This is a Final Pre-Solicitation Synopsis for a U.S. Army Corps of Engineers (USACE) Galveston District contract for maintenance dredging in Texas. The project involves pipeline dredging of the Gulf Intracoastal Waterway from Corpus Christi Bay to Port Isabel, including a Channel to Harlingen section, spanning Nueces, Kleberg, Kenedy, Willacy, and Cameron Counties. The solicitation is 100% unrestricted with a firm-fixed price contract estimated over $10,000,000, to be issued in July 2025 with responses expected in August 2025.
Key contract details include a 127-calendar day completion time for the base schedule, with liquidated damages for delays. Dredging work on the GIWW and Port Isabel Small Boat Harbor must be completed within the Laguna Madre sea grass window (November-February), though this restriction does not apply to the Channel to Harlingen sections. The contractor must provide performance and payment bonds within 5 calendar days of award and begin work within 10 calendar days of the Notice to Proceed. Subcontracting goals include 76% Small Business, with additional targets for Small Disadvantaged, Woman-Owned, HubZone, Veteran-Owned, and Service-Disabled Veteran-Owned Small Businesses.
View the file
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Final Pre-Solicitation Synopsis
W912HY25BA007
The U. S. Army Corps of Engineers, Galveston District Office requires a contract for
FY25 USACE Galveston District GIWW Corpus Christi Bay to Port Isabel w/ Channel to Harlingen Pipeline Dredging, Nueces, Kleberg, Kenedy, Willacy, and Cameron
Counties, Texas 100% UNRESTRICTED.
THE WORK CONSISTS OF:
The work will consist of maintenance dredging via pipeline dredge of the Gulf Intracoastal Waterway- Corpus Christi Bay to Port Isabel w/ Channel to Harlingen Maintenance Dredging. All dredging work on the GIWW and Port Isabel Small Boat Harbor sections to be completed within the Laguna Madre Sea grass window between November and February. Sea grass restriction does not apply to Channel to Harlingen sections. Currently, there is one base CLIN (Schedule 1) and four (4) options.
1. Completion Time for Schedule No. 1 for this project is estimated at 127 calendar days after acknowledgement of the Notice to Proceed. If the contractor fails to complete the work within the time specified, the contractor shall pay liquidated damages to the Government in an amount to be determined for each calendar day of delay until the work is completed or accepted.
2. Other Information: n/a
3. The solicitation issued will be a firm-fixed price contract award. Estimated magnitude for this effort is estimated over $10,000,000.00.
4. Bonding Requirements - The Contractor will be required to provide the
Performance and Payment Bonds within 5 calendar days after award. The contractor shall begin work within 10 calendar days after acknowledgement of the Notice to Proceed.
5. Furnish pre-award documents within 2 working days after Bid Opening.
Prior Government contract work is not required for submitting a response to the solicitation.
The Solicitation issued will be Firm Fixed Price. This solicitation is subject to the availability of funds. The Solicitation is UNRESTRICTED. The Solicitation will be issued on or about JULY 2025. Response date on or about AUGUST 2025.
The North American Industrial Classification System (NAICS) Code applicable to this project is Construction 237990. The Small Business Size Standard is $37,000,000.00.
Dredging
All offerors are encouraged to visit the Army’s Single Face to Industry Website at Beta Sam website at https://www.sam.gov to view and download the plans, specification and or any amendments for this procurement. Plans and specifications will not be available in paper format or on compact disc. To register as an “Interested Vendor”, visit https://www.sam.gov . Offerors must be registered with the SAM, Systems for Award Management, in order to receive a Government contract award. To register, the SAM address is: https://www.sam.gov/portal/public/SAM/ . The Contract Specialist for this solicitation will be Danelle Tate, at email danelle.m.tate@usace.army.mil .
Subcontracting goals for the Galveston District are: 76.0% - Small Business; 1.0% - Small Disadvantaged Business; 5.0% - Woman-Owned Small Business; 3.0% - HubZone Small Business; 17% - Veteran-Owned Small Business and 16.0% - Service Disabled Veteran-Owned Small Business.