This solicitation seeks a contractor to provide bridge painting and concrete repair services at three dam locations in Pennsylvania. The selected contractor will remove existing coating systems including lead-based paints from bridges at Indian Rock Dam and Foster J. Sayers Dam, and power wash surfaces at Curwensville Dam. The contractor will then apply new coating systems and repair concrete at specified locations. Bids are due by the listed solicitation number and response date. The contractor must be certified under SSPC QP-1 and QP-2, and follow all safety and environmental requirements including containment, air and soil monitoring, and waste disposal plans. Work shall be completed within 180 days of notice to proceed.
View the file
Other files
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Bridge Lead Paint Removal and Concrete Repair BRIDPAINTCONCREP
PROJECT TABLE OF CONTENTS
DIVISION 01 - GENERAL REQUIREMENTS
01 11 00 SUMMARY OF WORK
01 14 00 WORK RESTRICTIONS
01 30 00 ADMINISTRATIVE REQUIREMENTS
01 33 00 SUBMITTAL PROCEDURES
01 42 00 SOURCES FOR REFERENCE PUBLICATIONS
-- End of Project Table of Contents --
PROJECT TABLE OF CONTENTS Page 1
01 35 26 GOVERNMENTAL SAFETY REQUIREMENTS
01 4 5 00.00 10 QUALITY CONTROL
01 50 00 TEMPORARY CONSTRUCTION FACILITIES CONTROL
01 57 19 TEMPORARY ENVIRONMENTAL CONTROLS
01 74 19 CONSTRUCTION WASTE MANAGEMENT AND DISPOSAL
01 78 00 CLOSEOUT SUBMITTALS
SECTION 01 11 00
SUMMARY OF WORK
08/15
PART 1 GENERAL
1.1 Scope of Work
Statement of Work: The contractor shall provide all labor, supervision, materials, equipment, and supplies required for the following work as described below.
Location 1 - Indian Rock Dam: Surface preparation and application of a new coating system to the Indian Rock Dam Spillway Bridge. Surface preparation includes removal of the existing coating system including lead-based paints.
Debris generated during paint removal operations shall be contained in accordance with the “Containment Method 2” in Section 3.4.2. All metallic surfaces shall be painted in accordance with “Painting Method 1” in Section
4.6.7.9. See Exhibit 1.
Location 2 - Foster J Sayers Dam: Surface preparation and application of a new coating system to the Foster J Sayers Dam Service Bridge. Surface preparation includes removal of the existing coating system including lead-based paints. Debris generated during paint removal operations shall be contained in accordance with the “Containment Method 2” in Section 3.4.2.
All metallic surfaces shall be painted in accordance with “Painting Method 1” in Section 4.6.7.9. In addition, the large concrete spall area in the north face of the gate structure shall be repaired according to Section
4.6.10. See Exhibit 2, Photograph No. 4.
Concrete repairs of large spall area in the gate structure (Tower) concrete, below corbel. Work includes identifying extent of delaminated and unsound concrete, removing concrete, and preparing surface and reinforcing rebar.
Patching material shall be a two component, polymer-modified, cementitious non sag, shrinkage compensated trowel grade mortar with corrosion inhibitor that has a coefficient of thermal expansion compatible with concrete and a minimum 28-day compressive strength of 5000 psi. Repair material shall be mixed, extended, applied, and cured per manufacturer’s recommendations. See Exhibit 4 for details on Foster J. Sayers concrete repairs.
Location 3 - Curwensville Dam: Surface preparation and application of a new coating system to the Curwensville Dam Service Bridge. Surface preparation includes power washing of the existing coating system. Debris generated during paint removal operations shall be contained in accordance with the “Containment Method 3” in Section 3.4.2. All surfaces in which at least one coat of the existing coating remains shall be painted using “Painting Method 2” in Section 4.6.7.10. Exposed metallic surfaces shall be painted using “Painting Method 1” in Section 4.6.7.9. See Exhibit 3.
1.2. Work Locations and Points of Contact: Location 1: Indian Rock Dam, York, Pennsylvania. (39.922456, -76.753303). Head Dam Operator Steve Young,
(717) 792-0312 Location 2: Foster Sayers Dam, Howard, Pennsylvania.
(41.048578, -77.609936). Head Dam Operator Craig Eisenhower, (570) 962-2500 Location 3: Curwensville Dam, Curwensville, Curwensville Pennsylvania.
SECTION 01 11 00 Page 1
(40.954480, -78.528119). Head Dam Operator Tim Smay, (814) 236-2000
2. SPECIAL CONDITIONS
2.1. Commencement of Work: Work shall commence no later than 60 days after award and be completed within 180 days of notice to proceed. The start date will be coordinated with the COR.
2.2. Performance of Work: The Contractor shall perform work only during normal Corps of Engineers duty hours (7:00 a.m. to 4:00 p.m., Monday through Friday, excluding national holidays). Exceptions to this condition must be coordinated with and approved in advance by the Operations Manager of Susquehanna River Project, Brian Luprek 570-649-6855.
2.3. Accident Prevention: In performing this contract the Contractor shall comply with all current Federal, State, and Local safety regulations, including Corps of Engineers Safety and Health Requirement Manual EM 385-1-1 and shall comply with any subsequent changes. Information regarding acquiring the Corps of Engineers Safety and Health Requirement Manual EM 385-1-1 may be found on the USACE Headquarters website at http://www.usace.army.mil/SafetyandOccupationalHealth/EM38511,2008BeingRevised.aspx.
Prior to commencement of work under this contract the Contractor shall furnish to the Government an Accident Prevention Plan in accordance with Section I, Article 01.A.12 of the EM 385-1-1, dated 30 November 2014.
2.4. In the event of an accident or injury involving contractor personnel or equipment in performance of work, the Contractor shall immediately notify the Government representative by the most expedient means feasible. The Contractor shall complete forms furnished and/or provide a written description of the incident within 24 hours of notification to do so.
2.5. Operations and Storage Areas: The Contractor shall confine all operations (including storage of materials) to areas authorized or approved by the Head Dam Operator. The Contractor shall hold and save the Government, its officers, and agents free and harmless from liability of any nature occasioned by the Contractor’s performance.
2.6. Housekeeping: The Contractor shall keep the work area, including storage areas, free from accumulations of waste materials. Before completing the work, the Contractor shall remove from the work site and premises, any rubbish, tools, equipment, and materials that are not property of the Government. Upon completing the work, the Contractor shall restore the work area to the original condition, satisfactory to the Contracting Officer’s Representative (COR).
2.7. Environmental Protection: The Contractor is required to comply with all Federal, State, and Local environmental regulations.
2.8. Permits and Licenses: The Contractor shall, at his/her own expense, obtain any license or permits required to perform the contract. The Contractor shall comply with all Federal, State and Local laws and regulations and shall comply with any subsequent changes.
2.9. Records and Reports: In addition to the administrative requirements dictated elsewhere in this contract, the Contractor shall complete a Daily Construction Quality Control Report form to maintain record of contract performance, accident/injury incidence, and observance of project deficiencies. Forms will be distributed at pre-work conference. All required submittals shall be submitted to the COR.
SECTION 01 11 00 Page 2
VIA Post Mail: U.S. Army Corps of Engineers Susquehanna River Project ATTN: Brian Luprek 5960 Susquehanna Trail Suite 1 Turbotville, PA 17772
VIA Electronic Mail: Brian.K.Luprek@usace.army.mil
2.10. Superintendent: The Contractor shall act as, or provide a Superintendent who is responsible for quality control whenever the work specified herein is being performed. The Superintendent shall conduct overall management coordination and be the central point of contact with the Government for performance of all work under this contract. The Superintendent and any individual designated to act for him/her shall have full authority to contractually commit the Contractor for prompt action on matters pertaining to the administration of the entire contract. Such authorization shall be submitted in writing to the Government representative. The Superintendent shall deal directly with the designated, for normal day-to-day administration of the contract provisions.
Superintendent’s (s) will be required to attend pre-work conference prior to commencing work under this contract.
2.11. Project Operation: Curwensville Lake, Foster J. Sayers Dam, and Indian Rock Dam are flood control projects and the Contractor’s access to the work area and the execution of the requirements specified herein shall not interfere with the daily operations of the projects or employees. It is the responsibility of the Contractor to coordinate all work with the site POCs. Access to intake towers at the Curwensville and Foster J. Sayers Dams shall be maintained throughout the performance of the contract. Vehicular traffic shall be maintained across the Indian Rock Dam Spillway bridge. Disruptions or impediments to traffic during construction will require a traffic control plan in accordance with the Pennsylvania MUTCD to be submitted for approval. Reference drawing of the bridges are attached.
3. SAFETY, HEALTH, AND ENVIRONMENTAL REQUIREMENTS
3.1. Perform work in accordance with all applicable health, safety, and environmental requirements as well as EM 385-1-1. Submit matters of Interpretation of Safety, Health, and Environmental Requirements to the COR for resolution before starting work. Where the regulations conflict, the most stringent requirements shall apply. This paragraph supplements the health, safety, and environmental requirements of EM 385-1-1.
3.2. Safety: Submit an Accident Prevention Plan. Comply with all applicable safety standards.
3.2.1. Abrasive Blasting: For abrasive blasting comply with the requirements in Section 06.I of EM 385-1-1. In addition to the requirements in Section 20 of EM 385-1-1, use hoses and hose connections of a type to prevent shock from static electricity. Hose lengths shall be joined by approved couplings of a material and type designed to prevent erosion and weakening of the couplings. The couplings and nozzle attachments shall fit on the outside of the hose and designed to prevent accidental disengagement.
3.2.2. Workers Other Than Blasters: Protect workers, other than blasting operators working in close proximity of abrasive blasting operations, by
SECTION 01 11 00 Page 3 utilizing MSHA/NIOSH-approved half-face or full-face air purifying respirators equipped with high-efficiency particulate air (HEPA) filters, eye protection meeting or exceeding ASSE/SAFE Z87.1 and hearing protectors (ear plugs and/or ear muffs) providing a noise reduction rating of at least 20 dBA or as needed to provide adequate protection. Personal protective equipment shall be provided where required by 29 CFR 1910.146 and in accordance with 29 CFR 1910, Subpart I.
3.2.3. Cleaning Before and After Abrasive Blasting: Cleaning with compressed air shall be in accordance with Section 20.B.5 of EM 385-1-1 and personnel shall be protected as specified in 29 CFR 1910.134. When cleaning with solvents, provide ventilation where required by 29 CFR 1910.146 or where the concentration of solvent vapors exceeds 10 percent of the Lower Explosive Limit (LEL). Ventilation shall be in accordance with 29 CFR 1910.94, paragraph (c)(5).
3.2.4. Paint Mixing: Local exhaust ventilation shall be provided in the area where coatings are mixed. This ventilation system shall be capable of providing at least 100 linear fpm of capture velocity in the mixing zone.
Exposure of skin and eyes shall be avoided by wearing appropriate chemically resistant gloves, apron, safety goggles, and face shields meeting or exceeding the requirements of ASSE/SAFE Z87.1. A combination unit, comprised of an eyewash and deluge shower, within close proximity to the mixing operation shall be provided in accordance with ISEA Z358.1, paragraph (9).
Individuals who have a history of, or develop a sensitivity to epoxy or polyurethane resin systems, shall not conduct work tasks or otherwise be exposed to such chemicals.
3.2.5. Paint Spraying: Submit a Respiratory Protection Plan. During all spray painting operations, spray painters shall use approved SCBA or SAR (air line) respirators, unless valid air sampling has demonstrated contaminant levels to be consistently within concentrations that are compatible with air-purifying respirator Assigned Protection Factor (APF).
Persons with facial hair that interferes with the sealing surface of the facepiece to face seal or interferes with respirator valve function shall not be allowed to perform work requiring respiratory protection.
Air-purifying chemical cartridge/canister half- or full-facepiece respirators that have a particulate prefilter and are suitable for the specific type(s) of gas/vapor and particulate contaminant(s) may be used for nonconfined space painting, mixing, and cleaning (using solvents). These respirators may be used provided the measured or anticipated concentration of the contaminant(s) in the breathing zone of the exposed worker does not exceed the APF for the respirator and the gas/vapor has good warning properties or the respirator assembly is equipped with a NIOSH-approved end of service life indicator for the gas(es)/vapor anticipated or encountered.
Where paint contains toxic elements that may become airborne during painting in nonconfined spaces, air-purifying half- and full-facepiece respirators or powered air-purifying respirators equipped with appropriate gas vapor cartridges, in combination with a high-efficiency filter, or an appropriate canister incorporating a high-efficiency filter, shall be used.
3.2.6. Explosion Proof Equipment: Electrical wiring, lights, and other equipment located in the paint spraying area shall be of the explosion proof type designed for operation in Class I, Division 1, Group D, hazardous locations as required by the NFPA 70. Electrical wiring, motors, and other equipment, outside of but within 20 feet of any spraying area, shall not spark and shall conform to the provisions for Class I, Division 2, Group D, hazardous locations. Electric motors used to drive exhaust fans shall not be placed inside spraying areas or ducts. Fan blades and portable air ducts
SECTION 01 11 00 Page 4 shall be constructed of nonferrous materials. Motors and associated control equipment shall be properly maintained and grounded. The metallic parts of air-moving devices, spray guns, connecting tubing, and duct work shall be electrically bonded and the bonded assembly shall be grounded.
3.2.7. Further Precautions:
a. Workers shall wear nonsparking safety shoes.
b. Place and ground solvent drums, taken into the spraying area, on nonferrous surfaces. Maintain metallic bonding between containers and drums when materials are being transferred.
c. Inspect insulation on all power and lighting cables to ensure that the insulation is in excellent working condition and is free of all cracks and worn spots. Cables shall be further inspected to ensure that no connections are within 50 feet of the operation, that lines are not overloaded, and that they are suspended with sufficient slack to prevent undue stress or chafing.
3.2.8. Ignition Sources: Ignition sources, to include lighted cigarettes, cigars, pipes, matches, or cigarette lighters shall be prohibited in area of solvent cleaning, paint storage, paint mixing, or paint application.
3.2.9. Site Safety and Health Officer: Provide a site Safety and Health Officer (SSHO) at the work site at all times to perform safety and occupational health management, surveillance, inspections, and safety enforcement for the Contractor. The Contractor Quality Control (QC) person may be the SSHO on this project. The SSHO must have completed the 30-hour OSHA Construction Safety class or have completed an equivalent course accompanied by 5 years of construction industry safety experience or 3 years if he possesses a Certified Safety Professional (CSP) degree. An average of at least 24 hours of formal safety training every 4 years is required. For this project the SSHO must maintain competent person status for at least the following areas of competency: Lead in accordance with 29 CFR 1926.62;
Scaffolding; Fall protection; Personal protective equipment and clothing to include selection, use and maintenance.
3.2.10. Site Safety and Health Officer (SSHO) Duties:
3.2.10.1. Conduct daily safety and health inspections and maintain a written log which includes area/operation inspected, date of inspection, identified hazards, recommended corrective actions, estimated and actual dates of corrections. Attach safety inspection logs to the Contractors' daily quality control report.
3.2.10.2. Conduct mishap investigations and complete required reports.
Maintain the OSHA Form 300 and Daily Production reports for prime and sub-contractors.
3.2.10.3. Maintain applicable safety reference material on the job site.
3.2.10.4. Attend the pre-construction conference, pre-work meetings including preparatory inspection meeting, initial phase meeting and periodic in-progress meetings.
3.2.10.5. Implement and enforce accepted Accident Prevention Plans (APP) and Activity Hazard Analyses (AHA).
3.2.10.6. Maintain a safety and health deficiency tracking system that
SECTION 01 11 00 Page 5 monitors outstanding deficiencies until resolution. Post a list of unresolved safety and health deficiencies on the safety bulletin board.
3.2.10.7. Ensure sub-contractor compliance with safety and health requirements. Failure to perform the above duties will result in dismissal of the superintendent and/or SSHO, and a project work stoppage. The project work stoppage will remain in effect pending approval of a suitable replacement.
3.2.11. Training Certification: Submit a certificate for each employee and supervisor, signed and dated by the training provider, stating that the employee or supervisor has received the required lead training and is certified to perform or supervise lead removal.
3.2.12. Preconstruction Safety Conference:
3.2.12.1. Contractor representatives who have a responsibility or significant role in accident prevention on the project shall attend the preconstruction conference. This includes the project superintendent, site safety and health officer, quality control supervisor, or any other assigned safety and health professionals who participated in the development of the APP (including the Activity Hazard Analyses (AHAs) and special plans, program and procedures associated with it).
3.2.12.2. Discuss the details of the submitted APP to include incorporated plans, programs, procedures and a listing of anticipated AHAs that will be developed and implemented during the performance of the contract. This list of proposed AHAs will be reviewed at the conference and an agreement will be reached between the Contractor and the Contracting Officer's representative as to which phases will require an analysis. In addition, establish a schedule for the preparation, submittal, review, and acceptance of AHAs to preclude project delays.
3.2.12.3. Deficiencies in the submitted APP will be brought to the attention of the Contractor at the preconstruction conference, and the Contractor shall revise the plan to correct deficiencies and re-submit it for acceptance. Do not begin work until there is an accepted APP.
3.2.13. Accident Prevention Plan: Use a qualified person to prepare the written site-specific APP. Prepare the APP in accordance with the format and requirements of USACE EM 385-1-1 and as supplemented herein. Cover all paragraph and subparagraph elements in USACE EM 385-1-1, Appendix A, "Minimum Basic Outline for Accident Prevention Plan". Specific requirements for some of the APP elements are described below. The APP shall be job-specific and address any unusual or unique aspects of the project or activity for which it is written. The APP shall interface with the Contractor's overall safety and health program. Include any portions of the Contractor's overall safety and health program referenced in the APP in the applicable APP element and made site-specific. The Government considers the Prime Contractor to be the "controlling authority" for all work site safety and health of the subcontractors. The APP shall be signed by the person and firm (senior person) preparing the APP, the Contractor, the on-site superintendent, the designated site safety and health officer and any designated CSP. Submit the APP to the Contracting Officer 15 calendar days prior to the date of the preconstruction conference for acceptance. Work cannot proceed without an accepted APP. Once accepted by the Contracting Officer, the APP and attachments will be enforced as part of the contract.
Disregarding the provisions of this contract or the accepted APP will be
SECTION 01 11 00 Page 6 cause for stopping of work, at the discretion of the Contracting Officer, until the matter has been rectified. Once work begins, changes to the accepted APP shall be made with the knowledge and concurrence of the Contracting Officer, project superintendent, SSHO and quality control manager. Should any hazard become evident, stop work in the area, secure the area, and develop a plan to remove the hazard. Notify the Contracting Officer within 24 hours of discovery. Eliminate/remove the hazard. In the interim, take all necessary action to restore and maintain safe working conditions in order to safeguard onsite personnel, visitors, the public (as defined by ASSE/SAFE A10.34,) and the environment. Continuously reviewed and amended the APP, as necessary, throughout the life of the contract.
Incorporate unusual or high-hazard activities not identified in the original APP as they are discovered.
3.2.14. Activity Hazard Analysis (AHA): The Activity Hazard Analysis (AHA) format shall be in accordance with USACE EM 385-1-1. Submit the AHA for review at least 15 calendar days prior to the start of each phase. Format subsequent AHAs as amendments to the APP. The analysis should be used during daily inspections to ensure the implementation and effectiveness of the activity's safety and health controls. The AHA list will be reviewed periodically (at least monthly) at the Contractor supervisory safety meeting and updated as necessary when procedures, scheduling, or hazards change.
Develop the activity hazard analyses using the project schedule as the basis for the activities performed. Any activities listed on the project schedule will require an AHA. The AHAs will be developed by the contractor, supplier or subcontractor and provided to the prime contractor for submittal to the Contracting Officer.
3.2.15. OSHA Inspections: The Contractor shall immediately notify the Contracting Officer when an OSHA Compliance Official (Federal or State representative) presents credentials and informs the Contractor that the workplace will be inspected for OSHA compliance. The Contractor shall also notify the Contracting Officer upon determination that an exit interview will take place upon completion of the OSHA inspection.
3.2.16. Emergency Medical Treatment: Contractors will arrange for their own emergency medical treatment. Government has no responsibility to provide emergency medical treatment.
3.2.17. Fall Protection Equipment and Systems: Enforce use of the fall protection equipment and systems designated for each specific work activity in the AHA at all times when an employee is exposed to a fall hazard.
Protect employees from fall hazards as specified in EM 385-1-1, section 21.
Personal fall arrest systems are required when working from an articulating or extendible boom, swing stages, or suspended platform. In addition, personal fall arrest systems are required when operating other equipment such as scissor lifts if the work platform is capable of being positioned outside the wheelbase. The need for tying-off in such equipment is to prevent ejection of the employee from the equipment during raising, lowering, or travel. Fall protection must comply with 29 CFR 1926.500, Subpart M, USACE EM 385-1-1 and ASSE/SAFE A10.32.
3.2.17.1. Personal Fall Arrest Equipment: Personal fall arrest equipment, systems, subsystems, and components shall meet ASSE/SAFE Z359.1. Only a full-body harness with a shock-absorbing lanyard or self-retracting lanyard is acceptable personal fall arrest body support device. Body belts may only be used as a positioning device system (for uses such as steel reinforcing assembly and in addition to approved fall arrest system). Harnesses shall have a fall arrest attachment affixed to the body support (usually a Dorsal
SECTION 01 11 00 Page 7
D-ring) and specifically designated for attachment to the rest of the system. Only locking snap hooks and carabiners shall be used. Webbing, straps, and ropes shall be made of synthetic fiber. The maximum free fall distance when using fall arrest equipment shall not exceed 6 feet. The total fall distance and any swinging of the worker (pendulum-like motion) that can occur during a fall shall always be taken into consideration when attaching a person to a fall arrest system.
3.2.18. Working over Water: In addition to the required fall protection systems, safety skiff, personal floatation devices, life rings etc., are required when working above or next to water in accordance with USACE EM 385-1-1, paragraphs 05.H. and 05.I. The area beneath the bridges are not normally inundated but may become inundated during high water events. The requirements of this section shall be enforced when required by the
EM385-1-1.
3.2.19. Horizontal Lifelines: Design, install, certify and use under the supervision of a qualified person horizontal lifelines for fall protection as part of a complete fall arrest system which maintains a safety factor of
2 (29 CFR 1926.500).
3.2.20. Guardrails and Safety Nets: Design, install and use guardrails and safety nets in accordance with EM 385-1-1 and 29 CFR 1926 Subpart M.
3.2.21. Rescue and Evacuation Procedures: When personal fall arrest systems are used, the contractor must ensure that the mishap victim can self-rescue or can be rescued promptly should a fall occur. Prepare a Rescue and Evacuation Plan as part of the AHA and include a detailed discussion of the following: methods of rescue; methods of self-rescue; equipment used;
training requirement; specialized training for the rescuers; procedures for requesting rescue and medical assistance; and transportation routes to a medical facility. Include the Rescue and Evacuation Plan within the Activity Hazard Analysis (AHA) for the phase of work and the Accident Prevention Plan
(APP).
3.2.22. Scaffolding:
3.2.22.1. Stilts: The use of stilts for gaining additional height in construction, renovation, repair or maintenance work is prohibited.
3.2.22.2. Work Access Platform: The Contractor shall provide and erect approved solid floor debris shield and work access platform system such as Safespan Multi-Span, Swing-Lo Suspended Scaffolding, or approved equal required for access and construction for this contract. Debris shields shall be provided to protect all locations where overhead work poses a hazard to the traveling public or project personnel and is not necessarily limited to the area under work platforms. During all operations of this contract, the Contractor shall not be permitted to drop material or debris from the bridge. Protective shields shall be used to catch falling material and shield the area below the work. If the Government determines that adequate protective shields are not being provided, the work shall be suspended until adequate protective shields are employed at no additional cost to the Government.
3.2.22.2.1. Platform Design: The design of the work access platform shall specifically address any necessary strengthening of existing bridge members required during platform construction or connection to the bridge. The design shall also specifically detail all connections to the bridge. The Contractor shall not modify, damage, or attach the work access platform system to any existing bridge member to construct or operate the platform
SECTION 01 11 00 Page 8 system without approval from the Government. Any modification to the bridge shall be detailed in the erection drawings and approved by a registered Professional Engineer. Such modifications shall be submitted for Government review and approval. Any damage to the existing structure and its appurtenances occurring during work access platform installation shall be repaired by the Contractor at no expense to the Government.
3.2.22.2.2. Platform Removal: The Contractor shall remove and properly dispose of all temporary apparatuses and work access platform systems used throughout the project, as soon as they serve their intended purpose. The Contractor shall bring any disturbed element surrounding the temporary apparatus and/or support systems to its original condition, subject to the Government's approval.
3.2.23. Portable Extension Cords: Size portable extension cords in accordance with manufacturer ratings for the tool to be powered and protected from damage. Immediately removed from service all damaged extension cords. Portable extension cords shall meet the requirements of
NFPA 70.
3.3. Health: Prepare and submit a Medical Surveillance Plan.
3.3.1. Air Monitoring: Prepare and submit an Air Monitoring Test Plan.
Perform air sampling and testing as needed to assure that workers are not exposed to contaminants above the permissible exposure limit. In addition, provide the COR with a copy of the Air Monitoring Test Report from the laboratory within five working days of the sampling date, and provide results from direct-reading instrumentation on the same day the samples are collected. Prepare and submit an Airborne Sampling Plan as specified in the Submittals paragraph.
3.3.2. Medical Status: Prior to the start of work, and annually thereafter, prepare a Medical Status Report. Medically evaluate all Contractor employees working with or around paint systems, thinners, blast media, those required to wear respiratory protective equipment, and those who will be exposed to high noise levels for the particular type of exposure they may encounter.
Maintain medical records as required by 29 CFR 1910.20. The evaluation shall include:
a. Audiometric testing and evaluation of employees who will work in a noise environment with a time weighted average greater than or equal to 90 dBA.
b. Vision screening (employees who use full-facepiece respirators shall not wear contact lenses).
c. Medical evaluation shall include, but shall not be limited to, the following:
(1) Medical history including, but not limited to, alcohol use, with emphasis on liver, kidney, and pulmonary systems, and sensitivity to chemicals to be used on the job.
(2) General physical examination with emphasis on liver, kidney, and pulmonary system.
(3) Determination of the employee's physical and psychological ability to wear respiratory protective equipment and to perform job-related tasks.
SECTION 01 11 00 Page 9
(4) Determination of baseline values of biological indices for later comparison to changes associated with exposure to paint systems and thinners or blast media, which include: liver function tests to include SGOT, SGPT, GGPT, alkaline phosphates, bilirubin, complete urinalysis, EKG (employees over age 40), blood urea nitrogen (bun), serum creatinine, pulmonary function test, FVC, and FEV, chest x-ray (if medically indicated), blood lead and ZPP (for individuals where it is known there will be an exposure to materials containing lead), other criteria that may be deemed necessary by the Contractor's physician, and Physician's statements for individual employees that medical status would permit specific task performance. (5) For lead-based paint removal, the medical requirements of 29 CFR 1926.62 shall also be included. Prepare and submit a Lead-Based Paint Worker Protection Plan.
3.3.3. Change in Medical Status: Any employee whose medical status has changed negatively due to work related chemical and/or physical agent exposure while working with or around paint systems and thinners, blast media, or other chemicals shall be evaluated by a physician, and obtain a physicians statement as described in paragraph MEDICAL STATUS prior to allowing the employee to return to those work tasks. Provide the COR a Change in Medical Status Report detailing any negative changes in employee medical status and the results of the physicians reevaluation statement.
3.4. Environmental Protection: Prepare an Environmental Protection Plan and comply with the following environmental protection criteria.
3.4.1. Waste Classification, Handling, and Disposal: Prepare and submit a Waste Classification, Handling, and Disposal Plan. The Contractor is responsible for assuring the disposal of all hazardous and nonhazardous waste generated during the project in accordance with all applicable Federal, state and local requirements. Waste generated from abrasive blasting lead-containing paints with recyclable steel or iron abrasives shall be disposed of as a hazardous waste or shall be stabilized with proprietary pre-blast additives regardless of the results of 40 CFR 261 App II, Mtd 1311. Where stabilization is preferred, employ a proprietary blast additive that has been blended with the blast media prior to use. Place hazardous waste in properly labeled, closed containers shielded adequately to prevent dispersion of the waste by wind or water. Any evidence of improper storage shall be cause for immediate shutdown of the project until corrective action is taken. Store nonhazardous waste in closed containers separate from hazardous waste storage areas. All hazardous waste shall be transported by a licensed transporter in accordance with 40 CFR 263 and 49 CFR 171, Subchapter C. All nonhazardous waste shall be transported in accordance with local regulations regarding waste transportation. In addition to the number of copies required by 40 CFR 262.22, one copy of each Waste Manifest will be supplied to the Contracting Officer prior to transportation.
3.4.1.1. Lead Waste Management: The Lead Waste Management Plan shall comply with applicable requirements of federal, State, and local hazardous waste regulations and address:
a. Identification and classification of hazardous wastes associated with the work.
b. Estimated quantities of wastes to be generated and disposed of.
c. Names and qualifications of each contractor that will be transporting, storing, treating, and disposing of the wastes. Include the facility
SECTION 01 11 00 Page 10 location and operator and a 24-hour point of contact. Furnish two copies of proof of EPA, State, and, local hazardous waste permits, manifests, and Transporter Number.
d. Names and qualifications (experience and training) of personnel who will be working on-site with hazardous wastes.
e. List of waste handling equipment to be used in performing the work, to include cleaning, volume reduction, and transport equipment.
f. Spill prevention, containment, and cleanup contingency measures including a health and safety plan to be implemented in accordance with 29 CFR 1926.65.
g. Work plan and schedule for waste containment, removal and disposal.
Wastes shall be cleaned up and containerized daily. Proper containment of the waste includes using acceptable waste containers (e.g., 55-gallon drums) as well as proper marking/labeling of the containers.
h. Unit cost for waste disposal according to this plan.
3.4.2. Containment: Prepare a Containment Plan. Contain debris generated during paint removal operations in accordance with the containment method specified in Section 1.1.
Containment Method 1: SSPC Guide 6, Class 2A
Containment Method 2: SSPC Guide 6, Class 1A
Containment Method 3: SSPC Guide 6, Class 4W
NOTE: Sections 3.4.3 through 3.4.6 only apply to Location 2 (Foster J Sayers Dam).
3.4.3. Visible Emissions Monitoring: Prepare a Visible Emissions Monitoring Plan for Location 2 only. Measure the time of emissions in accordance with 40 CFR 60, App A, Mtd 22. Monitor visible emissions for not less than 15 minutes of every hour. Calculate visible emissions for each hour by extrapolation. In no case shall visible emissions extend greater than 150 feet in any direction horizontal from the containment. In no case shall visible emissions be observed in the area of any sensitive receptor. If such emissions occur the job shall be shut down immediately and corrective action taken. Notify the foreman whenever visible emissions exceed 40 seconds in a 1 hour period for lead based paint removal operations and 200 seconds in a 1 hour period for nonhazardous paint removal operations. The foreman shall be notified and the job shall be shut down and corrective action taken whenever visible emissions for lead based paint removal operations exceed 75 seconds and for nonhazardous paint removal operations. The foreman shall be notified and the job shall be shut down and corrective action taken whenever visible emissions for lead based paint removal operations exceed 75 seconds in a 2 hour period or 300 seconds in a 2 hour period for nonhazardous paint removal operations. Total observed visible emissions from the containment shall not exceed 1 percent and 5 percent of the work day for lead based paint and nonhazardous paint removal operations respectively. Shutdown and corrective action shall be taken to prevent such an occurrence. Document each time that the work is halted due to a violation of the visible emissions criteria.
Documentation shall include the cause for shutdown and the corrective action taken to resolve the problem.
SECTION 01 11 00 Page 11
3.4.4. TSP Monitoring: Prepare a TSP Monitoring Plan for Location 2 only.
Perform TSP monitoring. The positioning of air monitoring equipment shall be in accordance with 40 CFR 58, App E, Subpart (8). In addition, use a minimum of two TSP monitors at the project site, one downwind from the project and one in the area of greatest public access (e.g. playground, school yard, or homeowner's yard). Conduct TSP-lead monitoring in accordance with 40 CFR 50, App B. Monitoring shall be conducted throughout the entire period that abrasive blasting and cleanup operations are performed. Failure to meet air quality regulatory limits shall require air monitoring to be repeated immediately after corrective actions have been taken. Also conduct pre-project TSP monitoring. The pre-project TSP monitoring shall be conducted a minimum of 2 weeks prior to the beginning of the project.
Continue the monitoring for a minimum of 3 days to establish background levels. Submit a TSP Test Report to the Contracting Officer within 48 hours including:
a. Name and location of jobsite.
b. Date of monitoring.
c. Time of monitoring (i.e., time monitoring begins and ends each day).
d. Identification and serial number of monitoring units.
e. Drawing showing specific location of monitoring units.
f. Drawing showing specific location of paint removal operation and the method of removal or work activity being performed.
g. Wind direction and velocity.
h. A flow chart verifying the rate of air flow across the filter throughout the sampling period.
i. Name and address of laboratory.
j. Laboratory test procedure.
k. Laboratory test results.
l. Signatures of field and la boratory technicians conducting the work.
3.4.5. Water Quality: Prepare a Water Quality Plan for Location 2 only.
Conduct operations in such a manner that lead-containing and other hazardous paint debris do not contaminate the water and so that NPDES permits in accordance with EPA regulation 40 CFR 122 are not required for the project.
In the event that there are any releases of lead paint debris into the waterway, with reportable quantities of hazardous substances designated pursuant to Section 311 of the Clean Water Act, they shall be reported to the EPA in accordance with 40 CFR 117 and 40 CFR 355. Releases or spills that carry into waterways or storm sewers shall be thoroughly documented.
The documentation shall include the time and location of the release, amount of material released, actions taken to clean up the debris, amount of debris recovered, and corrective action taken to avoid a reoccurrence. Releases shall also be reported to the Coast Guard and other state and local authorities as appropriate. If the release is equivalent to 10 pounds or more of lead-containing material in a 24-hour period, it is considered to be a reportable quantity under CERCLA. Comply with 40 CFR 302.
SECTION 01 11 00 Page 12
3.4.6. Soil Quality: Prepare a Soil Quality Plan for Location 2 only.
Establish and implement practices and procedures for preventing contamination of the soil from the removal of lead-containing or other hazardous paints. Unless otherwise directed by the Contracting Officer, soil shall be considered to have been contaminated by the Contractor's operation if an increase in the total lead content of 100 PPM or greater over background levels occurs. For purposes of computing the increase, compute the mean background levels and the mean post-removal levels. The 100 PPM criterion is met if the difference between the means is less than 100 PPM plus the 95 percent confidence limit. Soil sampling and testing shall be conducted prior to the beginning of the project and after the project is completed. Interim testing may also be performed in the event the Contractor or COR wants to confirm that the containment system and work practices continue to provide satisfactory protection of the soil. Unless otherwise directed by the COR, the following minimum test locations shall be selected for soil analysis. Two locations shall be selected beneath or immediately adjacent to the structure being prepared and additional samples shall be taken within 100 feet in each direction of the project (i.e., N, S, E, W) in which soil is present. The number of soil sample locations shall be sufficient to adequately characterize the soil contaminant levels within and around the project area. Five composite samples shall be collected at each location. Each of the five samples shall be comprised of five individual plugs of soil combined in a single bag. The composite samples at each location shall be collected using the following procedure:
a. Place a 1-square foot template at each location.
b. Remove a sample of soil 3/4 inch in diameter and 1/2 inch in depth at the center of the template and at each of the four corners. Place the five soil plugs into a single bag. This represents one of the five samples to be removed at a given location.
c. Move the template 1 inch in any direction and repeat the process to collect the second sample. Place all plugs in a separate bag. Move the template 1 additional inch farther to collect the third, fourth, and fifth samples.
d. Identify each sample bag with the date, specific location of the sample, name and signature of the sampling technician, and complete chain of custody records.
e. It is critical that the specific location of each sample be thoroughly measured and documented as the final project testing (and any interim testing) shall be sampled in the precise locations.
Three samples collected at each location shall be analyzed. One of the remaining two samples shall be maintained by the Contractor for the duration of the project and the other by the COR in the event reanalysis is required.
Lead-containing samples shall be analyzed in accordance with EPA testing guidance as published in 40 CFR 261, App III, by a laboratory listed by the American Industrial Hygiene Association (AIHA) as being proficient in conducting the test. Note that if it is determined that contamination of the soil has occurred as a result of the paint removal operations, TCLP testing will be employed to determine if the soil shall be handled and disposed of as a hazardous waste. The initial sampling of the soil for total lead content does not establish whether the soil would be considered hazardous by TCLP testing. As a result, at the Contractor's option, additional prework soil samples may be removed (minimum of 105 grams is required for a single test at each site) to conduct TCLP testing to establish whether the soil
SECTION 01 11 00 Page 13 would be classified as hazardous prior to project startup. In the event that there is a release of lead paint debris onto the soil and if the release is 10 pounds or more of lead-containing material in a 24-hour period, it is considered to be a reportable quantity under CERCLA. Comply with 40 CFR 302.
Thoroughly document the occurrence of any spills of lead debris into the soil. The documentation shall include the time and location of the release, amount of material released, actions taken to clean up the debris, amount of debris reclaimed, and corrective action taken to avoid a reoccurrence. The documentation shall be provided to the Contracting Officer and shall also include the Soil Quality Test Report.
4. TECHNICAL SPECIFICATIONS
4.1. General: The contractor shall provide all labor, supervision, materials, equipment and supplies required for surface preparation and application of a new coating system to the Indian Rock Dam, Foster Sayers Dam, and Curwensville Dam.
4.2. Qualifications: Qualifications and experience shall comply with the following.
4.2.1. Qualified Painting Contractor: The Contractor shall be a certified SSPC-QP 1 Painting Contractor. Submit a copy of the SSPC-QP 1 Certificate.
4.2.2. Qualified Hazardous Paint Removal Contractor: The Contractor shall be a certified SSPC-QP 2 Painting Contractor. Provide a copy of the SSPC-QP 2 Certificate.
4.2.3. Coating Thickness Gage Qualification: Submit a Coating Thickness Gage Qualification certificate for each gage. Magnetic flux thickness gages as described in ASTM D 7091 shall be used to make all coating thickness measurements on ferrous metal substrates. Gages shall have an accuracy of +/- 3 percent or better. Gages to be used on the job shall be certified by the manufacturer as meeting these requirements.
4.3. Delivery, Storage, and Handling: Process and package paints to ensure that within a period of one year from date of manufacture, they will not gel, liver, or thicken deleteriously, or form gas in the closed container.
Paints, unless otherwise specified or permitted, shall be packaged in standard containers not larger than 5 gallons, with removable friction or lug-type covers. Each container of paint or separately packaged component thereof shall be labeled to indicate the purchaser's order number, date of manufacture, manufacturer's batch number, quantity, color, component identification and designated name, and formula or specification number of the paint together with special labeling instructions, when specified. Paint shall be delivered to the job in unbroken containers. Paints that can be harmed by exposure to cold weather shall be stored in ventilated, heated shelters. All paints shall be stored under cover from the elements and in locations free from sparks and flames.
4.4. Ambient Conditions: Paint shall be applied only to surfaces that are above the dew point temperature and that are completely free of moisture as determined by sight and touch. Paint shall not be applied to surfaces upon which there is detectable frost or ice. Except as otherwise specified, the temperature of the surfaces to be painted and of air in contact therewith shall be not less than 45 degrees F during paint application nor shall paint be applied if the surfaces can be expected to drop to 32 degrees F or lower before the film has dried to a reasonably firm condition. During periods of inclement weather, painting may be continued by enclosing the surfaces and
SECTION 01 11 00 Page 14 applying artificial heat, provided the minimum temperatures and surface dryness requirements prescribed previously are maintained. Paint shall not be applied to surfaces heated by direct sunlight or other sources to temperatures that will cause detrimental blistering, pin holing, or porosity of the film.
4.5. Products: Submit Manufacturer’s Product Data Sheet for each product used.
4.5.1. Protective Coating for Painting Method 1: The coating system shall consist of inorganic zinc first coat, inhibitive polyamide epoxy intermediate coat, and aliphatic polyurethane finish coat. Coatings shall be selected form the listing identified by the Northeast Protective Coating Committee (NEPCOAT) in “Qualified Product List B”, and all coatings, thinners, and cleaners shall be the product of the same manufacturer.
NEPCOAT qualified products for protective coatings may be found at https://nepcoat.org/qualprod.htm.
Each successive coating shall be of a contrasting color to provide a visual assurance of complete coverage. Color samples produced by the finish coat manufacturer shall be submitted to the government for color selection.
4.5.2. Protective Coating for Painting Method 2:
4.5.2.1. A material will be selected that can be applied over directly to bare steel as well as over the existing coating with minor surface preparation. See Section 4.6.5.2 for details of the existing coating.
4.5.3. Thinner: Thinner shall be as recommended by the paint manufacturer.
4.5.4. Lead: Paints containing lead in excess of 0.02 percent by weight of the total nonvolatile content (calculated as lead metal) shall not be used.
4.5.5. Chromium: Paint containing zinc chromate or strontium chromate pigments shall not be used.
4.5.6. Volatile Organic Compound (VOC) Content: Paints shall comply with applicable state and local laws enacted to ensure compliance with Federal Clean Air Standards and shall conform to the restrictions of the local air pollution control authority.
4.5.7. Bridge Bearing Lubricant: Protective coating material shall be a permanent soft gel coating for anti-corrosion protection and lubrication of steel structures and components, specially formulated to resist the degrading action of sunlight and wind driven rain. The material shall have either of the following characteristics:
a. Lanolin Base
Color Off white Thinning None Required Coverage 1,100 sq. ft. at 80 mils per 55 Gals.
No.of Coats One Mixing Single component, none required Curing Time None, permanently soft Specific Gravity 0.875 - 0.885 Flash Point: Cleveland Open Cup (ASTM D 92) 404 degrees F 207°C
SECTION 01 11 00 Page 15
Unworked Penetration (ASTM D 217) 200 – 230 Dropping Point >200 degrees F
One such approved product is Fluid Film NAS, a product of the Eureka Chemical Company,…