE ELECTRICAL PLAN
DOCUMENT 00 01 15.00 28 Page 3
E-104 DWD-1-6-17/5 CONDUIT SCHEDULE
E-105 DWD-1-6-17/6 CABLE SCHEDULE
E-106 DWD-1-6-17/7 GENERAL CABLE ROUTING PLAN
E-201 DWD-1-6-17/8 RO CONTROLLER FRONT PANEL
ELEVATION
E-202 DWD-1-6-17/9 RO CONTROLLER INTERNAL PANEL
LAYOUT
E-203 DWD-1-6-17/10 RO CONTROLLER CONTROL
SCHEMATIC SHEET 1 OF 2
E-204 DWD-1-6-17/11 RO CONTROLLER CONTROL
SCHEMATIC SHEET 2 OF 2
E-205 DWD-1-6-17/12 RO CONTROLLER REMOTE PLC
CHASSIS I/O SLOT 2 DIGITAL
OUTPUT
E-206 DWD-1-6-17/13 RO CONTROLLER REMOTE PLC
CHASSIS I/O SLOT 3 AND 4
E-207 DWD-1-6-17/14 RO CONTROLLER REMOTE PLC
CHASSIS I/O SLOT 5 ANALOG
INPUT
E-301 DWD-1-6-17/15 MASTER STATION SERVICE PLC
CONFIGURATION
E-302 DWD-1-6-17/16 MASTER STATION SERVICE PLC
REMOTE RO PLC CHASSIS
CONFIGURATION
E-400 DWD-1-6-17/17 HYDRAULIC ACTUATORS P&ID
DIAGRAM STANDARD SYMBOLS
E-401 DWD-1-6-17/18 HYDRAULIC ACTUATORS P&ID
DIAGRAM
1.2.1 Use Of Government Prepared Contract CAD Electronic Files
a. No For Information Only drawings are available on CAD.
b. The Contractor assumes all risks associated in using electronic CAD drawings.
c. Electronic copies of CAD drawings are only available in Bentley DGN format.
d. The contract drawings shall govern if there are any discrepancies between the electronic copy and the contract drawing. The Contractor shall promptly notify the Contracting Officer of any discrepancies.
The Government will not be responsible to correct the electronic CAD drawing.
1.3 RESOURCE DRAWINGS (R)
These R drawings are included with the drawings for information only. The Government does not warrant the accuracy of the R drawings. The Government
DOCUMENT 00 01 15.00 28 Page 4 recommends that the Contractor verify the accuracy of R drawings.
Resource (R) drawings are as follows:
SHEET
NUMBER
FILE NUMBER DESCRIPTION Revision Number
Date
R-001 DWD-1-0-1/8 GENERAL - ISOMETRIC VIEW OF
GALLERIES IN MONOLITHS 14 THRU 37
R-002 DWD-1-4-2/15 CONCRETE OUTLINE - MONOLITHS 16
THRU 20 - PLAN AND ELEVATION I
R-003 DWD-1-4-2/16 CONCRETE OUTLINE - MONOLITHS 16
THRU 20 - PLAN AND ELEVATION II
R-004 DWD-1-4-2/17 CONCRETE OUTLINE - MONOLITHS 16
THRU 20 - SECTIONS
R-005 DWD-1-4-17/25 OUTLET WORKS - AIR VENT - PLAN AND
SECTION
R-006 DWD-1-4-17/29 OUTLET WORKS - VALVE ROOM - PLANS
AND DETAILS
R-007 DWD-1-4-17/30 OUTLET WORKS - VALVE ROOM - SECTIONS
R-008 DWD-1-5-17/7 OUTLET WORKS - TAINTER VALVE -
ELEVATION, SECTIONS & DETAILS
R-009 DWD-1-5-17/9 OUTLET WORKS - TAINTER VALVE
GUIDES - ELEVATION, SECTION AND
DETAILS
R-010 DWD-1-4-17/31 OUTLET WORKS - VALVE ROOM - DETAILS
& SECTIONS
R-011 DWD-1-4-17/32 OUTLET WORKS - VALVE ROOM -
REINFORCEMENT SECTIONS I
R-012 DWD-1-4-17/32.1OUTLET WORKS - CONDUIT -
REINFORCEMENT
R-013 DWD-1-4-17/33 OUTLET WORKS - VALVE ROOM -
REINFORCEMENT SECTIONS II
R-014 DWD-1-4-17/34 OUTLET WORKS - VALVE ROOM -
REINFORCEMENT SECTIONS III
R-015 14636-1 ECCENTRIC TRUNNION - ASSEMBLY
R-016 14636-2 ECCENTRIC TRUNNION - ASSEMBLY
R-017 14640 ECCENTRIC TRUNNION - CYLINDER
SUPPORT ASS'Y
R-018 14644 CYLINDER SUPPORT - WELDMENT
R-019 14658 ECCENTRIC TRUNNION - SEAL RETAINER
- GASKET
DOCUMENT 00 01 15.00 28 Page 5
R-020 14659 ECCENTRIC TRUNNION - BEARING
HOUSING
R-021 14660-1 ECCENTRIC TRUNNION - PILLOW BLOCK
R-022 14660-2 ECCENTRIC TRUNNION - PILLOW BLOCK
R-023 14661 ECCENTRIC TRUNNION - SHAFT
R-024 DWD-1-4-4/4 SPILLWAY - ABUTMENT PIER MONOLITH
20 - 1573 GALLERY AND DETAILS
R-025 DWD-1-4-3/2 SPILLWAY - MONOLITHS 18, 19 AND 20
- REINFORCEMENT DETAILS
R-026 DWD-1-4-3/1 SPILLWAY - MONOLITHS 18, 19 AND 20
- 1614.04 DECK REINFORCEMENT
R-027 DWD-1-4-4/5 SPILLWAY - MONOLITHS 18, 19 AND 20
- PIER REINFORCEMENT
R-028 DWD-1-4-4/6 SPILLWAY - ABUTMENT PIER MONOLITH
18 - REINFORCEMENT
R-029 DWD-1-4-4/8 SPILLWAY - ABUTMENT PIER MONOLITH
20 - REINFORCEMENT
R-030 DWD-1-4-4/9 SPILLWAY - ABUTMENT PIER MONOLITH
20 - REINFORCEMENT AND DETAILS
R-031 DWD-1-4-2/58 SHAFTS - ROOMS - GALLERIES - 1603
GALLERY TYPICAL REINFORCEMENT
-- End of Document --
DOCUMENT 00 01 15.00 28 Page 6
DIVISION 01 - GENERAL REQUIREMENTS
SECTION 01 00 00.00 28
GENERAL REQUIREMENTS
PART 1 GENERAL
1.1 VETERANS EMPLOYMENT EMPHASIS FOR U.S. ARMY CORPS OF ENGINEERS
CONTRACTS
PART 2 PRODUCTS (NOT USED)
PART 3 EXECUTION (NOT USED)
SECTION 01 00 00.00 28 Page 1
SECTION 01 00 00.00 28
GENERAL REQUIREMENTS
PART 1 GENERAL
1.1 VETERANS EMPLOYMENT EMPHASIS FOR U.S. ARMY CORPS OF ENGINEERS CONTRACTS
In addition to complying with the requirements outlined in FAR Part 22.13, FAR Provision 52.222-38, FAR Clause 52.222-35, FAR Clause 52.222-37, DFARS
222.13 and Department of Labor regulations, U.S. Army Corps of Engineers (USACE) contractors and subcontractors at all tiers are encouraged to promote the training and employment of U.S. veterans while performing under a USACE contract. While no set-aside, evaluation preference, or incentive applies to the solicitation or performance under the resultant contract, USACE contractors are encouraged to seek out highly qualified veterans to perform services under this contract. The following resources are available to assist USACE contractors in their outreach efforts:
Federal Veteran Employment Information http://www.fedshirevets.gov/index.aspx
Department of Labor Veterans Employment Assistance http://www.dol.gov/vets/
Department of Veterans Affairs-VOW to Hire Heroes Act http://benefits.va.gov/vow/
Army Wounded Warrior Program -http://wtc.army.mil/modules/employers/index.html
U.S. Chamber of Commerce Foundation-Hiring Our Heroes http://www.hiringourheroes.org/
Guide to Hiring Veterans - Reference Material https://obamawhitehouse.archives.gov/sites/default/files/docs/white_house_business_c
PART 2 PRODUCTS (NOT USED)
PART 3 EXECUTION (NOT USED)
-- End of Section --
SECTION 01 00 00.00 28 Page 2
DIVISION 01 - GENERAL REQUIREMENTS
SECTION 01 11 01.00 28
SUPPLEMENTARY REQUIREMENTS
PART 1 GENERAL
1.1 REFERENCES
1.2 SUBMITTALS
1.3 FIELD VERIFICATION OF SITE CONDITIONS
1.4 DEFINITIONS
1.5 REGULAR CLEANUP AND DEBRIS DISPOSAL
1.6 GOVERNMENT FURNISHED PROPERTY
1.7 GOVERNMENT ISSUED ITEMS
1.8 EQUIPMENT LIST
1.9 TESTING OF EQUIPMENT
1.10 DISPOSITION OF REMOVED EQUIPMENT
1.11 SALVAGE
1.12 PROTECTION AND RESTORATION OF EXISTING FACILITIES
1.13 PRE-CONSTRUCTION ON-SITE INSPECTION
1.14 CARE OF DRAINS
1.15 AIR PURITY CONTROL IN THE DAM
1.16 FIRE CONTROL
1.17 PROJECT SUPERINTENDENT
1.18 KEY PERSONNEL SUBSTITUTION
1.19 POST AWARD MEETINGS
1.19.1 Pre-Work Meeting
1.19.2 Pre-Construction Meeting
1.19.2.1 Minutes
1.19.2.2 Demobilizing And Remobilizing
1.19.3 RMS Orientation Meeting
1.20 WEEKLY PRODUCTION MEETINGS
1.20.1 Minutes
1.21 ADDITIONAL MEETINGS
1.22 RED ZONE MEETING
PART 2 PRODUCTS (Not Used)
PART 3 EXECUTION (Not Used)
ATTACHMENTS:
Weekly Meeting Agenda Template
SECTION 01 11 01.00 28 Page 1
SECTION 01 11 01.00 28
SUPPLEMENTARY REQUIREMENTS
PART 1 GENERAL
The work covered by this section of the specifications consists of work common to more than one section of these TECHNICAL SPECIFICATIONS.
1.1 REFERENCES
The publications listed below form a part of this specification to the extent referenced. The publications are referred to in the text by the basic designation only.
U.S. ARMY CORPS OF ENGINEERS (USACE)
EM 385-1-1 Safety and Health Requirements Manual
Comply with the current edition and all changes posted on the web as of the effective date of this solicitation.
1.2 SUBMITTALS
Government approval is required for submittals with a "G" designation;
submittals having an "I" designation are for information only. Designation following the "G" or "I" designation identifies the office that will review the submittal for the Government. Submit in accordance with SECTION
01 33 00 SUBMITTAL PROCEDURES:
SD-01 Preconstruction Submittals
Property Management Plan; G C
Equipment List; I C
Pre-Construction On-Site Inspection report; I, C
Air Purity Control Program; I C
Project Superintendent; I C
SD-07 Certificates
Key Personnel Substitution; G C
SD-11 Closeout Submittals
Government Issued Items; G C
1.3 FIELD VERIFICATION OF SITE CONDITIONS
Field verify all elevations, dimensions, and coordinates of existing features indicated on the contract drawings that affect new construction.
Any deviations shall be updated as per SECTION 01 78 00.00 28, CLOSEOUT
SECTION 01 11 01.00 28 Page 2
SUBMITTALS, paragraph WORKING AS-BUILT DRAWINGS.
Contact the COR a minimum of 2 weeks prior to schedule this activity to allow for proper coordination and for the Governemnt to install bulkheads.
Additionally, individuals conducting the field verification must comply with all Project Security, Access and Background requirements (see SECTION 01 14 00.10 28 PROJECT SITE SECURITY and SECTION 01 14 00.90 28 AT-OPSEC) and complete and submit training certifications for Fall Protection and HECP per SECTION 01 35 29.10 28 GOVERNMENTAL SAFETY REQUIREMENTS.
1.4 DEFINITIONS
a. Qualified Person.
As defined in EM 385-1-1; "DEFINITIONS", unless otherwise specified.
1.5 REGULAR CLEANUP AND DEBRIS DISPOSAL
With the exception of materials specifically indicated or specified to be salvaged for reuse in construction, or turned over to the Government, all wastes and demolished materials shall become the property of the Contractor and shall be removed from the job site daily in accordance with Federal, State, and local regulations. Furnish waste containers. All waste containers provided by the Contractor shall be emptied daily.
1.6 GOVERNMENT FURNISHED PROPERTY
Submit a Property Management Plan in accordance with FAR Clause 52.245-1 Government Property.
1.7 GOVERNMENT ISSUED ITEMS
Return to the Government all items issued to the Contractor from the Government, including but not limited to the following: keys, ID and security badges, radios, pagers, and excess/unused Government Furnished Property/Equipment. Submit documentation signed by the Contractor and Contracting Officer indicating items have been returned or fully accounted for. Format of submittal will be discussed and agreed upon at the Pre-Work Meeting.
1.8 EQUIPMENT LIST
Furnish a complete list of all equipment to be used on the Project 30 days prior to commencement of on-site work. Submit a revised list in the event of change of equipment. Lists shall include rented equipment as well as lease-purchase or sale-leaseback equipment. The initial list and the revised lists shall indicate dates equipment is assigned to or removed from the Project and adequate identification or description of each item of equipment including manufacturer's name (abbreviated), model number, manufacturer's serial number, year of manufacture, and Contractor's assigned serial or record number.
1.9 TESTING OF EQUIPMENT
Before any machinery or mechanized equipment is put to use on the job, it shall be inspected and tested by a qualified person and determined to be in safe operating condition. Cranes or derricks shall be tested by the Contractor or a qualified testing agency in accordance with EM 385-1-1.
SECTION 01 11 01.00 28 Page 3
Equipment shall be large enough to safely handle proposed picks or tasks without exceeding the crane rating established by these tests.
1.10 DISPOSITION OF REMOVED EQUIPMENT
With the exception of the items listed in the paragraph below titled "SALVAGE" or as otherwise specified in other sections of the specifications, all existing equipment removed and not reinstalled shall become the property of the Contractor, removed from the Project site, and disposed of in a legal manner. Materials that cannot be removed daily may be temporarily stored on-site at an approved area. Salvaged materials shall not be sold on the project site.
1.11 SALVAGE
Some items will remain the property of the Government during the contract and after completion. Salvage shall include removal of the material, equipment, etc., from its present location and transporting, bundling, protecting, cleaning, and storing it on-site as directed. Salvage items will be those specified. Adequate property control records shall be maintained for all materials or equipment specified to be salvaged. These records may be in accordance with the Contractor's system of property control. The Contractor shall be responsible for the adequate storage and protection of all salvaged materials and equipment and shall replace all salvage materials and equipment which are stolen, broken, or damaged during the salvage operations as the result of the Contractor's negligence, or while in the Contractor's care.
The following items shall be salvaged:
1. 480V Circuit Breakers & Buckets from DCQ3.
2. Any removed PLC components.
1.12 PROTECTION AND RESTORATION OF EXISTING FACILITIES
Reference FAR 52.236-9 Protection of Existing Vegetation, Structures, Equipment, Utilities, and Improvements (Apr 1984).
1.13 PRE-CONSTRUCTION ON-SITE INSPECTION
Prepare a Pre-Construction On-Site Inspection report of existing conditions, prior to start of on-site work, with the Contracting Officer (KO). Document existing site conditions prior to Construction by digital photographs, and/or videos along with descriptive narrative report to the KO within five (5) days after completion.
1.14 CARE OF DRAINS
Existing floor drains shall not be used for disposal of any solid material or any liquids other than clear water. Demonstrate that the pipes and drains are unobstructed when so directed.
1.15 AIR PURITY CONTROL IN THE DAM
Take all necessary precautions to maximize the control, and prevention, of all dust and fumes created by operations under this contract. To the maximum extent possible, all dust and dirt shall be removed by vacuum cleaning. At least 30 working days prior to commencement of work in the
SECTION 01 11 01.00 28 Page 4 dam, submit for approval, in writing, a proposed Air Purity Control Program.
Air Purity Control Program shall include, but not necessarily be limited to, the following:
(1) Adequate isolation and ventilation of air arcing, welding, burning, and grinding operations.
(2) Provision of exhaust ducts that shall discharge outside the powerhouse structure where mechanical ventilation is used.
(3) Controlled operation of power driven tools.
(4) Furnishing and removing of oiled sawdust or other dust preventatives in areas that cannot be properly rendered free from excessive dusting by vacuum cleaning or other methods.
(5) Vacuum cleaning of spaces within the work areas where dust accumulates.
(6) Air-, electrical-, or battery-driven equipment may be used inside the dam.
(7) Internal-combustion engine powered equipment will not be permitted to operate inside the dam unless exhausted to the exterior except for short periods of time (not to exceed 15 minutes in a 2 hour window) to unload materials and equipment.
Depending upon the Contractor's plant, equipment, and methods of operation, additional provisions for satisfactory air purity control will be required and shall be included in the proposed Air Purity Control Program.
1.16 FIRE CONTROL
Each piece of internal combustion engine driven equipment used at the work site shall be equipped with a fire extinguisher in accordance with recommendation National Fire Protection Association (NFPA) as appropriate.
The minimum approved rating of extinguishers shall not be less than 5-B:C.
1.17 PROJECT SUPERINTENDENT
At all times during performance of this contract and until the work is completed and accepted, assign and have on the worksite, a competent superintendent as per FAR Clause 52.236-6 "Superintendence by the Contractor". Submit Superintendent name and contact information prior to start of on-site construction.
1.18 KEY PERSONNEL SUBSTITUTION
If the Contractor plans on replacing any Key personnel (Project Superintendent, CQC System Manager, or CQC staff Members) they must have the approval of the Contracting Officer. Personnel shall possess the qualifications that meet or exceed those stated in the specifications for the position of the individual they are replacing. Submit qualifications of new personnel at least 15 calendar days in advance of date of replacement.
SECTION 01 11 01.00 28 Page 5
1.19 POST AWARD MEETINGS
1.19.1 Pre-Work Meeting
Within 15 calendar days after receipt of Notice to Proceed, attend a Pre-Work Meeting. Senior Level members of the Contractor's staff involved with this contract shall participate in this meeting to discuss the overall contract requirements. The Government will lead this meeting and take the meeting minutes.
1.19.2 Pre-Construction Meeting
The Project Superintendent shall coordinate with the Contracting Officer and establish the date of the Pre-Construction Meeting. The meeting will be held at the Project site at least one (1) week prior to mobilizing to the job site. The Project Superintendent shall lead the Pre-Construction Meeting discussing the Contractor's plan on executing the work at the project site, schedule, required clearances and timeframe for them, and plan for implementing safety and quality control. The Government will have key members from the Project staff to discuss environmental and clearance issues. Key members of the contractor staff shall attend this meeting including the Quality Control (QC) System Manager, Site Safety and Health Officer (SSHO) and any other members determined by the Government to be required.
1.19.2.1 Minutes
The Project Superintendent shall be responsible for taking the meeting minutes and shall send them electronically within 48 hours of the meeting to the Government's Project Engineer, Quality Assurance Representative, and Resident Engineer.
1.19.2.2 Demobilizing And Remobilizing
Anytime the Contractor demobilizes from the site and remobilizes at a later date, another Pre-Construction Meeting shall be held and shall follow the requirements listed above.
1.19.3 RMS Orientation Meeting
a. An RMS (Resident Management System) Orientation Meeting will be held within Fifteen (15) calendar days after receipt of Notice to Proceed. See SECTION 01 45 01.00 28 RESIDENT MANAGEMENT SYSTEM CONTRACTOR MODE (RMS CM) for additional information. Orientation meeting will be at District Headquarters, and may occur in conjunction with, but not at the same time as, the Pre-Work meeting. Coordinate meeting date and time with the Contracting Officer a minimum of 7 calendar days prior to the meeting.
b. At a minimum, the Contractor's RMS-CM Administrator and QC system manager shall attend the RMS Orientation meeting. A Government Representative will lead the orientation. Anticipate the following at the meeting:
1. Allow for a maximum 4 hour duration.
2. Cover the following topics, at a minimum, in RMS Contractor Mode (CM):
SECTION 01 11 01.00 28 Page 6
i. Contractor use of RMS (CM) system.
ii. Contractor Data.
iii. Quality Control Reports.
iv. Submittals.
v. RFIs.
vi. Payment.
3. Receive a follow-up handout/guide for reference on the above items.
c. Contractor employees shall bring a computer with Wi-Fi capability (to gain access to the Internet), with RMS pre-loaded.
d. The RMS Orientation Meeting is required for Contractors with no prior RMS experience. The RMS Orientation Meeting, is optional, but may be requested, for all other Contractors.
1.20 WEEKLY PRODUCTION MEETINGS
During all onsite construction work the Project Superintendent shall lead a weekly production meeting using the attached "Weekly Meeting Agenda Template " to brief the Government on the status of the project. All elements listed in the agenda shall be thoroughly discussed. For example, the Project Superintendent shall provide the Government a three (3) week "look-ahead" that describes all the planned construction activities, onsite and offsite, over the next three (3) weeks. These activities shall align to the overall construction schedule submitted under SECTION 01 32 01.00 28 PROJECT SCHEDULE, and if the three (3) week "look-ahead" differs from the construction schedule, the construction schedule shall be updated to include these changes by the next scheduled update. Key members of the Contractor's staff shall attend this meeting, including the Quality Control System Manager, who is responsible for discussing QC aspects of the work as outlined under SECTION 01 45 04.00 28 CONTRACTOR QUALITY CONTROL and SSHO.
The Government reserves the right to require any person from the Contractor's staff, such as the Project Manager, Engineer, scheduler, etc., or key subcontractor personnel to attend this meeting, if Government feels their participation is required.
1.20.1 Minutes
The Project Superintendent shall be responsible for taking the meeting minutes and shall send them electronically within 24 hours of the meeting to the Government's Project Engineer, Quality Assurance Representative, and Resident Engineer.
1.21 ADDITIONAL MEETINGS
Record the minutes of all meetings, including all conference calls, that occur between the Contractor and Government. Send minutes electronically within 24 hours of the meeting to the Contracting Officer for concurrence.
E-mail subject line shall include project name and meeting topic.
SECTION 01 11 01.00 28 Page 7
1.22 RED ZONE MEETING
Within one (1) month of completing the project or when the project is 80 percent completed, the Contractor’s Superintendent shall set up and lead a Red Zone meeting. The Contractor’s Superintendent shall contact the Contracting Officer to Schedule this meeting. The Government’s representative will include the Contracting Officer, key personnel from the Project, Project Engineer, Quality Assurance Representative, and Resident Engineer. The key people from the Contractor shall be, at a minimum, the Project Superintendent, Quality Control System Manager, Scheduler, key subcontractors personnel, and Project Manager.
The purpose of this meeting is to develop an overall schedule for all activities required by both the Government and Contractor and to complete the project. The Government will come prepared with all their activities, key dates, and durations for all work required by the Government to complete the project. The Contractor shall provide the same information for all of their activities. The Contractor’s scheduler shall input all of this information into the Contractor’s project schedule during the meeting.
This schedule shall be updated weekly, or as needed, based on the information from the weekly production meetings for both the Government and Contractor activities.
PART 2 PRODUCTS (Not Used)
PART 3 EXECUTION (Not Used)
SECTION 01 11 01.00 28 Page 8
Weekly Meeting agenda template
Schedule - Work scheduled over the next week Three week look ahead Overall Schedule Review
Submittals Review- Submittal Register Submittals approved by QC Outstanding Submittals RFI’s Letters
Coordination - Clearances required over the next week, include the following:
A description of the work to be performed under the Clearance.
Determine the correct energy isolation points needed to perform the work safely.
Physical barriers, protective grounds, piping blanks, or bulkheads that shall be used, including locations.
Determine the procedure and method of testing for stored energy if applicable.
The date and time the Clearance shall be required.
The estimated length of time the system or equipment shall be out of service and the time to return the system or equipment to service in an emergency.
Coordination issues
Safety- Review of AHA’s for ongoing work Pending AHA’s
Required for new work Status of Gov’t approval
Safety issues
QC -
Preparatory meetings Held over last week- status of meeting minutes
Required over the next week Initial meetings over the next week Follow up over the next week Rework list Review Deficiency tracking log
This page intentionally left blank
DIVISION 01 - GENERAL REQUIREMENTS
SECTION 01 14 00.10 28
PROJECT SITE RESTRICTIONS
PART 1 GENERAL
1.1 SUBMITTALS
1.2 SITE CONDITIONS AND OPERATIONAL RESTRICTIONS
1.3 EMPLOYEE TRAINING AND IDENTIFICATION SUMMARY
1.4 PROJECT SECURITY
1.4.1 Dworshak Project Security
1.4.1.1 Vehicle Access for Dworshak Dam
1.4.1.2 Contractor Employee Access
1.4.2 Identification of Employees
1.4.3 Delivery of Equipment
1.5 ELEVATOR USE
1.6 WORK SCHEDULES
1.6.1 Contractor's Work Schedule
1.6.2 Government's Work Schedule
1.7 USE OF WALLA WALLA DISTRICT PARKS
PART 2 PRODUCTS (Not Used)
PART 3 EXECUTION (Not Used)
SECTION 01 14 00.10 28 Page 1
SECTION 01 14 00.10 28
PROJECT SITE RESTRICTIONS
PART 1 GENERAL
1.1 SUBMITTALS
Government approval is required for submittals with a "G" designation;
submittals having an "I" designation are for information only. A designation following the "G" or "I" designation identifies the office that will review the submittal for the Government. Submit the following in accordance with SECTION 01 33 00 SUBMITTAL PROCEDURES:
SD-01 Preconstruction Submittals
Employee Training And Identification Summary; I C
Elevator Protection Plan; G, C
1.2 SITE CONDITIONS AND OPERATIONAL RESTRICTIONS
The following information is provided:
a. Due to operational requirements, only one RO Valve may be out of service. Once the Contractor starts working on a valve, all work must be completed, to include testing and commissioning, before working on the next valve. The decision on which valve will be taken out of service first will be discussed at the pre-work meeting.
b. The Government will set the maintenance bulkhead at the start of the onsite work window. It takes one day to accomplish this task. The Contractor shall provide a minimum of 1 week notice prior to when they require the bulkheads installed.
c. The Government will remove the maintenance bulkhead at the completion so commissioning and flow testing can be performed. Removal also takes one day. The Contractor shall provide a minimum of 1 week notice prior to when they require the bulkheads removed.
d. The Government's 50 Ton Intake Crane will be available for the work within the working load and movement limits of the crane. The intake crane will be available for use by the Contractor at such times as not required for other maintenance and repair work performed by Government personnel. The Government will furnish electric power, lubrication, and normal maintenance including adjustments without cost to the Contractor. Give the Government at least 24 hours notice in advance each time use of the cranes is desired on weekdays and 48 hours notice for use on weekends and Federal holidays.
e. A 12-ton auxilary hook will be the primary means of moving material and equipment up and down the access hatches.
f. One set of lifting slings will be available for use by the Contractor.
SECTION 01 14 00.10 28 Page 2
1.3 EMPLOYEE TRAINING AND IDENTIFICATION SUMMARY
a. Provide a spreadsheet containing the following information for all Contractor and Subcontractor personnel working on the Project site:
1. Employee name.
2. Employee photo ID Type Issued: Proximity Card #*** (for Gate/Door Access) OR Photo ID Only.
3. Date Photo ID Issued.
4. Date Photo ID Returned.
5. All applicable employee training that has been completed.
Include all training from Section 01 35 29.10 28 GOVERNMENTAL
SAFETY REQUIREMENTS, 01 14 00.90 28 INTEGRATING ANTITERRORISM (AT)
AND OPERATIONS SECURITY (OPSEC), and other as specified.
b. Submit EMPLOYEE TRAINING AND IDENTIFICATION SUMMARY prior to beginning of Contractor on-site work. Update and resubmit within 48 hours of any changes.
1.4 PROJECT SECURITY
The Project site is a secured area and access onto the Project is restricted. The security measures affect all of the Contractor's vehicles and personnel. There will be delays when entering Projects due to locked gates, vehicle inspections, and personnel checks. Inspections and checks may include inspection of tool boxes, brief cases, lunch boxes, and other containers. Weapons, alchohol and illegal drugs are not allowed on the project site.
1.4.1 Dworshak Project Security
1.4.1.1 Vehicle Access for Dworshak Dam
Work vehicle access for Dworshak Dam is across the top of the dam. Only Contractor's work vehicles and equipment that are essential to the conduct of the work will be allowed in gated work areas. All Contractor vehicles shall display suitable permanent or temporary company identification. All vehicles that pass through the locked gate will be subject to being searched.
1.4.1.2 Contractor Employee Access
a. Only contractor and subcontractor employees cleared through the processes described in SECTION 01 14 00.90 28, "INTEGRATING ANTITERRORISM (AT) AND OPERATIONS SECURITY (OPSEC)" shall be admitted to the worksite.
b. All cleared contractor and subcontractor employees shall be required to follow the Dworshak Project Access Control Policy. Project personnel will present an overview of the Policy upon first arrival to site, and a copy of the written Policy will be available at any time for viewing.
Contractor and subcontractor employees shall be required to sign acknowledgement that they understand and will follow this guidance.
SECTION 01 14 00.10 28 Page 3
c. The Project will issue proximity access badges and/or hard keys as necessary for the contractor to accomplish the work. The number issued and the individuals to whom they will be assigned will be at the discretion of the Project. All access badges and keys shall be immediately surrendered to the Project upon release of the employee, upon project completion, or upon the Project's request.
1.4.2 Identification of Employees
a. Each contractor and subcontractor employee shall be required to have company-issued identification on their person at all times. When work conditions permit, this identification shall be worn by the employee visibly on his/her person.
b. Every Contractor employee (prime or subcontractor) shall have a hard hat meeting the requirements of EM 385-1-1. Hardhats shall display the Prime Contractor name, subcontractor name, and the employee's name.
Contractor employee hardhats shall not be white with red markings. It shall be the responsibility of the Project Superintendent to enforce this requirement.
1.4.3 Delivery of Equipment
Contractor is responsible for delivery and receipt of all materials and equipment. Deliverables should be scheduled during normal working hours when possible to allow security inspection of truck and cargo. Government personnel will not be available to assist contractor in these activities.
1.5 ELEVATOR USE
a. The North and South Tower elevators are available for Contractor use. Protect the interior of the elevator from damage that may occur during use. Submit an elevator protection plan, that details what means and methods will be used to protect the elevator from damage.
b. Elevator capacity shall not be exceeded (North Elevator is 2500 pounds and South Elevator is 2000 pounds). Elevator use is at Contractors' own risk. The Government does not guarantee operation, or availability, of the elevator.
1.6 WORK SCHEDULES
1.6.1 Contractor's Work Schedule
At the Pre-Work Meeting, furnish a schedule of number of working days per week, shifts per day, and hours per shift for contract work. The Contractor shall furnish notification of any change of schedule of regular work hours, overtime work hours, and shifts of work crews and personnel at the site. This notification shall be provided a minimum of 48 hours prior to any schedule change to allow suitable scheduling of Government personnel and inspection. Exception to this requirement may be allowed in case of schedule change due to emergency conditions.
1.6.2 Government's Work Schedule
The maintenance crews at the dam work from 6:30 a.m. to 5:00 p.m., Monday through Thursday. Crews and staff do not work on weekends and Federal
SECTION 01 14 00.10 28 Page 4 holidays. If a Federal holiday falls on a Friday, the crews and staff do not work on the preceeding Thursday. A powerhouse operator is at the site 24 hours a day, 7 days a week, including Federal holidays but is not available to assist the Contractor.
If the Contractor requires Government support or assistance outside of normal work hours, the Contractor must make a formal written request to the Contracting Officer at least one week prior to the date that support/assistance is needed. The Government will review this request, but there is no guarantee that Government support or assistance can be provided.
1.7 USE OF WALLA WALLA DISTRICT PARKS
Special consideration for the use of the Walla Walla District Camping Grounds will not be given to the Contractor if they plan on camping at these sites. The Contractor's crew may not use Government parking lots near the Dworshak Dam for RV parking.
PART 2 PRODUCTS (Not Used)
PART 3 EXECUTION (Not Used) -- End of Section --
SECTION 01 14 00.10 28 Page 5
DIVISION 01 - GENERAL REQUIREMENTS
SECTION 01 14 00.90 28
INTEGRATING ANTITERRORISM (AT) AND OPERATIONS SECURITY (OPSEC)
PART 1 GENERAL
1.1 REFERENCES
1.2 SUBMITTALS
1.2.1 Biographical Information Submittal
1.3 AT LEVEL 1 TRAINING
1.4 ACCESS AND GENERAL PROTECTION/SECURITY POLICY AND PROCEDURES
1.5 DOD FACILITY REQUIREMENTS (COMMON ACCESS CARD NOT REQUIRED)
1.6 SUSPICIOUS ACTIVITY REPORTING TRAINING (iWATCH, CORPS Watch, or See
Something, Say Something)
1.7 CONTRACTS THAT REQUIRE OPSEC TRAINING
1.8 EMPLOYEE ESCORT
1.9 PRE-SCREEN CANDIDATES USING E-VERIFY PROGRAM
PART 2 PRODUCTS (NOT USED)
PART 3 EXECUTION (NOT USED)
SECTION 01 14 00.90 28 Page 1
SECTION 01 14 00.90 28
INTEGRATING ANTITERRORISM (AT) AND OPERATIONS SECURITY (OPSEC)
PART 1 GENERAL
The work covered by this section of the specifications consists of work common to more than one section of these TECHNICAL SPECIFICATIONS. This contract does not require access to or handling of classified material.
This contract does not require access to sensitive information, or equipment. It does require access to restricted areas. Dworshak Dam is considered a restricted area.
1.1 REFERENCES
The publications listed below form a part of this specification to the extent referenced. The publications are referred to within the text by the basic designation only.
U.S. ARMY (DA)
AR 190-13 (2011) The Army Physical Security Program
Army Directive 2014-05 (2014) Policy and Implementation Procedures for Common Access Card Credentialing and Installation Access for Uncleared Contractors
Website for Department of the Army Regulations:
http://armypubs.army.mil/
Federal Acquisition Regulation (FAR)
FAR 52.204-9 (2015) Personal Identity Verification of Contractor Personnel
1.2 SUBMITTALS
Government approval is required for submittals with a "G" designation;
submittals having an "I" designation are for information only. The designation following the "G" or "I" designation identifies the office that will review the submittal for the Government. Submit the following in accordance with SECTION 01 33 00 SUBMITTAL PROCEDURES:
SD-01 Preconstruction Submittals
Anti Terrorism (AT) Level 1; I, SLE iWATCH, CORPS Watch, or See Something, Say Something; I, C
Level 1 OPSEC training; I, C
Pre-Screen Candidates Using E-Verify Program; I, SLE
Biographical Information; G, C
SECTION 01 14 00.90 28 Page 2
1.2.1 Biographical Information Submittal
Submit Biographical Information to the COR via email as a password protected pdf file for all personnel requiring unescorted access.
See paragraph "ACCESS AND GENERAL PROTECTION/SECURITY POLICY AND PROCEDURES" for additional information and details on items to submit.
1.3 AT LEVEL 1 TRAINING
All contractor employees, including all associated sub-contractor employees, requiring access to government facilities and controlled access areas shall complete Anti Terrorism (AT) Level 1 awareness training within 30 days after Notice to Proceed, and annually thereafter until project completion. Submit certificates of completion for each employee to the contracting officer representative (COR) or to the contracting officer (if a COR is not assigned), within 5 calendar days after initial completion of training or annual refresher.
The contractor shall retain employee training certificates for the duration of the contract and maintain a current roster. The roster shall contain the names of employees who have completed the training along with their most recent training completion date. The contractor shall update the roster and resubmit to the contracting officer no later than 5 calendar days after completion of refresher training or a new employee completes certification.
AT Level I awareness training can be completed in approximately two (2) hours and is available at the following website:
http://jko.jten.mil/courses/atl1/launch.html
1.4 ACCESS AND GENERAL PROTECTION/SECURITY POLICY AND PROCEDURES
All contractor employees, including all associated sub-contractor employees, shall comply with all applicable facility access and security policies and procedures. Local facility policies and procedures shall be provided by a government representative.
The contractor shall provide all information required for background checks to meet facility access requirements. Background checks will be performed by Walla Walla District Security Office. Contractor workforce must comply with all personal identity verification requirements (FAR 52.204-9, Personal Identity Verification of Contractor Personnel:
http://www.ecfr.gov/cgi-bin/text-idx?rgn=div8&node=48:2.0.1.1.1.2.1.28) as directed by DOD and/or local policy.
For each individual that will be working at this site, submit an excel spreadsheet containing the individual's full name and date of birth to satisfy the information required to conduct the background check. The COR will provide a copy of the excel spreadsheet to be used at the Pre-work meeting. Background check must be approved for an individual before they can access the site.
In addition to the changes otherwise authorized by the changes clause of this contract, should the Force Protection Condition (FPCON) at any facility change, the Government may require changes in contractor security matters or processes.
SECTION 01 14 00.90 28 Page 3
1.5 DOD FACILITY REQUIREMENTS (COMMON ACCESS CARD NOT REQUIRED)
Contractor employees, including all associated sub-contractor employees, shall comply with adjudication standards and procedures using the National Crime Information Center Interstate Identification Index (NCIC-III)and Terrorist Screening Database (TSDB) (Army Directive 2014-05 / AR 190-13), applicable facility and area access security policies and procedures (provided by a government representative, as NCIC and TSDB are available).
1.6 SUSPICIOUS ACTIVITY REPORTING TRAINING (iWATCH, CORPS Watch, or See Something, Say Something)
The contractor employees, including all associated sub-contractor employees, shall take one of the following trainings on the suspicious activity reporting program; iWATCH, CORPS WATCH, SEE SOMETHING, SAY SOMETHING. These trainings are available on the internet and the links to the training sites are shown below.
This training is to inform employees of the types of behavior to watch for and instruct employees to report suspicious activity to the security representative. This training shall be completed within 30 calendar days of Notice to Proceed and within 30 calendar days of new employees commencing performance with the results reported to the COR or to the contracting officer (if a COR is not assigned), NLT 5 calendar days after the completion of the training.
a. iWATCH\ Website: http:://www.myarmyonesource.com/familyprogramsandservices/ iwatchprogram/default.aspx
b. CORPS WATCH Website:
http://www.spa.usace.army.mil/Missions/CivilWorks/Recreation/CorpsWatch.aspx
c. SEE SOMETHING, SAY SOMETHING Website: https://www.dhs.gov/see-something-say-something
1.7 CONTRACTS THAT REQUIRE OPSEC TRAINING
All new contractor employees, including all associated sub-contractor employees, will complete Level I OPSEC Training within 30 calendar days of their reporting for duty. Additionally, all employees must complete annual OPSEC awareness training until project completion. The contractor shall submit Level 1 OPSEC training certificates of completion for each affected employee, to the COR or to the contracting officer (if a COR is not assigned), within 5 calendar days after completion of training.
OPSEC awareness training is available at the following website:
https://securityawareness.usalearning.gov/opsec/index.htm or it can be provided by the OPSEC Officer in presentation form which will be documented via memorandum.
1.8 EMPLOYEE ESCORT
All contractor employees, including all associated sub-contractor employees, who are not in possession of the appropriate security clearance or access privileges, will be escorted in sensitive or restricted areas and/or areas where they may be exposed to classified and/or sensitive
SECTION 01 14 00.90 28 Page 4 materials.
1.9 PRE-SCREEN CANDIDATES USING E-VERIFY PROGRAM
The Contractor must pre-screen Candidates using the E-verify Program ( http://www.uscis.gov/e-verify) website to meet the established employment eligibility requirements. The Vendor must ensure that the Candidate has two valid forms of Government issued identification prior to enrollment to ensure the correct information is entered into the E-verify system.
An initial list of verified/eligible Candidates must be provided to the COR or to the contracting officer (if a COR is not assigned), no later than 30 business days after receipt of receipt of Notice to Proceed.
*When contracts are with individuals, the individuals will be required to complete a Form I-9, Employment Eligibility Verification, with the designated Government representative. This Form will be provided to the Contracting Officer and shall become part of the official contract file.
PART 2 PRODUCTS (NOT USED)
PART 3 EXECUTION (NOT USED)
SECTION 01 14 00.90 28 Page 5
This page intentionally left blank
DIVISION 01 - GENERAL REQUIREMENTS
SECTION 01 22 00.00 28
MEASUREMENT AND PAYMENT
PART 1 GENERAL
1.1 RETAINAGE OF PAYMENT
1.2 CLIN 0001 RO VALVE 1 UPGRADE
1.3 CLIN 0002 INSPECT AND REPAIR STRIPPED HOLES - RO VALVE 1
1.4 CLIN 0003 INSPECT AND REPAIR DAMAGED EMBEDDED SURFACE - 7.5 SQ FT X
¼" (90 CUBIC INCHES) FOR RO VALVE 1
1.5 CLIN 0004 RO VALVE 2 UPGRADE
1.6 CLIN 0005 INSPECT AND REPAIR STRIPPED HOLES - RO VALVE 2
1.7 CLIN 0006 INSPECT AND REPAIR DAMAGED EMBEDDED SURFACE - 7.5 SQ FT X
¼" (90 CUBIC INCHES) FOR RO VALVE 2
1.8 CLIN 0007 RO VALVE 3 UPGRADE
1.9 CLIN 0008 INSPECT AND REPAIR STRIPPED HOLES - RO VALVE 3
1.10 CLIN 0009 INSPECT AND REPAIR DAMAGED EMBEDDED SURFACE - 7.5 SQ FT
X ¼" (90 CUBIC INCHES) FOR RO VALVE 3
PART 2 PRODUCTS (Not Applicable)
PART 3 EXECUTION (Not Applicable)
SECTION 01 22 00.00 28 Page 1
SECTION 01 22 00.00 28
MEASUREMENT AND PAYMENT
PART 1 GENERAL
In each instance, the contract price for an item shall constitute full compensation for furnishing all plant, labor, equipment, and materials, and for performing all operations required to complete the work included in the item as herein specified, or as otherwise approved.
1.1 RETAINAGE OF PAYMENT
Retainage in the amount of 10% of original contract award amount will be withheld until the final submittals, listed below, have been approved by the Government. The 10% retainage for final submittals will not be held until such time as the Contractor has earned 90 percent of the original contract value. See SECTION 01 78 00.00 28 "CLOSEOUT SUBMITTALS" for additional information.
a. Final Operation and Maintenance Manuals and Parts Catalogs.
b. Final Shop Drawings.
c. Final As-built Drawings.
d. Final Record Drawings.
e. Final Spare Parts submission.
f. Return of Government Issued Items.
1.2 CLIN 0001 RO VALVE 1 UPGRADE
RO Valve 1 Upgrade will be measured for payment as a complete pay item (JOB). Payment will be made at the lump sum price for CLIN 0001, "RO Valve 1 Upgrade," which price and payment shall be full compensation for all work required for the construction of Dworshak RO Valve 1, complete, as specified and approved.
1.3 CLIN 0002 INSPECT AND REPAIR STRIPPED HOLES - RO VALVE 1
Inspect and repair an estimated quantity of 96 stripped holes for RO Valve 1 will be measured for payment as a per unit pay item (EA). Payment will be made at a per unit price for CLIN 0002, "Inspect and Repair Stripped Holes - RO Valve 1" which price and payment shall be full compensation for all work required to inspect and repair 96 stripped holes for RO Valve 1, complete, as specified and approved.
1.4 CLIN 0003 INSPECT AND REPAIR DAMAGED EMBEDDED SURFACE - 7.5 SQ FT X ¼"
(90 CUBIC INCHES) FOR RO VALVE 1
Inspect and repair an estimated 90 cubic inches of damaged embedded surface behind the seals will be measured for payment as a per unit pay item (CU).
Payment will be made at per unit price for CLIN 0003 "Inspect and Repair Damaged Embedded Surface - 7.5 sq ft x ¼" (90 cubic inches) for RO Valve 1" which price and payment shall be full compensation for all work required to inspect and repair 90 cubic inches of damaged embedded surface for RO Valve 1, complete, as specified and approved.
SECTION 01 22 00.00 28 Page 2
1.5 CLIN 0004 RO VALVE 2 UPGRADE
The RO Valve 2 Upgrade will be measured for payment as a complete pay item (JOB). Payment will be made at the lump sum price for CLIN 0004, "RO Valve 1 Upgrade," which price and payment shall be full compensation for all work required for the construction of Dworshak RO Valve 2, complete, as specified and approved.
1.6 CLIN 0005 INSPECT AND REPAIR STRIPPED HOLES - RO VALVE 2
Inspect and repair an estimated quantity of 96 stripped holes for RO Valve 2 will be measured for payment as a per unit pay item (EA). Payment will be made at a per unit price for CLIN 0002, "Inspect and Repair Stripped Holes - RO Valve 2" which price and payment shall be full compensation for all work required to inspect and repair 96 stripped holes for RO Valve 2, complete, as specified and approved.
1.7 CLIN 0006 INSPECT AND REPAIR DAMAGED EMBEDDED SURFACE - 7.5 SQ FT X ¼"
(90 CUBIC INCHES) FOR RO VALVE 2
Inspect and repair an estimated 90 cubic inches of damaged embedded surface behind the seals will be measured for payment as a per unit pay item (CU).
Payment will be made at per unit price for…
This is the start of the file's text. The full file is on GovTribe.