B.08.02 - Solicitation (Released) - W912HP24R2000 - Reception Complex Ph II.pdf

PDF 2 MB Posted

Attached to
Reception Barracks Complex Phase II at Fort Jackson, South Carolina
Solicitation number
W912HP24R2000
Issued by

About this file

This document is a solicitation for the Reception Barracks Complex Phase II at Fort Jackson, South Carolina. The project involves new construction of a reception processing center, battalion headquarters, company operations facilities, trainee barracks, medical clinic, storage building, swing space, optical fabrication laboratory, and supporting site infrastructure. The work is being procured as an unrestricted, best value trade-off negotiated acquisition with a total estimated value between $100M and $250M. A Project Labor Agreement (PLA) will be required. Proposals are due by July 8, 2024 and the Government intends to conduct discussions with offerors in the competitive range. The evaluation factors are Past Performance, Management Approach, Small Business Participation, and Price. The Department of the Army Corps of Engineers, Charleston District is the contracting agency.

View the file

Other files

File Type Posted
B.08.03 - Amendment 0003 (released) - W912HP24R2000 - Reception Complex Ph II.pdf PDF
B.08.03 - Amendment 0003 Conformed Solicitation - W912HP24R2000 - Reception Complex Ph II.pdf PDF
B.08.03 - Amendment 0002 Conformed Solicitation - W912HP24R2000 - Reception Complex Ph II.pdf PDF
B.08.03 - Amendment 0002 (released) - W912HP24R2000 - Reception Complex Ph II.pdf PDF
B.08.03 - Amendment 0001 (released) - W912HP24R2000 - Reception Complex Ph II.pdf PDF
B.08.03 - Amendment 0001 Conformed Solicitation - W912HP24R2000 - Reception Complex Ph II.pdf PDF
B.08.03 - Amendment 0001 Attachement Pre-proposal Sign-In - W912HP24R2000 - Reception Complex P~.pdf PDF
B.08.02 Vol 2b. Reception Building - FP-PL-ME-EL-TC.pdf PDF
B.08.02 Vol 4. Optical Lab.pdf PDF
B.08 REDACTED - SPE - Signed Class JA for Basis of Design Items.pdf PDF
B.08.02 Ft Jackson RTA Specs Volume 1 (Divisions 00-06).pdf PDF
B.08.02 Ft Jackson RTA Specs Volume 2 (Divisions 07-23).pdf PDF
B.08.02 Ft Jackson RTA Specs Volume 3 (Divisions 25-33).pdf PDF
B.08.02 Vol 1b. Civil Site - DEMO-SITE-GRAD-STORM.pdf PDF
B.08.02 Vol 1d. Civil Site - EROSION.pdf PDF
B.08.02 Vol 7. Swing Space.pdf PDF
B.08.02 Vol 3. Barracks Building.pdf PDF
B.08.02 Vol 1c. Civil Site - WALL-STAIRS-JOINT LAY-UTIL.pdf PDF
B.08.02 Vol 1e. Civil Site - LA-SITE EL.pdf PDF
B.08.02 Vol 2a. Reception Building - GEN-AR-ST-ID.pdf PDF
B.08.02 Vol 1a. Civil Site - GEN-SURV-SOIL.pdf PDF
B.08.02 Vol 5. Storage Building.pdf PDF
Show all 22

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Title: Reception Complex Phase 2 at Ft. Jackson, SC

The w ork involves new construction of a Reception Complex, Phase 2 at Ft. Jackson.

This acquisition is being advertised as Full and Open (Unrestricted) utilizing HubZone price evaluation preference.

NAICS Code is 236220, Commerical and Institutional Building Construction.

Magnitude of Construction: $100M- $250M

HOLLY SOPIAK

NOTE: In sealed bid solicitations "offer" and "offeror" mean "bid" and "bidder".

10. THE GOVERNMENT REQUIRES PERFORMANCE OF THE WORK DESCRIBED IN THESE DOCUMENTS

NEGOTIATED

07-Jun-2024

(RFP)

(IFB)

X

CALL:

B. TELEPHONE NO. (Include area code) (NO COLLECT CALLS)

See Item 7

2. TYPE OF SOLICITATION

SEALED BID

3. DATE ISSUED

9. FOR INFORMATION A. NAME

SOLICITATION

NSN 7540-01-155-3212 1442-101 STANDARD FORM 1442 (REV. 4-85)

Prescribed by GSA

FAR (48 CFR) 53.236-1(e)

11. The Contractor shall begin performance w ithin _______10 calendar days and complete it w ithin ________1100 calendar days after receiving aw ard, X notice to proceed. This performance period is X mandatory, negotiable. (See _________________________52.211-10

12 A. THE CONTRACTOR MUST FURNISH ANY REQUIRED PERFORMANCE AND PAYMENT BONDS?

(If "YES," indicate within how many calendar days after award in Item 12B.)

X YES NO

13. ADDITIONAL SOLICITATION REQUIREMENTS:

A. Sealed offers in original and __________ copies to perform the w ork required are due at the place specif ied in Item 8 by ___________ local time ______________08 Jul 2024 (date). If this is a sealed bid solicitation, offers must be publicly opened at that time.

shall be marked to show the offeror's name and address, the solicitation number, and the date and time of fers are due.

B. An offer guarantee X is, is not required.

C. All offers are subject to the (1) w ork requirements, and (2) other provisions and clauses incorporated in the solicitation in full text or by reference.

D. Offers providing less than _______120 calendar days for Government acceptance after the date offers are due w ill not be considered and w ill be rejected.

SOLICITATION, OFFER,

AND AWARD

(Construction, Alteration, or Repair)

1. SOLICITATION NO.

IMPORTANT - The "offer" section on the reverse must be fully completed by offeror.

4. CONTRACT NO.

7. ISSUED BY CODE

US ARMY CORPS OF ENGINEERS, CHARLESTON

69-A HAGOOD AVENUE

CHARLESTON SC 29403

W912HP

PAGE OF PAGES

1 OF

CODE

(Title, identifying no., date):

12B. CALENDAR DAYS

11:00 AM (hour)

Sealed envelopes containing offers

5. REQUISITION/PURCHASE REQUEST NO. 6. PROJECT NO.

8. ADDRESS OFFER TO (If Other Than Item 7)

843-329-2331FAX:TEL: 843-329-8193 TEL: FAX:

W912HP24R2000 79

20B. SIGNATURE

(REV. 4-85)STANDARD FORM 1442 BACK

TO SIGN

NSN 7540-01-155-3212

SOLICITATION, OFFER, AND AWARD (Continued) (Construction, Alteration, or Repair)

CODE FACILITY CODE

17. The offeror agrees to perform the w ork required at the prices specif ied below in strict accordance w ith the terms of this solicitation, if this offer is accepted by the Government in w riting w ithin ________ calendar days after the date offers are due.

the minimum requirements stated in Item 13D. Failure to insert any number means the offeror accepts the minimum in Item 13D.)

AMOUNTS SEE SCHEDULE OF PRICES

18. The offeror agrees to furnish any required performance and payment bonds.

19. ACKNOWLEDGMENT OF AMENDMENTS

(The offeror acknowledges receipt of amendments to the solicitation -- give number and date of each)

AMENDMENT NO.

DATE

20A. NAME AND TITLE OF PERSON AUTHORIZED TO SIGN

OFFER (Type or print)

AWARD (To be completed by Government)

21. ITEMS ACCEPTED:

22. AMOUNT 23. ACCOUNTING AND APPROPRIATION DATA

24. SUBMIT INVOICES TO ADDRESS SHOWN IN ITEM

(4 copies unless otherwise specified)

CODE

(Insert any number equal to or greater than

20C. OFFER DATE

25. OTHER THAN FULL AND OPEN COMPETITION PURSUANT TO

10 U.S.C. 2304(c) 41 U.S.C. 253(c)

CODE27. PAYMENT WILL BE MADE BY:26. ADMINISTERED BY

(Include ZIP Code)14. NAME AND ADDRESS OF OFFEROR 15. TELEPHONE NO. (Include area code)

See Item 14

(Include only if different than Item 14)16. REMITTANCE ADDRESS

30B. SIGNATURE

29. AWARD (Contractor is not required to sign this document.)

document and return _______ copies to issuing office.) Contractor agrees Your of f er on this solicitation, is hereby accepted as to the items listed. This award con-to f urnish and deliv er all items or perf orm all work, requisitions identif ied summates the contract, which consists of (a) the Gov ernment solicitation and on this f orm and any continuation sheets f or the consideration stated in this y our of f er, and (b) this contract award. No f urther contractual document is contract. The rights and obligations of the parties to this contract shall be necessary .

gov erned by (a) this contract award, (b) the solicitation, and (c) the clauses, representations, certif ications, and specif ications or incorporated by ref er-ence in or attached to this contract.

30A. NAME AND TITLE OF CONTRACTOR OR PERSON AUTHORIZED 31A. NAME OF CONTRACTING OFFICER (Type or print)

30C. DATE

(Type or print)

TEL: EMAIL:

31B. UNITED STATES OF AMERICA 31C. AWARD DATE

BY

CONTRACTING OFFICER WILL COMPLETE ITEM 28 OR 29 AS APPLICABLE

(Contractor is required to sign this28. NEGOTIATED AGREEMENT

(M ust be fully completed by offeror)OFFER

Section 00 10 00 - Solicitation, Contract Line Item Number (CLIN) Schedule

ITEM NO SUPPLIES/SERVICES QUANTITY UNIT UNIT PRICE AMOUNT

0001 1 Job Base Bid Civil and Site WorkFFP

Site Preparation and Development, Including All Utilities & Communications Infrastructure, hazardous material abatement and demolition complete per Drawings and Specifications, excluding work identified separately and all utility work identified separately to be performed by utilities

FOB: Destination

PSC CD: Y1JZ

NET AMT

0002 1 Job Base Bid Construct Reception BuildingFFP incl. Battalion HQ and Medical), complete, per Drawings and Specifications.

Includes achieving Third Party Certification (USGBC BD+C, v4 LEED Silver)

0003 1 Job BASE BID: Construct Optical FabricationFFP complete per Drawings and Specifications. Includes achieving Third Party Certification (USGBC BD+C, v4 LEED Silver)

0004 1 Job BASE BID Construct Swing SpaceFFP including all related civil, site, utilities. complete per Drawings and Specifications.

Includes initial prep for constructing new Swing Space, then demolition and restoration of the site after use.

0005 1 Job BASE BID Construct Storage BuildingFFP complete per Drawings and Specifications

0006 1 Job

OPTION BID OPTION 1A*:FFP

Construct Trainee Barracks (including all related civil, site, utilities, and telecommunications), complete per Drawings and Specifications. Includes achieving Third Party Certification (USGBC BD+C, v4 LEED Silver)

0007 1 Job

OPTION BID OPTION 1B*FFP

Demolish existing Medical Clinic (1890) and Audiology Building (1891), including Foundations and related site and utilities, complete per Drawings and Specifications

0008 1 Job

OPTION BID OPTION 2*FFP

Construct 50 Temporary flagpole stands with all state flags, complete per Drawings and Specifications

0009 1 Job

OPTION BID OPTION 3*FFP

Purchase Green Power for the project from an approved Green Power company, to earn 2 LEED points in LEED v4 or v4.1

TOTAL OF BASE BID ITEMS (CLINS 0001-0005) $_________________________

TOTAL OF OPTION BID ITEMS (CLINS 0006-0009) $_________________________

TOTAL (COMBINATION OF ALL BID ITEMS 0001-0009) $_________________________

Notes:

1) Enter prices where space is provided for ALL items. Failure to follow this instruction may render the proposal non-responsive and the proposal will not be considered for award.

DEFENSE PRIORITY & ALLOCATION

This contract when awarded is a ( ) DX rated order; (x) DO (DO-C2) rated order certified for national defense, emergency preparedness, and energy program use under the Defense Priorities and Allocations System (DPAS) (15 CFR700), and the Contractor will be required to follow all of the requirements of this regulation.

Section 00 21 16 - Instructions to Proposers

PROCEDURES FOR SUBMITTAL OF OFFERS AND PROPOSAL EVALUATION

1. Overview

1.1. This Request for Proposal (RFP) solicits work for the construction of a Reception

Barracks Complex Phase II at Fort Jackson, SC. Construction includes a reception processing center, battalion headquarters and company operations facilities (COF), trainee barracks, medical clinic, overhead protection/canopy, storage building, swing space, optical fabrication laboratory, and building information systems. A temporary swing space for the reception processing center is required during the construction.

Supporting facilities include site development, utilities and connections, perimeter security devices, lighting, paving, parking, walks, curbs and gutters, storm drainage, landscaping, fencing, and signage.

1.2. Proposal Submissions and the Best Value Trade-off Source Selection Process: This process requires offerors to submit technical and performance capability information for evaluation by the Government against the uniform requirements identified in evaluation factors. Each of the factors will be evaluated against the evaluation criteria set out in this section.

2. Submittal of Offers

2.1. Who May Submit: Any legally organized Offeror qualified and eligible to receive an award under applicable laws and regulations.

2.1.1. The Government will consider past performance of affiliates of the Offeror and those entities in a teaming agreement, whether a predecessor company, affiliated company, subsidiary (including wholly owned subsidiaries), or subcontractors, if the resources of those affiliates will have a direct impact on the performance of this contract, such that the affiliate will have meaningful involvement in contract performance.

2.1.2. Contractor Team Arrangements.

2.1.2.1. Recognition of Contractor Teams. In accordance with FAR Subpart 9.6, it is Government policy to recognize the integrity and validity of contractor team arrangements. For a teaming arrangement to be recognized for purposes of source selection evaluation and the application of non-price factors and sub-factors, there must be full disclosure of the teaming arrangement and company relationships in the team's proposal. The proposal must include a narrative that explains the major or critical aspects of the work to be performed by each team member. For joint venture teams, the proposal must also include an agreement that has been or will be executed prior to award between/among all team members. In the case of prime-sub teams, the prime contractor remains fully responsible for contract performance, regardless of any team arrangement between the prime contractor and its subcontractors.

However, regardless of whether a formal team arrangement is proposed or recognized, consistent with FAR 9.104, the Government may consider the responsibility of subcontractor team members when it may adversely affect the prospective prime contractor’s responsibility or when it is in the Government’s interest to do so.

2.1.2.2. Joint Venture Team Agreement. For joint venture offerors, a joint venture agreement that will govern he performance of the work by the joint venture must be submitted with the proposal. The agreement must address the following items: identification of team members, a delineation of roles and responsibilities of team members, the duration of the agreement, and the percentages of the participants including the controlling party. Agreements should not be subject to substantive revision because the agreement will be part of the evaluation process. The timely submission of the executed teaming agreement prior to award shall be a precondition to a finding of responsibility.

2.1.2.3. Restriction on Substitution. Regardless of any provision to the contrary in a team or subcontract agreement, any entity whose experience is submitted and attributed to the offeror for purposes of the Past Performance evaluation is required to meaningfully participate in any resulting contract as described in the offeror’s proposal. In the case of a prime-sub team arrangement where the subcontractor’s past performance is attributed to the prime for evaluation purposes, the Contracting Officer may permit the substitution of another subcontractor.

2.2. General Proposal Submission Requirements. To assure timely and equitable evaluation of proposals, Offerors must follow the instructions contained herein.

Offerors are required to meet all solicitation requirements, including terms and conditions, representations and certifications, and technical requirements, in addition to those identified as evaluation factors. The Offeror shall submit in the proposal all requested information specified in this section of the Request for Proposal (RFP) solicitation at or before the exact time specified. There will be no public opening of the proposals received as a result of this RFP. Failure to meet a requirement may result in an offer being ineligible for award. Copies of the RFP are available by INTERNET ACCESS ONLY. All RFP documents will be made available for viewing at the Sam.Gov website (https://sam.gov). All Solicitation Amendments will be made available for viewing in Sam.Gov. It shall be the Offeror’s responsibility to check the website for any Solicitation Amendments.

The Contracting Officer (KO) has determined there is a reasonable probability of adequate price competition in this acquisition. Upon examination of the initial offers, the KO will review this determination and if, in the KO's opinion, adequate price competition exists, no additional cost information will be requested and certification under FAR 15.406-2 will not be required.

However, if at any time during this competition, the KO determines that adequate price competition no longer exists; Offerors may be required to submit information to the extent necessary for the KO to determine the reasonableness and affordability of the price. The Government will evaluate all proposals pursuant to FAR 15.305(a).

Therefore, each initial offer should contain the Offeror’s best terms from a technical and price standpoint. Due to the magnitude of this procurement and in accordance with DFARS 215.306, it is the Government’s intent to conduct discussions with offerors in the competitive range following the procedures at FAR 15.306(c) and (d).

If an Offeror believes that the requirements in these instructions contain an error, omission or are otherwise unsound, the Offeror shall immediately notify the Contracting Division in writing (e-mail is the preferred method) with supporting rationale. Questions or other Requests for Information (RFI) shall be submitted via ProjNet (See Section 2.2.1).

This Request for Proposal (RFP) does not commit the Government to reimburse any costs incurred in the preparation and submission of a proposal or for any other costs incurred by any firm submitting a proposal in response to this Solicitation. Issuance of this RFP does not constitute an award commitment on the part of the Government. Proposals must set forth full, accurate and complete information as required by this RFP, including attachments, if applicable. The penalty for making false statements is prescribed in 18 U.S.C. § 1001.

Offerors are cautioned that “parroting” of the Technical requirements with a statement of intent to perform does not reflect an understanding of the requirement or capability to perform.

Offerors are responsible for including sufficient details to permit a complete and accurate evaluation of each proposal. Proprietary information shall be clearly marked.

2.2.1. Inquiries. Interested parties with technical inquiries shall submit their inquiries in writing via “Bidder Inquiry” in ProjNet at www.projnet.org\projnet. The bidder inquiry key is KN78DY-AH8ATX. The Government reserves the right to decline addressing certain questions. Further, no questions, unless in the Government’s interest, will be answered any later than seven (7) calendar days prior to the stated deadline for responses to this announcement.

Questions and answers will be made via ProjNet; any changes to contract requirements will only be made through amendment(s). Official amendments to the RFP will be made on Sam.Gov. All Offerors are encouraged to register on ProjNet for alerts to stay abreast of Q&A’s that are posted in reference to this solicitation. Only self-registered users on ProjNet can submit & review inquiries.

To self-register, go to the webpage, click Register, select Agency USACE, SAC Charleston District, enter the required information, and select Register. Once registered, enter your email address and the Bidder Inquiry Key and from there you may submit and view inquiries. Those submitting inquiries will receive a system generated email notification when their inquiry has been processed and answered. It is the Offeror’s responsibility to monitor for inquiries and responses.

2.2.2. Electronic Proposals.

The Offeror’s bid/proposal shall be submitted electronically, as described below. The Offeror’s proposal shall not contain classified data. The use of hyperlinks in proposals are prohibited. The offeror’s technical proposal is due no later than the time specified in block 13 of the SF1442. The offeror’s price proposal (Volume III) is due approximately twenty-one (21) calendar days from the time specified (The time applicable will be the same) in block 13 of the SF1442. An amendment will be posted clarifying the date and time following receipt of the initial technical proposals.

NOTE: The only authorized transmission method for offers in response to this solicitation is electronically via Procurement Integrated Enterprise Environment

(PIEE) Solicitation Module. NO OTHER TRANSMISSION METHODS (EMAIL, FACSIMILE, REGULAR MAIL, HAND CARRIED, ETC.) WILL BE ACCEPTED.

The Offeror’s proposal must be received by the Government by the date/time specified in the solicitation.

2.2.2.1. INSTRUCTIONS FOR SUBMITTING ELECTRONIC BIDS:

In an effort to reduce paperwork and cost, all bids shall be submitted electronically through the PIEE site. Submission shall be in Adobe PDF format.

Electronic submission sent via facsimile will not be accepted. Hand carried delivery or USPS/UPS/Fedex delivery of hard copies and/or CD-ROMs is not authorized.

Submissions that are received after the submission time requested will be considered late and as such will be processed in accordance with FAR 15.208

2.2.2.2. INSTRUCTIONS TO FOLLOW TO GAIN ACCESS TO THE WEBSITE:

Web Based Training for registration and proposal submission is available as a separate portal on the main page of the site or by visiting https://pieetraining.eb.mil/wbt/xhtml/wbt/sol/index.xhtml.

Although you can search, review, and open non-restricted solicitations without logging in, you must establish a personal account in the system and register for the Proposal Manager role before you are able to submit a proposal. This account is activated by your Contractor Administrator (CAM).

Instructions for registering are as follows:

a. Navigate to https://piee.eb.mil/

b. Select Register [top right]

c. Select Vendor

d. Create a User ID and Password and follow the prompts [next]

e. Create Security Questions [next]

f. Complete your User Profile Information [next]

g. Complete your Supervisor or Approving Official Information. This official will act as the CAM who will ultimately approve your account. If you are unsure of who this is please go to https://piee.eb.mil/xhtml/unauth/lookup/gamLookup.xhtml to locate the CAM for your company for assistance. [next]

h. Complete Roles - Step 1. Select SOL-Solicitation, Step 2. Select Proposal

Manager, Step 3. Click Add Roles, Step 4. Fill in your Location Code (CAGE Code) [next]

i. Provide a justification for your registration [next]

VERIFY ACCOUNT STATUS/CAPABILITIES. Once the Proposal Manager account has been approved, verify that your account is showing active under the profile page. Also, once you click on the specified solicitation, verify that the “Offer” tab is visible next to the “Solicitation” tab at the top of the page.

The proposal will be submitted through the “Offer” tab. It is imperative that this is verified early in the process in order to mitigate any potential problems with the submission of your proposal.

2.2.2.3. INSTRUCTIONS TO FOLLOW ON THE PIEE WEBSITE FOR OFFER

SUBMISSION:

In order to submit through the Solicitation Module in PIEE, you must have an active Proposal Manager role in PIEE at https://piee.eb.mil/.

To upload the proposal in Solicitation module in PIEE:

1. Ensure you have an active role as with the Proposal Manager in PIEE.

2. Log into PIEE at https://piee.eb.mil/ to access the Solicitation Module.

3. Select Solicitation icon.

4. At the Home screen of the Solicitation Module, select the Search link to find the solicitation you intend to post an offer against.

5. In the Solicitation Search Criteria filter by entering the complete solicitation number and for Status, select Open, then click Search.

6. When search results display, select the solicitation number link to open the solicitation.

7. The solicitation displays, with information as view only.

8. To post the offer, click the Offer tab.

9. Click the Add button to add an offer to the solicitation.

10. Select the applicable CAGE Code for which you are submitting the offer.

The list is prefiltered based on the CAGEs in the Proposal Manager’s profile.

11. Click on the Choose Files link to upload attachments that comprise your offer.

12. Enter Signature Date and click Signature button after entering all necessary information.

13. Sign Document pop-up will be displayed requiring the user to enter a Digital Pin and OTP.

Click the Sign and Submit button to continue.

14. After successfully adding the Offer a success message of the submission will be displayed providing confirmation of on-time/late proposal receipt.

2.2.3. File Size Limitations. Offerors are advised if needed, to break the files down into smaller sections in order to upload. In such cases, please divide the sections as logically as possible and be sure to clearly name the files as specified below.

2.2.4. File Names. To ensure your submission is received and processed appropriately, it is important that interested parties CAREFULLY ensure their electronic files adhere to the following naming convention: Each filename shall begin with the solicitation number, followed by the word “RESPONSE”, followed by your firm’s name, and finally a brief file description. EXAMPLES:

“W912HP24R2000 RESPONSE Firmname Volume I.pdf” “W912HP24R2000 RESPONSE Firmname Volume II.pdf”

2.2.5. File Organization, Formatting, and other instructions. Although hard copies are not accepted, each file shall be clearly indexed, and logically assembled.

Font size shall be 10 or larger. Pages shall be letter sized--larger page sizes (such as 11x17 foldouts, etc.) will be counted as two pages. Offerors shall prepare proposals in the English language. Proposals shall be in a narrative format, organized and titled so that each section of the proposal follows the order and format of the factors. Information presented should be organized so as to pertain to only the evaluation factor in the section that the information is presented. Information pertaining to more than one evaluation factor should be repeated in each section for each factor. Electronic files shall be in pdf format, in searchable text.

2.2.6. Upload Completion & Deadline. For the purposes of establishing whether a bid submission is considered timely, the government considers the date and time the submission is completely uploaded into the PIEE website. Do not assume that electronic communication is instantaneous. It can take several minutes or even hours in some cases.

The Government will not be responsible for submissions delivered to any location or to anyone other than those designated to receive bids. Offerors are responsible for ensuring that bids are submitted so as to reach the designated recipient. Offerors are responsible for allowing for allowing sufficient time for the bid to be received in accordance with the instructions provided.

Submissions after the deadline will be processed in accordance with FAR 15.208.

3. Definitions: The following definitions are provided to assist evaluators in the evaluation process:

3.1. Strength. An aspect of an offerors’ proposal that has merit or exceeds specified performance or capability requirements in a way that will be advantageous to the

Government during contract performance.

3.2. Significant Strength. An aspect of an offerors’ proposal that has appreciable merit or appreciably exceeds specified performance or capability requirements in a way that will be appreciably advantageous to the Government during contract performance.

NOTE: Strengths and significant strengths identified in the successful offerors proposal will be incorporated in the resultant contract, if deemed appropriate.

3.3. Weakness. A flaw in the proposal that increases the risk of unsuccessful contract performance.

3.4. Significant Weakness. A flaw in the proposal that appreciably increases the risk of unsuccessful contract performance.

3.5. Deficiency. A material failure of a proposal to meet a government requirement or a combination of significant weaknesses in a proposal that increases the risk of unsuccessful contract performance to an unacceptable level.

3.6. Uncertainty. Any aspect of a non-cost/price factor proposal for which the intent of the offeror is unclear (e.g., more than one way to interpret the offer or inconsistencies in the proposal indicating that there may have been an error, omission or mistake).

3.7. Adverse Past Performance. Past performance information that supports a less than satisfactory rating on any evaluation.

4. General Proposal Format

Proposal sections should parallel the submission requirements identified herein.

4.1. Volume I shall include the following information:

Volume I – Title Page: Include the title of the solicitation, solicitation number, Offeror name, and date of the submittal.

Volume I – Table of Contents Volume I – Tab A: Standard Form 1442 - completed and signed by authorized individual(s) of the Offeror. Offers submitted in the name of a Joint Venture must be signed in accordance with the terms and conditions specified in the joint venture agreement as evidenced in the proposal.

Volume I – Tab B: Proposal Data Sheet (Attachment 1) Volume I – Tab C: Section 00 45 00 Representations and Certifications Volume I – Tab D: Teaming/Joint Venture Agreements (if applicable) Volume I – Tab E: Proof of Bonding Capability – The Offeror is not required to submit a bid bond at the time of the Technical Proposal but is required to submit a letter, from the contractor’s surety validating the Offeror’s bonding capability and a power of attorney if applicable. Any letter found to be insufficient may affect an Offeror’s responsibility determination.

Volume I – Tab F: Proof of Financial Ability – o Submit Proof of Financial Ability (Most recent financial statement covering assets and liabilities). Include the name, address, and telephone number of the offeror’s banking institution. If the offeror is a joint venture, submit this information for each joint venture member.

o Provide a list of all current contracts held, total dollar value, award date, anticipated completion, performance and payment bond amount.

4.2. Volume II shall include the following information:

Volume II – Table of Contents Volume II – Tab G: Teaming/Joint Venture Agreements (Duplicate of Volume I if applicable) Volume II – Tab H: Factor 1: Past Performance Volume II – Tab I: Factor 2: Management Approach Narrative Volume II – Tab J: Factor 3: Small Business Participation Agreement

NOTE: Failure to place the required submission information under the appropriate tab may result in a lower rating if the evaluators cannot readily find the appropriate information.

Any specified page limits will be strictly adhered to and enforced. Information submitted which exceeds the specified limit will not be evaluated.

4.3. Volume III shall include the following information:

Volume III – Title Page: Include the title of the solicitation, solicitation number, Offeror name, and date of the submittal.

Volume III – Table of Contents Volume III – Tab K: Factor 4: Completed Bid Schedule (Price) Volume III – Tab L: Bid Bond o Bid bonds shall be submitted electronically accompanying the Price Volume

Volume III – Tab M: Subcontracting Plan o Each Large Business offeror shall provide a Small Business Subcontracting

Plan that contains all the elements required by FAR 52.219-9 (and supplements). This plan shall be submitted separately from the Small Business Participation Plan information required above, which applies to both large and small businesses. The goals within the Subcontracting Plan shall match those submitted within the Small Business Participation Plan. The Small Business Subcontracting Plan is not a requirement for evaluation in source selection, but rather a requirement for award to a large business and will be incorporated into any resultant contract.

Volume III – Tab N: Factor 5: Project Labor Agreement

5. Tab K – Completed Bid Schedule (Price)

5.1. Price will not be rated but will be a factor in establishing the completive range prior to discussions and in making the best value decision for award of any resultant contract.

5.2. The price will be evaluated on base proposal plus all options (if any).

5.3. The Government will perform a price analysis on all proposals received. Price analysis will be performed on the Price Schedule(s) in accordance with FAR 15.404- 1, to determine fairness and reasonableness. Historical price information, competitive price information, the Independent Government Estimate (IGE), or any other pricing tool as necessary will be utilized in this analysis. The evaluation will determine the extent to which the price proposal is consistent with the requirements of the RFP.

5.4. The Government may determine that a proposal is unacceptable if the prices proposed are materially unbalanced between line items or subline items (FAR 15.404- 1). Unbalanced pricing exists when, despite an acceptable total evaluated price, the price of one or more contract line items is significantly overstated or understated as indicated by the application of cost or price analysis techniques.

6. Tab H – Factor 1 – Past Performance

6.1. Submission Requirements

6.1.1. The Offeror shall demonstrate a record of past experience on recent and relevant projects using the Past Performance Questionnaire Summary Sheet, Attachment 2, and the Past Performance Questionnaire (PPQ), Attachment 3 at the end of this section. The PPQ is provided for the Offeror to submit to the client (Point of Contact) for each relevant project submitted.

Offeror must ensure correct phone numbers and email addresses are provided for the client. Completed PPQs must be submitted with your proposal by the specified closing date and time. Offerors should follow-up with clients to ensure timely submittal of completed questionnaires. If the offeror is unable to obtain a completed PPQ from a point of contact for a project(s) before proposal closing date, the Offeror shall complete blocks 1 – 5 of the PPQ and submit it with the proposal. Please note that, at a minimum, this first page of the PPQ must contain sufficient information for the government to determine the relevancy of the project. In addition, this will provide contract and client information for the respective project(s).

The Government may call and confirm information provided by the Offeror on the PPQs with the points of contact to the extent necessary to verify the information in the PPQ or to obtain additional information. The Government reserves the right to interview other individuals with direct knowledge of the offeror’s performance. The Offeror must provide the correct phone numbers and email addresses for the client Point of Contact. If the Government is unable to verify the information provided on the PPQs with the client Point of Contact, or by other sources available (e.g., CPARS), the Government reserves the right to disregard that project when evaluating the Offeror’s past performance and experience. Similarly, it is important for the PPQs to be signed by the Point of Contact. If PPQs are not signed by the client, the Government reserves the right to disregard the past performance ratings for that particular project.

By exception, the client may request submission of questionnaires directly to the Government’s point of contact (Contract Specialist), Holly Sopiak.

Request may be made via email to Holly.J.Sopiak@usace.army.mil. This request must be coordinated by the client in advance no later than five (5) business days before the proposal due date. If the PPQ fails to arrive before the closing date and time, or if the information on the PPQ is insufficient to determine the Offeror’s name and appropriate solicitation number, it will not be considered.

Offerors are cautioned that the information submitted pertaining to a project shall be limited to the PPQ form and an additional page referenced below and shall contain enough information to determine the recency and relevancy of a project.

Likewise, Project Information not submitted on the provided PPQ form will not be considered. Offerors shall not incorporate by reference into their proposal PPQs previously submitted for other solicitations. Offerors may submit PPQs submitted on other procurements provided they are on the NAVFAC/USACE Past Performance Questionnaire Form.

Offerors may attach one (1) additional single-sided page (per PPQ) to further describe how the project is relevant to the RFP requirements. The following items shall be able to be derived from either the PPQ or the additional page:

a) Project Title, Contract Number, Location, and identify the entity serving as the Prime Contractor. Provide the role of the submitting offeror if not serving as the Prime Contractor.

b) Current percentage of construction complete and when it was or will be completed. If project is not yet complete, provide a description of work remaining to be completed.

c) Scope of the project, to include purpose/use of facility.

d) Size of the project (sq ft). Differentiate square footage of new construction versus renovation if the project includes both.

e) Role of firm; provide a description of type of work performed and percentage of work self-performed.

f) Dollar value of the project. List award and final including explanations for cost increases over 10%.

g) Award date, original Construction Completion Date (CCD) and explanations for schedule growth over 10%.

i) Whether the project was design/build (indicate designer of record) or design/bid/build.

j) Customer Primary Point of Contact and alternate POC (name, relationship to project, agency/firm affiliation, city, state, current and correct phone number, and current and correct email address).

In addition to the PPQ, the Offeror’s proposal shall include the Past Performance Questionnaire Summary Sheet (Attachment 2) to provide a summary of the PPQs included and/or submitted to clients. The summary sheet shall include information for all columns.

If the offeror is a joint venture, the projects may be submitted for the joint venture itself or by members of the joint venture. Offerors are advised to submit projects wherein the Offeror, or proposed joint venture members, played a significant role and to clearly define those roles. If any Offeror has multiple functions or divisions, limit the project examples to those performed by the division or unit submitting the offer.

Ensure that the PPQs submitted for this Factor clearly describe the relevant characteristics of the project.

6.1.2. Submission Requirements:

6.1.2.1. The Prime / Construction Offeror shall submit a minimum of three (3), but no more than five (5), substantially complete (80% construction complete) or completed projects as the prime contractor or a major subcontractor within the last seven (7) years prior to the date of the issuance of the solicitation which are relevant to the work described in the scope of this contract. If an Offeror submits more than five (5) total project examples, only the first five

(5) in the order in which the submitted projects appear in the proposal will be evaluated. (See following paragraphs.)

6.1.2.2. Recency. All projects submitted for the Prime / Construction Offeror must be substantially completed (80% construction complete) within the last seven (7) calendar years prior to the issuance of this solicitation. An Indefinite Quantity Indefinite Delivery (IDIQ) contract may be submitted only if a single task order could be considered similar to this project. Submissions referencing the base indefinite delivery contract alone will not be considered. Task orders may not be combined in order for the project to be considered similar or to meet minimum dollar thresholds stated herein.

6.1.2.3. Relevancy. To be considered relevant, projects must meet the following criteria: Have a total project value of at least $45,000,000 at the time of award and be for new construction within the Continental United States (CONUS) that are similar in scope. Total project value includes the total value of vertical (building) construction and supporting facilities. Vertical (building) construction must represent no less than $25M of the $45M total project value.

6.1.2.3.1. Projects completed outside the Continental United States

(OCONUS) may also be considered if the Offeror can demonstrate that the project(s) was completed using similar construction techniques and standards as CONUS projects, i.e., U.S.

Government installations. “Similar” construction can be defined as of the same type building(s) and complexity to that of the Reception Barracks Complex Phase II.

6.1.2.3.2. Specifically projects considered similar in scope to this requirement include new construction of Administrative/Office Facilities, Medical Facilities, Barracks/Dormitory Facilities. Renovation of facilities will not be considered similar in scope.

6.1.2.3.3. Other elements of relevancy that will result in additional consideration for a higher relevancy rating:

i. projects that are LEED Silver certified. Actual LEED certification rather than simply the incorporation of LEED or sustainable features.

ii. performance among dispersed multiple sites, buildings, and/or facilities, i.e., projects that are part of a campus, industrial park, etc.

iii. performance that involves construction of buildings greater than 50,000 SF

iv. performance that involves construction of projects which includes significant site work including utility infrastructure, storm drainage, site grading, paving, and parking, and/or landscaping.

v. Projects that involve phasing of construction, i.e., buildings or other significant elements of work completed prior to continuing construction,

6.2. Other Sources. In addition to the above, the Government may review any other sources of available information other than those provided by the Offeror for evaluating past performance. These other sources may include but are not limited to, past performance information retrieved through the Past Performance Information Retrieval System (PPIRS), including Contractor Performance Assessment Reporting System (CPARS), using all CAGE/UEI numbers identified in the proposal on the Proposal Data Sheet, inquiries of owner representative(s), Federal Awardee Performance and Integrity Information System (FAPIIS), Electronic Subcontract Reporting System (eSRS), and any other known sources not provided by the Offeror.

If a CPARS evaluation exists for a submitted project, it will be considered.

While the Government may elect to consider data from other sources, the offeror must provide detailed, current, accurate and complete past performance information for evaluation by the Government.

6.3. Evaluation Criteria

6.3.1. Past Performance Evaluation: The past performance and experience evaluation results in an assessment of the Government’s confidence in the ability of the Offeror to meet the solicitation requirements. The past performance evaluation considers each Offeror’s demonstrated record of performance and experience on recent and relevant projects that involve a similar scope and magnitude of effort and complexities as this solicitation requires. One performance confidence assessment rating is assigned for each Offeror after evaluating the Offeror’s recent past performance and experience, focusing on performance and experience that is relevant to the contract requirements.

6.3.2. Recency and Relevancy Evaluation: Projects must meet the minimum criteria in sections 6.1. (and subsections) to be considered recent and relevant. If minimum criteria are met, projects will then be evaluated against the requirements of the RFP. Projects will be evaluated for relevancy based on the description of the project.

TABLE 1 - Past Performance Relevancy Ratings

Rating Definition Very Relevant Present/past performance effort involved essentially the same scope and magnitude of effort and complexities this solicitation requires.

Relevant Present/past performance effort involved similar scope and magnitude of effort and complexities this solicitation requires.

Somewhat Relevant Present/past performance effort involved some of the scope and magnitude of effort and complexities this solicitation requires.

Not Relevant Present/past performance effort involved little or none of the scope and magnitude of effort and complexities this solicitation requires.

6.3.3. Confidence Assessment:

6.3.3.1. The SSEB may have a higher level of confidence in an Offeror’s past performance if its proposal demonstrates successful performance in a wide variety of the similar work types as described in section 6.1.3.1. 2 of this RFP.

Conversely, the SSEB may have a decreased level of confidence in Offerors whose past performance is limited amongst the project types described in this RFP.

6.3.3.2. The Government will evaluate the Offeror's past performance and experience using the sources available to it including but not limited to: the example projects identified by the Offeror and submitted on the PPQs and any additional information received from references and CPARS or other sources.

Offerors may be provided an opportunity to address any negative past performance information, through clarifications, which the Offeror has not previously had an opportunity to respond if such information is determined to impact the rating to be assessed.

6.3.3.3. The Government will consider the recency of the performance, the relevancy including the context of the data, and the quality of the performance and general trends in performance and source of the information to reach a confidence assessment rating using Past Performance Confidence Ratings.

6.3.3.4. If no recent/relevant performance record is available or the Offeror’s performance record and experience is so sparse that no meaningful confidence assessment rating can be reasonably assigned this factor will be assigned a rating of “Unknown Confidence” (Neutral).

TABLE 2 - Performance Confidence Assessments

Rating Description

Substantial Confidence Based on the offeror’s recent/relevant performance record, the Government has a high expectation that the offeror will successfully perform the required effort.

Satisfactory Confidence Based on the offeror’s recent/relevant performance record, the Government has a reasonable expectation that the offeror will successfully perform the required effort.

Limited Confidence Based on the offeror’s recent/relevant performance record, the Government has a low expectation that the offeror will successfully perform the required effort.

No Confidence Based on the offeror’s recent/relevant performance record, the Government has no expectation that the offeror will successfully perform the required effort.

Unknown Confidence (Neutral) No recent/relevant performance record is available, or the offeror’s performance record is so sparse that no meaningful confidence assessment rating can be reasonably assigned.

7. Tab I – Factor 2: Management Approach Narrative

7.1. Submission Requirements:

7.1.1. Project Organization Chart. The offeror shall submit a Project Organization Chart including all team members and key subcontractors identified in the proposal and depicting each Key Personnel position intended to perform on the contract. The organizational chart must identify and integrate the positions of different team members and subcontractors and show lines of authority. The Project Organization Chart must be specific to this procurement, and not a generic document. The Organization Chart is limited to one-page NTE 11” x 17” in size.

7.1.2. Organization Narrative. The offeror shall submit a narrative consistent with the Project Organization Chart that describes what firms will be used, their roles and responsibilities and any contractual arrangements that have been established.

Recognized contractor team arrangements must meet the requirements of Section 2.1.2., above. List the major work elements to be self-performed by the Offeror’s in-house workforce(s), the major work elements to be performed by each key subcontractor, and any significant work items for which a subcontractor has not been identified. The Team Organization narrative is limited to three 8-1/2” x 11” pages.

7.1.3. Management Plan. The Offeror shall provide a Management Plan developed specifically for this project. The information should make it clear that the Offeror has the ability to deliver a quality product and effectively manage all team members and subcontractors, as well as the ability to coordinate all work throughout construction. As a minimum, the plan should address the following:

Quality Control Procedures: Describe the Offeror’s quality control approach and capabilities to maintain quality control throughout construction. The discussion should address the offeror’s understanding of, familiarity with, and intended use of the U.S. Army Corps of Engineers specific procedures and automated information management/tracking systems related to quality control. Describe the proposed quality control organization, including the staffing plan required by Section 01 45 00.10.

Subcontractor Management: Describe how the Offeror will coordinate and control all subcontractors to be utilized on the project. Discuss methods to be employed to avoid conflict between subcontractors.

Scheduling and Phasing: Describe the time control capabilities and systems to be used to plan the work and how the schedule will be used to manage construction. The narrative shall demonstrate a clear understanding of the project phasing and sequencing of construction required by the RFP.

Preparation and Submission of As-Built Documents: Describe how the Offeror will maintain an accurate set of as-builts throughout the project, including the method that will be used to capture mark-ups on the construction drawings and how will this information be disseminated to the Government at close out.

Contract close out: Describe the Offeror’s intended procedure to be used for close out of the project.

The Management Plan may include narrative and/or graphics and is limited to seven 8- 1/2” x 11” pages. Although a standard format is not specified, each of the items of information should be presented in essentially the same order as discussed below.

7.2. Evaluation Criteria:

7.2.1. Management Evaluation: The Government will evaluate the adequacy and feasibility of the Offeror's Management Approach. The Government will evaluate completeness, reasonableness, risk, and logic of each of the proposals’ Project Organization Chart, Organization Narrative, and Management Plan. A proposal lacking any one of these three items will be rated Unacceptable. The Project Organization Chart must integrate all team members/positions and key subcontractors, and show lines of authority.

Omission of entities or individuals, the failure to depict lines of authority, or the submission of a generic organization chart may result in a rating of Unacceptable. The Organization Narrative must be consistent with the Project Organization Chart, and include a discussion of roles, responsibilities, contractual arrangements, and major work items that is logical, and includes a viable approach to perform the work. Omission of one or more of these items may result in a rating of Unacceptable. The Management Plan will be evaluated to ensure that it includes distinct sections describing Quality Control Procedures, Subcontractor Management, Scheduling and Phasing, Preparation and Submission of As-Built Documents, and Contract close out.

Omission of adequate descriptions specific to this project for any area of the Management Plan may result in a rating of Unacceptable.

7.2.2. The Government will evaluate the strengths, weaknesses, and any deficiencies in the submission, as defined above (See Section 3 above).

Based on the submission provided, the Government will evaluate the Offeror’s overall management narrative, and its understanding and capability to execute an awarded contract. For this factor, Offerors will be assigned a combined risk rating from the following table, based on the evaluation of the Offeror’s proposal in accordance with the requirements of the solicitation.

TABLE 3 - Combined Technical/Risk Ratings

Adjectival Rating Definition Outstanding Proposal indicates an exceptional approach and understanding of the requirements and contains multiple strengths, and risk of unsuccessful performance is very low.

Good Proposal indicates a thorough approach and understanding of the requirements and contains at least one strength, and risk of unsuccessful performance is low.

Acceptable

Proposal meets requirements and indicates an adequate approach and understanding of the requirements, and risk of unsuccessful performance is no worse than moderate.

Marginal Proposal has not demonstrated an adequate approach and understanding of the requirements, and/or risk of unsuccessful contract performance is high.

Unacceptable Proposal does not meet requirements of the solicitation, and thus…