B.01.01 - Combined Synopsis-Solicitation W912DQ24Q1038.pdf

PDF 1 MB Posted

Attached to
Vegetative Management and Herbicide Application Services for Kanopolis Project Office
Solicitation number
W912DQ24Q1038
Issued by

About this file

This is a combined synopsis/solicitation from the U.S. Army Corps of Engineers seeking quotes for vegetation management and herbicide application services at Kanopolis Lake in Kansas. The contractor will provide labor, equipment, and supervision to perform mowing, trimming, and herbicide application in administration and park areas from April through August, with pre-emergent application beginning earlier as weather allows. Quotes are due by March 6th, with award by March 29th and a period of performance from April 1st through March 31st, with optional one-year extensions for two additional years. The solicitation is set aside for small businesses and identifies NAICS code 561730 with a $9.5 million size standard. The Army Corps of Engineers is the contracting agency.

View the file

Other files

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

SEE ADDENDUM

(No Collect Calls)

W912DQ24Q1038 01-Mar-2024

b. TELEPHONE NUMBER

816-389-3812

8. OFFER DUE DATE/LOCAL TIME

12:00 PM 06 Mar 2024

5. SOLICITATION NUMBER 6. SOLICITATION ISSUE DATE

AUTHORIZED FOR LOCAL REPRODUCTION

PREVIOUS EDITION IS NOT USABLE

STANDARD FORM 1449 (REV. 2/2012)

Prescribed by GSA – FAR (48 CFR) 53.212

(TYPE OR PRINT)

(SIGNATURE OF CONTRACTING OFFICER)

ADDENDA ARE

26. TOTAL AWARD AMOUNT (For Gov t. Use Only )

23.

CODE 10. THIS ACQUISITION IS

SUCH ADDRESS IN OFFER

17b. CHECK IF REMITTANCE IS DIFFERENT AND PUT

BELOW IS CHECKED

TELEPHONE NO.

W912DQ9. ISSUED BY

18b. SUBMIT INVOICES TO ADDRESS SHOWN IN BLOCK 18a. UNLESS BLOCK

7. FOR SOLICITATION

INFORMATION CALL:

a. NAME

KATHERINE S AVERY

2. CONTRACT NO. 3. AWARD/EFFECTIVE DATE 4. ORDER NUMBER

(TYPE OR PRINT)

30b. NAME AND TITLE OF SIGNER 30c. DATE SIGNED 31b. NAME OF CONTRACTING OFFICER

30a. SIGNATURE OF OFFEROR/CONTRACTOR 31a.UNITED STATES OF AMERICA

0 27a. SOLICITATION INCORPORATES BY REFERENCE FAR 52.212-1. 52.212-4. FAR 52.212-3. 52.212-5 ARE ATTACHED.

25. ACCOUNTING AND APPROPRIATION DATA

1. REQUISITION NUMBER

20.

ADDITIONAL SHEETS SUBJECT TO THE TERMS AND CONDITIONS SPECIFIED.

OFFEROR TO COMPLETE BLOCKS 12, 17, 23, 24, AND 30

SOLICITATION/CONTRACT/ORDER FOR COMMERCIAL ITEMS

ARE NOT ATTACHED

27b. CONTRACT/PURCHASE ORDER INCORPORATES BY REFERENCE FAR 52.212-4. FAR 52.212-5 IS ATTACHED. ADDENDA ARE ARE NOT ATTACHED

(BLOCK 5), INCLUDING ANY ADDITIONS OR CHANGES WHICH ARE

SET FORTH HEREIN, IS ACCEPTED AS TO ITEMS:

. YOUR OFFER ON SOLICITATION

28. CONTRACTOR IS REQUIRED TO SIGN THIS DOCUMENT AND RETURN

% FOR:SET ASIDE:UNRESTRICTED OR X

SMALL BUSINESSX

17a.CONTRACTOR/ CODE FACILITY

OFFEROR CODE

USACE, KANSAS CITY +

FEDERAL BLDG, CT-C +

601 E 12TH ST RM 647

KANSAS CITY MO 64106-2896

18a. PAYMENT WILL BE MADE BY CODE

RATED ORDER UNDER

DPAS (15 CFR 700)

13a. THIS CONTRACT IS A

13b. RATING

CODE15. DELIVER TO CODE 966219 16. ADMINISTERED BY

12. DISCOUNT TERMS11. DELIVERY FOR FOB DESTINA-

TION UNLESS BLOCK IS

MARKED

SEE SCHEDULE

14. METHOD OF SOLICITATION

RFQ IFB RFPX

KANOPOLIS PROJECT OFC

DANIEL HAYS

105 RIVERSIDE DR

MARQUETTE KS 67464

TEL: (816) 389-3093 FAX:

816-389-2029/2030FAX:

TEL: 816-389-3812 SERVICE-DISABLED

VETERAN-OWNED

SMALL BUSINESS

8(A)

HUBZONE SMALL

BUSINESS

SIZE STANDARD:

$9,500,000

NAICS:

561730

X

OFFER DATED

29. AWARD OF CONTRACT: REF.

DELIVER ALL ITEMS SET FORTH OR OTHERWISE IDENTIFIED ABOVE AND ON ANY

COPIES TO ISSUING OFFICE. CONTRACTOR AGREES TO FURNISH AND

EMAIL:

TEL:

31c. DATE SIGNED

SEE SCHEDULE

SCHEDULE OF SUPPLIES/ SERVICESITEM NO. QUANTITY UNIT UNIT PRICE AMOUNT

24.22.21.19.

WOMEN-OWNED SMALL BUSINESS (WOSB)

ELIGIBLE UNDER THE WOMEN-OWNED

SMALL BUSINESS PROGRAM

EDWOSB

32g. E-MAIL OF AUTHORIZED GOVERNMENT REPRESENTATIVE

SOLICITATION/CONTRACT/ORDER FOR COMMERCIAL ITEMS

(CONTINUED)

PAGE 2 OF64

ACCEPTED, AND CONFORMS TO THE CONTRACT, EXCEPT AS NOTED: ______________________________________________________

32a. QUANTITY IN COLUMN 21 HAS BEEN

RECEIVED INSPECTED

32b. SIGNATURE OF AUTHORIZED GOVERNMENT

REPRESENTATIVE

32c. DATE 32d. PRINTED NAME AND TITLE OF AUTHORIZED GOVERNMENT

REPRESENTATIVE

32e. MAILING ADDRESS OF AUTHORIZED GOVERNMENT REPRESENTATIVE 32f . TELEPHONE NUMBER OF AUTHORIZED GOVERNMENT REPRESENTATIVE

37. CHECK NUMBER

FINALPARTIALCOMPLETE

36. PAYMENT35. AMOUNT VERIFIED

CORRECT FOR

34. VOUCHER NUMBER

FINAL

33. SHIP NUMBER

PARTIAL

38. S/R ACCOUNT NUMBER 39. S/R VOUCHER NUMBER 40. PAID BY

41a. I CERTIFY THIS ACCOUNT IS CORRECT AND PROPER FOR PAYMENT

41b. SIGNATURE AND TITLE OF CERTIFYING OFFICER 41c. DATE

42a. RECEIVED BY (Print)

42b. RECEIVED AT (Location)

42c. DATE REC'D (YY/MM/DD) 42d. TOTAL CONTAINERS

STANDARD FORM 1449 (REV. 2/2012) BACK

Prescribed by GSA – FAR (48 CFR) 53.212

AUTHORIZED FOR LOCAL REPRODUCTION

PREVIOUS EDITION IS NOT USABLE

SEE SCHEDULE

20.

SCHEDULE OF SUPPLIES/ SERVICES

21.

QUANTITY UNIT

22. 23.

UNIT PRICE

24.

AMOUNT

19.

ITEM NO.

Section A - Solicitation/Contract Form

COMBINED SYNOPSIS/SOLICITATION

SYNOPSIS/SOLICITATION

This is a combined synopsis/solicitation for commercial services prepared in accordance with the format in subpart

12.6 as supplemented with additional information included in this notice. This announcement constitutes only the solicitation; quotes are being requested and a written solicitation (SF 1449) will not be issued.

The solicitation number for this acquisition is W912DQ-24-Q-1038 and it is being issued as a Request for Quotes

(RFQ).

The solicitation documents and incorporated provisions and clauses are those in effect through Federal Acquisition Circular (FAC) 2024-02.

This RFQ shall be set aside for small businesses and the associated North American Industry Classification system (NAICS) code is 561730, “Landscaping Services" and the business size standard is $9,500,000.00.

Applicable Provisions and Clauses The following provisions and clauses listed below apply to the combined synopsis/solicitation and final Service Contract:

Far 52.212-1, Instructions to Offerers- Commercial does apply to this acquisition with no addenda to the provision and is located in Section L of this combined synopsis/solicitation.

Far 52.212-2, Evaluation - Commercial Edited does apply to this acquisition with no addenda to the provision and is in Section M of this combined synopsis/solicitation.

FAR 52.212-3, Offerer Representations and Certifications -- Commercial Items, does apply to this acquisition with no addenda to the provision, and is in Section K of this combined synopsis/solicitation.

FAR 52.212-4, Contract Terms and Conditions - Commercial Items, does apply to this acquisition with no addenda to the provision. These specific clauses required are in Section I of this combined synopsis/solicitation.

FAR 52.212-5, Contract Terms and Conditions - Required to Implement Statutes or Executive Orders- Commercial Items, applies to this acquisition. These specific clauses required are in Section I of this combined synopsis/solicitation.

Site Visit If any contractors are interested in a site visit, please schedule your visit with Amy Snively;

Project Manager: Daniel Walter Hays Phone Number: (816) 389-3093 E-Mail: DANIEL.W.HAYS@USACE.ARMY.MIL

System for Award Management In accordance with FAR 52.212-l(k): By submission of a quote, the contractor acknowledges the requirement that a prospective awardee shall be registered in the SAM database prior to award, during performance and through final payment of any contract resulting from this solicitation. If the contractor does not become registered in the SAM database in the time prescribed by the Contracting Officer, the Contracting Officer will proceed with award to the next otherwise successful registered contractor. Contractor may obtain information on registration and annual confirmation requirements via the SAM.gov database accessed through https://www.sam.gov/SAM/. To be considered for award, all prospective contractors must be registered in the System for Award Management (SAM) website or https://www.sam.gov/SAM/. It is highly encouraged that all prospective contractor's start the SAM' s registration process as soon as possible.

If you were not previously registered, please go to https://www.sam.gov. Instructions for new registration are also located at the following link https://www.sam.gov/SAM/transcript/Quick_Guide_for_Updating_or_Renewing_SAM_Registrations.pdf.

OFFERORS INTERESTED IN RESPONDING TO THIS RFQ MUST SUBMIT THEIR QUOTE ON THE

ATTACHED SYNOPSIS/SOLICITATION. Award will be made to the quote providing the best value. Any questions regarding this synopsis/solicitation must be submitted by e-mail to the point of contact below. The Government reserves the right to cancel this combined synopsis/solicitation at any time.

The Contractor is responsible for furnishing all equipment, labor, operators, supervision/site superintendent, quality control, supplies, materials, and incidentals necessary to satisfactorily perform and provide all services listed under the statement of the Service Contract to the location set forth by the Army Corps of Engineer’s District Projects.

Quotes are due by 6 March at 12 pm CST.

Request for Quote (RFQ)

This requirement will be synopsized and solicited through the Procurement Integrated Enterprise Environment (PIEE) System Solicitation Portal. Quotes will be received and accepted through either the PIEE Solicitation Portal or by emailing Katherine Avery at katherine.s.avery@usace.army.mil.

In order to submit a quote for this requirement through the PIEE Solicitation Portal, Contractors will first need to register for the PIEE ‘Proposal Manager’ role.

How to Register:

1. Navigate to https://wawf.eb.mil/

2. Select Register [top right]

3. Select Vendor

4. Create a User ID and Password and follow the prompts [next]

5. Create Security Questions [next]

6. Complete your User Profile Information [next]

7. Complete your Supervisor or Approving Official Information [next]

8. Complete Roles - Step 1. Select SOL-Solicitation, Step 2. Select Proposal Manager, Step

2. Click Add Roles, Step 4. Fill in your Location Code (CAGE Code) [next] ensures

9. Provide a justification for your registration [next]

10. Follow the remaining prompts to submit your registration To learn more about the PIEE Solicitation Portal and for training/instructions on submitting your quote, please visit the Web Base Training Page below: https://pieetraining.eb.mil/wbt/xhtml/wbt/sol/solicitation/proposals.xhtml

Procurement Technical Assistance Center (PTAC) If you have questions about Government procurements in general or need assistance in the preparation of your proposal, a local Procurement Technical Assistance Center (PTAC) may be able to help. The Procurement Technical Assistance Program was authorized by Congress in 1985 in an effort to expand the number of businesses capable of participating in the Government marketplace. To locate a PTAC near you, go to http://www.aptac-us.org/contracting-assistance/. THIS A FREE SERVICE BY A NON-PROFIT PAID FOR BY THE U.S.

GOVERNMENT.

Section B - Supplies or Services and Prices

ITEM NO SUPPLIES/SERVICES QUANTITY UNIT UNIT PRICE AMOUNT

0001 1 Season Mow and Trim Services

FFP

The Contractor shall provide labor, material, and equipment as specified to perform vegetative management and herbicide application services to areas as described in this Performance Work Statement (PWS) and elsewhere in the contract.

Administration/Dam Areas.

FOB: Destination

PSC CD: S208

NET AMT

0002 1 Season Mow and Trim Services

FFP

The Contractor shall provide labor, material, and equipment as specified to perform vegetative management and herbicide application services to areas as described in this Performance Work Statement (PWS) and elsewhere in the contract.

Park/Recreation Areas.

1001 1 Season OPTION Mow and Trim Services FY25

FFP

The Contractor shall provide labor, material, and equipment as specified to perform vegetative management and herbicide application services to areas as described in this Performance Work Statement (PWS) and elsewhere in the contract.

Administration/Dam Areas.

1002 1 Season OPTION Mow and Trim Services FY25

FFP

The Contractor shall provide labor, material, and equipment as specified to perform vegetative management and herbicide application services to areas as described in this Performance Work Statement (PWS) and elsewhere in the contract.

Park/Recreation Areas.

2001 1 Season OPTION Mow and Trim Services FY26

FFP

The Contractor shall provide labor, material, and equipment as specified to perform vegetative management and herbicide application services to areas as described in this Performance Work Statement (PWS) and elsewhere in the contract.

Administration/Dam Areas.

2002 1 Season OPTION Mow and Trim Services FY26

FFP

The Contractor shall provide labor, material, and equipment as specified to perform vegetative management and herbicide application services to areas as described in this Performance Work Statement (PWS) and elsewhere in the contract.

Park/Recreation Areas.

Section C - Descriptions and Specifications

PERFORMANCE WORK STATEMENT

Vegetative Management & Herbicide Application Services

Kanopolis Project Office

C.1 General Information

C.1.1 Background: Kanopolis Lake was the first lake built in Kansas by the Corps of Engineers Kansas City District. Construction of Kanopolis Dam began in 1940 and was completed in 1948. The lake has a drainage area of 7,860 square miles. At the multipurpose elevation of 1,463msl, the lake has a surface area of 3,400 acres or 61,382 acre-feet with 41 miles of shoreline. During periods of heavy rain the lake increases in size, as runoff is stored, providing downstream flood protection. Recreation, fish and wildlife enhancement, and water quality also are benefits of the lake. Many routine maintenance items are contracted to the private sector. Mowing, refuse collection, office janitorial and facility cleanup are just a few of the activities that are performed by private contractors for the Corps.

C.1.2 Scope of Work: The Contractor shall provide labor, material, and equipment as specified to perform vegetative management and herbicide application services to areas as described in this Performance Work Statement (PWS) and elsewhere in the contract. Acceptable performance standards and current regulations are provided for each task. The Contractor shall monitor performance and ensure compliance in accordance with the terms and conditions.

C.1.3 Period of Performance: The contract shall begin 1 April or date of award and continue through 31 August (growing season). Application of pre-emergent may begin as early in the year as weather conditions allow.

C.1.4 Post Award Conference: The contractor shall attend a required pre-work orientation with the Government's representative at the Kanopolis Project Office within 3 days prior of the first workday.

C.1.5 Quality Control: The Contractor shall develop a Quality Control Plan designed to demonstrate how the Contractor will meet the needs of the project. The Quality Control Plan shall document how the Contractor will identify and correct performance shortfalls. Complete records of all inspection work performed by the contractor must be maintained and made available to the government during contract performance.

C.1.6 Quality Assurance:

C.1.6.1 The Government will monitor the Contractor’s performance under this contract using quality assurance procedures developed by the Government. Typical procedures might include random inspections on service areas and documentation of findings. This should not be considered an exhaustive list. A primary objective of Government Quality Assurance will be to determine the effectiveness of the Contractor’s quality control system.

C.1.6.2 The government reserves the right to inspect and test all services called for by the contract, to the extent practicable at all times and places during the term of the contract. The government will perform inspections and tests in a manner that will not unduly delay the work.

C.1.6.3 If any of the services do not conform to contract requirements, the government will request the contractor to perform the services again, where appropriate, in conformity with contract requirements, at no increase in contract amount. When the defects in services cannot be corrected by re-performance, the government may (1) require the contractor to take necessary action to ensure that future performance conforms to contract requirements and (2) reduce the contract price to reflect the reduced value of the services performed.

C.1.6.4 If the contractor fails to promptly re-perform the services or to take the necessary action to ensure future performance in conformity with contract requirements, the government may by contract, or otherwise: (1) perform the services and charge to the Contractor any cost incurred by the government that is directly related to the performance of such service or (2) terminate the contract in whole or in part.

C.1.7 Workmanship:

C.1.7.1 In order to assure that the work performed under this contract is performed in a strictly first-class manner, the Contractor shall designate, in writing, a responsible member of each crew who shall serve as a contact for matters concerning quality, performance or non-performance of the required work assigned to that crew. The employee(s) designated in accordance with the above requirement shall be qualified and fully competent with full authority to act for, and on the behalf of the Contractor as necessary to ensure that the work described herein is performed in accordance with these specifications. The Contractor shall furnish the above written designation to the COR at the Project no later than the first day of the contract. The designation shall include the names(s), address(es) and phone number(s) of the individuals he intends to assign to this work. The Contracting Officer reserves the right to disapprove any individual whom he considers to be incompetent to perform the work required. Such disapprovals will be given to the Contractor by written notice and the Contracting Officer’s decision shall represent a final decision.

C.1.7.2 Contractor’s employees shall be fully clothed at all times while performing these services. “Fully Clothed” shall be deemed to mean that a shirt, (or T-shirt), trousers and shoes shall be worn at all times. Clothing shall be neat and clean in appearance. Contractor personnel shall utilize tact, diplomacy and courtesy at all times when dealing with the public. Service will be allowed on weekdays from 7:00 am – 4:00 pm.

C.1.7.3 Equipment breakdown shall not relieve the Contractor of the responsibility of performing the work as specified. It shall be the responsibility of the Contractor to assure that he has, or can obtain on short notice, sufficient backup equipment to continue the services as specified without interruption in the event of mechanical failure of his primary equipment.

C.1.7.4 Apply herbicide to all areas listed under Herbicide Application sites. In most cases, the result should be a clean, vegetation free area. Some areas involve the control of certain species (ie woody vegetation). In those areas, it will be the Contractor’s responsibility to insure that the target species are all that are affected. The Contractor shall consider any impacts for potential erosion on service areas and to base any vegetation free border on topography and wash out potential as needed under the discretion of the COR. If any erosion or wash out does occur the Contractor must notify the COR.

C.1.7.5 The Contractor will be responsible for selecting the appropriate chemical to be used based on site location, proximity to the public, environmental concerns, target species and best commercial practices. Information will be provided to the government regarding the chemical(s) to be used prior to application. Biodegradable dye will be used as a marker to insure even applications.

C.1.7.6 The Contractor will guarantee at least a 99% vegetation free control 100% of the time of all serviced areas during the growing season (April through September). Should the level of control fall below 99%, the contractor will be responsible for the re-treatment of the subject area(s) to achieve the desired result, at no additional cost to the government. In order to maintain this level of vegetation control, it is anticipated that the contractor will need to make at least one Quality Control visit each month to insure that the desired results are being achieved prior to submitting the monthly invoice. Payment will not be made until this level of control is accomplished.

C.1.7.7 All contractor personnel applying herbicide shall be appropriately trained and licensed. Copies of all licenses and certifications will be provided to the government prior to the start of work. Appropriate insurance will also be in place and documentation provided prior to the start of work.

C.1.7.8 The serviced areas will present a neat, even kill of all target species. Spray patterns will provide an even border between treated and untreated areas. A 1 foot (approx.) vegetation free border will be left around all hard-surfaced or rocked facilities (ie pads, parking lots, etc.).

C.1.7.9 Work will not be done on days when the wind exceeds 10 mph in developed areas (15 mph in undeveloped areas) or when wet weather could affect the application.

C.1.7.10 The government will provide water for tank filling. The Contractor will provide hoses and backflow-preventers. Clean-out of chemical tanks and disposal of chemical containers will not be done on government property. The Contractor will have spill kits available on all vehicles used on government property adequate to the type and quantity of chemical on the vehicle. Contractor employees will be trained in the use of these kits and are expected to aggressively implement their use in the event of a spill.

C.1.7.11 The Contractor will be responsible for any damage to non-target species.

C.1.7.12 The Contractor will complete an herbicide application report form (furnished by the government) after all chemical applications whether initial or follow-up. Payment will not be made until the completed forms are provided.

C.1.8 Flood Control Project: Occasional retention of floodwaters may inundate portions of the public use areas, other areas, or access roads thereto, being serviced by this contract. In the event that inundation materially affects the scope of work, the Contractor shall be requested to submit a pricing proposal covering the unserviceable or affected portion of his/her work in order that an equitable adjustment to contract price can be negotiated and an adjustment made in accordance with the appropriate contract clause 52.212-4, para. entitled “Changes.” Payment for services not performed as a result of conditions state above shall be initially withheld until execution of an equitable adjustment can be made by contract modification.

PERFORMANCE REQUIREMENTS SUMMARY (PRS)

Performance Objective

Standard Performance Threshold

(Acceptable Level of Performance)

Method of Assessment

Remedy

Control

Vegetation in Park Areas

Refer to C.1.7.6

No more than two

(2) errors/customer complaints per service.

1) Periodic Inspections by Gov’t.

Re-performance Shall take place Within 24 hours.

Completion of

Herbicide Usage Report

Refer to C.1.7.5

No more than one

(1) error per year.

1) Periodic Inspections by Gov’t.

Quality Control

Plan

Refer to C.1.5

(1) error per year.

100% Inspection at the outset of the contract award and each option exercise period.

Coordination

Meeting

Refer to C.1.4 error.

100% Inspection annually

C.1.9 Lost articles, vandalism, facilities malfunction: To assist the visiting public in reclaiming lost articles, all property left by visitors and found during contract operations shall be turned in to the Project Office. Any evidence of vandalism, instances of facilities not operating properly, or facilities in need of repair shall be reported immediately to Project personnel.

C.1.10 Payment: Payment will be made monthly, during the growing season (April through August) upon the receipt of a proper invoice at the Project Office at the end of each month. It will be the Contractor’s responsibility to ensure that the 95% control level is achieved each month prior to the submission of the invoice. Payment will not be made until it is mutually agreed that the control level has been met.

C.1.11 Herbicide Application Sites

AREA SITE TO BE SERVICED

Administration 1. Guardrail on the west side of K-141, entire length of dam.10’ from asphalt roadway & Dam and Guardrail on east side of K-141, entire length of dam. Asphalt roadway edge to Downstream end of crest stone armoring. Approximately 10’.

2. Rock stockpiles, one on the north end of dam downstream on the embankment and the other located west of the outdoor storage area. Spraying to include a 4’ band on the perimeter of the piles as well as the rock-surfaced pad on which the stockpiles are stored.

3. The outdoor storage area located at the south end of the dam. Includes under and around all sorted equipment and materials.

4. Administration area equipment storage compound.

5. Under and adjacent to security fence.

6. Sidewalks and curbs.

7. Parking area south of maintenance building.

8. Rocked areas under wagon display and adjacent to building.

9. The collector ditch includes rock protection structures along Sand Creek starting at the south abutment and extending to the Parshall Flume on the north.

10. The rock surfaced roads are located on the embankment from the outlet parking lot on the south to the county road on the north. The collector system loop is also included.

11. Woody vegetation in the area bordered by the Parshall Flume on the north, the dam abutment on the south, the mowed slope on the west and Sand Creek on the east.

12. Area to be serviced includes roadways to the outdoor storage area. This area also includes weed control in the lilac beds at either side of the entrance gate.

13. The tower approach road located at the south end of the dam. The area to be serviced extends from K-141 to the tower bridge. The fisherman parking lot west of the tower gate is included.

14. The tower bridge approach includes the rock protection on either side of the tower approach road along with upstream levee stone armoring south of tower. Includes 1’ bare zone at toe of amoring.

15. Concrete waterways located adjacent to K-141 on the south end of dam and two concrete gutters on downstream side of embankment.

16. The paved road west of the office in the old project housing area.

17. Rock shoulder drains on the outlet road and rock ditch on east side of carpenter shop.

18. The table pads located at the outlet below project office.

19. Spillway road.

20. Administration volunteer campsite located west of north metal building.

21. Storage sheds gravel drives located in old project housing area.

22. Rock landscape beds at Information Center and Maintenance Shop.

23. Upstream embankment service road and 20’ on upstream and downstream sides of roadway as pool level allows.

Parks 1. Riverside camping and parking pads.

2. Riverside parking areas including fisherman parking area. Custodian drive and pull off on pad west of shower building.

3. Venango camping and parking pads.

4. The Venango parking lots and the overflow lot at the park entrance, the areas around the shower building , the areas around the boat ramp and “D” loop comfort stations, the lots at the redwood shelter, Loder Point, beach ATV area (including loading ramp and fence), and the areas by the traffic barrels on the beach road.

5. The Venango boat ramp includes the rock protection south of the ramp between the parking lot and the lake (excluding trees).

6. The Venango beach area including all sand areas bordered by the dam on the east, the concrete waterways on the west and north and the lake on the south and the rock armoring between the beach sand the upstream embankment.

7. The Cottonwood East Loop road located on the Venango beach road across from the beach shelter.

8. Waterways adjacent to the Venango beach.

9. Sand impact area around playground equipment in Venango and Riverside. This includes but is not limited to volleyball court, sandbox, swings, slides or any other recreational equipment or court.

10. Concrete picnic tables pads. Venango Beach, B Loop, C Loop, D Loop, and Riverside Park.

11. All non-living structures in all of mowed areas. Spraying to include a 1’ vegetation free radius around each ground contacting structure.

12. Around trees in all mowed areas. Spraying to include a 1’ vegetation free radius using a tree friendly herbicide (per label). Herbicide will not be applied to tree trunks or to trees possessing basal sprouts.

13. The Venango beach day use area rock parking lot located between booth and restroom.

14. Dumpster rock pads.

C.1.12 ANTITERRORISM/OPERATION SECURITY REQUIREMENTS

All contractor and all associated sub‐contractors employees shall comply with applicable installation, facility and area commander installation/facility access and local security policies and procedures (provided by government representative). The contractor shall also provide all information required for background checks to meet installation access requirements to be accomplished by installation Provost Marshal Office, Director of Emergency Services or Security Office. Contractor workforce must comply with all personal identity verification requirements as directed by DOD, HQDA and/or local policy. In addition to the changes otherwise authorized by the changes clause of this contract, should the Force Protection Condition (FPCON) at any individual facility or installation change, the Government may require changes in contractor security matters or processes.

All contractor and all associated sub‐contractors employees will receive a CORPS Watch information paper (provided by the authorized government representative) and provide a written acknowledgement to the COR, no later than 30 calendar days after contract start date or effective date of incorporation of this requirement into the contract.

The Contractor must pre‐screen candidates using the E‐verify Program (http://www.dhs.gov/E‐

Verify) website to meet the established employment eligibility requirements. The vendor must ensure that the candidate has two valid forms of government issued identification to ensure the correct information is entered into the E‐verify system. An initial list of verified/eligible candidates must be provided to the COR no later than 3 business days after the initial contract award.

Per the E-Verify Website the following exemptions apply:

Employers whose contracts are exempt from the E-Verify federal contractor rule are not required to enroll in E-Verify. A contract is considered exempt if any one of the following applies: (1) It is for fewer than 120 days. (2) It is valued at less than $150,000, the simplified acquisition threshold (Source:

http://www.uscis.gov/e-verify/federal-contractors/exemptions-and-exceptions).

All contract employees, including subcontractor employees who are not in possession of the appropriate security clearance, will be escorted in areas where they may be exposed to classified and/or sensitive materials and/or sensitive or restricted areas.

AT/OPSEC

U.S. Army Corps of Engineers (USACE)

CONTRACT REQUIREMENTS PACKAGE SECURITY REVIEW COVER SHEET

For use of this form, see the HQ-USACE OPORD 2022-03; the proponent agency is CECO-P.

SECTION I - CONTRACT INFORMATION

1. CONTRACT or REQUIREMENTS TITLE

Vegetative Management

2. LOCATION

Kanopolis Lake Project

3. SOLICITATION/CONTRACT NO.

TBD

4. CLASS APPROVAL REQUEST NUMBER

5. CONTRACT TYPE

Construction

MATOC/SATOC/IDIQ

Service

Supply

Task Order

Other (specify)

SECTION II - PURPOSE

This form documents the review of the requirements package (e.g., performance work statements (PWS), statements of work (SOW), statements of requirements (SOR)) for antiterrorism (AT) and other related protection matters to include, but not limited to: operation security (OPSEC), information assurance (IA), physical security, law enforcement, intelligence and industrial security. Army policy requires all services contracts, and supply contracts above the simplified acquisition level threshold (SAT), to include a signed AT/OPSEC cover sheet; this does not apply to supply contracts below the SAT, field ordering officer actions, or Government Purchase Card purchases. Local policy may require this form for supply contracts under the SAT based on risk and threat. HQ-USACE policy mandates that prior to submitting requirements packages to the supporting contracting activity, the Antiterrorism Officer (ATO) and OPSEC Officer for the Requiring Activity (RA) review (including coordination with other staff, as appropriate) each requirements package, unless a signed class approval request form is completed. If the RA does not have an ATO or OPSEC Officer, the first ATO and OPSEC Officer in the chain of command will review the contract for AT/OPSEC considerations. For contracts that involve Information Assurance/ Information Technology (IA/IT) services (e.g., desktop or network services, software or business system development/operations/ maintenance, or management of websites, servers, enterprise databases, etc.), the servicing Information Systems Security Officer (ISSO) or similar IA professional supporting the RA will review the contract for IA/IT considerations and sign this coversheet.

SECTION III - STANDARD CONTRACT LANGUAGE

Reviewers shall consider the applicability of each requirement, and check each block as "Yes" or "N/A." If the standard PWS/SOW/SOR language text found in Section IX of this form is sufficient to meet specific contract requirements, check "Yes" in the corresponding block below, and include this language in the PWS/SOW/SOR. If the standard language applies but additional language is required, check "Yes" and include both the standard language and additional contract specific language in the PWS/SOW/SOR. If standard PWS/SOW/SOR language does not apply, check "N/A.”

SECTION IV - REQUIRED CLAUSES

Required Clause(s) (see Section IX for sample language) YES N/A

1. General security requirements and guidance.

2. AT Level I training.

3. Physical security and access control requirements.

4. Contractor personnel requiring a common access card (CAC).

5. Security requirements for contract performance outside the US.

6. Suspicious Activity Reporting training (e.g. iWATCH, CorpsWatch, or See Something, Say Something).

7. Contract personnel requiring access to Government information systems.

8. Contracts requiring a formal OPSEC program.

9. Training requirements for the protection of sensitive information.

10. Information Assurance/Information Technology requirements.

11. Contracts requiring handling or access to classified information.

12. Threat Awareness Reporting Program.

13. Escorting in classified and/or sensitive areas.

14. Pre-screen candidates using E-Verify Program.

15. Contracts requiring armed security guards.

16. Contracts requiring delivery of food and water.

ENG FORM 6055, MAY 2022 PREVIOUS EDITIONS ARE OBSOLETE.

Page

SECTION V - REMARKS

1. CONTRACT TITLE

Vegetative Management

2. LOCATION

Kanopolis Lake Project

(The RA may add general information for the Reviewers below, but must also provide the complete requirements document (e.g., PWS, SOO, etc.)

SECTION VI - ANTITERRORISM REVIEWER'S SIGNATURE

I am ATO Level II certified and I have reviewed the requirements package and understand my responsibilities IAW Army Regulation 525‐13, Antiterrorism.

1. TYPED OR PRINTED NAME

HUBER, WILLIAM G.

2. RANK/CIVILIAN GRADE

GS11

3. PHONE NUMBER

816-389-3071

4. SIGNATURE

HUBER.WILLIAM.G.1142645129 Digitally signed by HUBER.WILLIAM.G.1142645129

Date: 2023.12.06 11:34:26 -06'00'

5. DATE

2023-12-06

SECTION VII - OPERATIONS SECURITY REVIEWER'S SIGNATURE

I am OPSEC Level II certified and have reviewed the requirements package to ensure that there are no OPSEC concerns regarding the release and/or publication of attached documentation to public forums as well as to determine OPSEC requirements for the Contractor, and understand my responsibilities IAW Army Regulation 530‐1, Operations Security.

1. TYPED OR PRINTED NAME

HUBER, WILLIAM G.

2. RANK/CIVILIAN GRADE

GS11

3. PHONE NUMBER

816-389-3071

4. SIGNATURE

HUBER.WILLIAM.G.1142645129 Digitally signed by HUBER.WILLIAM.G.1142645129

Date: 2023.12.06 11:41:22 -06'00'

5. DATE

2023-12-06

SECTION VIII - INFORMATION ASSURANCE REVIEWER'S SIGNATURE

(Required only if block 10 is checked “Yes.”)

I am certified at the appropriate Information Assurance Technology (IAT) and/or Information Assurance Management (IAM) level based on DoD 8570.01-M; I have reviewed the requirements package and understand my responsibilities in accordance with AR 25-2, Information Assurance.

1. TYPED OR PRINTED NAME 2. RANK/CIVILIAN GRADE 3. PHONE NUMBER

4. SIGNATURE 5. DATE

ENG FORM 6055, MAY 2022 Page

SECTION IX - STANDARD CONTRACT LANGUAGE

1. General security requirements and guidance: The security requirements described below apply to all contract personnel (including employees of the prime Contractor (“Contractor”) and all subcontractor employees) supporting the performance requirements of this contract. The Contractor is responsible for compliance with these security requirements. Questions regarding security matters shall be addressed to the designated Government representative (e.g., Contracting Officer Representative (COR), Requiring Activity (RA) representative, or Contracting Officer (if a COR or other RA representative is not appointed)). Contract personnel are critical to the overall security and safety of US Army Corps of Engineers (USACE) installations, facilities and activities, and security awareness training contributes to those efforts. The Department of Defense (DoD) and Army security training requirements specified below, if applicable, are performance requirements; all applicable contract personnel shall complete initial training within 30 days of contract award or the date new contract personnel begin performance on the contract. Within five business days from the completion of training, the Contractor shall provide written documentation (e.g., email or memorandum) to the Government representative. The documentation shall include the names of contract personnel trained and which training they completed; the Contractor shall maintain training records as part of their contract files and be prepared to provide copies of training certificates to the Government representative. Contractor personnel and vehicles are subject to search when entering federal installations. Additionally, all contract personnel shall comply with Force Protection Condition (FPCON) measures, Random Antiterrorism Measures (commonly referred to as “RAMs”), and Health Protection Condition (HPCON) measures. The Contractor is responsible for meeting performance requirements during elevated FPCON and/or HPCON levels in accordance with applicable RA plans and procedures --this includes identifying mission essential and non-mission essential personnel. In addition to the changes otherwise authorized by the changes clause of this contract, should the FPCON or HPCON levels at any individual facility or installation change, the Government may implement security changes that affect contract personnel. The Contractor shall ensure all contract personnel are aware of their security responsibilities, including any site-specific requirements identified in local policies or procedures.

2. Antiterrorism (AT) Level I training: All contract personnel requiring routine access to Army installations, facilities, and controlled access areas, or requiring network access shall complete initial and annual refresher AT Level I awareness training. Online AT Level I awareness training is available at https://jko.jten.mil/ (website subject to change).

3. Physical security and access control requirements: All contract personnel requiring physical access to a federal installation or facility shall comply with the access control procedures of that location. Contract personnel requiring unescorted access to meet contract performance requirements on a DoD installation in the US shall be vetted by the installation/facility Provost Marshal/Directorate of Emergency Services/Security Office using the National Crime Information Center-Interstate Identification Index (commonly referred to as “NCIC-III”) and Terrorist Screening Database (commonly referred to as “TSDB”). Contract personnel shall comply with all personal identity verification requirements specified in installation/facility policies and procedures. Contract personnel who do not meet requirements for unescorted access to USACE facilities shall coordinate escorted access with the Government representative, as needed. Contract personnel who receive keys, access cards, or lock combinations that provide access to government-owned property shall comply with key and lock control procedures of the RA.

4. Contract personnel requiring a common access card (CAC): Contract personnel will be issued a common access card (CAC) only if duties involve one of the following: (1) both physical access to a DoD facility and access to DoD information systems or networks; (2) remote access to a DoD information system or network using DoD-approved remote access procedures; or (3) physical access to multiple DoD facilities or multiple non-DoD federally controlled facilities on behalf of the DoD on a recurring basis for a period of 6 months or more. Before CAC issuance, contract personnel must have, at a minimum, a favorably adjudicated Tier 1 investigation or an equivalent or higher investigation in accordance with applicable Army regulations and Homeland Security Presidential Directive-12 (HSPD-12). At the discretion of the RA, an initial CAC may be issued based on a favorable review of a fingerprint check and a successfully scheduled Tier 1 investigation with the National Background Investigations Bureau. The RA provides contract personnel with additional information and forms to initiate the CAC issuance process, and/or to initiate background investigations, when required. Contract personnel shall complete these processes within established timelines to avoid delays.

5. Security requirements for contract performance outside the US: For contract performance requirements that involve services or delivery in a foreign country, the Contractor shall comply with the requirements of DFARS clause 252.225-7043. For performance requirements that involve contract personnel accompanying or supporting US Armed Forces deployed outside the US, the Contractor shall comply with the requirements of DFARS clause 252.225-7040. Contract personnel accessing DoD or other federal facilities outside the US shall comply with applicable Status of Forces Agreements and Geographic Combatant Command requirements. Prior to contract personnel traveling outside the US, the Contractor shall provide documentation of AT, OPSEC, and other required training to the Government representative. Additionally, contract personnel shall comply with requirements specified in the DoD Foreign Clearance Guide, including country and theater clearance processes.

6. Suspicious Activity Reporting training (e.g. iWATCH, CorpsWatch, or See Something, Say Something): All contract personnel shall receive initial and annual refresher training from the RA representative on the local suspicious activity reporting program. This locally developed training provides contract personnel with general information on suspicious behavior, and guidance on reporting suspicious activity to the project manager, security representative or law enforcement entity.

7. Contract personnel requiring access to Government information systems: All contract personnel with access to a government information system (including USACE business systems and CAC-enabled websites) shall comply with applicable DoD and Army regulations, and shall use the organization's UserID-Password Administration and Security System (U-PASS) at commencement of services to request network user accounts.

Contract personnel shall complete DoD Information Assurance Awareness training prior to accessing information systems, and annually thereafter.

ENG FORM 6055, MAY 2022 Page

W912DQ24Q1038

8. Contracts requiring a formal OPSEC program: The Contractor shall develop an OPSEC SOP/Plan within 90 days of contract award. The OPSEC SOP/Plan shall be reviewed and accepted by the RA OPSEC Officer. This plan will include a process to identify critical information, where it is located, who is responsible for it, how to protect it, and why it needs to be protected. In accordance with Army and DoD regulations, the contractor shall have a certified Level II OPSEC coordinator, who shall ensure OPSEC compliance during contract performance.

9. Training requirements for the protection of sensitive information: All contract personnel with access to critical information (as identified in the RA's OPSEC Program) shall complete initial and annual refresher OPSEC Level I Awareness training, which is available at the following websites:

https://www.iad.gov/ioss/, or http://www.cdse.edu/catalog/operations-security.html (websites subject to change). All contract personnel with access to Controlled Unclassified Information (CUI) shall complete initial and annual refresher CUI training in accordance with applicable Army policy.

10. Information Assurance (IA)/Information Technology (IT) requirements: All contract personnel performing IA/IT services must comply with DoD training and certification requirements specified in DoD 8570.01-M, Information Assurance Workforce Improvement Program, and maintain required background investigations specified in RA policy. Contract personnel shall provide the Government representative with documentation of certification(s) prior to performing on the contract. In accordance with applicable DoD, Army, and USACE regulations, the Contractor shall ensure that all information systems (IS) and platform information technology (PIT) systems developed and/or supported under this contract comply with cybersecurity and architectural requirements, including, but not limited to: security technical implementation guides (STIG)(e.g., the current version of the Application Security and Development STIG, and the internet access point (IAP) demilitarized zone (DMZ) STIG), and the use of security controls developed under the risk management framework documentation for the system or platform. The Contractor shall address questions regarding these provisions to the Government representative, who will coordinate between the Contractor and the USACE Chief Information Officer (CIO).

11. Contracts requiring handling or access to classified information: The prime Contractor shall have a Facility Clearance (FCL) at the appropriate level prior to performance on the contract; the RA will sponsor the prime contract company in obtaining the FCL. All cleared contract personnel shall comply with the FCL requirements, as well as applicable laws and regulations regarding contractor access to national security information. For classified contracts, the RA will generate the DD Form 254, which will be attached to the contract.

12. Threat Awareness Reporting Program: All contract personnel who maintain an active security clearance shall receive initial and annual refresher training on the Threat Awareness and Reporting Program (commonly referred to as “TARP”), provided by a Counterintelligence Agent. As determined by the servicing Counterintelligence Agent for the RA, contract personnel may complete web-based TARP training.

13. Escorting in classified and/or sensitive areas: In accordance with applicable regulations, all contract personnel who do not possess the appropriate security clearance or access privileges will be escorted in areas where they may be exposed to classified information or operations, sensitive information or activities, or restricted areas.

14. Pre-screen candidates using E-Verify Program: Contractors shall comply with the requirements set forth in FAR clause 52.222-54 Employment Eligibility Verification and FAR Subpart 22.18 in using the E-Verify Program at (https://www.e-verify.gov/) (website subject to change) to meet the contract employment eligibility requirements. Contractors are encouraged to cooperate with Federal and State agencies responsible for enforcing labor requirements to include eligibility for employment under United States immigration laws in accordance with FAR 22.102-1(i). An initial list of verified/ eligible candidates shall be provided to the COR no later than three business days after the initial contract award. When contracts are with individuals, the individuals will be required to complete a Form I-9, Employment Eligibility Verification, and submit it to the Contracting Officer to become part of the official contract file.

15. Contracts requiring armed security guards: All contract personnel performing contract security guard duties shall comply with the Individual Reliability Program in accordance with AR 190-56 (The Army Civilian Police and Security Guard Program), as well as applicable installation, facility and area commander installation/facility policies and procedures regarding storing weapons and ammunition in accordance with AR 190-11 (Physical Security of Arms Ammunition, and Explosives).

16. Contracts requiring delivery of food and water: The supplies delivered under this contract shall be transported in delivery conveyances maintained to prevent tampering with and/or adulteration or contamination of the supplies, and if applicable, equipped to maintain a prescribed temperature. All delivery vehicles and storage locations are subject to inspection at any time by the COR, Post Veterinarian, law enforcement officers, or other RA representatives authorized to conduct such inspections. When the sanitary conditions of the delivery conveyance have led, or may lead to product contamination, adulteration, constitute a health hazard, the delivery conveyance is not equipped to maintain prescribed temperatures, or the transport results in product “unfit for intended purpose,” supplies tendered for acceptance may be rejected without further inspection. As the holder of a contract with the DoD, the Contractor shall ensure that all products and/or packaging have not been tampered with or contaminated. The Contractor shall ensure all delivery conveyances are always locked or sealed, except when actively loading or unloading. Unsecured vehicles shall not be left unattended. All incoming truck drivers shall provide adequate identification upon request. In the event of an identified threat to a delivery location, or a heightened force protection/Homeland Security threat level, the Contractor may be required to adjust delivery routes to minimize vulnerability risks and enable direct delivery to DoD facilities.

ENG FORM 6055, MAY 2022

Page

POC INFORMATION

Contract Officer (KO): JOSHUA M HIGGINBOTHAM Phone Number: (816) 389-3059 E-Mail: joshua.m.higginbotham@usace.army.mil Purchasing Agent (PA/CS): KATHERINE S AVERY Phone Number: (816) 389-3719 E-Mail: katherine.s.avery@usace.army.mil

Section E - Inspection and…

This is the start of the file's text. The full file is on GovTribe.