Section 01 00 00 - General Requirements

SCOPE OF WORK

NRM Access Road Repairs

Harry S. Truman Dam and Reservoir

DESCRIPTION OF WORK AND GENERAL REQUIREMENTS

1 GENERAL

1.1 General

The U.S. Army Corps of Engineers, Harry S. Truman Dam and Reservoir, Warsaw Missouri has a need for road and parking lot repairs, as well as other associated work. These areas are for public access usage and are in remote locations. Contractor to provide the labor, materials, supplies, equipment, and mobilization needed for road repair areas. The Government shall not exercise any supervision or control over the contract and providers shall be accountable solely to the Contractor who, in turn is responsible to the Government.

1.2 Project Description

Project requires grading, shaping roads, and parking lots to repair damage by stormwater runoff. Construction of earthen berms/barriers shall be constructed using onsite materials. In addition to the work listed above the Contractor shall also perform culvert pipe replacement, tree limb removal with mulching and applying surface aggregate to roadways and parking lots in various locations around the lake.

1.3 Location

Project Location: The work is located at the United States Army Corps of Engineers (USACE) Harry S. Truman Dam and Reservoir in various remote locations around the lake area.

Construction Site Location:

Areas are in remote location and do not have physical address specific to each site. Refer to site maps for each location.

Administration Office:

Harry S. Truman Dam and Reservoir U.S. Army Corps of Engineers 15968 Truman Road Warsaw, MO 65355

1.4 Points of Contact

Primary Contact:

Larry Smith – Natural Resource Management Lead Office Phone: 816-389-3951 Mobile Phone: 660-223-3313 Email: larry.smith@usace.army.mil

Alternate Contact:

Tyler Clements – Natural Resource Specialist Office Phone: 816-389-2457 Mobile Phone: 660-292-1378 Email: Tyler.W.Clements@usace.army.mil

1.5 Work Hours

The standard workday is 7:00 am to 5:00 pm Monday thru Friday, excluding Federal holidays. Work hours may be adjusted with approval of Contracting Officer Representative (COR) or Operations Project Manager. Any request for variation from these hours shall be coordinated with the COR at a minimum of 48 hours in advance.

1.6 Schedule Constraints

1.6.1 Holiday Restrictions

No work on Federal Holidays- New Years, Martin Luther King Day, Presidents Day, Memorial Day, Juneteenth, Fourth of July, Labor Day, Columbus Day, Thanksgiving Day, and Christmas Day.

1.6.2 Schedule Constraints by Work Activity

The requirement for scheduling in advance of each work activity varies based on the date of the scheduled work activity, site location, and the type of work. Work activities that require limiting or restricting public vehicle access shall be coordinated closely with the COR and Contractor shall provide advanced notice of at least (7) calendar days for all scheduled work activities.

1.7 Site Visit/Project Photos

Interested parties are strongly encouraged to visit the sites prior to preparing and submitting their bid. Contractors are encouraged to attend the scheduled site visit on the solicitation prior to submitting a bid on this contract.

1.8 Submittals

The Contractor shall provide to the Government the submittals identified within this contract and submittals that are identified as necessary to ensure performance compliance. Once submittals are received the government has 10 working days for review and acceptance. All submittals except for post construction are required prior to construction commencing.

The Government will respond to the Contractor’s submittals with email, fax, or postal mail per the Contractor’s requested preference to the Government. The Government’s approval of submittals shall not be construed as a complete check of the contract requirements. Government approval will be an indication of a satisfactory submittal of the general method of compliance with the requirements of the contract. Government approval will not relieve the Contractor of the responsibility for contract compliance.

Government disapproved submittals shall be resubmitted by the Contractor addressing corrections and contract compliance. At the discretion of the Government, the Contractor may be directed by the Government to proceed with work in advance the submittals; however, the Contractor shall practice due diligence and continuity with the submittal process. Each submittal shall be attached to a USACE provided form 4025 and emailed to the primary point of contact/COR; refer to section Point of Contact of this SOW for contact information or COR Appointment Letter (post award).

1.8.1 Preconstruction Submittals SD-01:

1.8.1.1 Project Schedule

1.8.1.2 Quality Control Plan

1.8.1.3 Accident Prevention Plan

1.8.1.4 Activity Hazard Analysis

1.8.1.5 Insurance

1.8.1.6 Equipment List

1.8.2 Product Data SD-03:

1.8.2.1 Aggregate Gradation

1.8.2.2 Corrugated Polyethylene Drainage Pipe

1.8.2.3 Manufactures Installation Instructions for Corrugated Polyethylene Drainage Pipe

1.8.3 Closeout SD-11

1.8.3.1 Daily Reports

1.8.3.2 Contractor Exposure Hours

1.8.3.3 Photographic Documentation

1.8.3.4 Warranty Information

1.9 Submittals Definitions

The Contractor is responsible for the requirements of this contract and is encouraged to review the document in detail and to provide inquiries to the Government as necessary prior to preparing a proposal.

1.9.1 Contractor Daily Written and Photographic Documentation:

Contractor shall submit daily logs of work conducted to the COR. Contractor may use their own form for documentation or forms can be provided at the contractor’s request. Photos of all phases of the project are required and shall be submitted to COR in an agreed upon formatting upon job completion. Each photo shall have a time date stamp. It is recommended that daily logs are submitted daily.

The following information must be included:

Date Equipment Used Total hours worked that day Contractor Name Precipitation Controversial Matters Weather description Methods Used Miscellaneous Remarks Air temperature Work completed that day Size of crew Problems encountered

1.9.2 Project Schedule

Prior to any work being started the Contractor shall submit a project schedule for approval. The project schedule shall contain a chronological order of activities that progresses to project completion with closeout documents as its own activity. Each activity shall have a duration with a proposed start and end date.

Schedule of Values for each Activity- A Schedule of Values (SOV), is a list of every work item on a project, along with each item’s value or cost. This comprehensive work list represents the entire construction project and the entire contract price, from beginning to end. This schedule will be used to determine progress payment request.

1.9.3 Quality Control Plan (QCP)

The Contractor shall develop and maintain an effective quality control plan to ensure services are performed in accordance with this Scope of Work (SOW). Contractor shall develop and implement procedures to identify, prevent, and ensure non- recurrence of defective services. The Contractor’s quality control program assures that the work complies with the requirements of the contract. The QCP shall be submitted within 30 days after the contract has been awarded. After acceptance of the quality control plan the Contractor shall receive the contracting officer’s or COR acceptance in writing of any proposed change to his QC system.

Submit a detailed Contractor Quality Control (CQC) Plan that fully represents and conforms to the requirements of these specifications. At a minimum the CQC is to include the following:

1.9.3.1 Defined responsibilities of personnel that ensure the quality requirements for this contract are met. All responsibilities such as Superintendent, Site Safety and Health Officer (SSHO), and Quality Control Manager (QCM) shall be assigned to specific personnel and an alternate if the primary is not on-site.

Individual(s) who will be onsite during construction operations and who will have the authority to act for the Contractor to include the authority to stop work which is not in compliance with the contract.

1.9.3.2 Role Definitions- It is the decision of the Contractor on whether the following roles are the duties of a single individual or are assigned to multiple individuals. The Superintendent/ QCM/ SSHO shall meet the minimum requirements as stated in the EM385- 1-1. Duties shall include, but are not limited to, maintaining project status and communication with Government personnel, weekly progress reports including a weekly look ahead report. Coordination with the COR is critical for outages and equipment delivery. All personnel on site are required to have a photo ID on persons. The Government reserves the right to remove or reject personnel who do not meet qualifications or security requirements.

1.9.3.2.1 Superintendent is to direct the day-to-day operations on the construction site and control the short-term schedule as well as subcontractor coordination responsibilities.

1.9.3.2.2 Site Safety and Health Officer (SSHO) oversees inspecting site conditions to determine if hazards are present and has the authority to establish procedures and policies to overcome those hazardous situations.

1.9.3.2.3 Quality Control Manager (QCM) is responsible for managing and performing the daily QC responsibilities of the project to ensure the project is constructed in accordance with the established minimum standards. If minimal standards are not being met the QCM has the authority to implement changes to achieve those standards.

1.9.3.3 Submit a clearly defined proposed procedures for quality control, product sampling and testing as part of the plan.

1.9.3.4 Proposed methods for product performance controls, including method and frequency of product sampling and testing both in raw material form and cured product form. All costs associated with the testing laboratory work for quality assurance and quality control, as well as rework required to meet project requirements, shall be paid for by the contractor. No separate payment will be made for this work. It will be considered incidental to the work in which the material is utilized.

1.9.3.5 A scheduled performance and product test result shall be reviewed with the COR at a regularly scheduled progress meeting.

1.9.3.6 Inspection Forms and guidelines for quality control inspections in accordance with the standards specified in this Contract and submitted with the QCP.

1.9.3.7 Outline specific repair or replacement procedures for potential defects that occur within the installed system, following repair or replacement procedures that are compatible with the system being used.

Submit Repair or Replacement Procedures must adhere to the product manufacturer's written specifications for repair or replacement.

1.9.3.8 Key personnel phone numbers including e-mails and all other staff shall be included within the QCP.

1.9.3.9 Contractor Experience and Qualifications:

A statement letter of the Contractor’s experience and qualifications on company letterhead.

The lead personnel including the project manager, and the foreman shall have experience and demonstrated competency and experience to perform the scope of work contained in this contract. The name and experience of each lead individual performing work on this contract shall be submitted with the contractor qualifications.

1.9.3.10 Workmanship shall be of the highest grade in accordance with the best modern practices to conform to the specifications for the work being performed. The Contractor shall be responsible for quality control to ensure all components and workmanship meet requirements of this contract. Representatives of USACE reserves the right to inspect and witness the work, verify quality of workmanship and products used at any time, whether the work is performed in the field or at the Contractor’s shop.

1.9.4 Accident Prevention Plan

Contractor shall prepare a site-specific Accident Prevention Plan (APP). Prepare the APP in accordance with the format and requirements of USACE EM 385-1-1. Cover all paragraph and subparagraph elements in USACE EM 385-1-1, Appendix A, "Minimum Basic Outline for Accident Prevention Plan". The APP shall be job-specific and address any unusual or unique aspects of the project or activity for which it is written.

1.9.5 Activity Hazzard Analyze

An Activity Hazard Analysis must be provided prior to breaking ground. The Activity Hazard Analysis must address all foreseeable safety concerns including and not limited too; all construction safety features, safety zone protection, fire safety, personal protective equipment, equipment operations and any other safety concerns.

USACE uses the Activity Hazard Analysis (AHA) as part of a total risk management process. Contractors may use the AHAs or their own version such as a Job Safety Analyses (JSAs), or Job Hazard Analyses (JHAs), or similar Risk Management assessment tools. These documents are considered equivalent to, and acceptable substitutes for, the USACE’s AHA provided the data collected is the same as that required by the AHA.

1.9.6 Insurance Requirements

The Contractor shall maintain the required insurance coverage throughout the duration of project.

1.9.7 Equipment

Submit a list of specific equipment used for this contract, i.e., compact track loader, backhoe, man lift, grader, etc.

1.9.8 Product Data

Catalog cuts, illustrations, schedules, diagrams, performance charts, instructions and brochures illustrating size, physical , and other characteristics of materials, , or equipment for some portion of the work.

1.9.9 Close Out

Documentation to record compliance with technical or administrative requirements necessary to properly close out the contract.

1.9.9.1 Warranty

Warranty - At a minimum provide warranty for a period of not less than one year that the finished products, are free from defects in installation workmanship, to include everything in this Scope of Work for this project. Any material or construction phase that comes with a warranty longer than one year will be guaranteed for that period. All warranty paperwork will be provided to the COR at project completion. After Final Acceptance of the work, and prior to final payment, warranty information will be turned over to the Government.

1.10 Payment and Invoices:

Each line item on an invoice shall give a description including the Contract Line-Item Number (CLIN) and be in accordance with the submitted schedule of value. Upon receipt, the COR will certify that the requested amounts are appropriate before payment will be made. Invoices shall include all necessary information, including any necessary supporting documentation required as part of this Scope of Work. All invoices shall reflect the contract number, (Block 2 of the SF-1442).

1.11 Contractor Exposure Hours:

The Contractor shall track the number of man hours to perform the contract requirements. The total number of man hours per day shall be submitted to the Government with the invoice.

1.12 Occupancy of Premise

Before work is started, it is the contractor’s responsibility to arrange with COR a sequence of procedure, means of access, space for storage of materials and equipment, and use of approaches, corridors or excess required.

1.13 Demolition Plan

Prepare a Demolition Plan and submit proposed demolition, and removal procedures for approval before work is started. Include in the plan procedures for removal and disposition of materials. Take necessary precautions to avoid damage to existing items to remain in place, to be reused, or to remain the property of the Government. Repair or replace damaged items as approved by the COR.

1.14 Measurements and Quantities

The Contractor shall verify all measurements at the project site and shall be responsible for all dimensions, fittings, and the proper installation of all materials and equipment specified.

1.15 Permits

The Contractor shall be responsible for obtaining any required permit.

1.16 Hot Work Permit

The Contractor shall be liable for any fire loss to Government property attributable to negligence on the part of the Contractor, including failure to comply with fire prevention measures prescribed by terms of this contract.

1.17 Safety Requirements

1.17.1 Protections from Hazards

During progress of work, the Contractor shall protect all personnel, whether Government or civilian, from any and all safety hazards caused by the construction operations.

1.17.2 Traffic Control

Work is located within public use area and the contractor should take precautions to limit the personnel from entering the proximity of the construction location. Contractor shall provide all temporary signs, markers, and personnel as necessary to maintain safety in the worksite. All signs shall conform to the latest edition of the Manual of Uniform Control Devices (MUTCD).

1.17.3 U.S. ARMY CORPS OF ENGINEERS SAFETY AND HEALTH REQUIREMENTS MANUAL,

EM 385-1-1 (2014)

EM 385-1-1 and its changes are available at http://www.hq.usace.army.mil (at the HQ homepage, select Safety and Occupational Health). Select the appropriate manual. The Contractor shall be responsible for complying with the current edition and all changes posted on the web as of the effective date of this solicitation.

2014 Version: https://www.usace.army.mil/Missions/Safety-and-Occupational-Health/Safety-and-Health- Requirements-Manual/

1.17.4 Utilities Clearance

At least 72 hours prior to any excavation Missouri 811 or 1-800-DIG-RITE, shall be contacted for utilities clearances.

1.18 Special Requirements

Site specific special requirements will be specified, as necessary, in the contract documents.

1.18.1 Work is in remote locations and access is limited.

1.19 Security:

1.19.1 In unoccupied facilities, the Contractor shall be responsible for the security of the facility, i.e., all exterior doors shall be locked, windows closed and locked, etc.

1.19.2 The Contractor shall not be on site without prior notification to the Corps of Engineers COR or otherwise designated person(s).

1.19.3 Contractor personnel shall have valid civilian ID's and Contractor vehicles shall have a valid registration.

1.20 Antiterrorism/Operation Security Requirements

1.20.1 All contractor and all associated sub-contractors’ employees shall comply with applicable installation, facility and area commander installation/facility access and local security policies and procedures (provided by government representative). The contractor shall also provide all information required for background checks to meet installation/facility access requirements to be accomplished by installation Provost Marshal Office, Director of Emergency Services or Security Office. Contractor workforce must comply with all personal identity verification requirements (FAR clause 52.204-9, Personal Identity Verification of Contractor Personnel) as directed by DOD, HQDA and/or local policy. In addition to the changes otherwise authorized by the changes clause of this contract, should the Force Protection Condition (FPCON) at any installation or facility change, the Government may require changes in contractor security matters or processes.

1.20.2 The contractor and all associated sub-contractors shall receive a brief/training (provided by the RA) on the local suspicious activity reporting program. This locally developed training will be used to inform employees of the types of behavior to watch for and instruct employees to report suspicious activity to the project manager, security representative or law enforcement entity. This training shall be completed within 30 calendar days of contract award and within 30 calendar days of new employees commencing performance with the results reported to the COR NLT 5 calendar days after the completion of the training.

1.20.3 The Contractor must pre-screen Candidates using the E-verify Program (http://www.uscis.gov/e-verify) website to meet the established employment eligibility requirements. The Vendor must ensure that the

Candidate has two valid forms of Government issued identification prior to enrollment to ensure the correct information is entered into the E-verify system. An initial list of verified/eligible Candidates must be provided to the COR no later than 3 business days after the initial contract award." *When contracts are with individuals, the individuals will be required to complete a Form I-9, Employment Eligibility Verification, with the designated Government representative. This Form will be provided to the COR and shall become part of the official contract file.

1.20.4 Per the E-Verify Website the following exemptions apply:

Employers whose contracts are exempt from the E-Verify federal contractor rule are not required to enroll in E-Verify. A contract is considered exempt if any one of the following applies: (1) It is for fewer than 120 days. (2) It is valued at less than $150,000, the simplified acquisition threshold (Source:

http://www.uscis.gov/e-verify/federal-contractors/exemptions-and-exceptions).

1.21 Applicable Publications

The publications referenced herein shall be the most recent at the time of solicitation.

1.22 Worksite Housekeeping

1.22.1 The Contractor shall remove all trash and disposal material from the worksite before the end of each day.

The Contractor shall take all possible precautions to maintain the work site, always in a condition that will prevent damage or injury to person or property, Government or otherwise. The Contractor shall be responsible for all damages caused by the negligent acts or omissions of his employees, sub-contractors, or agents during Contract performance. Do not allow scrap/waste materials to accumulate on-site; transport immediately from the government property and legally dispose of them at the end of each working day.

The contractor will not be permitted to sell salvaged material on Government property. No persons other than the Contractors or sub-contractors’ employees shall be allowed to remove salvage from the site.

1.22.2 Schedule cleanup in a manner to cause the least possible obstruction and inconvenience to traffic, pedestrians, and property occupants. Excess excavated material will become the responsibility of the Contractor to haul off to a government local site on the Project within 2 miles radius.

1.23 Responsibility for Damage

Damage to Personal Property: The Contractor shall be solely responsible for all damage to Government and occupant personal property caused by the Contractors' personnel, subcontractors, his agents, or by the performance of his work.

1.24 Disposal of Materials

1.24.1 All wastes generated during Contractor operations shall be disposed of by the Contractor at his/her expense.

1.24.2 Solid wastes (excluding clearing debris) shall be placed in containers which are emptied on a regular schedule. Handling, storage, and disposal shall be conducted to prevent contamination. Segregation measures shall be employed so that no hazardous or toxic waste will become co-mingled with solid waste.

The Contractor shall transport solid waste off Government property and dispose of it in compliance with Federal, State, and local requirements for solid waste disposal. A Subtitle D RCRA permitted landfill shall be the minimum acceptable off-site solid waste disposal option. The Contractor shall verify that the selected transporters and disposal facilities have the necessary permits and licenses to operate. The Contractor shall comply with Federal, State, and local laws and regulations pertaining to the use of landfill areas.

1.24.3 Wastes classified as hazardous wastes under the Resource Conservation and Recovery Act shall be disposed of, unless otherwise specified in this contract. No hazardous waste shall be disposed of without prior review of the disposal documents, and the approval of the COR and the Directorate of Public Works Environmental Coordinator, or his designated representative. The Contractor shall provide an original copy of the disposal document from the approved EPA or State permitted disposal facility for each shipment of hazardous waste generated in this project to the CORs Representative.

1.25 Utilities

The Contractor is responsible for providing utilities for their employees. This shall include but not limited to electric, water, and restrooms.

1.26 Pre-Construction Meeting

Prior to commencement of any work being performed, the contractor shall participate in a pre-construction meeting with the CORs and other pertinent government officials. Pre-construction meeting date will be set within 10 calendars days of contract award.

1.27 Post Award Conference/Periodic Progress Meetings

The Contractor agrees to attend any post award conference convened by USACE in accordance with Federal Acquisition Regulation Subpart 42.5. The Contracting Officer, Contracting Officers Representative (COR), and other Government personnel, as appropriate, may meet periodically with the Contractor to review the Contractor's performance. At these meetings the Contracting Officer will apprise the Contractor of how the government views the Contractor's performance and the Contractor will apprise the Government of problems, if any, being experienced. Appropriate action shall be taken to resolve outstanding issues. These meetings shall be at no additional cost to the government.

1.28 Environmental Requirements

1.28.1 The Contractor shall minimize environmental pollution and damage that may occur as the result of construction operations. The environmental resources within the project boundaries and those affected outside the limits of permanent work shall be protected during the entire duration of this contract. The Contractor shall comply with all applicable environmental Federal, State, and local laws and regulations.

The Contractor shall be responsible for any delays resulting from failure to comply with environmental laws and regulations. During construction, the Contractor shall be responsible for identifying, implementing, and submitting for approval any additional requirements for environmental compliance.

1.28.2 If any cultural and/or human remains are inadvertently uncovered during construction, the work is to be halted until appropriate project and district personnel are notified and the remains are evaluated for National Register of Historic Places (NRHP) significance.

1.28.3 No clearing of trees will occur between 1 April and 31 October. Except 3” diameter hard woods or under can be cleared anytime during the 12-month year including all sizes of eastern red cedar and limbs of any size on trees.

1.28.4 Environmental Protection- Prior to the delivery of any material to the site, and before the start of any onsite construction activities, the Contractor and the Government Representative shall make a joint site survey.

This survey will include a review of work constraints and resources specifically identified as environmental features requiring protection along with the condition of trees, shrubs, and grassed areas immediately adjacent to the site of work and access route(s), as applicable. The Contractor shall protect those environmental features included in this survey and any indicated on the drawings, regardless of interference which their preservation may cause to the Contractor's work under the contract. The Contractor will review the requirements in this Section and any notes from the joint site survey with each worker prior to them beginning work at the site.

1.28.5 Environmental Assessment of Scope of Work Deviations

Any deviations, requested by the Contractor, from the drawings, plans and specifications, which may have an environmental impact, will be subject to approval by the COR and may require an extended review, processing, and approval time. The COR reserves the right to disapprove alternate methods, even if they are more cost effective, if the COR determines that the proposed alternate method will have an adverse environmental impact.

1.28.6 Water Resources

The Contractor shall monitor construction activities to prevent pollution of surface and ground waters.

Toxic or hazardous chemicals shall not be applied to soil or vegetation unless otherwise indicated. All water areas affected by construction activities shall be monitored by the Contractor. For construction activities immediately adjacent to impaired surface waters, the Contractor shall be capable of quantifying sediment or pollutant loading to that surface water when required by State or Federally issued Clean Water Act permits.

1.28.7 Sound Intrusions

The Contractor shall keep construction activities under surveillance and control to minimize environment damage by noise. All equipment to have factory installed muffler system and comply with standard equipment decibel ratings.

1.28.8 Fuel and Lubricants

Storage, fueling and lubrication of equipment and motor vehicles shall be conducted in a manner that affords the maximum protection against spill and evaporation. Fuel, lubricants, and oil shall be managed and stored in accordance with all Federal, State, Regional, and local laws, and regulations. Used lubricants and used oil to be discarded shall be stored in marked corrosion-resistant containers and recycled or disposed in accordance with 40 CFR 279, State, and local laws, and regulations.

1.28.9 Previously Used Equipment

The Contractor shall clean all previously used construction equipment prior to bringing it onto the project site. The Contractor shall ensure that the equipment is free from soil residuals, egg deposits from plant pests, noxious weeds, and plant seeds. The Contractor shall consult with the USDA jurisdictional office for additional cleaning requirements.

1.29 Time Extensions for Unusually Severe Weather

This provision specifies the procedure for determination of time extensions for unusually severe weather in accordance with:

a. This provision specifies the procedure for section (d) of the CONTRACT CLAUSE 52.249-10 titled "Default (Fixed Price Construction)". In order for the Contracting Officer to award a time extension under this clause, the following conditions must be satisfied:

(1) The weather experienced at the project site during the contract period must be found to be unusually severe, that is, more severe than the adverse weather anticipated for the project location during any given month.

(2) The unusually severe weather must actually cause a delay to the completion of the project. The delay must be beyond the control and without the fault or negligence of the Contractor.

b. The following schedule of monthly anticipated adverse weather delays is based on National Oceanic and Atmospheric Administration (NOAA) or similar data for the project location and will constitute the base line for monthly weather time evaluations. The Contractor's progress schedule must reflect these anticipated adverse weather delays in all-weather dependent activities for the duration of the project.

MONTHLY ANTICIPATED ADVERSE WEATHER DELAY WORKDAYS BASED ON (5) DAY WORK

WEEK *

Jan Feb Mar Apr May June Jul Aug Sep Oct Nov Dec Warsaw Mo 65355

10 8 7 7 9 8 7 8 6 6 5 8

c. Upon acknowledgment of the Notice to Proceed (NTP) and continuing throughout the duration of the contract, the Contractor shall record on the daily CQC report, the occurrence of adverse weather and resultant impact to normally scheduled work. Actual adverse weather delay days must prevent work on critical path activities for 50 percent or more of the Contractor's scheduled workday.

d. Within ten days of the following month, the Contractor shall provide in writing a list of proposed dates of the actual adverse weather delay days for each month. The number of actual adverse weather delay days shall include days impacted by actual adverse weather (even if adverse weather occurred in previous month), be calculated chronologically from the first to the last day of each month and be recorded as full days. If the number of actual adverse weather delay days exceeds the number of days anticipated in paragraph (b), above, the Contracting Officer will convert any qualifying delays to calendar days and issue a modification in accordance with the Contract Clause entitled "Default (Fixed Price Construction)". After the original contract completion date has passed, adverse weather that causes delay to the completion of the project will be granted day-for-day without deducting anticipated adverse weather delay days and will be converted from workdays to calendar days.

* Monthly anticipated weather delay days shall be adjusted proportionally if work is scheduled to be performed in a work week with greater than or less than a five-day work week. The following formula shall be used to adjust the monthly anticipated weather delays: Adjusted monthly anticipated weather delays = A multiplied by (B divided by C); where A = The monthly anticipated adverse weather delay for a particular month based on a five-day work week. B = The actual average number of days work is scheduled to be performed in a work week during that particular month. C = The number five (5) e.g., If the monthly anticipated adverse weather delay for January based on a five-day work week is 10 days, but the Contractor actually scheduled an average of a six-day work week for that month, the monthly anticipated weather delay would be adjusted by applying the above formula as follows: 10 x (6/5) = 12 days.

* Monthly anticipated weather delay days shall also be adjusted proportionally for those situations involving a fractional part of a month. Some examples are the month Notice to Proceed is acknowledged and the month of the original contract completion date. The following formula shall be used to adjust the monthly anticipated weather delays:

Adjusted monthly anticipated weather delays = D multiplied by (E divided by F); where

D = The monthly anticipated adverse weather delay for a particular month.

E = The number of calendar days during that fractional part of a particular month.

F = The number of calendar days in that particular month. e.g., The monthly anticipated adverse weather delay for the particular month is 9 days. The original contract completion date is on the twentieth (20th) day of a thirty (30) day month. The monthly anticipated adverse weather delay would be adjusted by applying the above formula as follows: 9 x (20/30) = 6 days.

1.30 FIELD OFFICE OVERHEAD (FOOH) ACCOUNTING METHOD

NOTICE TO OFFERORS: Declare below the single accounting practice that you will apply to this contract to calculate field office overhead for all change orders, modifications and requests for equitable adjustment. Pursuant to Federal Acquisition Regulations (FAR) Parts 31.105(d)(3) and 31.203(d)(1), an accounting practice that varies from modification to modification is not allowed. Select one of the following:

1. TIME DISTRIBUTION BASE FOR A PER DIEM RATE

See Field Office Overhead Per Diem Rate" paragraph below for more information on this accounting practice.

2. DIRECT COST DISTRIBUTION BASE FOR A PERCENTAGE MARKUP

See Field Office Overhead Percentage Markup" paragraph below for more information on this accounting practice.

3. OTHER ACCOUNTING PRACTICE THAT IS ALLOWABLE UNDER THE FAR AND

THAT USES A SINGLE DISTRIBUTION BASE

If you choose 3, you must describe the accounting practice in sufficient detail below to allow the contracting officer to determine what account practice is being utilized by your company and that it complies with the FAR.

Field Office Overhead Per Diem Rate If any change to the contract, issued pursuant to the Changes Clause or otherwise, for which the Government is responsible, causes an increase or decrease in the Contractor's cost of, or the time required for, performance under the contract, the Contracting Officer shall make an equitable adjustment and modify the contract in writing.

Under such equitable adjustment, no percentage markup for field office overhead shall be allowed. Additionally, no payment of field office overhead shall be allowed for any changes when the completion of the contract is not extended by reason of the change, except the Contractor may be reimbursed any variable expense it incurs due to the change, provided it can substantiate the variables. The Contractor shall be reimbursed for field office overhead using only a per diem basis when the completion of the contract is extended by reason of the change issued under any clause except the Default clause. Equitable adjustment shall be made for the costs that are incurred or are to be incurred due to the change. The Contractor shall provide a detailed breakdown of its proposed increase or decrease of costs as required by Contract Clause DFARS 252.236-7000 MODIFICATION OF PROPOSALS - PRICE

BREAKDOWN.

Field Office Overhead Percentage Markup If any change to the contract issued pursuant to the changes Clause, or otherwise, for which the Government is responsible, causes an increase or decrease in the Contractor's cost, or in the time required for performance under the contract, the Contracting Officer shall make an equitable adjustment and modify the contract in writing.

Under such equitable adjustment, no per diem rate for field office overhead shall be allowed in such a case, payment of field office overhead shall be allowed for any change using only a percentage markup basis regardless of whether the completion of the contract is or is not extended by reason of the change, except for modifications issued pursuant to the Default Clause. The Contractor shall provide a detailed breakdown of its proposed increase or decrease of costs as required by Contract Clause DFARS 252.236-7000

MODIFICATION OF PROPOSALS - PRICE BREAKDOWN.

1.31 Government Furnished Materials

Pursuant to Contract Clause FAR 52.245-1 Government Property, the Government will furnish the following materials and equipment for installation by the Contractor:

DESCRIPTION QUANTITY

Red Diamond Signs- installation in front of berms 12 U-Channel Post (Yellow) – installation in front of berms 12

Quantities indicated for the above-listed items marked with an asterisk are estimates. It is the intention of the Government to furnish all quantities of the asterisk items required to complete the work as specified, and the various quantities will be adjusted when necessary. Quantities stated for the above items not marked with an asterisk are all that will be furnished by the Government.

Material pickup arrangements made with COR and Contractor will pick up at Maintenance Compound near administrative office.

2 MATERIAL

2.1 Aggregate

Quantities of aggregate has been pre-determined and stated in Section 3 is quantity amount for each location.

2.1.1 32 Tons of 2” Base material shall meet MoDOT SECTION 1007 AGGREGATE FOR BASE. Type 1 or

Type 5 Aggregate can be used. Refer to MoDOT Section 1007 for details.

2.1.2 16 Tons of 3/4” (culvert crossing)- Base material shall meet MoDOT SECTION 1007 AGGREGATE FOR BASE. Type 1 or Type 5 Aggregate can be used. Refer to MoDOT Section 1007 for details.

2.1.3 1,380 Tons of 1” Aggregate for Surfacing (Road Rock), material shall be Grade “B” and meet MoDOT Section 1006.3

2.2 Corrugated Polyethylene Drainage Pipe

2.2.1 HDPE (High Density Polyethylene) Pipe, Type S - double wall with a corrugated exterior and a smooth interior wall.

2.2.1.1 Reference Specifications for Culvert Pipe

This specification references the latest edition and revisions of the following standard specifications:

• AASHTO M294 – Standard Specification for Corrugated Polyethylene Pipe, 300- to 1500-mm (12- to 60-in.) Diameter

• AASHTO M 252 – Standard Specification for Corrugated Polyethylene Drainage Pipe

• ASTM F2306 – Standard Specification for 12 to 60-in. (300 to 1500 mm) Annular Corrugated Profile-Wall Polyethylene (PE) Pipe and Fittings for Gravity-Flow Storm Sewer and Subsurface Drainage Applications

• ASTM D3350 – Standard Specification for Polyethylene Plastics Pipe and Fittings Materials

• ASTM D477 – Standard Specification for Elastomeric Seals (Gaskets) for Joining Plastic Pipe

• ASTM D2321 – Standard Practice for Underground Installation of Thermoplastic Pipe for Sewers and Other Gravity-Flow Applications

2.3 Quantities

2.3.1 Refer to Description of Work by Location and Quantities for each location in Execution Section for size and quantity details for each area.

3 EXECUTION

3.1 Grade Roads and Parking Lots

Grade roads in a manner that eliminates erosion trenches and washouts. When grading roads, a crown in the center of the roadway and sloping away on either side of the centerline is required. The slopes on either side of the centerline shall have a minimum slope of 2% and a maximum slope of 6%. The road shall be uniform throughout the entire road section to be repaired. The road shall be constructed to drain surface water to the side ditches and all ditches shall be kept open by the contractor.

Perform grading on parking lots to remove any erosion trenches or wash outs. All grading shall be sloped according to surrounding topography to provide for positive drainage of no more than 2% prior to applying aggregate.

The Contractor shall ensure final grade allows for proper drainage; ditches and shoulder are shaped; erosion control methods are installed to handle stormwater runoff; all debris is removed such as large rocks or vegetative debris.

3.2 Aggregate Roadway and Parking Lot Surfaces

The contractor shall haul and spread aggregate on roads, parking lots, access trails to ag fields, the quantity and size of rock as specified for each area in the drawings. Aggregate for roadways shall be spread the width of the delivery truck, at a minimum of 8 foot wide and a maximum of 10’ wide. Quantity of material as specified for each site location shall be spread evenly the entire length of roadway (site specific). The Contractor shall adjust thickness depth (up to 2” thick) to accommodate spreading of material the full length of roadway. Aggregate for parking lots shall spread the quantity of material as specified for each site location evenly. The Contractor shall adjust thickness depth to accommodate spreading of material evenly over the entire parking area.

Sub-base for parking lots shall be spread evenly over designated area and compacted. Compaction can be obtained by passing a minimum 8,000-pound machine over area until no more than ½” deflection of soil is obtained or other method that obtains the same result.

Submit copies of waybills or delivery tickets during progress of the work so quantities can be verified for each site area as specified.

3.3 Berm Installation

Berms shall be a minimum of 12’ deep (base width) x 18’ (estimate) roadway width x 6’ height in front of berm forming a peak 1’ wide. Berm shape is trapezoidal, and shape must be consistent through its length. Berm shall be built of material that is identified or approved by the COR from on-site or excess roadway overburden. The fill material may be obtained from behind the berm and not in front of berm (vehicle approach side). Fill material may be collected from the existing roadbed or at a location near the berm agreed upon by the Contracting Officer Representative if necessary or excess spoils from grading operation may be used. Soil compaction by machine rolling or tamping in place in lifts no more than one foot. Compaction can be obtained by passing a minimum 8,000-pound machine over lifts until no more than ½” deflection of soil is obtained or other method that obtains the same result. Note: roadway width may vary on existing roads, however contractor is to build berm from ditch to ditch with variances in widths.

Grass seed with a construction mix of 75% tall fescue and 25% rye grass. Rake in seed in sub-surface and apply a minimum of 6 pounds of seed mixture per berm.

All berms shall have 3 individual red diamond signs placed 5 feet in front of berm on u-channel metal post.

3.4 Sign Installation

Mount 3 individual red diamond signs with post at each berm site. Install at 42” height above ground level on a single u-channel post with bolts. Mounting height is measured from the ground level to the bottom edge (point of sign) of the sign panel. Sign placement must be within the approaching driver’s immediate cone-of-vision.

Placement must be carefully considered to ensure that each sign fits its location and achieves optimum visibility.

Uniformly space the signs across the width of roadway with the middle sign place in center of roadway.

Installation of u-channel post – these are standard signpost and can be driven in ground by a post driver or other suitable method such as boring a hole and concreting in place, so stability is obtained. Embedment depth of u-channel post is a minimum of 2’ 6” however these dimensions could vary based on encounters with underground obstruction such as solid rock. Variance of embedment depth could be allowed with COR approval related to unforeseen circumstances.

3.5 Corrugated Polyethylene Drainage Pipe (Culvert) Replacement

Culvert work will consist of removal and the new installation of a corrugated polyethylene pipe. Installation shall follow manufactures recommendation and submittal of installation procedures submitted prior to placement for approval including fill material.

Upon completion of the installation the road shall be reestablished to pre-construction grade and overlayed with 2” thick of 1” type “B” aggregated surfacing material.

3.6 Tree Limb Removal

Remove encroaching limbs or sprouts on designated roads by cutting or mulcher head machine. Examples include encroaching limbs adjacent to roads, access trails, field edges, and public use area. The contractor shall remove all encroaching tree limbs 5” in diameter or less, from the ground to 16’ above ground. Contractor shall remove limbs within 12’ from centerline of the road. The limb debris may be mulched and spread on shoulder closest to the timber or nearby designated area. A designated area will be provided within one mile by the government at each site area after award. Contractor has the option to remove woody debris off site and dispose of at no additional cost to the government. In no case shall debris be left in roadway or ditches.

3.7 Description of Work by Location and Quantities

The government will mark or flag location of starting and stopping points for gravel placement or installation of berm after post award with contractor.

3.7.1 Shawnee Bend (SB) Trail Access (Benton County, MO)

• Deliver and spread 1” crushed limestone with fines.

• SB #1, 610’ – 47 tons

• SB #2, 937’ – 73 tons

• SB #3, parking lot 20’ by 48’- spread 32 tons of 2” type 1 or type 5 base rock and 16 tons of 1” crushed limestone with fines.

3.7.2 Tadges (Benton County, MO)

• Deliver & spread 1” crushed limestone with fines in public parking lot.

• Dimension of parking lot 79’ by 70’

• 32 tons of rock spread evenly over parking lot.

3.7.3 Hermitage Road (Benton County, MO)

• Grade road from boundary line to berm. 530’ length of road.

• Build berm

• Install 3 diamond signs in front of berm on U-channel post.

3.7.4 Avery Marsh Access (Benton County, MO)

• Replace 18’ length x 20” diameter culvert pipe

3.7.5 Spring Branch (Benton County, MO)

• Deliver and spread 1” crushed limestone with fines from boundary line to public parking lot.

• Distance 880’ Length of road – 68 tons

• Tree limb removal from boundary line to berm. 880’

• Install berm and 3 red diamond signs & U-channel post.

3.7.6 Hickory County 239 (Benton County, MO)

• Deliver & spread 1” crushed limestone with fines.

• Distance 1190’ Length of Road – 92 tons

• SE 1201 - Berry Bend equestrian trail, (Henry County, MO)

3.7.7 SE 1201 - Berry Bend equestrian trail, (Henry County, MO)

• Grade road from boundary line to designated location. 1,253’

• Deliver and spread 1” crushed limestone with fines from boundary line to designated location.

• Distance 1,253’ Length of Road – 97 tons

3.7.8 SE 671 – Ag lease NW of U highway (Henry County, MO)

• Grade road from boundary line to lake. 4,274’

• Tree limb removal from boundary line to lake. 4,274’

3.7.9 SE 301 – Ag Lease SE of AA Marsh (Henry County, MO)

• Deliver and spread 1” crushed limestone with fines

• Distance 2,664’ Length of Road – 206 tons

3.7.10 SE 971 - French Bridge (Henry County, MO)

3.7.11 SE 20 – SW of WX, (Henry County, MO)

• Grade road from public parking lot to lake. 875’

• Tree limb removal from public parking lot to lake. 875’

• Deliver and spread 1” crushed limestone with fines.

• Distance 875’ Length of Road – 68 tons

3.7.12 Fishermen’s Loop – Sparrowfoot Campground, (Henry County, MO)

• Deliver & spread 1” crushed limestone with fines.

• Distance 1,629’ Length of Road – 126 tons

3.7.13 Sac River Parking Lot (St. Clair County, MO)

• Deliver and spread 1” crushed limestone with fines in parking lot.

• Aggregate 64 tons

3.7.14 Horseshoe Bend – End of CC Highway (St. Clair County, MO)

• Distance 2,192’ Length of Road – 170 tons

3.7.15 Windsor Crossing Ag Lease Access (Henry County, MO)

• Distance 4,140’ Length of Road – 320 tons

END of Section