B.08.02 Solicitation.W912DQ22B1004 RTA W_SPECS 20220211.pdf

PDF 4 MB Posted

Attached to
Wilson Relief Well Project, Russell County, KS (Wilson Dam on Saline River)
Solicitation number
W912DQ22B1004
Issued by

About this file

This is a solicitation for construction services related to the Wilson Relief Well project located in Russell County, Kansas. The solicitation seeks bids for work including installation and development of relief wells, modification of discharge piping for existing relief wells, lining of existing relief wells, abandonment of existing wells, earthwork, rockwork, and clearing of vegetated areas. Additional work includes replacement of drainage features. The scope of work includes furnishing all necessary equipment, labor, quality control, supplies and materials to satisfactorily perform construction activities such as relief well replacement. Bids are due by 15 March 2022 and shall be submitted electronically to the contract specialist. The solicitation is issued by the Department of the Army Corps of Engineers Engineering District Kansas City for an estimated price range between $500,000 and $1,000,000.

View the file

Other files

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

US Army Corps of Engineers Kansas City District Building Strong

Wilson Lake Dam Saline River, Kansas Install Relief Wells P2-480831

As Advertised

Construction Specifications and Solicitation

February 2022

W912DQ22B1004

This page was intentionally left blank for duplex printing.

TC-1

DEPARTMENT OF THE ARMY

Kansas City District, Corps of Engineers

647 Federal Building Kansas City, Missouri 64106

SPECIFICATIONS FOR PERFORMANCE

WILSON LAKE DAM

SALINE RIVER, KANSAS

INSTALL RELIEF WELLS

COVER

TABLE OF CONTENTS

DIVISION 00 PROCUREMENT AND CONTRACTING REQUIREMENTS

SECTION TITLE

00 01 05 CERTIFICATION PAGE

00 10 00 SOLICITATION

00 21 00 INSTRUCTIONS

00 45 00 REPRESENTATIONS AND CERTIFICATIONS

00 70 00 CONDITIONS OF THE CONTRACT

00 72 00 GENERAL CONDITIONS

DIVISION 1 – GENERAL REQUIREMENTS

SECTION TITLE

01 11 00 SUMMARY OF WORK

01 20 00 PRICE AND PAYMENT PROCEDURES

01 30 00 ADMINISTRATIVE REQUIREMENTS

01 32 16.00 23 SMALL PROJECT CONSTRUCTION PROGRESS SCHEDULES

01 33 00 SUBMITTAL PROCEDURES

01 35 26 GOVERNMENTAL SAFETY REQUIREMENTS

01 45 00.00 10 01 45 00.15 10 01 50 00

QUALITY CONTROL

RESIDENT MANAGEMENT SYSTEM CONTRACTOR MODE (RMS CM)

TEMPORARY CONSTRUCTION FACILITIES AND CONTROLS

01 57 19 TEMPORARY ENVIRONMENTAL CONTROLS

01 74 19 01 78 00 01 78 23

CONSTRUCTION WASTE MANAGEMENT AND DISPOSAL

CLOSEOUT SUBMITTALS

OPERATIONS AND MAINTENANCE DATA

DIVISION 02 – EXISTING CONDISTIONS

02 41 00 DEMOLITION

DIVISION 31 – EARTHWORK

31 00 00 EARTHWORK

31 11 00 CLEARING AND GRUBBING

DIVISION 32 – EXTERIOR IMPROVEMENTS

32 92 19 SEEDING

DIVISION 33 – UTILITIES

33 26 00.00 10 RELIEF WELLS

33 40 00 STORM DRAINAGE UTILITIES

This page was intentionally left blank for duplex printing.

Wilson Relief Well Project

The Wilson Relief Well project w ill include Construction Activities for installation of relief w ells at Wilson Dam, Kansas located in Russell County. The covered w ork w ill include all activities associated w ith installation and development of relief w ells along w ith associated outfalls, modif ication of the discharge piping for existing relief w ells, lining of existing relief w ells and abandonment of existing w ells. The covered w ork w ill also include earthw ork, rockw ork, and clearing of vegetated areas. Additional w ork w ill include replacement of drainage features to transmit f low s from relief w ells and seepage from the sandstone face upstream of the outlet w orks.

X

SHEILA D NIMROD 816-389-2252

NOTE: In sealed bid solicitations "offer" and "offeror" mean "bid" and "bidder".

10. THE GOVERNMENT REQUIRES PERFORMANCE OF THE WORK DESCRIBED IN THESE DOCUMENTS

NEGOTIATED

11-Feb-2022

(RFP)

(IFB)

CALL:

B. TELEPHONE NO. (Include area code) (NO COLLECT CALLS)

See Item 7

2. TYPE OF SOLICITATION

SEALED BID

3. DATE ISSUED

9. FOR INFORMATION A. NAME

SOLICITATION

NSN 7540-01-155-3212 1442-101 STANDARD FORM 1442 (REV. 4-85)

Prescribed by GSA FAR (48 CFR) 53.236-1(e)

11. The Contractor shall begin performance w ithin _______10 calendar days and complete it w ithin ________270 calendar days after receiving aw ard, X notice to proceed. This performance period is X mandatory, negotiable. (See _________________________52.211-10

12 A. THE CONTRACTOR MUST FURNISH ANY REQUIRED PERFORMANCE AND PAYMENT BONDS?

(If "YES," indicate within how many calendar days after award in Item 12B.)

X YES NO

13. ADDITIONAL SOLICITATION REQUIREMENTS:

A. Sealed offers in original and __________2 copies to perform the w ork required are due at the place specif ied in Item 8 by ___________ local time ______________15 Mar 2022 (date). If this is a sealed bid solicitation, offers must be publicly opened at that time.

shall be marked to show the offeror's name and address, the solicitation number, and the date and time offers are due.

B. An offer guarantee X is, is not required.

C. All offers are subject to the (1) w ork requirements, and (2) other provisions and clauses incorporated in the solicitation in full text or by reference.

D. Offers providing less than _______90 calendar days for Government acceptance after the date offers are due w ill not be considered and w ill be rejected.

SOLICITATION, OFFER,

AND AWARD

(Construction, Alteration, or Repair)

1. SOLICITATION NO.

IMPORTANT - The "offer" section on the reverse must be fully completed by offeror.

4. CONTRACT NO.

7. ISSUED BY CODE

USACE, KANSAS CITY +

FEDERAL BLDG, CT-C

601 E 12TH ST RM 647

KANSAS CITY MO 64106-2896

W912DQ

PAGE OF PAGES

1 OF

CODE

(Title, identifying no., date):

12B. CALENDAR DAYS

10:00 AM (hour) Sealed envelopes containing offers

5. REQUISITION/PURCHASE REQUEST NO. 6. PROJECT NO.

8. ADDRESS OFFER TO (If Other Than Item 7)

816-389-2029/2030FAX:TEL: 816-389-3812 TEL: FAX:

W912DQ22B1004 101

20B. SIGNATURE

(REV. 4-85)STANDARD FORM 1442 BACK

TO SIGN

NSN 7540-01-155-3212

SOLICITATION, OFFER, AND AWARD (Continued) (Construction, Alteration, or Repair)

CODE FACILITY CODE

17. The offeror agrees to perform the w ork required at the prices specif ied below in strict accordance w ith the terms of this solicitation, if this offer is accepted by the Government in w riting w ithin ________ calendar days after the date offers are due.

the minimum requirements stated in Item 13D. Failure to insert any number means the offeror accepts the minimum in Item 13D.)

AMOUNTS SEE SCHEDULE OF PRICES

18. The offeror agrees to furnish any required performance and payment bonds.

19. ACKNOWLEDGMENT OF AMENDMENTS

(The offeror acknowledges receipt of amendments to the solicitation -- give number and date of each)

AMENDMENT NO.

DATE

20A. NAME AND TITLE OF PERSON AUTHORIZED TO SIGN

OFFER (Type or print)

AWARD (To be completed by Government)

21. ITEMS ACCEPTED:

22. AMOUNT 23. ACCOUNTING AND APPROPRIATION DATA

24. SUBMIT INVOICES TO ADDRESS SHOWN IN ITEM

(4 copies unless otherwise specified)

CODE

(Insert any number equal to or greater than

20C. OFFER DATE

25. OTHER THAN FULL AND OPEN COMPETITION PURSUANT TO

10 U.S.C. 2304(c) 41 U.S.C. 253(c)

CODE27. PAYMENT WILL BE MADE BY:26. ADMINISTERED BY

(Include ZIP Code)14. NAME AND ADDRESS OF OFFEROR 15. TELEPHONE NO. (Include area code)

See Item 14

(Include only if different than Item 14)16. REMITTANCE ADDRESS

30B. SIGNATURE

29. AWARD (Contractor is not required to sign this document.)

document and return _______ copies to issuing office.) Contractor agrees Your of f er on this solicitation, is hereby accepted as to the items listed. This award con-to f urnish and deliv er all items or perf orm all work, requisitions identif ied summates the contract, which consists of (a) the Gov ernment solicitation and on this f orm and any continuation sheets f or the consideration stated in this y our of f er, and (b) this contract award. No f urther contractual document is contract. The rights and obligations of the parties to this contract shall be necessary .

gov erned by (a) this contract award, (b) the solicitation, and (c) the clauses, representations, certif ications, and specif ications or incorporated by ref er-ence in or attached to this contract.

30A. NAME AND TITLE OF CONTRACTOR OR PERSON AUTHORIZED 31A. NAME OF CONTRACTING OFFICER (Type or print)

30C. DATE

(Type or print)

TEL: EMAIL:

31B. UNITED STATES OF AMERICA 31C. AWARD DATE

BY

CONTRACTING OFFICER WILL COMPLETE ITEM 28 OR 29 AS APPLICABLE

(Contractor is required to sign this28. NEGOTIATED AGREEMENT

(M ust be fully completed by offeror)OFFER

Section 00 01 05 - Certification Page

CAUTION PAGE

CAUTION !

BEFORE SIGNING AND EMAILING YOUR BID, please take note of the following, as failure to perform any one of these actions may cause your bid to be rejected.

a. AMENDMENTS: Have you acknowledged receipt of ALL Amendments? If in doubt as to number of amendments issued, please contact our office.

b. EMAILED BIDS: : INCLUDE A BID COVERSHEET WITH THE EMAILED BID. The Coversheet will show the Contractor name and address, the solicitation number (W912DQ22B1004), title of project, amendments received, and the date and time bids are due.

Mail in bids will not be accepted.

c. AMENDED BID PAGES: If any of the Amendments furnished amended bid pages, the amended bid page(s) must be used in submitting your bid.

d. LATE BIDS: Late bids will not be accepted. The date and time the bid is received by the Government will be used and not the time submitted.

e. BID GUARANTEE: Sufficient bid guarantee in proper form must be furnished with your bid, if your bid exceeds $150,000.

f. MISTAKE IN BID: Have you reviewed your bid prices for possible errors in calculations or work left out?

g. FACSIMILE BIDS AND MODIFICATIONS: Will not be considered. Facsimile withdrawals will not be considered.

h. HAND-DELIVERED BID: At this time, only emailed bids will be accepted.

i. BUY AMERICAN ACT: All bidders are cautioned that, prior Government conduct notwithstanding, the Contractor's selection of a domestic construction material which would require the subsequent selection of a foreign construction material for compatibility is not a justification for waiver of the Buy American Act. It is the Contractor's responsibility to verify, prior to submitting the materials for approval that each system can be built to meet the contract specifications without the use of foreign construction materials.

j. SUBMISSION OF BIDS AND BID OPENING: Due to the COVID-19 Global Pandemic, the Government is taking precautions to ensure the safety and health of all Contractors and Government employees. Electronic bids are REQUIRED. Mail-in and hand-delivered bids are NOT ALLOWED. The Contractor is required to ensure that the bid package is legible and completed. Bid bonds shall be copied to where the seals are legible in the copy. All documents shall be submitted in MSWord or Acrobat Adobe format.

k. SUPPLEMENTAL BID SCHEDULE: In addition to the Contract Line Item Schedule, contractors should complete the Supplemental Bid Schedule(s) provided. The Supplemental Bid Schedule(s) are not contractually binding. The Government will use the Supplemental Bid Schedule(s) to assist in the evaluation of bid prices. The individual supplemental bid schedule items should add up to the prices for the Contract Line Item Schedule (section 00 10 00 – Solicitation). In the event that the CLIN subtotal in a Supplemental Bid Schedule does not match the CLIN total in the Contract Line Item Schedule (section 00 10 00 – Solicitation) the Contract Line Item Schedule (section 00 10 00 – Solicitation) will be the price evaluated by the Government.

To Submit your bid electronically, to the Contract Specialist Sheila Nimrod at Sheila.d.nimrod@usace.army.mil . Keep in mind that due to email safeguards and the size of your bid package, emails may not be received immediately by the Government. Bids shall be received by the date and time specified for the bid opening. Refer to FAR 52.214-7 for how late bid packages are handled.

As another precaution, the conference room will be closed off to the public for viewing. In lieu of this, there will be a conference phone line available for all who are interested in attending the bid opening. The following information will be needed if you would like to call in for the bid opening:

Conference Line Number/Access code: 1-844 800-2712 Meeting Number:199 138 9013 # Security code: 1234

SYSTEM FOR AWARD MANAGEMENT (SAM):

In accordance with FAR 52.204-7: By submission of an offer, the offeror acknowledges the requirement that a prospective awardee shall be registered in the SAM database prior to bid opening, during performance and through final payment of any contract resulting from this solicitation. If the Offeror does not become registered in the SAM database in the time prescribed by the Contracting Officer, the Contracting Officer will proceed to award to the next otherwise successful registered Offeror. Offerors may obtain information on registration and annual confirmation requirements via the SAM database accessed through https://www.sam.gov/SAM/pages/public/index.jsf . It is highly encouraged that all prospective Offeror’s start the SAM’s registration process as soon as possible.

OFFEROR MUST BE REGISTERED IN THE SYSTEM FOR AWARD MANAGEMENT

PRIOR TO THE BID OPENING OR THE CONTRACT OFFICER MAY PROCEED WITH

AWARD TO THE NEXT SUCCESSFUL CONTRACTOR.

SAM.GOV REGISTRATION IS FREE OF CHARGE

mailto:Sheila.d.nimrod@usace.army.mil https://www.sam.gov/SAM/pages/public/index.jsf

If you were not previously registered, please go to https://www.sam.gov. Instructions for new registration are also located at the following site:

https://www.sam.gov/SAM/pages/public/help/samQUserGuides.jsf

IMPORTANT NOTE: SPRS NIST SP 800-171 Notice: Per DFARS 252.204-7012 the selected awardee offeror will need to be registered in NIST SP 800-171 prior to award of any contract/task order or any modification that is to exercise an option period or extend the period of performance of a contract/task order. To learn more information about the NIST SP 800-171 and learn how to register please go to https://www.sprs.csd.disa.mil/nistsp.htm.

If you have questions about Government procurements in general or need assistance in the preparation of your proposal, a local Procurement Technical Assistance Center (PTAC) may be able to help. The Procurement Technical Assistance Program was authorized by Congress in 1985 in an effort to expand the number of businesses capable of participating in the Government marketplace. To locate a PTAC near you, go to https://www.aptacus. org/find-a- ptac/

THIS A FREE SERVICE BY A NON PROFIT PAID FOR BY THE US GOVERNMENT.

ELECTRONIC BIDS ARE REQUIRED. MAILED AND HAND-DELIVERED BIDS ARE

NOT ALLOWED.

The Contractor is required to ensure that the proposal package is legible and complete. Bid bonds shall be copied and scanned so that all required raised seals are legible.

To submit your proposal by electronic mail (email) submit it to Contract Specialist, Sheila Nimrod (sheila.d.nimrod@usace.army.mil). Keep in mind that due to email safeguards and the size of your proposal package, emails may not be received immediately by the Government. The USACE email system will not accept attachments larger than 50MB. Bids shall be received by the date and time specified in the solicitation document.

It is recommended you contact the contract specialist by phone or email to confirm receipt of your proposal. Due to possible delays in networks and email it is highly recommended that proposals are submitted as early as possible. Do not wait until the last minute or your proposal may be late.

If the emailed proposal is not received due to technical issues or network issues, refer to FAR 52.214-7 for how late proposals are handled. If you have not confirmed receipt of your bid please note: Per this clause it is recommended that bidders ensure;” ….. it was transmitted through an electronic commerce method authorized by the IFB, it was received at the initial point of entry to the Government infrastructure not later than 5:00 p.m. one working day prior to the date specified for receipt of bids.”

If you have any questions, or cannot gain access to the conference line, contact Sheila Nimrod, Contract Specialist at (816) 389-2252.

https://www.sam.gov/SAM/pages/public/help/samQUserGuides.jsf https://www.sprs.csd.disa.mil/nistsp.htm https://www.aptacus/

IMPORTANT NOTE: Bidders should review specification 01 30 00, paragraph 1.24 Field Office Overhead (FOOH) . Please review choices and make a selection and return that page with your bid.

(END)

CLAUSES INCORPORATED BY FULL TEXT

252.204-7017 PROHIBITION ON THE ACQUISITON OF COVERED DEFENSE TELECOMMUNICATIONS

EQUIPMENT OR SERVICES--REPRESENTATION (DEC 2019)

The Offeror is not required to complete the representation in this provision if the Offeror has represented in the provision at 252.204-7016, Covered Defense Telecommunications Equipment or Services--Representation, that it “does not provide covered defense telecommunications equipment or services as a part of its offered products or services to the Government in the performance of any contract, subcontract, or other contractual instrument.”

(a) Definitions. Covered defense telecommunications equipment or services, covered mission, critical technology, and substantial or essential component, as used in this provision, have the meanings given in the 252.204-7018 clause, Prohibition on the Acquisition of Covered Defense Telecommunications Equipment or Services, of this solicitation.

(b) Prohibition. Section 1656 of the National Defense Authorization Act for Fiscal Year 2018 (Pub. L. 115-91) prohibits agencies from procuring or obtaining, or extending or renewing a contract to procure or obtain, any equipment, system, or service to carry out covered missions that uses covered defense telecommunications equipment or services as a substantial or essential component of any system, or as critical technology as part of any system.

(c) Procedures. The Offeror shall review the list of excluded parties in the System for Award Management (SAM) at https://www.sam.gov for entities that are excluded when providing any equipment, system, or service to carry out covered missions that uses covered defense telecommunications equipment or services as a substantial or essential component of any system, or as critical technology as part of any system, unless a waiver is granted.

(d) Representation. If in its annual representations and certifications in SAM the Offeror has represented in paragraph (c) of the provision at 252.204-7016, Covered Defense Telecommunications Equipment or Services-- Representation, that it “does” provide covered defense telecommunications equipment or services as a part of its offered products or services to the Government in the performance of any contract, subcontract, or other contractual instrument, then the Offeror shall complete the following additional representation:

The Offeror represents that it [ ] will [ ] will not provide covered defense telecommunications equipment or services as a part of its offered products or services to DoD in the performance of any award resulting from this solicitation.

(e) Disclosures. If the Offeror has represented in paragraph (d) of this provision that it “will provide covered defense telecommunications equipment or services,” the Offeror shall provide the following information as part of the offer:

(1) A description of all covered defense telecommunications equipment and services offered (include brand or manufacturer; product, such as model number, original equipment manufacturer (OEM) number, manufacturer part number, or wholesaler number; and item description, as applicable).

(2) An explanation of the proposed use of covered defense telecommunications equipment and services and any factors relevant to determining if such use would be permissible under the prohibition referenced in paragraph (b) of this provision.

https://www.sam.gov/

(3) For services, the entity providing the covered defense telecommunications services (include entity name, unique entity identifier, and Commercial and Government Entity (CAGE) code, if known).

(4) For equipment, the entity that produced or provided the covered defense telecommunications equipment (include entity name, unique entity identifier, CAGE code, and whether the entity was the OEM or a distributor, if known).

(End of provision)

Section 00 10 00 - Solicitation

ITEM NO SUPPLIES/SERVICES QUANTITY UNIT UNIT PRICE AMOUNT

0001 1 Job Site and Earthwork

FFP

Includes mobilization and demobilization, clearing of vegetated areas, pre-construction surveys, site protection measures such as fencing or high visibility markings, earthwork associated with added fills in accordance with the plans and specifications.

The work that will be covered by this contract consists of furnishing all equipment, labor, operators, supervisors/site superintendent, quality control, supplies, materials, and incidentals necessary to satisfactorily perform and provide construction to potentially include, but not limited to relief well replacement.

FOB: Destination

PSC CD: Y1KA

NET AMT

0002 1 Job Relief Well (RW) Installation

FFP

Lining, Modification, and Abandonment

Includes drilling, installation, development, inspection, and all other construction activities associated with installation of new wells, modification of existing wells, or abandonment of existing wells and rockwork around RWs. New wells to be installed include RW-3B, RW-4B. includes modification of the riser pipes for existing relief wells RW-11A, RW-12, RW-12A, and RW-13. Includes abandonment of existing RW-1 in accordance with the plans and specifications.

The work that will be covered by this contract consists of furnishing all equipment, labor, operators, supervisors/site superintendent, quality control, supplies, materials, and incidentals necessary to satisfactorily perform and provide construction to potentially include, but not limited to relief well replacement.

0003 1 Job OPTION Pipe Extension

FFP

Includes all work pertinent to extension of the existing 54 inch pipe approximately 130ft including earthwork associated with the pipe extension as well as rockwork at the pipe outfall in accordance with the plans and specifications.

The work that will be covered by this contract consists of furnishing all equipment, labor, operators, supervisors/site superintendent, quality control, supplies, materials, and incidentals necessary to satisfactorily perform and provide construction to potentially include, but not limited to RW replacement.

0004 1 Job OPTION Relief Well (RW)

FFP

Installation and Lining Includes drilling, installation, development, inspection, and all other construction activities associated with installation of RW-2B and lining of RW-2A in accordance with the plans and specifications.

The work that will be covered by this contract consists of furnishing all equipment, labor, operators, supervisors/site superintendent, quality control, supplies, materials, and incidentals necessary to satisfactorily perform and provide

0005 1 Job OPTION Relief Well (RW)

FFP

Installation and Lining

Includes drilling, installation, development, inspection, and all other construction activities associated with installation of RW-9B and lining of RW-9A in accordance with the plans and specifications.

The work that will be covered by this contract consists of furnishing all equipment, labor, operators, supervisors/site superintendent, quality control, supplies, materials, and incidentals necessary to satisfactorily perform and provide

0006 1 Job OPTION Relief Well (RW)

FFP

Installation and Lining Includes drilling, installation, development, inspection, and all other construction activities associated with installation of RW-10B and lining of RW-10A in accordance with the plans and specifications.

The work that will be covered by this contract consists of furnishing all equipment, labor, operators, supervisors/site superintendent, quality control, supplies, materials, and incidentals necessary to satisfactorily perform and provide

0007 1 Job OPTION Relief Well (RW)

FFP

Installation and Lining Includes drilling, installation, development, inspection, and all other construction activities associated with installation of RW-11B and lining of RW-11A in accordance with the plans and specifications.

The work that will be covered by this contract consists of furnishing all equipment, labor, operators, supervisors/site superintendent, quality control, supplies, materials, and incidentals necessary to satisfactorily perform and provide

0008 1 Job OPTION Relief Well (RW)

FFP

Installation and Lining

Includes drilling, installation, development, inspection, and all other construction activities associated with installation of RW-12B and lining of RW-12A in accordance with the plans and specifications.

The work that will be covered by this contract consists of furnishing all equipment, labor, operators, supervisors/site superintendent, quality control, supplies, materials, and incidentals necessary to satisfactorily perform and provide

0009 1 Job OPTION Relief Well (RW)

FFP

Installation

Includes drilling, installation, development, inspection, and all other construction activities associated with installation of RW-1B in accordance with the plans and specifications.

The work that will be covered by this contract consists of furnishing all equipment, labor, operators, supervisors/site superintendent, quality control, supplies, materials, and incidentals necessary to satisfactorily perform and provide

0010 1 Job OPTION Relief Well (RW)

FFP

Installation and Lining

Includes drilling, installation, development, inspection, and all other construction activities associated with installation of RW-6B and lining of RW-6A in accordance with the plans and specifications.

The work that will be covered by this contract consists of furnishing all equipment, labor, operators, supervisors/site superintendent, quality control, supplies, materials, and incidentals necessary to satisfactorily perform and provide

0011 1 Job OPTION Relief Well (RW)

FFP

Installation and Lining

Includes drilling, installation, development, inspection, and all other construction activities associated with installation of RW-7B and lining of RW-7A in accordance with the plans and specifications.

The work that will be covered by this contract consists of furnishing all equipment, labor, operators, supervisors/site superintendent, quality control, supplies, materials, and incidentals necessary to satisfactorily perform and provide

0012 1 Job OPTION Relief Well (RW)

FFP

Installation and Lining

Includes drilling, installation, development, inspection, and all other construction activities associated with installation of RW-8B and lining of RW-8A in accordance with the plans and specifications.

The work that will be covered by this contract consists of furnishing all equipment, labor, operators, supervisors/site superintendent, quality control, supplies, materials, and incidentals necessary to satisfactorily perform and provide

0013 1 Job OPTION Relief Well (RW)

FFP

Installation and Lining

Includes drilling, installation, development, inspection, and all other construction activities associated with installation of RW-5B and lining of RW-5A in accordance with the plans and specifications.

The work that will be covered by this contract consists of furnishing all equipment, labor, operators, supervisors/site superintendent, quality control, supplies, materials, and incidentals necessary to satisfactorily perform and provide

DELIVERY INFORMATION

CLIN DELIVERY DATE QUANTITY SHIP TO ADDRESS DODAAC /

CAGE

0001 N/A N/A N/A N/A

0002 N/A N/A N/A N/A

0003 N/A N/A N/A N/A

0004 N/A N/A N/A N/A

0005 N/A N/A N/A N/A

0006 N/A N/A N/A N/A

0007 N/A N/A N/A N/A

0008 N/A N/A N/A N/A

0009 N/A N/A N/A N/A

0010 N/A N/A N/A N/A

0011 N/A N/A N/A N/A

0012 N/A N/A N/A N/A

0013 N/A N/A N/A N/A

52.236-2 DIFFERING SITE CONDITIONS (APR 1984)

(a) The Contractor shall promptly, and before the conditions are disturbed, give a written notice to the Contracting Officer of

(1) subsurface or latent physical conditions at the site which differ materially from those indicated in this contract, or

(2) unknown physical conditions at the site, of an unusual nature, which differ materially from those ordinarily encountered and generally recognized as inhering in work of the character provided for in the contract.

(b) The Contracting Officer shall investigate the site conditions promptly after receiving the notice. If the conditions do materially so differ and cause an increase or decrease in the Contractor's cost of, or the time required for, performing any part of the work under this contract, whether or not changed as a result of the conditions, an equitable adjustment shall be made under this clause and the contract modified in writing accordingly.

(c) No request by the Contractor for an equitable adjustment to the contract under this clause shall be allowed, unless the Contractor has given the written notice required; provided, that the time prescribed in (a) above for giving written notice may be extended by the Contracting Officer.

(d) No request by the Contractor for an equitable adjustment to the contract for differing site conditions shall be allowed if made after final payment under this contract.

(End of clause)

252.204-7019 NOTICE OF NIST SP 800-171 DOD ASSESSMENT REQUIREMENTS (NOV 2020)

(a) Definitions.

Basic Assessment, Medium Assessment, and High Assessment have the meaning given in the clause 252.204-7020, NIST SP 800-171 DoD Assessments.

Covered contractor information system has the meaning given in the clause 252.204-7012, Safeguarding Covered Defense Information and Cyber Incident Reporting, of this solicitation.

(b) Requirement. In order to be considered for award, if the Offeror is required to implement NIST SP 800-171, the Offeror shall have a current assessment (i.e., not more than 3 years old unless a lesser time is specified in the solicitation) (see 252.204-7020) for each covered contractor information system that is relevant to the offer, contract, task order, or delivery order. The Basic, Medium, and High NIST SP 800-171 DoD Assessments are described in the NIST SP 800-171 DoD Assessment Methodology located at https://www.acq.osd.mil/dpap/pdi/cyber/strategically_assessing_contractor_implementation_of_NIST_SP_800- 171.html.

https://www.acq.osd.mil/dpap/pdi/cyber/strategically_assessing_contractor_implementation_of_NIST_SP_800-171.html https://www.acq.osd.mil/dpap/pdi/cyber/strategically_assessing_contractor_implementation_of_NIST_SP_800-171.html

(c) Procedures.

(1) The Offeror shall verify that summary level scores of a current NIST SP 800-171 DoD Assessment (i.e., not more than 3 years old unless a lesser time is specified in the solicitation) are posted in the Supplier Performance Risk System (SPRS) (https://www.sprs.csd.disa.mil/) for all covered contractor information systems relevant to the offer.

(2) If the Offeror does not have summary level scores of a current NIST SP 800-171 DoD Assessment (i.e., not more than 3 years old unless a lesser time is specified in the solicitation) posted in SPRS, the Offeror may conduct and submit a Basic Assessment to webptsmh@navy.mil for posting to SPRS in the format identified in paragraph (d) of this provision.

(d) Summary level scores. Summary level scores for all assessments will be posted 30 days post-assessment in SPRS to provide DoD Components visibility into the summary level scores of strategic assessments.

(1) Basic Assessments. An Offeror may follow the procedures in paragraph (c)(2) of this provision for posting Basic Assessments to SPRS.

(i) The email shall include the following information:

(A) Cybersecurity standard assessed (e.g., NIST SP 800-171 Rev 1).

(B) Organization conducting the assessment (e.g., Contractor self-assessment).

(C) For each system security plan (security requirement 3.12.4) supporting the performance of a DoD contract--

(1) All industry Commercial and Government Entity (CAGE) code(s) associated with the information system(s) addressed by the system security plan; and

(2) A brief description of the system security plan architecture, if more than one plan exists.

(D) Date the assessment was completed.

(E) Summary level score (e.g., 95 out of 110, NOT the individual value for each requirement).

(F) Date that all requirements are expected to be implemented (i.e., a score of 110 is expected to be achieved) based on information gathered from associated plan(s) of action developed in accordance with NIST SP 800-171.

(ii) If multiple system security plans are addressed in the email described at paragraph (d)(1)(i) of this section, the Offeror shall use the following format for the report:

Brief CAGE codes description of Date of Total Date score of System security plan supported by this the plan assessment score 110 will plan architecture achieved https://www.sprs.csd.disa.mil/ mailto:webptsmh@navy.mil

(2) Medium and High Assessments. DoD will post the following Medium and/or High Assessment summary level scores to SPRS for each system assessed:

(i) The standard assessed (e.g., NIST SP 800-171 Rev 1).

(ii) Organization conducting the assessment, e.g., DCMA, or a specific organization (identified by Department of Defense Activity Address Code (DoDAAC)).

(iii) All industry CAGE code(s) associated with the information system(s) addressed by the system security plan.

(iv) A brief description of the system security plan architecture, if more than one system security plan exists.

(v) Date and level of the assessment, i.e., medium or high.

(vi) Summary level score (e.g., 105 out of 110, not the individual value assigned for each requirement).

(vii) Date that all requirements are expected to be implemented (i.e., a score of 110 is expected to be achieved) based on information gathered from associated plan(s) of action developed in accordance with NIST SP 800-171.

(3) Accessibility.

(i) Assessment summary level scores posted in SPRS are available to DoD personnel, and are protected, in accordance with the standards set forth in DoD Instruction 5000.79, Defense-wide Sharing and Use of Supplier and Product Performance Information (PI).

(ii) Authorized representatives of the Offeror for which the assessment was conducted may access SPRS to view their own summary level scores, in accordance with the SPRS Software User's Guide for Awardees/Contractors available at https://www.sprs.csd.disa.mil/pdf/SPRS_Awardee.pdf.

(iii) A High NIST SP 800-171 DoD Assessment may result in documentation in addition to that listed in this section.

DoD will retain and protect any such documentation as "Controlled Unclassified Information (CUI)" and intended for internal DoD use only. The information will be protected against unauthorized use and release, including through the exercise of applicable exemptions under the Freedom of Information Act (e.g., Exemption 4 covers trade secrets and commercial or financial information obtained from a contractor that is privileged or confidential).

SCR_CT_007 MAGNITUDE OF PROJECT—CONSTRUCTION (Jul 2002)

The magnitude of this project is represented by the following estimated price range (contracting officer mark as appropriate):

_____Less than $25,000

_____Between $25,000 and $100,000

_____Between $100,000 and $250,000

_____Between $250,000 and $500,000

_XX__Between $500,000 and $1,000,000 https://www.sprs.csd.disa.mil/pdf/SPRS_Awardee.pdf

_____Between $1,000,000 and $5,000,000

_____Between $5,000,000 and $10,000,000

_____Between $10,000,000 and $25,000,000

_____Between $25,000,000 and $100,000,000

_____Between $100,000,000 and $250,000,000

_____Between $250,000,000 and $500,000,000

_____Over $500,000,000

(End)

TPL_NWK_001 Points of Contact

CONTRACT

SPECIALIST:

Sheila Nimrod PHONE: (816) 389-2252 E-MAIL: Sheila.d.nimrod@usace.army.mil

PROJECT

MANAGER:

Bradley Pettijohn PHONE: (816) 389-3823 E-MAIL: Bradley.a.pettijohn@usace.army.mil

SUBMISSION REQUIREMENTS

All bids are due by the time specified in box 13 A.

Submit one (1) original and one (1) copy of the following:

a. Bid schedule - complete by fully entering all amounts in the supplemental bid schedule.

b. Ensure Bid is signed by a Principal of your company with authority to do so.

c. Ensure all Amendments are acknowledged.

d. Bid Bonds – (Original with raised seal) required with your submission. (See solicitation for details).

e. When submitting your bid ensure the project name “Wilson Dam Relief Well Replacement” and IFB Number “ W912DQ22B1004” appear in the Subject Box of Your Email. Failure to follow directions may result in your bid being late.

INQUIRIES/QUESTIONS

Prospective Bidders shall submit contracting and technical inquiries and questions concerning this solicitation document via Bidder Inquiry in ProjNet at www.projnet.org/projnet.

a. To submit and review bid inquiry items, bidders will need to be a current registered user or self-register into the system. To self-register, go to the aforementioned web page and click on the BID tab. Select Bidder Inquiry, select agency USACE, enter the Bidder Inquiry Key for this http://www.projnet.org/projnet solicitation listed below, your email address, and then click login. Fill in all required information and click create user. Verify that information on the next screen is correct and click continue.

b. From this page, you may view all bidder inquiries or add a new inquiry.

c. Bidders will receive an acknowledgement of their questions via email, followed by an answer to their questions after it has been processed by our technical team. ***Please Note: Bidders shall only submit one (1) Question per inquiry. All inquiries containing multiple questions shall be rejected***

d. The Solicitation Number is: W912DQ22B1004

e. The Plan Room Key is: NA

f. The Bidder Inquiry Key is: BMWW6E-8PYMI7

The Bidder Inquiry System will be unavailable for new inquiries after 3 March 2022, at 3:00 PM Central time in order to ensure adequate time is allotted to form an appropriate response to inquiries and amend the Solicitation if necessary.

Bidders are requested to review the specification in its entirety, and review the Bidder Inquiry System for answers to questions prior to submission of a new inquiry.

The ProjNet call center operates weekdays from 8AM to 5PM U.S. Central Time Zone (Chicago) or by appointment for OCONUS. The telephone number for the Call Center is 1-800-428-HELP.

Email to staff@rcesupport.com.

SUPPL BID SCHDULE R4 20220121

SUPPLEMENTAL BID SCHEDULE

The contractor shall complete the following Supplemental Bid Schedule in addition to the Bid Schedule. This Supplemental Bid Schedule is not contractually binding. The Government will use this Supplemental Bid Schedule to assist in the evaluation of prices. The individual supplemental bid items should add up to the prices for the bid schedule. In the event that the CLIN subtotal in the supplemental bid schedule does not match the CLIN total in the bid schedule, the bid schedule shall control and will be the price evaluated by the Government.

CLIN 0001

Site and Earthwork Est. Qty. Unit Unit Price Subtotal

Mob/Demob 1 JOB - $ Clearing and Grubbing 1 JOB - $ Earthwork 1 JOB - $

SUBTOTAL $

mailto:staff@rcesupport.com

CLIN 0002

Relief Well Installation, Lining, Modification, and Abandonment

Est. Qty. Unit Unit Price Subtotal

Relief Wells 1 JOB - $ Relief Well Riser Pipe Modifications

1 JOB - $

Rockwork 1 JOB - $ Relief Well Abandonment 1 JOB - $

CLIN 0003 - OPTION

Pipe Extension Est. Qty. Unit Unit Price Subtotal

54" Line Renovations 1 JOB - $ Earthwork 1 JOB - Rockwork 1 JOB - Clearing and Grubbing 1 JOB -

CLIN 0004 - OPTION

Relief Well Installation and Lining Est. Qty. Unit Unit Price Subtotal

Relief Well 1 JOB - $ Lining Wells 1 JOB -

CLIN 0005 - OPTION

Relief Well 1 JOB - $

CLIN 0006 - OPTION

Relief Well 1 JOB - $

CLIN 0007 - OPTION

Relief Well 1 JOB - $

CLIN 0008 - OPTION

Relief Well 1 JOB - $

CLIN 0009 - OPTION

Relief Well 1 JOB - $

CLIN 0010 - OPTION

Relief Well 1 JOB - $

CLIN 0011 - OPTION

Relief Well 1 JOB - $

CLIN 0012 - OPTION

Relief Well 1 JOB - $

CLIN 0013 - OPTION

Relief Well 1 JOB - $

CONTRACT

TOTAL

Note: Any work not specifically noted shall be priced with the most closely related CLIN.

Section 00 21 00 - Instructions

CLAUSES INCORPORATED BY REFERENCE

52.204-7 System for Award Management OCT 2018 52.204-16 Commercial and Government Entity Code Reporting AUG 2020 52.204-18 Commercial and Government Entity Code Maintenance AUG 2020 52.214-3 Amendments To Invitations For Bids DEC 2016 52.214-4 False Statements In Bids APR 1984 52.214-5 Submission Of Bids DEC 2016 52.214-6 Explanation To Prospective Bidders APR 1984 52.214-7 Late Submissions, Modifications, and Withdrawals of Bids NOV 1999 52.214-18 Preparation of Bids-Construction APR 1984 52.214-19 Contract Award-Sealed Bidding-Construction AUG 1996 52.214-34 Submission Of Offers In The English Language APR 1991 52.214-35 Submission Of Offers In U.S. Currency APR 1991 52.217-3 Evaluation Exclusive Of Options APR 1984 52.217-4 Evaluation Of Options Exercised At The Time Of Contract

Award

JUN 1988

52.217-5 Evaluation Of Options JUL 1990 52.232-13 Notice Of Progress Payments APR 1984

52.216-1 TYPE OF CONTRACT (APR 1984)

The Government contemplates award of a Firm Fixed-Price contract resulting from this solicitation.

52.222-5 CONSTRUCTION WAGE RATE REQUIREMENTS--SECONDARY SITE OF THE WORK (MAY

2014)

(a)(1) The offeror shall notify the Government if the offeror intends to perform work at any secondary site of the work, as defined in paragraph (a)(1)(ii) of the FAR clause at 52.222-6, Construction Wage Rate Requirements,of this solicitation.

(2) If the offeror is unsure if a planned work site satisfies the criteria for a secondary site of the work, the offeror shall request a determination from the Contracting Officer.

(b)(1) If the wage determination provided by the Government for work at the primary site of the work is not applicable to the secondary site of the work, the offeror shall request a wage determination from the Contracting Officer.

(2) The due date for receipt of offers will not be extended as a result of an offeror's request for a wage determination for a secondary site of the work.

52.222-23 NOTICE OF REQUIREMENT FOR AFFIRMATIVE ACTION TO ENSURE EQUAL

EMPLOYMENT OPPORTUNITY FOR CONSTRUCTION (FEB 1999)

(a) The offeror's attention is called to the Equal Opportunity clause and the Affirmative Action Compliance Requirements for Construction clause of this solicitation.

(b) The goals for minority and female participation, expressed in percentage terms for the Contractor's aggregate workforce in each trade on all construction work in the covered area, are as follows:

Goals for minority participation for each trade

Goals for female participation for each trade

1.5% 6.9%

These goals are applicable to all the Contractor's construction work performed in the covered area. If the Contractor performs construction work in a geographical area located outside of the covered area, the Contractor shall apply the goals established for the geographical area where the work is actually performed. Goals are published periodically in the Federal Register in notice form, and these notices may be obtained from any Office of Federal Contract Compliance Programs office.

(c) The Contractor's compliance with Executive Order 11246, as amended, and the regulations in 41 CFR 60-4 shall be based on (1) its implementation of the Equal Opportunity clause, (2) specific affirmative action obligations required by the clause entitled "Affirmative Action Compliance Requirements for Construction,'' and (3) its efforts to meet the goals. The hours of minority and female employment and training must be substantially uniform throughout the length of the contract, and in each trade. The Contractor shall make a good faith effort to employ minorities and women evenly on each of its projects. The transfer of minority or female employees or trainees from Contractor to Contractor, or from project to project, for the sole purpose of meeting the Contractor's goals shall be a violation of the contract, Executive Order 11246, as amended, and the regulations in 41 CFR 60-4. Compliance with the goals will be measured against the total work hours performed.

(d) The Contractor shall provide written notification to the Deputy Assistant Secretary for Federal Contract Compliance, U.S. Department of Labor, within 10 working days following award of any construction subcontract in excess of $10,000 at any tier for construction work under the contract resulting from this solicitation. The notification shall list the --

(1) Name, address, and telephone number of the subcontractor;

(2) Employer's identification number of the subcontractor;

(3) Estimated dollar amount of the subcontract;

(4) Estimated starting and completion dates of the subcontract; and

(5) Geographical area in which the subcontract is to be performed.

(e) As used in this Notice, and in any contract resulting from this solicitation, the "covered area" is State; Kansas, County: Russell, City: Sylvan

52.225-10 NOTICE OF BUY AMERICAN REQUIREMENT--CONSTRUCTION MATERIALS (MAY 2014)

(a) Definitions. “Commercially available off-the-shelf (COTS) item,” “construction material,” “domestic construction material,” and “foreign construction material,” as used in this provision, are defined in the clause of this solicitation entitled “Buy American --Construction Materials” (Federal Acquisition Regulation (FAR) clause 52.225-9).

(b) Requests for determinations of inapplicability. An offeror requesting a determination regarding the inapplicability of the Buy American statute should submit the request to the Contracting Officer in time to allow a determination before submission of offers. The offeror shall include the information and applicable supporting data required by paragraphs (c) and (d) of the clause at FAR 52.225-9 in the request. If an offeror has not requested a determination regarding the inapplicability of the Buy American statute before submitting its offer, or has not received a response to a previous request, the offeror shall include the information and supporting data in the offer.

(c) Evaluation of offers. (1) The Government will evaluate an offer requesting exception to the requirements of the Buy American statute, based on claimed unreasonable cost of domestic construction material, by adding to the offered price the appropriate percentage of the cost of such foreign construction material, as specified in paragraph (b)(3)(i) of the clause at FAR 52.225-9.

(2) If evaluation results in a tie between an offeror that requested the substitution of foreign construction material based on unreasonable cost and an offeror that did not request an exception, the Contracting Officer will award to the offeror that did not request an exception based on unreasonable cost.

(d) Alternate offers.

(1) When an offer includes foreign construction material not listed by the Government in this solicitation in paragraph (b)(2) of the clause at FAR 52.225-9, the offeror also may submit an alternate offer based on use of equivalent domestic construction material.

(2) If an alternate offer is submitted, the offeror shall submit a separate Standard Form 1442 for the alternate offer, and a separate price comparison table prepared in accordance with paragraphs (c) and (d) of the clause at FAR 52.225-9 for the offer that is based on the use of any foreign construction material for which the Government has not yet determined an exception applies.

(3) If the Government determines that a particular exception requested in accordance with paragraph (c) of the clause at FAR 52.225-9 does not apply, the Government will evaluate only those offers based on use of the equivalent domestic construction material, and the offeror shall be required to furnish such domestic construction material. An offer based on use of the foreign construction material for which an exception was requested--

(i) Will be rejected as nonresponsive if this acquisition is conducted by sealed bidding; or

(ii) May be accepted if revised during negotiations.

52.228-1 BID GUARANTEE (SEP 1996)

(a) Failure to furnish a bid guarantee in the proper form and amount, by the time set for opening of bids, may be cause for rejection of the bid.

(b) The bidder shall furnish a bid guarantee in the form of a firm commitment, e.g., bid bond supported by good and sufficient surety or sureties acceptable to the Government, postal money order, certified check, cashier's check, irrevocable letter of credit, or, under Treasury Department regulations, certain bonds or notes of the United States.

The Contracting Officer will return bid guarantees, other than bid bonds, (1) to unsuccessful bidders as soon as practicable after the opening of bids, and (2) to the successful bidder upon execution of contractual documents and bonds (including any necessary coinsurance or reinsurance agreements), as required by the bid as accepted.-

(c) The amount of the bid guarantee shall be 20% percent of the bid price or $3,000,000.00, whichever is less.-

(d) If the successful bidder, upon acceptance of its bid by the Government within the period specified for acceptance, fails to execute all contractual documents or furnish executed bond(s) within 10 days after receipt of the forms by the bidder, the Contracting Officer may terminate the contract for default.-

(e) In the event the contract is terminated for default, the bidder is liable for any cost of acquiring the work that exceeds the amount of its bid, and the bid guarantee is available to offset the difference.

52.232-16 PROGRESS PAYMENTS (JUN 2020)

The Government will make progress payments to the Contractor when requested as work progresses, but not more frequently than monthly, in amounts of $2,500 or more approved by the Contracting Officer, under the following conditions:

(a) Computation of amounts.

(1) Unless the Contractor requests a smaller amount, the Government will compute each progress payment as 80 percent of the Contractor's total costs incurred under this contract whether or not actually paid, plus financing payments to subcontractors (see paragraph (j) of this clause), less the sum of all previous progress payments made by the Government under this contract. The Contracting Officer will consider cost of money that would be allowable under Federal Acquisition Regulation (FAR) 31.205-10 as an incurred cost for progress payment purposes.

(2) The amount of financing and other payments for supplies and services purchased directly for the contract are limited to the amounts that have been paid by cash, check, or other forms of payment, or that are determined due and will be paid to subcontractors--

(i) In accordance with the terms and conditions of a subcontract or invoice; and

(ii) Ordinarily within 30 days of the submission of the Contractor's payment request to the Government.

(3) The Government will exclude accrued costs of Contractor contributions under employee pension plans until actually paid unless--

(i) The Contractor's practice is to make contributions to the retirement fund quarterly or more frequently; and

(ii) The contribution does not remain unpaid 30 days after the end of the applicable quarter or shorter payment period (any contribution remaining unpaid shall be excluded from the Contractor's total costs for progress payments until paid).

(4) The Contractor shall not include the following in total…

This is the start of the file's text. The full file is on GovTribe.