SEE ADDENDUM
(No Collect Calls)
W912EF22Q0028 13-Jan-2022
b. TELEPHONE NUMBER
509-527-7217
8. OFFER DUE DATE/LOCAL TIME
10:00 AM 27 Jan 2022
5. SOLICITATION NUMBER 6. SOLICITATION ISSUE DATE
AUTHORIZED FOR LOCAL REPRODUCTION
PREVIOUS EDITION IS NOT USABLE
STANDARD FORM 1449 (REV. 2/2012)
Prescribed by GSA – FAR (48 CFR) 53.212
(TYPE OR PRINT)
(SIGNATURE OF CONTRACTING OFFICER)
ADDENDA ARE
26. TOTAL AWARD AMOUNT (For Gov t. Use Only )
23.
CODE 10. THIS ACQUISITION IS
SUCH ADDRESS IN OFFER
17b. CHECK IF REMITTANCE IS DIFFERENT AND PUT
BELOW IS CHECKED
TELEPHONE NO.
W912EF9. ISSUED BY
18b. SUBMIT INVOICES TO ADDRESS SHOWN IN BLOCK 18a. UNLESS BLOCK
7. FOR SOLICITATION
INFORMATION CALL:
a. NAME
ALAN N INGLIS
2. CONTRACT NO. 3. AWARD/EFFECTIVE DATE 4. ORDER NUMBER
(TYPE OR PRINT)
30b. NAME AND TITLE OF SIGNER 30c. DATE SIGNED 31b. NAME OF CONTRACTING OFFICER
30a. SIGNATURE OF OFFEROR/CONTRACTOR 31a.UNITED STATES OF AMERICA
0 27a. SOLICITATION INCORPORATES BY REFERENCE FAR 52.212-1. 52.212-4. FAR 52.212-3. 52.212-5 ARE ATTACHED.
25. ACCOUNTING AND APPROPRIATION DATA
1. REQUISITION NUMBER
20.
ADDITIONAL SHEETS SUBJECT TO THE TERMS AND CONDITIONS SPECIFIED.
OFFEROR TO COMPLETE BLOCKS 12, 17, 23, 24, AND 30
SOLICITATION/CONTRACT/ORDER FOR COMMERCIAL ITEMS
ARE NOT ATTACHED
27b. CONTRACT/PURCHASE ORDER INCORPORATES BY REFERENCE FAR 52.212-4. FAR 52.212-5 IS ATTACHED. ADDENDA ARE ARE NOT ATTACHED
(BLOCK 5), INCLUDING ANY ADDITIONS OR CHANGES WHICH ARE
SET FORTH HEREIN, IS ACCEPTED AS TO ITEMS:
. YOUR OFFER ON SOLICITATION
28. CONTRACTOR IS REQUIRED TO SIGN THIS DOCUMENT AND RETURN
% FOR:SET ASIDE:UNRESTRICTED OR X
SMALL BUSINESSX
17a.CONTRACTOR/ CODE FACILITY
OFFEROR CODE
USAED, WALLA WALLA - CONTRACTING DIV.
ALAN INGLIS
201 N. THIRD AVENUE
WALLA WALLA WA 99362-1876
18a. PAYMENT WILL BE MADE BY CODE
RATED ORDER UNDER
DPAS (15 CFR 700)
13a. THIS CONTRACT IS A
13b. RATING
CODE15. DELIVER TO CODE 960449 16. ADMINISTERED BY
12. DISCOUNT TERMS11. DELIVERY FOR FOB DESTINA-
TION UNLESS BLOCK IS
MARKED
SEE SCHEDULE
14. METHOD OF SOLICITATION
RFQ IFB RFPX
ARMY CORPS OF ENGINEERS
PERFORMANCE SPECIALIST
MCNARY TRAINING
PO BOX 1230
UMATILLA OR 97882-1230
TEL: 547-922-1326 FAX: 547-922-1326
FAX:
TEL: 509-527-7217 SERVICE-DISABLED
VETERAN-OWNED
SMALL BUSINESS
8(A)
HUBZONE SMALL
BUSINESS
SIZE STANDARD:
$16,500,000
NAICS:
541360
X
OFFER DATED
29. AWARD OF CONTRACT: REF.
DELIVER ALL ITEMS SET FORTH OR OTHERWISE IDENTIFIED ABOVE AND ON ANY
COPIES TO ISSUING OFFICE. CONTRACTOR AGREES TO FURNISH AND
EMAIL:
TEL:
31c. DATE SIGNED
SEE SCHEDULE
SCHEDULE OF SUPPLIES/ SERVICESITEM NO. QUANTITY UNIT UNIT PRICE AMOUNT
24.22.21.19.
WOMEN-OWNED SMALL BUSINESS (WOSB)
ELIGIBLE UNDER THE WOMEN-OWNED
SMALL BUSINESS PROGRAM
EDWOSB
32g. E-MAIL OF AUTHORIZED GOVERNMENT REPRESENTATIVE
SOLICITATION/CONTRACT/ORDER FOR COMMERCIAL ITEMS
(CONTINUED)
PAGE 2 OF24
ACCEPTED, AND CONFORMS TO THE CONTRACT, EXCEPT AS NOTED: ______________________________________________________
32a. QUANTITY IN COLUMN 21 HAS BEEN
RECEIVED INSPECTED
32b. SIGNATURE OF AUTHORIZED GOVERNMENT
REPRESENTATIVE
32c. DATE 32d. PRINTED NAME AND TITLE OF AUTHORIZED GOVERNMENT
REPRESENTATIVE
32e. MAILING ADDRESS OF AUTHORIZED GOVERNMENT REPRESENTATIVE 32f . TELEPHONE NUMBER OF AUTHORIZED GOVERNMENT REPRESENTATIVE
37. CHECK NUMBER
FINALPARTIALCOMPLETE
36. PAYMENT35. AMOUNT VERIFIED
CORRECT FOR
34. VOUCHER NUMBER
FINAL
33. SHIP NUMBER
PARTIAL
38. S/R ACCOUNT NUMBER 39. S/R VOUCHER NUMBER 40. PAID BY
41a. I CERTIFY THIS ACCOUNT IS CORRECT AND PROPER FOR PAYMENT
41b. SIGNATURE AND TITLE OF CERTIFYING OFFICER 41c. DATE
42a. RECEIVED BY (Print)
42b. RECEIVED AT (Location)
42c. DATE REC'D (YY/MM/DD) 42d. TOTAL CONTAINERS
STANDARD FORM 1449 (REV. 2/2012) BACK
Prescribed by GSA – FAR (48 CFR) 53.212
AUTHORIZED FOR LOCAL REPRODUCTION
PREVIOUS EDITION IS NOT USABLE
SEE SCHEDULE
20.
SCHEDULE OF SUPPLIES/ SERVICES
21.
QUANTITY UNIT
22. 23.
UNIT PRICE
24.
AMOUNT
19.
ITEM NO.
W912EF22Q0028
Section SF 1449 - CONTINUATION SHEET
INSTRUCTIONS TO OFFERORS
This is a request for quote for Gudgeon Anchor Geophysical Surveying in accordance with the technical specifications for the U.S. Army Corps of Engineers, Walla Walla District, at McNary Dam, Umatilla, WA.
Registration at www.sam.gov is required. Failure to register in the SAM database will make an offeror ineligible for award. Effective 29 April 2018, the notarized letter process is now mandatory on all CURRENT registrants at SAM who have a requirement to update data on their SAM record. The notarized letter is mandatory and is required in order for the GSA Federal Service Desk (FSD) to activate the entity's registration. Both Federal Assistance entities and all non-Federal entities must mail the original, signed copy of the notarized letter to the Federal Service Desk.
Failure to do so within 30 days of activation may result in the registration no longer being active. Mail the completed, signed, notarized letter to:
FEDERAL SERVICE DESK
ATTN: SAM.GOV REGISTRATION PROCESSING
460 INDUSTRIAL BLVD
LONDON, KY 40741-7285
UNITED STATES OF AMERICA
Completion of the required FAR 52.212-3, Offeror Representations and Certifications – Commercial Items is required. When you complete your SAM registration, the link to complete your Representations and Certifications is also available. Please do not hesitate to contact Alan Inglis, or the SAM website for assistance or have questions.
TO ENSURE RECEIPT OF YOUR QUOTE, PLEASE SEND TO THE ATTENTION OF ALAN INGLIS
AT alan.n.inglis@usace.army.mil .
Please return all pages of this request for quote. Be sure to also complete Blocks 17a, 30a, 30b, and 30c on page 1.
Name: _____________________________________________________________
Contact Telephone Number: ____________________________________________
Email Address: __________________________________________________________________
Company’s Federal Tax Identification Number: ____________________________________________
CAGE CODE: _________________________ DUNS Number ________________________________
Total Amount of Contract: ____________________________
The System for Award Management (SAM) is online. SAM replaced FBO. If you have been using FBO, you should now go to www.sam.gov to find your information.
Completion of FAR 52.212-3 Offeror Representations and Certifications–Commercial Items – Alternate 1 (May 2014). Electronic completion is encouraged (see http://farsite.hill.af.mil to download Representations and Certifications).
An offeror shall complete only paragraph (b) of this provision if the offeror has completed the annual representations and certifications electronically via https://www.acquisition.gov. If an offeror has not completed the annual representations and certifications electronically at www.sam.gov, the offeror shall complete only paragraphs (b) through (i) of this provision.
In accordance with FAR Part 29.3 – State and Local Taxes, and per Title 4 of US Code 104-107, the Government is exempt from paying state and local taxes. Exempt tax identification number 91-0828090.
ADDENDUM TO FAR 52.212-1 INSTRUCTIONS TO OFFERORS – COMMERCIAL ITEMS
Submission of Price Quote – Offeror shall submit 1 copy of the following:
1. Signed and dated Standard Form 1449 (Solicitation/Contract/Order for Commercial Items)
2. Signed and dated Standard Form 30, if applicable, for any Amendments to the Solicitation
3. Completed schedule (pricing information) for all contract line item numbers
4. Completed Clause 52.212-3 Alt I, “Offeror Representations and Certifications—Commercial Items” as noted above.
PRICES QUOTED MUST BE VALID FOR 30 DAYS. Solicitation shall result in a firm-fixed-price contract.
All pricing shall include shipping FOB destination (include shipping cost in price).
BUSINESS HOURS: The standard business hours for the Walla Walla District, Corps of Engineers are Monday through Friday from 8:00 a.m. to 4:00 p.m., excluding federal holidays.
BASIS FOR AWARD
The Government will award one contract resulting from this solicitation in accordance with FAR 13.106 to the responsible offeror meeting or exceeding all solicitation requirements and representing the best value based on price.
Bidder Inquiry:
All inquiries regarding this solicitation are to be submitted via Bidder Inquiry. Telephone and email inquiries will not be accepted. Bidder Inquiry is a web-site that allows bidders to post questions regarding the solicitation and view all questions by other bidders and responses by USACE. Bidder Inquiry can be accessed through ProjNet at (https://www.projnet.org)
To submit and review inquiry items, prospective vendors will need to use the Bidder Inquiry Key presented below and follow the instructions listed below the key for access. A prospective vendor who submits a comment /question will receive an acknowledgement of their comment/question via email. Another email to the same address will notify the prospective vendor once the reply is available for viewing.
TIMING OF BIDDER INQUIRIES: Bidders are encouraged to submit their bidder inquiries promptly. The Government will make every effort to answer all bidder inquiries; however, the closer to the bid or proposal due date an inquiry is received, the less likely it is that a timely response can be provided.
The Bidder Inquiry Key is: BIKN5Y-STWHUI
Specific Instructions for ProjNet Bid Inquiry Access:
1. From the ProjNet home page linked above, click on Quick Add on the upper right side of the screen.
2. Identify the Agency. This should be marked as USACE.
3. Key. Enter the Bidder Inquiry Key listed above.
4. Email. Enter the email address you would like to use for communication.
5. Click Continue. A page will then open saying that a user account was not found and will ask you to create one using the provided form.
6. Enter your First Name, Last Name, Company, City, State, Phone, Email, Secret Question, Secret Answer, and Time Zone. Make sure to remember your Secret Question and Answer as they will be used from this point on to access the ProjNet system.
7. Click Add User. Once this is completed you are now registered within ProjNet and are currently logged into the system.
Instructions for Entering Questions:
1. After you are logged in click on the "post new inquiry", it is on the left side of the window under the Word
"Submit" a.) This is the window where you will enter your questions b.) Comment Classification: Click on the down arrow to the right of the words “Please select from below”, select “Public” c.) Discipline: This is where you select who this question should be directed to. Example; if the question is about an electrical drawing or specification select: “Electrical” from the pull down list.
d.) Sheet. Enter the sheet number of the drawing you are asking about.
e.) Detail. Enter the detail name of the detail shown on the drawing that you are asking about.
f.) Specification. Enter the Specification number and paragraph number.
g.) File. Use this if you are going to attach a pdf file.
h.) Question. Enter your question here.
Specific Instructions for Future ProjNet Bid Inquiry Access:
1. For future access to ProjNet, you will not be provided any type of password. You will utilize your Secret Question and Secret Answer to log in.
2. From the ProjNet home page linked above, click on Quick Add on the upper right side of the screen.
3. Identify the Agency. This should be marked as USACE.
4. Key. Enter the Bidder Inquiry Key listed above.
5. Email. Enter the email address you used to register previously in ProjNet.
6. Click Continue. A page will then open asking you to enter the answer to your Secret Question.
7. Enter your Secret Answer and click Login. Once this is completed you are now logged into the system.
For questions about the ProjNet Bidder Inquiry, please contact the Call Center help desk toll free at 1-800-428- HELP, which operates from 8AM to 5PM (Central US time zone). Bidder inquiry help questions can also be emailed to the helpdesk at staff@projnet.info
ITEM NO SUPPLIES/SERVICES QUANTITY UNIT UNIT PRICE AMOUNT
0001 1 Job Gudgeon Anchor GPR Geophysical Surveying
FFP
IAW Performance Work Statement.
NOTE: The requirements in DFARS 252.211-7003, Item Identification and Valuation, are applicable for this line item. The contractor shall provide DoD unique identification or a DoD recognized unique identification equivalent.
FOB: Destination
PSC CD: B518
NET AMT
PERFORMANCE WORK STATEMENT
PERFORMANCE WORK STATEMENT
McNary Downstream Miter Gate Monoliths - Concrete Subsurface Investigation
1. BACKGROUND and PURPOSE
Background
The embedded gudgeon anchors for the McNary downstream miter gate have exceeded the recommended service life and are programmed for replacement in FY24. The four gudgeon anchors are embedded in the two mass concrete monoliths at the downstream end of the navigation lock (Monoliths 38 and 39). The monoliths are plain, unreinforced concrete gravity sections, that were post-tensioned in the 1970’s with over 100 prestressing units (bundled 7-wire strands) to arrests cracks and stabilize the monoliths. Additionally, there are multiple embedded utilities running through the concrete.
Purpose
The Contractor will provide all labor, supplies and equipment to conduct a concrete subsurface investigation of the two downstream gate monoliths (M38 and M39) using Ground Penetrating Radar (GPR). Information obtained from the GPR scans will provide spatial information needed for replacement of the miter gate gudgeon anchors and appurtenances. The Contractor will use state-of-the-art methods and equipment to scan to the maximum depth possible from selected surfaces. The Contractor will identify and locate all known and unknown embedded objects subject to the limitations of the scanning technology. The Contractor will map all scanned objects in a three-dimensional computer/CAD model.
The following surfaces will be scanned at each monolith (in order of priority):
1) Deck, elevation 348.0.
2) Lockside wall face, elevation 348.0-318.0.
3) Downstream wall face, elevation 348.0-328.0.
4) Select wall faces in the stairways, elevation 345.0-320.0.
Produce a three-dimensional CAD model and two-dimensional drawings with all items detected during the scan (embedded objects, monoliths cracks and voids). Identify all deviations from the Government-furnished model and as-built drawings. Provide dimensions in feet-inches along with estimated limits of precision (plus/minus x-number inches) for each dimension.
Reference surfaces are the actual deck, downstream and lockside wall surfaces of each monolith. Report dimensions as dimensional coordinates relative to these surfaces. The origin (0,0,0) of the coordinate system is the point of intersection of the lockside face, the downstream face and the deck surface.
2. REFERENCES
a. EM 385-1-1 Safety and Health Requirements Manual
b. ER 1110-2-1150 Engineering and Design for Civil Works Projects
References for Hazardous Energy Control Program (HECP) Awareness
c. NWWOM 385-1-20, USACE Walla Walla District, Safe Clearance Program for the Control of Hazardous Energy
d. ER 385-1-31, Engineering Regulation, Safety and Occupational Health, Control of Hazardous Energy
e. 29 CFR 1910.147, Control of Hazardous Energy (Lockout/Tagout)
f. 29 CFR 1910.333, Selection and Use of Safe Work Practices
g. 29 CFR 1910.269, Hazardous Energy Control (Lockout/Tagout) Procedures
h. American National Standards Institute (ANSI) C2, National Electrical Safety Code
i. Occupational Safety and Health Administration (OSHA) Instruction STD 1-7.3, The Control of
Hazardous Energy (Lockout/Tagout) – Inspection Procedures and Interpretive Guidance
The Contractor is responsible for complying with the current published edition and all changes posted on the web as of the effective date of the Contract.
3. GOVERNMENT FURNISHED MATERIALS
a. Activity Hazard Analysis (AHA) Template
b. Resource Drawings: McNary Navigation Lock
c. 2D drawings of surfaces to be scanned
d. Photos of surfaces to scanned
e. 3D Microstation model of monoliths with post-tensioning
4. TASK DESCRIPTION
4.1 Task 1 – Project Management, Accounting and Quality Control Provide management, coordination and direction to the Contractor’s Project Team to complete quality project deliverables on time. Schedule and supervise tasks and maintain liaison and coordination with the Contracting Officer Representative (COR). Perform a quality control review of all deliverables. Submit documentation of the QC review with the miter gate survey report. Progress status reports are not required for this contract.
4.2 Task 2 - Pre-Work Requirements
Perform the following:
a. Review all Government provided materials.
b. Participate in a kickoff meeting (phoncon). Kickoff meeting will be with U.S. Army Corps of Engineers (USACE) key personnel to review the entire Task Description, review the schedule and deliverable submittal dates, and review expectations for final deliverable.
c. Submit all required submittals, forms and training certificates identified below.
4.2.1 Develop and submit a Quality Control Plan for Subsurface Investigation
Develop and submit a Quality Control (QC) Plan which incorporates ground penetrating radar (GPR) to identify, locate, and characterize existing embedded objects. GPR equipment shall be state-of-the-art, suitable for optimal accuracy at the maximum depths possible. Operators must have a minimum of 5 years of experience utilizing the equipment and software. Operators identified in the QC Plan, shall be those operating the equipment and performing pos-processing analysis for the submitted report, unless otherwise approved by the Contracting Officer.
The plan shall include the following:
1) Description, including drawings, of recommended surfaces and areas of data collection.
2) Equipment to be used, including manufacturer and model number.
3) Post-processing software(s) for data analysis and graphical output, including manufacturer and version.
4) Equipment and software operator information to include experience, certifications, and qualifications.
5) Procedures for site-specific equipment calibration.
6) Procedures for data acquisition and verification.
7) Examples of digital records of measurement data to be used.
8) Description and example of graphical, dimensioned results.
9) Degree of precision/expected tolerances for this project based on site conditions and depths of scan.
10) Subsurface Scan Report template. Include the reports' organization, data included, how data will be presented, and how all required information will be conveyed in the report.
11) Include an example Subsurface Scan report.
12) List potential problems or difficulties that could hinder on-site scanning efforts or otherwise reduce the extent and quality of the investigation, along with proposed risk-reduction measures (weather, access, concurrent site activities, etc).
4.3 Task 3 On-site work for Subsurface Scanning
4.3.1 Pre-work Meeting and Clearances
Prior to starting on-site work, attend a short meeting at the dam. The meeting shall include Contractor personnel and USACE representatives. The meeting will include discussions of the work plan and safety issues. At the completion of the meeting, clearances will be established in accordance with Lockout/Tagout procedures discussed in Section 7 below.
4.3.2 Subsurface Scan
Scan the areas specified in accordance with the approved Quality Control Plan. The scanning activities shall be performed during the period of 1st – 16th March 2022 during the annual river navigation outage. There may be concurrent maintenance and inspection activities in the navigation lock during this period. Immediately report any problems or issues which could reduce the extent or quality of the subsurface investigation. Refer to Section 8.3 below for crane support by USACE for access to the wall surfaces.
4.4 Task 4 Subsurface Scan Report
Submit a Draft Subsurface Scan Report for each of the conditions surveyed. Provide post-processing of raw scan data. Produce two-dimensional drawings and a three-dimensional graphical computer model that illustrates the location of embedded objects, monoliths cracks and voids along with any deviations from the as-built 3D model provided by the Government. Provide dimensions in feet-inches along with estimated limits of precision (plus/minus x-number inches) for each dimension.
Reference surfaces are the actual concrete surfaces of the deck, downstream and chamber wall surfaces of each monolith. Report all dimensions as dimensional coordinates relative to these surfaces. The origin (0,0,0) of the coordinate system is the point of intersection of the lockside face, the downstream face and the deck surface.
Report shall include but not limited to the following:
1) Surfaces scanned.
2) GPR equipment used.
3) Weather.
4) Temperature.
5) Date and Time.
6) Equipment Calibration Date and Results.
7) Digital records of the measurement and post-processing data.
8) Problems or difficulties that may have arisen during the on-site work, along with any actions taken in response.
9) Update the drawing sheets provided by the Government for each monolith showing all objects, cracks and voids identified during the scan along with dimensions to the reference faces of the monolith:
a. Deck plans
b. Lockside elevations
c. Downstream elevations
d. Stairway wall elevations
10) Update the 3D Microstation model provided by the Government with all objects, cracks and voids identified during the scan. Provide new solid model features representing the location, shape and size of each newly identified feature. For features already included in the Government-provided model, label “confirmed correct” or clearly indicate with new solid features any deviations from the model.
11) Mark the concrete with scan results in stairwells.
USACE will review the Draft Report. A review meeting will be held to discuss the draft report. The meeting shall be no longer than 2 hours. Upon completion of the review meeting, submit a Final Report. Submit the draft and final reports in electronic PDF format and include all 2D and 3D Microstation electronic files and raw electronic data from the GPR scan and post-processing.
5. SCHEDULE AND DELIVERABLE SUBMITTAL DATES
Scheduled Milestones And Deliverables Time
Kickoff Meeting (phoncon) Within 3 days of contract award
Submit Miter Gate Quality Control Plan, access forms, AHA, APP, and Fall Protection & HECP training certifications
Within 2 weeks of contract award
Perform Subsurface Scan at McNary Lock and Dam Between 3/01/20 and 3/16/20 (USACE crane support for 2 days each side of the lock maximum)
Submit Draft Report 6 weeks from completion of on-site work
USACE Review Period 3 weeks from receipt of draft reports
Review Meeting (phoncon) Within 3 weeks from receipt of draft reports
Submit Final Report 2 weeks from completion of Review Conference
Submit all deliverables electronically to the COR.
6. AUTHORIZED CHANGES
Changes in scope, time, or deliverables can only be authorized by the Contracting Officer. Notify the Contracting Officer immediately if direction is received to perform work outside the scope of the contract. Changes in scope will be negotiated and a written modification issued before proceeding with the work.
7. SAFETY
7.1 General. Comply with the requirements of the Corps Safety Manual, EM 385-1-1.
Furnish safety equipment required for all work related to this contract. All Contractor personnel shall wear hardhats and boots at all times when performing on-site work. Appoint one Authorized Individual for the on-site work as outlined in EM 385-1-1 to install locks for HECP safe clearance procedures.
7.1.1 Fall Protection. All individuals requiring use of fall protection shall complete training and use fall protection equipment in accordance with EM 385-1-1. The fall protection plan and training shall be in accordance with EM 385-1-1 (see Section 21). The fall protection and rescue plan shall be included in the APP.
7.1.2 Lockout/Tagout (LOTO)-Safe Clearance or Hazardous Energy Control Program (HECP) Procedures
All work on-site shall meet the requirements of "Safety and Occupational Health Office; Safe Clearance Program for the Control of Hazardous Energy, NWWP 385-1-20." A digital copy may be obtained at the web address shown below in paragraph, Safe Clearance Training. Safe clearance procedures are used by Project and Contractor personnel to protect personnel, equipment and the environment as well as ensuring continuity of service. Any work performed by the Contractor that requires taking Project operated equipment out of service shall be done only after a formal clearance is obtained through the Government. Violations will be reported to the Issuing Individual and violations may result in disciplinary action ranging from retraining to removal of safe clearance authorization.
The following applies to LOTO and HECP procedures:
a. The Government will provide safe clearance tags and will issue isolation locks to Contractors for clearances using the Government safe procedures. The Contractor shall provide their own personal safety locks, meeting OSHA standards, for use with the Government's safe clearance procedures. See NWWP 385-1-20, Chapter 6 – Locks and Tags, and Chapter 10 – Contractor Personnel for further guidance.
b. Government HECP procedures shall be used on equipment/systems owned by the Government. It shall also be used on all points interfacing with Government owned equipment/systems. In instances where equipment is owned by the Contractor, not yet turned over to the Government, or Equipment which is not tied into Government energy sources, the Contractor may use their own Lockout/Tagout Program.
Contractor programs shall be pre-approved by the Responsible Official.
c. Project-specific training will be given to all Authorized Individuals by the Operations Chief or designee and will be approximately 30 minutes in length. The Authorized Individuals shall be required to brief their personnel of any Project-specific clearance information. Training is only required once per year and is, with the exception of Project-specific training, valid for every facility within the Walla Walla District. If the Responsible Official or Government designee determines that the Authorized Individual’s knowledge of the HECP procedures is inadequate, the Responsible Official may administer a retest. See NWWP 385-1-20 Chapter 5 – Training for further guidance.
Safe Clearance Training
All Contractor personnel are required to take the level of HECP training commensurate with their job duties.
Based on the scope of work and size of crew, the Contractor shall have the appropriate number of Authorized Individuals trained to ensure that there are no delays. All Contractor personnel working in areas under a Safe Clearance shall be trained as Affected Persons. Any non-working personnel that will be entering an area under Safe Clearance shall take Awareness level training. Training and written tests for the modules below shall be completed on-line prior to commencing on-site work. Time estimates for training follow:
a. Awareness Level Training: Approximately 1 hour (non-working personnel, vendors and visitors)
b. Affected Persons: Approximately 2 hours in addition to Awareness Level training
c. Authorized Individuals: Approximately 3 hours in addition to Awareness Level training and Affected Personnel Training
A copy of the Safe Clearance Program for the Control of Hazardous Energy (NWWP 385-1-20) can be found on the Walla Walla District Internet site at:
http://www.nww.usace.army.mil/Portals/28/docs/contracting/OP385120.pdf.
Training is an annual requirement and will expire one year from completion date. Training is provided by Vivid Learning Systems and is available on line at http://Hecp.vividlms.com. Cost for the training is displayed on the home page.
7.1.3 Activity Hazard Analysis. An AHA will be done covering all hazards related to the work, steps taken to mitigate the hazard, and the risk associated with the hazard as outlined in EM 385-1-1. All employees shall attend a safety meeting prior to performing any work. A blank AHA template will be provided.
7.1.4 Accident Prevention Plan. Develop as outlined in EM 385-1-1 Appendix A. The abbreviated version is acceptable for this contract as outlined Paragraph 11 of Appendix A. (01.A.11)
7.2 Safety equipment. The following is a list of minimum safety equipment the Contractor is expected to supply.
The safety equipment shall meet the requirements in EM385-1-1.
1. Safety Boots
2. Hard Hat
3. Personal safety locks (padlocks) for each person for safe clearance procedures
4. Traffic Cones
5. Safety Vest
6. Hearing Protection
7. Safety Harness
7.3 Corrective Action. Whenever the Contracting Officer detects any noncompliance with these requirements or any condition that poses a serious or imminent danger to the health or safety of any personnel, the Contracting Officer will notify the Contractor and request immediate corrective action. Lack of notice from the Contracting Officer does not relieve the Contractor from compliance requirements and responsibility. After receipt of notice from the Contracting Officer, the Contractor shall immediately take corrective action. Such notice, when delivered to the Contractor at the site of the work, shall be deemed sufficient for the purpose of notification. If the Contractor fails or refuses to comply promptly, the Contracting Officer may issue an order stopping all or part of the work until satisfactory corrective action has been taken.
8. Site Conditions & Access.
8.1 Existing Conditions. Take precautions to prevent damage to existing facilities while performing work under this contract. Upon completion of the work, all the existing facilities shall be left in a condition equal to the condition existing at time of the start of on-site work. All costs for Contractor-caused damage will be at the Contractor’s expense.
The Contractor is encouraged to mark the concrete nondestructively, as needed to ensure scanning accuracy, subject to approval by the CO.
Electric power is available from the existing electrical systems and will be supplied at no cost. Power is available from existing 120 volt, 1 phase, 15 ampere receptacles. The Government receptacles are located at various locations in each Miter Gate machinery room. During the installation of the instruments and data acquisition equipment, temporary wiring may be required to facilitate the work. The location of all temporary power lines and connections are subject to Contracting Officer approval. All temporary circuits, wire, extension cords and devices shall comply with EM 385-1-1 and shall be furnished, installed, connected, maintained and removed by the Contractor in a workmanlike manner prior to final acceptance by the Government. All temporary electrical lines and appurtenances shall be furnished and installed at no additional cost to the Government.
No phone service is available for use through the Project's phone system. Cell coverage is available but is limited.
The Government's restrooms on the Project will be available (not guaranteed) for use by Contractor personnel, and will be supplied at no cost to the Government.
8.2 Access to work area. Access to USACE Projects is controlled and access is restricted. Contractor personnel that are non-US citizen require a minimum of 30 days to be approved for site access. Coordinate access to the site through the COR.
Access to work area for personnel shall be from south side of the Project through the security guard station. Check in with the security guard on the south shore to receive and return access badges. Once badges are issued, the Contractor may access the Dam from the north (Washington) side.
Project access roads are secured with locked gates. All vehicles that pass through the locked gates will be subject to search. Only work vehicles and equipment that are essential to the conduct of the work will be allowed in the secured work areas. Parking will be limited due to space available. Maintain a thruway for emergency vehicle access at all times for both sides of the dam. Display suitable permanent or temporary identification with company name or logo on all Contractor vehicles. Setup safety cones around work vehicles.
The maintenance crews (which includes the crane operator and riggers) will be available during normal working hours, which is from 0630-1700 (minus breaks at 0900-0915, 1130-1200 and 1430-1445) during the 1-16 March 2022 on-site work window. A powerhouse operator is at the site 24 hours a day, 7 days a week, including Federal holidays.
All contractor and all associated sub-contractors employees shall comply with applicable installation, facility and area commander installation/facility access and local security policies and procedures (provided by government representative). In addition to the changes otherwise authorized by the changes clause of this contract, should the Force Protection Condition (FPCON) at any installation or facility change, the Government may require changes in contractor security matters or processes.
8.3 Crane Support. USACE will provide crane as needed for access (crane, man basket, operator, riggers, and lifting devices) for up to four days (normal working hours, two days per monolith). USACE can only support one crane or scissor lift at one time. Contractor will provide their own ladders where needed, such as within the stairways. Should the Contractor choose to use industrial roped access methods, the Contractor will be responsible for providing all qualified personnel and equipment needed to do so.
9. PRESCREENING OF EMPLOYEES
The Contractor must pre-screen all employees, including subcontractors, using the E-verify website (http://www.dhs.gov/E-Verify) to ensure that workers meet the established employment eligibility requirements.
The Contractor must ensure that the individuals undergoing screening have two valid forms of Government issued identification prior to pre-screening to ensure that the correct information is entered into the E-verify system. An initial list of verified/eligible employees must be provided to the COR no later than one day prior to the site visit.
10. BIOGRAPHICAL INFORMATION
Submit full name and date of birth to the COR for each person that will be performing on-site work. This will allow USACE to conduct a background check so those individuals can have unescorted access at the project.
10.1 Access and General Protection/Security Policy and Procedures
All contractor and all associated sub-contractors employees shall comply with applicable installation, facility and area commander installation/facility access and local security policies and procedures (provided by government representative). The contractor shall also provide all information required for background checks to meet installation/facility access requirements to be accomplished by installation Provost Marshal Office, Director of Emergency Services or Security Office. Contractor workforce must comply with all personal identity verification requirements (FAR 52.204-9, Personal Identity Verification of Contractor Personnel: http://www.ecfr.gov/cgi-bin/text-idx?rgn=div8&node=48:2.0.1.1.1.2.1.28) as directed by DOD, HQDA and/or local policy. In addition to the changes otherwise authorized by the changes clause of this contract, should the Force Protection Condition (FPCON) at any installation or facility change, the Government may require changes in contractor security matters or processes.
10.2 NCIC-III and Terrorist Screening
Contractor and all associated sub-contractors employees shall comply with adjudication standards and procedures using the National Crime Information Center Interstate Identification Index (NCIC-III) and Terrorist Screening Database (TSDB) (Army Directive 2014-05 / AR 190-13:
https://login.us.army.mil/login/fcc/caclogin.fcc?TYPE=33554433&REALMOID=06-649cf860-c8b5-1004-92e2- 8333a0560000&GUID=&SMAUTHREASON=0&METHOD=GET&SMAGENTNAME=-SM-dJOn510aZOr7gECZuNJeP%2b), applicable installation, facility and area commander installation/facility access and local security policies and procedures (provided by government representative, as NCIC and TSDB are available), or, at OCONUS locations, in accordance with status of forces agreements and other theater regulations.
CLAUSES INCORPORATED BY REFERENCE
52.203-3 Gratuities APR 1984 52.203-12 Limitation On Payments To Influence Certain Federal
Transactions
JUN 2020
52.203-16 Preventing Personal Conflicts of Interest JUN 2020 52.203-17 Contractor Employee Whistleblower Rights and Requirement
To Inform Employees of Whistleblower Rights
JUN 2020
52.203-18 Prohibition on Contracting With Entities That Require Certain Internal Confidentiality Agreements or Statements-- Representation
JAN 2017
52.204-4 Printed or Copied Double-Sided on Postconsumer Fiber Content Paper
MAY 2011
52.204-7 System for Award Management OCT 2018 52.204-9 Personal Identity Verification of Contractor Personnel JAN 2011 52.204-13 System for Award Management Maintenance OCT 2018 52.204-16 Commercial and Government Entity Code Reporting AUG 2020 52.204-18 Commercial and Government Entity Code Maintenance AUG 2020 52.204-21 Basic Safeguarding of Covered Contractor Information
Systems
DEC 2021
52.204-22 Alternative Line Item Proposal JAN 2017 52.204-24 Representation Regarding Certain Telecommunications and
Video Surveillance Services or Equipment
DEC 2021
52.209-7 Information Regarding Responsibility Matters OCT 2018 52.209-11 Representation by Corporations Regarding Delinquent Tax
Liability or a Felony Conviction under any Federal Law
FEB 2016
52.212-1 Instructions to Offerors--Commercial Products and Commercial Services
DEC 2021
52.212-3 Offeror Representations and Certifications--Commercial Products and Commercial Services
DEC 2021
52.212-4 Contract Terms and Conditions--Commercial Products and Commercial Services
DEC 2021
52.212-5 (Dev) Contract Terms and Conditions Required to Implement Statutes or Executive Orders--Commercial Products and Commercial Services (Deviation 2018-O0021)
DEC 2021
52.223-3 Hazardous Material Identification And Material Safety Data FEB 2021 52.223-5 Pollution Prevention and Right-to-Know Information MAY 2011 52.223-10 Waste Reduction Program MAY 2011 52.237-2 Protection Of Government Buildings, Equipment, And
Vegetation
APR 1984
52.242-13 Bankruptcy JUL 1995 52.243-1 Changes--Fixed Price AUG 1987 52.246-4 Inspection Of Services--Fixed Price AUG 1996 52.247-34 F.O.B. Destination NOV 1991 52.253-1 Computer Generated Forms JAN 1991 252.201-7000 Contracting Officer's Representative DEC 1991 252.203-7000 Requirements Relating to Compensation of Former DoD
Officials
SEP 2011
252.203-7002 Requirement to Inform Employees of Whistleblower Rights SEP 2013 252.203-7003 Agency Office of the Inspector General AUG 2019 252.203-7005 Representation Relating to Compensation of Former DoD
Officials
NOV 2011
252.204-7003 Control Of Government Personnel Work Product APR 1992 252.204-7004 Antiterrorism Awareness Training for Contractors. FEB 2019 252.204-7008 Compliance With Safeguarding Covered Defense Information
Controls
OCT 2016
252.204-7009 Limitations on the Use or Disclosure of Third-Party Contractor Reported Cyber Incident Information
OCT 2016
252.204-7012 Safeguarding Covered Defense Information and Cyber Incident Reporting
DEC 2019
252.204-7015 Notice of Authorized Disclosure of Information for Litigation Support
MAY 2016
252.204-7016 Covered Defense Telecommunications Equipment or Services -- Representation
DEC 2019
252.204-7017 Prohibition on the Acquisition of Covered Defense Telecommunications Equipment or Services -- Representation
MAY 2021
252.204-7018 Prohibition on the Acquisition of Covered Defense Telecommunications Equipment or Services
JAN 2021
252.204-7019 Notice of NIST SP 800-171 DoD Assessment Requirements NOV 2020 252.204-7020 NIST SP 800-171 DoD Assessment Requirements NOV 2020 252.217-7028 Over And Above Work DEC 1991 252.223-7006 Prohibition On Storage, Treatment, and Disposal of Toxic or
Hazardous Materials
SEP 2014
252.223-7008 Prohibition of Hexavalent Chromium JUN 2013 252.225-7001 Buy American And Balance Of Payments Program-- Basic DEC 2017 252.225-7012 Preference For Certain Domestic Commodities DEC 2017 252.225-7048 Export-Controlled Items JUN 2013 252.232-7010 Levies on Contract Payments DEC 2006 252.237-7010 Prohibition on Interrogation of Detainees by Contractor
Personnel
JUN 2013
252.237-7023 Continuation of Essential Contractor Services OCT 2010 252.237-7024 Notice of Continuation of Essential Contractor Services. OCT 2010 252.243-7001 Pricing Of Contract Modifications DEC 1991 252.243-7002 Requests for Equitable Adjustment DEC 2012 252.244-7000 Subcontracts for Commercial Items JAN 2021 252.247-7023 Transportation of Supplies by Sea FEB 2019
CLAUSES INCORPORATED BY FULL TEXT
52.204-26 COVERED TELECOMMUNICATIONS EQUIPMENT OR SERVICES--REPRESENTATION (OCT
2020)
(a) Definitions. As used in this provision, “covered telecommunications equipment or services” and "reasonable inquiry" have the meaning provided in the clause 52.204-25, Prohibition on Contracting for Certain Telecommunications and Video Surveillance Services or Equipment.
(b) Procedures. The Offeror shall review the list of excluded parties in the System for Award Management (SAM) (https://www.sam.gov) for entities excluded from receiving federal awards for “covered telecommunications equipment or services”.
(c) Representations.
(1) The Offeror represents that it [ ___ ] does, [ ___ ] does not provide covered telecommunications equipment or services as a part of its offered products or services to the Government in the performance of any contract, subcontract, or other contractual instrument.
(2) After conducting a reasonable inquiry for purposes of this representation, the offeror represents that it [ ___ ] does, [ ___ ] does not use covered telecommunications equipment or services, or any equipment, system, or service that uses covered telecommunications equipment or services.
(End of provision)
52.209-2 PROHIBITION ON CONTRACTING WITH INVERTED DOMESTIC CORPORATIONS--
REPRESENTATION (NOV 2015)
(a) Definitions. Inverted domestic corporation and subsidiary have the meaning given in the clause of this contract entitled Prohibition on Contracting with Inverted Domestic Corporations (52.209-10).
(b) Government agencies are not permitted to use appropriated (or otherwise made available) funds for contracts with either an inverted domestic corporation, or a subsidiary of an inverted domestic corporation, unless the exception at 9.108-2(b) applies or the requirement is waived in accordance with the procedures at 9.108-4.
(c) Representation. The Offeror represents that--
(1) It [ ___ ] is, [ ___ ] is not an inverted domestic corporation; and
(2) It [ ___ ] is, [ ___ ] is not a subsidiary of an inverted domestic corporation.
52.212-5 CONTRACT TERMS AND CONDITIONS REQUIRED TO IMPLEMENT STATUTES OR
EXECUTIVE ORDERS--COMMERCIAL PRODUCTS AND COMMERCIAL SERVICES (NOV 2021)
(a) The Contractor shall comply with the following Federal Acquisition Regulation (FAR) clauses, which are incorporated in this contract by reference, to implement provisions of law or Executive orders applicable to acquisitions of commercial products and commercial services:
(1) 52.203-19, Prohibition on Requiring Certain Internal Confidentiality Agreements or Statements (JAN 2017) (section 743 of Division E, Title VII, of the Consolidated and Further Continuing Appropriations Act, 2015 (Pub. L.
113-235) and its successor provisions in subsequent appropriations acts (and as extended in continuing resolutions)).
(2) 52.204-23, Prohibition on Contracting for Hardware, Software, and Services Developed or Provided by Kaspersky Lab and Other Covered Entities (NOV 2021) (Section 1634 of Pub. L. 115-91).
(3) 52.204-25, Prohibition on Contracting for Certain Telecommunications and Video Surveillance Services or Equipment. (NOV 2021) (Section 889(a)(1)(A) of Pub. L. 115-232).
(4) 52.209-10, Prohibition on Contracting with Inverted Domestic Corporations (Nov 2015).
(5) 52.233-3, Protest After Award (AUG 1996) (31 U.S.C. 3553).
(6) 52.233-4, Applicable Law for Breach of Contract Claim (OCT 2004) (Public Laws 108-77 and 108-78 (19 U.S.C. 3805 note)).
(b) The Contractor shall comply with the FAR clauses in this paragraph (b) that the Contracting Officer has indicated as being incorporated in this contract by reference to implement provisions of law or Executive orders applicable to acquisitions of commercial products and commercial services: [Contracting Officer check as appropriate.]
___ (1) 52.203-6, Restrictions on Subcontractor Sales to the Government (JUN 2020), with Alternate I (NOV 2021) (41 U.S.C. 4704 and 10 U.S.C. 2402).
___ (2) 52.203-13, Contractor Code of Business Ethics and Conduct (NOV 2021) (41 U.S.C. 3509).
___ (3) 52.203-15, Whistleblower Protections under the American Recovery and Reinvestment Act of 2009 (JUN 2010) (Section 1553 of Pub. L. 111-5). (Applies to contracts funded by the American Recovery and Reinvestment Act of 2009.)
X (4) 52.204-10, Reporting Executive Compensation and First-Tier Subcontract Awards (JUN 2020) (Pub. L. 109-
282) (31 U.S.C. 6101 note).
___ (5) [Reserved]
___ (6) 52.204-14, Service Contract Reporting Requirements (Oct 2016) (Pub. L. 111-117, section 743 of Div. C).
___ (7) 52.204-15, Service Contract Reporting Requirements for Indefinite-Delivery Contracts (Oct 2016) (Pub.
L. 111-117, section 743 of Div. C).
X (8) 52.209-6, Protecting the Government's Interest When Subcontracting with Contractors Debarred, Suspended, or Proposed for Debarment. (NOV 2021) (31 U.S.C. 6101 note).
___ (9) 52.209-9, Updates of Publicly Available Information Regarding Responsibility Matters (OCT 2018) (41 U.S.C. 2313).
____ (10) [Reserved]
____ (11) 52.219-3, Notice of HUBZone Set-Aside or Sole-Source Award (SEP 2021) (15 U.S.C. 657a).
____ (12) 52.219-4, Notice of Price Evaluation Preference for HUBZone Small Business Concerns (SEP 2021) (if the offeror elects to waive the preference, it shall so indicate in its offer) (15 U.S.C. 657a).
____ (13) [Reserved]
X (14)(i) 52.219-6, Notice of Total Small Business Set-Aside (NOV 2020) (15 U.S.C. 644).
____ (ii) Alternate I (MAR 2020) of 52.219-6.
____ (15)(i) 52.219-7, Notice of Partial Small Business Set-Aside (NOV 2020) (15 U.S.C. 644).
____ (ii) Alternate I (MAR 2020) of 52.219-7.
____ (16) 52.219-8, Utilization of Small Business Concerns (OCT 2018) (15 U.S.C. 637(d)(2) and (3)).
____ (17)(i) 52.219-9, Small Business Subcontracting Plan (NOV 2021) (15 U.S.C. 637(d)(4)).
____ (ii) Alternate I (NOV 2016) of 52.219-9.
____ (iii) Alternate II (NOV 2016) of 52.219-9.
____ (iv) Alternate III (JUN 2020) of 52.219-9.
____ (v) Alternate IV (SEP 2021) of 52.219-9.
____ (18) (i) 52.219-13, Notice of Set-Aside of Orders (MAR 2020) (15 U.S.C. 644(r)).
____ (ii) Alternate I (MAR 2020) of 52.219-13.
____ (19) 52.219-14, Limitations on Subcontracting (SEP 2021) (15 U.S.C. 657s).
____ (20) 52.219-16, Liquidated Damages—Subcontracting Plan (SEP 2021) (15 U.S.C. 637(d)(4)(F)(i)).
____ (21) 52.219-27, Notice of Service-Disabled Veteran-Owned Small Business Set-Aside (SEP 2021) (15 U.S.C.
657f).
X (22) (i) 52.219-28, Post-Award Small Business Program Rerepresentation (SEP 2021) (15 U.S.C. 632(a)(2)).
____ (ii) Alternate I (MAR 2020) of 52.219-28.
____ (23) 52.219-29, Notice of Set-Aside for, or Sole-Source Award to, Economically Disadvantaged Women- Owned Small Business Concerns (SEP 2021) (15 U.S.C. 637(m)).
____ (24) 52.219-30, Notice of Set-Aside for, or Sole-Source Award to, Women-Owned Small Business Concerns Eligible Under the Women-Owned Small Business Program (SEP 2021) (15 U.S.C. 637(m)).
____ (25) 52.219-32, Orders Issued Directly Under Small Business Reserves (MAR 2020) (15 U.S.C. 644(r)).
____ (26) 52.219-33, Nonmanufacturer Rule (SEP 2021) (15 U.S.C. 657s).
X (27) 52.222-3, Convict Labor (JUN 2003) (E.O. 11755).
X (28) 52.222-19, Child Labor--Cooperation with Authorities and Remedies (JAN 2020) (E.O. 13126).
X (29) 52.222-21, Prohibition of Segregated Facilities (APR 2015).
X (30)(i) 52.222-26, Equal Opportunity (SEPT 2016) (E.O. 11246).
____ (ii) Alternate I (FEB 1999) of 52.222-26.
____ (31)(i) 52.222-35, Equal Opportunity for Veterans (JUN 2020) (38 U.S.C. 4212).
____ (ii) Alternate I (JUL 2014) of 52.222-35.
____ (32)(i) 52.222-36, Equal Opportunity for Workers with Disabilities (JUN 2020) (29 U.S.C. 793).
____ (ii) Alternate I (JUL 2014) of 52.222-36.
____ (33) 52.222-37, Employment Reports on Veterans (JUN 2020) (38 U.S.C. 4212).
____ (34) 52.222-40, Notification of Employee Rights Under the National Labor Relations Act (DEC 2010) (E.O.
13496).
X (35)(i) 52.222-50, Combating Trafficking in Persons (NOV 2021) (22 U.S.C. chapter 78 and E.O. 13627).
____ (ii) Alternate I (MAR 2015) of 52.222-50 (22 U.S.C. chapter 78 and E.O. 13627).
____ (36) 52.222-54, Employment Eligibility Verification (NOV 2021). (E. O. 12989). (Not applicable to the acquisition of commercially available off-the-shelf items or certain other types of commercial products or commercial services as prescribed in FAR 22.1803.)
____ (37)(i) 52.223-9, Estimate of Percentage of Recovered Material Content for EPA–Designated Items (MAY 2008) (42 U.S.C. 6962(c)(3)(A)(ii)). (Not applicable to the acquisition of commercially available off-the-shelf items.)
____ (ii) Alternate I (MAY 2008) of 52.223-9 (42 U.S.C. 6962(i)(2)(C)). (Not applicable to the acquisition of commercially available off-the-shelf items.)
____ (38) 52.223-11, Ozone-Depleting Substances and High Global Warming Potential Hydrofluorocarbons (JUN 2016) (E.O. 13693).
____ (39) 52.223-12, Maintenance, Service, Repair, or Disposal of Refrigeration Equipment and Air Conditioners
(JUN 2016) (E.O. 13693).
____ (40) (i) 52.223-13, Acquisition of EPEAT® Registered Imaging Equipment (JUN 2014) (E.O.s 13423 and 13514).
____ (ii) Alternate I (OCT 2015) of 52.223-13.
____ (41)(i) 52.223-14, Acquisition of EPEAT® Registered Televisions (JUN 2014) (E.O.s 13423 and 13514).
____ (ii) Alternate I (JUN 2014) of 52.223-14.
____ (42) 52.223-15, Energy Efficiency in Energy-Consuming Products (MAY 2020) (42 U.S.C. 8259b).
____ (43)(i) 52.223-16, Acquisition of EPEAT®-Registered Personal Computer Products (OCT 2015) (E.O.s 13423 and 13514).
____ (ii) Alternate I (JUN 2014) of 52.223-16.
X…