B.01.01 Combined Synopsis Solicitation 21R1015 (FINAL).pdf
PDF 1 MB Posted
- Attached to
- Perry Lake Herbicide Application Services
- Solicitation number
- W912DQ21R1015
View the file
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
SEE ADDENDUM
(No Collect Calls)
W912DQ21R1015 07-Jan-2021
b. TELEPHONE NUMBER
816-389-3812
8. OFFER DUE DATE/LOCAL TIME
03:00 PM 07 Feb 2021
5. SOLICITATION NUMBER 6. SOLICITATION ISSUE DATE
AUTHORIZED FOR LOCAL REPRODUCTION
PREVIOUS EDITION IS NOT USABLE
STANDARD FORM 1449 (REV. 2/2012)
Prescribed by GSA – FAR (48 CFR) 53.212
(TYPE OR PRINT)
(SIGNATURE OF CONTRACTING OFFICER)
ADDENDA ARE
26. TOTAL AWARD AMOUNT (For Gov t. Use Only )
23.
CODE 10. THIS ACQUISITION IS
SUCH ADDRESS IN OFFER
17b. CHECK IF REMITTANCE IS DIFFERENT AND PUT
BELOW IS CHECKED
TELEPHONE NO.
W912DQ9. ISSUED BY
18b. SUBMIT INVOICES TO ADDRESS SHOWN IN BLOCK 18a. UNLESS BLOCK
7. FOR SOLICITATION
INFORMATION CALL:
a. NAME
JERI L HALTERMAN
2. CONTRACT NO. 3. AWARD/EFFECTIVE DATE 4. ORDER NUMBER
(TYPE OR PRINT)
30b. NAME AND TITLE OF SIGNER 30c. DATE SIGNED 31b. NAME OF CONTRACTING OFFICER
30a. SIGNATURE OF OFFEROR/CONTRACTOR 31a.UNITED STATES OF AMERICA
0 27a. SOLICITATION INCORPORATES BY REFERENCE FAR 52.212-1. 52.212-4. FAR 52.212-3. 52.212-5 ARE ATTACHED.
25. ACCOUNTING AND APPROPRIATION DATA
1. REQUISITION NUMBER
20.
ADDITIONAL SHEETS SUBJECT TO THE TERMS AND CONDITIONS SPECIFIED.
OFFEROR TO COMPLETE BLOCKS 12, 17, 23, 24, AND 30
SOLICITATION/CONTRACT/ORDER FOR COMMERCIAL ITEMS
ARE NOT ATTACHED
27b. CONTRACT/PURCHASE ORDER INCORPORATES BY REFERENCE FAR 52.212-4. FAR 52.212-5 IS ATTACHED. ADDENDA ARE ARE NOT ATTACHED
(BLOCK 5), INCLUDING ANY ADDITIONS OR CHANGES WHICH ARE
SET FORTH HEREIN, IS ACCEPTED AS TO ITEMS:
. YOUR OFFER ON SOLICITATION
28. CONTRACTOR IS REQUIRED TO SIGN THIS DOCUMENT AND RETURN
% FOR:SET ASIDE:UNRESTRICTED OR X
SMALL BUSINESSX
17a.CONTRACTOR/ CODE FACILITY
OFFEROR CODE
USACE, KANSAS CITY
FEDERAL BLDG CT-C 601 E 12TH ST RM 647
KANSAS CITY MO 64106-2896
18a. PAYMENT WILL BE MADE BY CODE
RATED ORDER UNDER
DPAS (15 CFR 700)
13a. THIS CONTRACT IS A
13b. RATING
CODE15. DELIVER TO CODE 966218 16. ADMINISTERED BY
12. DISCOUNT TERMS11. DELIVERY FOR FOB DESTINA-
TION UNLESS BLOCK IS
MARKED
SEE SCHEDULE
14. METHOD OF SOLICITATION
RFQ IFB RFPX
USACE, KANSAS CITY +
JASON HURLEY
PERRY LAKE PROJECT OFFICE 10419 PERRY PARK DR
PERRY KS 66073
TEL: 816-389-3035 FAX: 785-597-5739
816-389-2029 / 2030FAX:
TEL: 816-389-3812 SERVICE-DISABLED
VETERAN-OWNED
SMALL BUSINESS
8(A)
HUBZONE SMALL
BUSINESS
SIZE STANDARD:
$8,000,000
NAICS:
561730
X
OFFER DATED
29. AWARD OF CONTRACT: REF.
DELIVER ALL ITEMS SET FORTH OR OTHERWISE IDENTIFIED ABOVE AND ON ANY
COPIES TO ISSUING OFFICE. CONTRACTOR AGREES TO FURNISH AND
EMAIL:
TEL:
31c. DATE SIGNED
SEE SCHEDULE
SCHEDULE OF SUPPLIES/ SERVICESITEM NO. QUANTITY UNIT UNIT PRICE AMOUNT
24.22.21.19.
WOMEN-OWNED SMALL BUSINESS (WOSB)
ELIGIBLE UNDER THE WOMEN-OWNED
SMALL BUSINESS PROGRAM
EDWOSB
32g. E-MAIL OF AUTHORIZED GOVERNMENT REPRESENTATIVE
SOLICITATION/CONTRACT/ORDER FOR COMMERCIAL ITEMS
(CONTINUED)
PAGE 2 OF77
ACCEPTED, AND CONFORMS TO THE CONTRACT, EXCEPT AS NOTED: ______________________________________________________
32a. QUANTITY IN COLUMN 21 HAS BEEN
RECEIVED INSPECTED
32b. SIGNATURE OF AUTHORIZED GOVERNMENT
REPRESENTATIVE
32c. DATE 32d. PRINTED NAME AND TITLE OF AUTHORIZED GOVERNMENT
REPRESENTATIVE
32e. MAILING ADDRESS OF AUTHORIZED GOVERNMENT REPRESENTATIVE 32f . TELEPHONE NUMBER OF AUTHORIZED GOVERNMENT REPRESENTATIVE
37. CHECK NUMBER
FINALPARTIALCOMPLETE
36. PAYMENT35. AMOUNT VERIFIED
CORRECT FOR
34. VOUCHER NUMBER
FINAL
33. SHIP NUMBER
PARTIAL
38. S/R ACCOUNT NUMBER 39. S/R VOUCHER NUMBER 40. PAID BY
41a. I CERTIFY THIS ACCOUNT IS CORRECT AND PROPER FOR PAYMENT
41b. SIGNATURE AND TITLE OF CERTIFYING OFFICER 41c. DATE
42a. RECEIVED BY (Print)
42b. RECEIVED AT (Location)
42c. DATE REC'D (YY/MM/DD) 42d. TOTAL CONTAINERS
STANDARD FORM 1449 (REV. 2/2012) BACK
Prescribed by GSA – FAR (48 CFR) 53.212
AUTHORIZED FOR LOCAL REPRODUCTION
PREVIOUS EDITION IS NOT USABLE
SEE SCHEDULE
20.
SCHEDULE OF SUPPLIES/ SERVICES
21.
QUANTITY UNIT
22. 23.
UNIT PRICE
24.
AMOUNT
19.
ITEM NO.
Section A - Solicitation/Contract Form
SYNOPSIS / SOLICITATION
This is a combined synopsis/solicitation for commercial items prepared in accordance with the format in subpart
12.603 as supplemented with additional information included in this notice. This announcement constitutes the only solicitation, proposals are being requested and a written solicitation will not be issued.
The solicitation number for this acquisition is W912DQ21R1015 and it is being issued as a Request for Quotes
(RFQ).
Offers are due on February 7, 2021 at 3:00 PM Local Time. Offers shall be submitted in PDF via e-mail to jeri.l.halterman@usace.army.mill . All offers must be good for at least 90 days from offer due date. If you have any questions please contact Mrs. Jeri Halterman at jeri.l.halterman@usace.army.mil or 816- 389-2198.
The solicitation documents and incorporated provisions and clauses are those in effect through Federal Acquisition Circular (FAC) 2005-84.
This synopsis/solicitation will be awarded as a 100% Small Business Set-aside and the associated North American Industry Classification system (NAICS) code is 561730, “Landscaping Services” and the business size standard is $8,000,000.00.
Product/Service Code: F014 Natural Resources – Conservation – Tree Thinning
Description of Services Required: The U.S. Army Corps of Engineers Kansas City District has a need for Herbicide Application Service, at the Perry Lake Project, in Jefferson County, Kansas. The contractor shall provide all personnel, equipment, supplies, facilities, transportation, tools, materials, supervision, and other items and non-personal services necessary to perform the Herbicide Application Services as defined in this Performance Work Statement except for those items specified as government furnished property and services.
The Contractor shall comply with all Federal, state, and local laws, ordinances, statutes and regulations pertaining to the provided services.
Place of Contract Performance: Jefferson County, Kansas 66073
Far 52.212-1, Instructions to Offerors- Commercial does apply to this acquisition with no addenda to the provision and is located in Section L of this combined synopsis/solicitation.
Far 52.212-2, Evaluation - Commercial Edited does apply to this acquisition with no addenda to the provision and is located in Section M of this combined synopsis/solicitation.
FAR 52.212-3, Offeror Representations and Certifications -- Commercial Items, does apply to this acquisition with no addenda to the provision, and is located in Section K of this combined synopsis/solicitation.
FAR 52.212-4, Contract Terms and Conditions - Commercial Items, does apply to this acquisition with no addenda to the provision. These specific clauses required are located in Section I of this combined synopsis/solicitation.
FAR 52.212-5, Contract Terms and Conditions - Required to Implement Statutes or Executive Orders- Commercial Items, applies to this acquisition. These specific clauses required are located in Section I of this combined synopsis/solicitation.
Additional contract requirement(s) or terms and conditions are located in Section J of this combined synopsis/ solicitation.
In accordance with FAR 52.212-1(k) the prospective awardee shall be registered and active in https://beta.sam.gov/ for their System Award Management (SAM).
PLEASE NOTE: SAM.GOV procedures have been changed as of 8 November 2019. Interested vendors must go to beta.SAM.gov to register in SAM and to review current notices or announcements.
Contractors may obtain information on registration and annual confirmation requirements via the Internet at https://beta.sam.gov/ or by calling (866) 606-8220.
The beta System for Award Management (SAM) is a Federal Government owned and operated free web site. If you are a small business needing assistance with registering or help with navigating through the website you may contact the Association for Procurement Technical Assistance Centers for help with actions such as beta.SAM.gov registration.
If you have questions about Government procurements in general or need assistance in the preparation of your proposal, a local Procurement Technical Assistance Center (PTAC) may be able to help. The Procurement Technical Assistance Program was authorized by Congress in 1985 in an effort to expand the number of businesses capable of participating in the Government marketplace. To locate a PTAC near you, go to http://www.aptac-us.org/sam-registration/
Section B - Supplies or Services and Prices
ITEM NO SUPPLIES/SERVICES QUANTITY UNIT UNIT PRICE AMOUNT
0001 1 Season Herbicide Application - Base Period
FFP
The contractor shall furnish all herbicide applications services at Perry Lake as defined in the Performance Work Statement (PWS) located in Section C of this contract. The period of performance (POP) for the work to be performed is 1 April 2021 through 30 September 2021.
FOB: Destination
PSC CD: F014
NET AMT
0002 1 Season OPTION Herbicide Application-Option Period 1
FFP
The contractor shall furnish all herbicide application services at Perry Lake as defined in the Performance Work Statement (PWS) located in Section C of this contract. The period of performance (POP) for the work to be performed is 1 April 2022 through 30 September 2022.
0003 1 Season OPTION Herbicide Application-Option Period 2
FFP
The contractor shall furnish all herbicide application services at Perry Lake as defined in the Performance Work Statement (PWS) located in Section C of this contract. The period of performance (POP) for the work to be performed is 1 April through 30 September 2023
Section C - Descriptions and Specifications
PERFORMANCE WORK STATEMENT
HERBICIDE APPLICATION SERVICES
PERRY LAKE PROJECT, PERRY, KANSAS
Performance Work Statement
C.1.1 General Information: Perry Dam is located three (3) miles north of Perry, Kansas in Jefferson County, at mile 5.3 of the Delaware River in the northeast portion of the state. It is situated within 50 miles of one-third of the state’s population. Three of the state’s four metropolitan areas are in close proximity to the lake: Topeka, Kansas City, and Lawrence. Due to the lake’s proximity to these population areas, the lake will continue to receive high use.
C.1.2 Scope of Work
The Contractor shall provide all labor, equipment, fuel, materials and supplies, and supervision necessary to accomplish vegetative management services at the Administration Area, Dam Area, Outlet Park, Thompsonville Park, Rock Creek Park, Old Town Park, Old Military Trail Park, Longview Park, Slough Creek Park, Perry Park, and the Perry ATV Riding Area of the Perry Lake in Jefferson County, Kansas. Services shall be completed as described in this Performance Work Statement (PWS) and elsewhere in the contract. The Contractor shall perform tasks listed in Section C-10.
Acceptable performance standards and current regulations are provided for each task.
The Contractor shall monitor performance and ensure compliance in accordance with the terms and conditions.
C.1.2.1 Dates and Hours of Performance: April 1 through 30 September of each year during this contract. All work shall be performed Monday through Thursday between the hours of 7:00 a.m. and 7:00 p.m. and Friday between the hours of 7:00 a.m. and 12:00 p.m. No work will be performed on weekends or holidays. Each individual work item shall be performed pursuant to the schedule for that work item set forth in Section C-5. Services rendered outside the time periods specified shall not be compensated unless specifically approved in writing by the Contracting Officer or his authorized representative.
C.1.2.2 Pre-Award Site Visit: During open period for proposals, it is highly recommended contractor representative schedule site visit to better understand scale of work to be accomplished.
C.1.3 Post-Award Conference
After award, but prior to commencement of work, the Contractor shall contact the Contracting Officer’s Representative, to arrange a mutually agreeable time to meet at the Perry Project Office to review the contract requirements and details of the work.
C.1.4 Quality Control
C.1.4.1 The Contractor will develop a Quality Control Plan designed to demonstrate how the Contractor will meet the needs of the project. The Quality Control Plan will document how well the Contractor is meeting these needs and will be submitted for approval prior to work on this contract.
C.1.4.2 An inspection system covering all work tasks stated in the contract to include supplies. Said inspection system shall include a check-off sheet for personnel to fill out each time an area is sprayed. It shall specify areas to be sprayed and inspected on a per-spraying basis and satisfaction of compliance by Corps quality assurance personnel.
C.1.4.3 A method of identifying deficiencies in the quality of services performed before the level of performance becomes unacceptable. The contractor shall use process control procedures and quality data analysis techniques.
C.1.4.4 Corrective action procedures for deficiencies and measures to prevent recurrence: The corrective actions will address the deficiency and an action to prevent future deficiencies. Additional inspection(s) is/are not considered a corrective action.
The Quality Control Plan shall be evaluated for adequacy and changed or updated by the contractor as a part of all corrective actions by the contractor.
C.1.5 QUALITY ASSURANCE
C.1.5.1 Quality Assurance Surveillance Plan: A Quality Assurance Surveillance Plan (QASP) will be used during the life of the contract to ensure that the Service Provider is performing the services required by this PWS in an acceptable manner. The Government develops the QASP and the Project Office administers the Plan through Quality Assurance Evaluators (QAEs).
C.1.5.2 The government has the right to inspect and test all services called for by the contract, to the extent practicable at all times and places during the term of the contract.
The government will perform inspections and tests in a manner that will not unduly delay the work.
C.1.5.3 Contractor understands that the QASP is solely for the benefit of the Government in ensuring the contractor completes its required work in accordance with this contract. Government officers shall never exercise supervision over the contractor’s employees and any defects noted shall be brought to the attention of contractor’s designated representative. Failure of the Government to identify a defect shall not constitute waiver of the Government’s rights concerning that defect.
C.1.5.4 In the event of unsatisfactory performance of specified work, the Contractor may be directed to re-perform the unsatisfactory services at no additional cost to the Government. Re-performance as directed by the Government shall be completed within two (2) days. Failure of the Contractor to perform the work as specified, or to reperform work as directed within the allotted time, may result in reduction of the contract price in proportion to the portion(s) of the work not accomplished. Amounts to be withheld will be determined by prorating the amount of services satisfactorily performed against the amount of services required. When the defects in services cannot be corrected by re-performance, the government may (1) require the contractor to take necessary action to ensure that future performance conforms to contract requirements;
and (2) reduce the contract price to reflect the reduced value of the services performed.
Payment will not be made for work not performed or not performed to standard.
Payment will be made when spraying(s) and inspection(s) is/are completed. It will be the Contractor’s responsibility to ensure that the 96% control level is achieved prior to the submission of the invoice to the Perry Project Office. Payment will not be made until it is mutually agreed that the control level has been met. If the contractor fails to promptly perform the services again or to take the necessary action to ensure future performance in conformity with contract requirements, the government may: (1) by contract, or otherwise, perform the services and charge to the Contractor any cost incurred by the government that is directly related to the performance of such service or
(2) terminate the contract in whole or in part.
C.1.5.5 Performance by Third Party or Government Personnel: In addition to the above remedies for nonperformance, the Government reserves the right to cause the specified work to be performed by a third party or Government personnel and the cost incurred thereby will be levied against the Contractor. Any time Government personnel are used because of Contractor’s nonperformance, the cost levied against the Contractor will include all direct costs associated with the performance of the specified work. Government personnel will be used only when time is of the essence and the interests of the Government would not be served by securing a third party to perform the specified work.
C.1.6 Coordination with the Project Office
C.1.6.1 As each item of work is completed, the Contractor’s representative at the job shall enter the time that the item of work was completed on a Contractor’s Daily Worksheet (See example, Section C.11.2). Completed and signed worksheets shall be delivered to the Contracting Officer’s Representative (or his/her designee) each day services are performed.
C.1.6.2 Day-to-day contact with Government personnel and telephone communication shall normally provide adequate information exchange. The Government reserves the right to schedule meetings at the Project Office as necessary to insure strict compliance with the terms of this contract. Such meetings shall be scheduled, to the extent possible, at mutually convenient times. However, upon notice, the Contractor shall attend meetings regarding matters affecting this contract and the time spent in such meetings shall be at no additional charge to the Government.
C.1.6.3 To assist the visiting public in reclaiming lost articles, all property left by visitors and found during spraying operations shall be turned in to the Project Office.
C.1.6.4 Any evidence of vandalism, instances of facilities not operating properly, or are in need of repair, shall be promptly reported to project personnel.
C.1.7 Insurance: In accordance with FAR 52.228-5, Insurance-Work on a Government Installation, the contractor shall obtain and maintain the following insurance policies during the period of performance under this contract and shall provide proof of insurance to the Contracting Officer’s Representative prior to commencement of duties:
Worker’s Compensation Coverage complying with applicable State Statute Employer’s Liability Minimum amount of $100,000 per occurrence Commercial General Liability Minimum amount of $100,000 per person, $300,000 per occurrence for bodily injury, & $20,000 per accident for property damage.
Motor Vehicle Liability Minimum amount of $100,000 per person, $300,000 per occurrence for bodily injury, & $20,000 per accident for property damage.
NOTE: Coverage required (above) are minimums. If higher limits of coverage are required by state statute, the contractor shall be responsible for obtaining such additional coverage.
C.1.8 Licensing: It shall be the responsibility of the Contractor to comply with all Federal,state, and local laws governing health, training, operational, and licensing requirements as may be applicable and required for application of commercial pesticide (including OSHA Hazard Communication Standard 29 CFR 1910.1200).
The Contractor's employee applying chemicals under this contract shall possess an appropriate COMMERCIAL APPLICATOR'S LICENSE acceptable to the state in which work is to be accomplished. However, an applicator may be unlicensed if allowed by law and if closely supervised by an immediate, onsite supervisor who is licensed in accordance with the above requirement.
C.1.9 Contractor Personnel
C.1.9.1 All Contractor personnel shall be fully clothed, at all times, while performing these services. “Fully clothed” shall be deemed to mean that a shirt (or T-shirt), trousers and shoes shall be worn at all times, except that this requirement shall not be construed to replace or eliminate the necessity for the wearing of appropriate protective clothing or devices as may be required for the application of various chemicals.
Clothing shall be clean and neat in appearance.
C.1.9.2 Contractor personnel shall utilize tact, diplomacy, and courtesy at all times during contact with the public. The contractor or any of his or her employees shall not consume any alcohol or drugs (except prescription drugs) during duty hours or within the eight (8) hour period next preceding duty hours.
C.1.9.3 The Contractor shall designate, in writing, a responsible member of each work crew who shall serve as the contact for matters involving quality and performance of the required work assigned to that crew. The employee(s) designated in accordance with the above requirement shall be qualified and fully competent and shall insure that the work described herein is performed in accordance with these specifications. The Contractor shall furnish the above written designation to the Contracting Officer’s Representative at the project the first day that an individual is a “responsible party.” The designation shall include the name(s), address(es), and telephone number(s) of the responsible individual(s).
C.1.9.4 Employee Qualifications; Background Checks: Only U.S. Citizens, lawful resident aliens, and persons holding a valid work visa are permitted to work on this contract. The contractor shall submit to the Corps the names of each foreign national proposed for performance under this contract/task order, along with documentation to verify that he/she was legally admitted into the United States and has authority to work in the U.S. All contractor employees and subcontractors will also submit to the Contracting Officer’s Representative a background check investigation prior to beginning work.
C.1.10. Safety Requirements Prior to beginning work on the Contract, the Contractor shall have an approved Accident Prevention Plan. This plan shall be in accordance with the most recent EM 385-1-1 (See Section C.11 Applicable Forms and Publications). The plan is intended to be a viable document and enhance the safety of Project staff and visitors. The Contractor will be expected to take a vital interest in safety, hazard, and educate their employees to work and plan their work safely. Proper driving techniques and defensive driving will be practiced to prevent vehicle accidents and property damage. All vehicles will comply with all local, state and federal laws and be operated on roadways at all times.
C.1.11 Required Submissions: The Contractor shall submit the following documents to the Contracting Officer's Representative at the Project Office:
(1) Insurance: Proof of requirement insurance in the form of a copy of the insurance policy or a binder issued by the insurer, to be delivered no later than the pre-work conference or prior to the start of the contract period.
(2) Licensing: Proof of proper licensing, to be delivered no later than the start of the contract period.
(3) Chemical Labels: A label for each chemical being utilized under this contract, to be delivered no later than the pre-work conference.
(4) OSHA Compliance: Evidence of compliance with OSHA Hazard Communication Standard 29 CFR 1910.1200, to be delivered not later than the pre-work conference, as follows:
(a) A hazardous material inventory of all materials used on the contract.
(b) Safety Data Sheets (SDS's) for all materials listed in the inventory.
(c) A procedure to ensure that all containers are properly labeled.
(d) A written hazard communication program which includes employee training and methods of communicating hazards and protective measures to employees and others.
(5) Designation of "responsible party" in accordance with C.1.9.3.
(6) Background checks and proof of authority to work in the U.S. for all proposed employees in accordance with C.1.9.4.
The Contractor will NOT be allowed to proceed on this contract until all the above-required submissions have been furnished.
C.2.0 Identification of Contractor Personnel: Two types of identification are required for each employee and subcontractor who will provide services on the contract: (a) a tamper-proof laminated identification card that identifies the name of the contractor’s company, a clear employee photograph at least 1 by 1 ¼ inches, the employee’s typed name, signature, date of birth, eye color, sex, height, and weight, and the signature, date and phone number of the company representative issuing the card, and (b) a valid U.S. Photo ID that shows the individual’s name, photograph, and signature; acceptable photo IDs include American driver’s license, State identification cards, passports, and resident alien cards (green cards). The company ID shall be worn in a conspicuous place and both types of ID shall be carried on the person of the employee and made available for inspection, upon request by any Government representative or member of the public.
C.2.1 Other Contractors The Government may undertake or award other contracts for additional work, and the Contractor shall fully cooperate with such other contractors and Government employees. All work must be carefully planned and fitted not to interfere with such other work. The Contractor shall not commit or permit any act that will interfere with the performance of work by other contractors or by Government employees.
C.2.2 ANTITERRORISM/OPERATION SECURITY REQUIREMENTS
All contractor and all associated sub‐contractors employees shall comply with applicable installation, facility and area commander installation/facility access and local security policies and procedures (provided by government representative). The contractor shall also provide all information required for background checks to meet installation access requirements to be accomplished by installation Provost Marshal Office, Director of Emergency Services or Security Office. Contractor workforce must comply with all personal identity verification requirements as directed by DOD, HQDA and/or local policy. In addition to the changes otherwise authorized by the changes clause of this contract, should the Force Protection Condition (FPCON) at any individual facility or installation change, the Government may require changes in contractor security matters or processes.
All contractor and all associated sub‐contractors employees will receive a CORPS Watch information paper (provided by the authorized government representative) and provide a written acknowledgement to the COR, no later than 30 calendar days after contract start date or effective date of incorporation of this requirement into the contract.
The Contractor must pre‐screen candidates using the E‐verify Program (http://www.dhs.gov/E‐Verify) website to meet the established employment eligibility requirements. The vendor must ensure that the candidate has two valid forms of government issued identification to ensure the correct information is entered into the Everify system. An initial list of verified/eligible candidates must be provided to the COR no later than 3 business days after the initial contract award.
Per the E-Verify Website the following exemptions apply:
Employers whose contracts are exempt from the E-Verify federal contractor rule are not required to enroll in E-Verify. A contract is considered exempt if any one of the following applies: (1) It is for fewer than 120 days. (2) It is valued at less than $150,000, the simplified acquisition threshold (Source: http://www.uscis.gov/everify/federalcontractors/ exemptions-and-exceptions).
All contract employees, including subcontractor employees who are not in possession of the appropriate security clearance, will be escorted in areas where they may be exposed to classified and/or sensitive materials and/or sensitive or restricted areas.
C.3 Definitions
ALP: Acceptable Level of Performance
Contracting Officer’s Representative means an individual designated and authorized in writing by the contracting officer to perform specific technical or administrative functions.
Fully-Clothed: Deemed to mean that a sleeved shirt (or T-shirt), trousers, and shoes shall be worn at all times. Clothing shall present a professional appearance and shall not be ripped, torn, or dirty. Clothing shall also contain logos or badges that clearly identify the wearer as a contractor employee. These requirements shall not be construed to replace or eliminate the necessity for the wearing of appropriate protective clothing or devices as may be required for the application of various chemicals.
PWS: Performance Work Statement
Quality Assurance (QA): A method used by the Government to provide some measure of control over the quality of purchased goods and services received.
Quality Control (QC): A method used by the Contractor to control the quality of goods and services provided.
Vegetative Free: An area is considered vegetative free if 95% of all plants within a treated area die within 5 days after application of herbicide.
C.4 Government-Furnished Materials and Supplies: The Government will furnish the following consumable items to the Contractor. The Government will retain control of expendables, to be dispensed on an as-needed basis for use in performance of the contract.
1. Water
2. Contractor Daily Worksheets
3. Herbicide Application Report Form
C.5 Contractor-Furnished Equipment and Supplies
The Contractor shall furnish all equipment and supplies to execute this contract that are not specifically identified in Section C.3 of this PWS as Government-Furnished supplies and equipment or specifically identified in the section. Equipment breakdown shall not relieve the Contractor of the responsibility of performing the work as specified. It shall be the responsibility of the Contractor to assure that he/she has, or can obtain on short notice, sufficient backup equipment to continue the services as specified without interruption in the event of mechanical failure of his primary equipment.
C.6 Specific Tasks
C.6.1 General Information The Contractor shall provide all manpower, equipment, fuel, tools, materials and supplies, and supervision and other items and service necessary to perform all tasks and functions identified in the section except as specified in Section C.4 as Government Furnished equipment and supplies.
C.6.1.2 The Contractor shall establish a work schedule indicating the days and hours during which services will be performed on a regular basis. The schedule shall be submitted in writing to the Contracting Officer or his authorized representative for approval no later than the first week of work. Changes in the approved schedule shall be submitted for approval prior to implementing the change.
C.6.1.3 Apply herbicide to all areas listed under the Herbicide Application sites. In most cases, the end result should be a clean, vegetative free area.
C.6.1.4 The Contractor will be responsible for selecting the appropriate herbicide to be used based on site location, proximity to the public, environmental concerns, target species, and best commercial practices. All herbicides shall be approved by USEPA and the State of Kansas, and shall be approved by the COR prior to application.
Information in the form of labels and brochures will be provided to the government regarding the chemical(s) to be used prior to application. Biodegradable blue dye will be used as a marker.
C.6.1.5 The Contractor shall provide and maintain at least a 96% vegetative free control of all serviced areas during the growing season (April through September). Should the level of control fall below 96%, the Contractor will be responsible for the retreatment of the subject area(s) to achieve the desired result at no additional cost to the Government. It is the obligation of the Contractor to make sufficient site visits to verify results throughout the growing season and performance periods.
C.6.1.6 The serviced areas will present a neat, even kill of all target species. Spray patterns will provide an even border between treated and untreated areas. A 1-foot (approx.) vegetative free border will be left around all hard-surfaced or rocked facilities (i.e. pads, parking lots, etc.).
C.6.1.7 There will be no work on days when the wind exceeds 15 mph in developed areas or when wet weather could affect the application. It will be the Contractor’s responsibility to check with the project office regarding weather conditions prior to application. The Government reserves the right to halt spraying operations should weather conditions, in the opinion of the COR, warrant.
C.6.1.8 The Government will provide water, at specified locations, for tank filling. The Contractor will provide hoses and backflow-preventers. Clean out of chemical tanks and disposal of chemical containers will not be permitted on Government property. The Contractor will have spill kits available on all vehicles used on Government property that will insure adequate coverage of the type and quantity of chemical(s) used. Contractor employees will be trained in the use of these kits and are expected to aggressively implement their use in the event of a spill.
C.6.1.9 The Contractor will be responsible for any damage to non-target species. The Contractor shall replace any non-target species accidentally killed with an equivalent plant or tree as approved by the Contracting Officer, and shall plant the replacement and provide a one-year guarantee of survival of the replacement.
C.6.1.10 The Contractor will complete a herbicide application report form (furnished by the Government) after all chemical applications whether initial or follow-up. Payment will not be made until the completed forms are provided.
C.6.1.11 In the event that an area is missed or is not serviced, the Contractor agrees to return and re-perform the unsatisfactory or missed services immediately upon receipt of notice from the Contracting Officer or his representative.
C.6.1.12 Services shall be performed so as to provide the desired vegetation-free appearance during the growing season (1 March through 30 September). Application of pre-emergent may begin as early in the year as weather conditions allow.
C.6.1.13 The Contractor shall treat sewage lagoons for 100% control of aquatic vegetation such as Duckweed, growing within the lagoons. The Contractor will schedule and perform this application at the time when it shall be the most effective in controlling target species for the season
C.7 Inspection and Sampling Prior to beginning each item involving chemical application, the Contractor (or his authorized representative) shall notify the Contracting Officer Representative of the times he will begin mixing and applying chemicals (in order to permit inspection by Government personnel of the mixing and application methods).
C.8 Alternate Chemicals, Rates of Application or Mix Ratios Application of chemicals shall be in accordance with label direction for the material used. When other than anticipated pests or disease is encountered, or when it is the professional opinion of the Contractor that the use of different mix ratios, rates of application, or chemicals other than those specified will produce better results, the Contractor may request permission for their use. Any such request shall be in writing and shall specify the chemical, its uses, rates of application and cost. A label for the requested chemical shall be furnished with the Contractor’s request. Requests shall be submitted to the Project Manager at least 30 days prior to intended use. If granted, permission for the use of an alternate mix ratio, rate of application, or chemical will be in writing from the Contracting Officer or his authorized representative. Chemicals, rates, or mixture ratios other than those specified will not be used in the absence of the above specified request and approval. When the use results in an increase or decrease in Contractor cost or time, an equitable adjustment will be made to the contract price, through the issuance of a contract modification.
C.9 Measurement Exact limits of chemical application shall be as directed by the Contracting Officer or his designated representative at the Project. All acreages and quantities are approximate.
It shall be the responsibility of the Contractor to determine exact quantities and conditions affecting performance of this work.
C.10 Coverage
Bid items indicating “full coverage” shall receive chemical treatment of the entire area.
Bid items indicating “spot treatment” shall receive chemical treatment of targeted vegetation only.
C.11 Performance Requirements Summary
Required Service Standard Performance
Requirements (Acceptable Level of Performance)
Methods of Surveillance
Quality Control Refer to C.1.4 96% Compliance
(4% Maximum defective allowed)
-Periodic Inspection by Government -Public Visitor Complaint
Specific Tasks Refer to C.6 99% Compliance
(4% maximum defective allowed)
-Periodic Inspection by Government
-Public Visitor Complaint
Safety Refer to C.1.10 96% Compliance
(4% maximum defective allowed)
-Periodic Inspection by Government
-Public Visitor Complaint
C.12 Service Facilities/Areas
Dam and Outlet Area:
1. Spot treatment of vegetation on face of dam, from water line to guardrail and grass line to guardrail.
2. All wicks, extensions, collector ditches, and rock areas on both sides of the outlet structure
3. Guard rail along upper dam road
4. West dam parking lot and guardrail
5. Lower dam road guardrail
6. Relief well drainage ditch
7. Outlet stilling basin riprap and outlet channel riprap running from spillway road and downstream
8. Outlet east parking lots (including curb stops and fencing) and trash containment area
9. Outlet east day use shelter, shelter parking lot, and shelter sidewalk
10. Outlet east vault toilet sidewalk
11. Outlet west vault toilet sidewalk, parking lots (including curb stops and fencing) and trash containment area
12. Gravel parking lots running parallel of Delaware River in outlet west day use area
13. Delaware Marsh Cul-de-sac
14. ATV Area Parking lot/curbing/trash containment area
15. ATV Area shelter/shelter sidewalk
16. ATV Area bathroom sidewalk
17. Base of all sign posts (12 inch diameter at base of all posts)
Administration Area:
1. Levee rip rap (all rocked areas)
2. Volunteer camp sites
3. Administration area perimeter fencing, parking lots and sidewalks
4. Weather Station
5. Dedication Point parking lots/playground border where composite edging is present/shelter/sidewalk/any sand areas
6. Administration vault toilet parking lot and sidewalk
7. Rip rap between dedication point parking lot and the lake
8. Base of all sign posts (12 inch diameter at base of all posts)
Perry Park:
1. Beach shelter, parking lot, curbing, and trash containment area
2. Beach restroom sidewalks
3. Sidewalk leading to beach
4. All sidewalks/splash pad areas around outdoor showers
5. Beach perimeter, clear delineation between sand and grass
6. Beach volleyball court and swings, and all sand area
7. Vegetation between lakeshore and beach parking lot
8. All areas with rip rap rock
9. Radio Tower – spray all gravel areas and along fence perimeter
10. Base perimeter of water tower
11. Base of all sign posts (12 inch diameter at base of all posts)
Slough Creek Park:
1. Fee Booth, Entrance Dump Station, and trash containment area
2. Bur Oak Camp Loop (sites 1 – 39)
- Bur Oak Camp Restroom parking lot and sidewalk
- Trash containment area
3. Locust Camp Loop (sites 1 – 24)
- Locust Camp restroom parking lot and sidewalk
- Trash containment area
4. Lagoon Fence (lagoon located between Locust loop and Worthington loop) and Lagoon to control aquatic vegetation.
5. Worthington Camp Loop (sites 1 – 86)
- Worthington Camp restrooms parking lots and sidewalks (x4)
- Worthington Camp Shower House parking lot and sidewalk
- Worthington Dump Station and trash containment area
- Worthington Boat Ramp and boat ramp parking lot and all rip-rap around boat ramp (minimum 15 feet from edge of boat ramp lanes from the start of the launch lanes to the water’s edge)
- Trash containment area
- Playground parking lot
- Playground border where composite edging is present
6. Lagoon Fence (lagoon located between Worthington loop and South Point loop) and Lagoon to control aquatic vegetation.
7. South Point Camp Loop (sites 1 – 90)
- South Point Camp restrooms and sidewalks (x5)
- Trash containment area
8. Limestone Cove Camp Loop (sites 1 – 16)
- Limestone Cove bathroom parking lots and sidewalks (x1)
9. Slough Creek Park Group Camp West parking sites/curbing/shelter/trash containment area and restroom
10. Slough Creek group camp shower house sidewalk and parking lot
11. Lagoon fence (lagoon located between group camps) and lagoon to control Aquatic vegatation
12. Slough Creek Thunder Ridge Trail head parking lot
13. Slough Creek Devil’s Gap Boat Ramp and parking lot, curbing, all rip-rap around boat ramp (minimum 15 feet from edge of boat ramp lanes from the start of the launch lanes to the water’s edge), and trash containment area
14. Slough Creek Perry lake trail trailhead parking lot
15. Base of all sign posts and campsite marker posts (12 inch diameter at base of all posts)
Longview Park:
1. Volunteer campsite
2. Electric Group Camp area gravel roadway
3. Electric Group Camp area campsites (26 individual sites)
4. Primitive ground camp area parking sites
5. Primitive Group Camp area bathroom parking sites and sidewalks.
6. Primitive group camp area roads
6. Lagoon Fence and lagoon to control aquatic vegetation
7. Longview shower house parking lot and sidewalk
8. Longview dump station and trash containment area
9. Disc Golf Course parking lot
10. Longview Boat Ramp/boat ramp parking lot/and boat ramp sidewalk, rip rap along shore between parking lot, all rip-rap around boat ramp (minimum 15 feet from edge of boat ramp lanes from the start of the launch lanes to the water’s edge) curbing, and trash containment area
11. Guardrails leading into the park
12. Base of all sign posts and campsite marker posts (12 inch diameter at base of all posts)
13. Access road into campground
Slough Creek Bridge Boat Ramp
1. Boat ramp parking lot, curbing, self-pay station/information center, vault toilet sidewalk, trash containment area, and all rip-rap around boat ramp (minimum 15 feet from edge of boat ramp lanes from the start of the launch lanes to the water’s edge)
2. Base of all sign posts and campsite marker posts (12 inch diameter at base of all posts)
Old Military Trail
1. Trailhead parking lot and guardrails
2. Base of all sign posts (12 inch diameter minimum at base of all posts)
Old Town Park:
1. Old Town Boat Ramp/boat ramp parking lot/rip rap surrounding boat ramp/upper parking lot, curbing, and trash containment area
2. Old Town Boat Ramp bathroom sidewalk
3. Old Town Campground A loop (sites 1 – 18)
4. Old Town Campground B loop (sites 1 – 4)
5. Removed
6. Removed
7. Old Town Campground E loop (sited 1-15)
8. Lagoon to control aquatic vegetation
9. Old Town bathroom sidewalk near “D” loop
10. Old Town shower house parking lot and sidewalks
11. Lagoon, Ball Field, ball field fence
12. Spray all sand areas in the playground
13. Gravel parking lot in “E” loop
14. Gravel parking lot in A loop
15. Removed
16. Gravel parking lot at baseball field
17. Base of all sign posts and campsite marker posts (12 inch diameter at base of all posts)
Rock Creek Park:
1. Big Rock camping loop and parking spots
2. Edwardsville Tent Camping parking lot
3. Edwardsville bathroom and bathroom sidewalks
4. Edwardsville trash containment area
5. Peninsula Campground shower house, shower house parking lot and sidewalks
6. Rock Creek Peninsula entrance area, dump station, and trash containment area
7. Peninsula Loop A (sites 1 – 26)
8. Peninsula Loop B (sites 27 – 62)
9. Peninsula Loop C (sites 63 – 78)
10. Peninsula bathroom sidewalk located in Loop C
11. Parking lots in Peninsula loop and main access road in park
12. Whippoorwill Campground (sites 1 -14)
13. Whippoorwill bathroom sidewalk15. Walnut Grove Cove drive and parking lot
16. Walnut Grove Cove bathroom and bathroom sidewalk
18. Guard rails throughout campground
19. Playground parking lot and playground border where composite edgings if present
20. Base of all sign posts and campsite marker posts (12 inch diameter at base of all posts)
21. Lagoon perimeter fence and lagoon to control aquatic vegetation
22. All rip rap rock areas along road edges from asphalt to the end of the rip rap/grass line.
23. All rip rap rocked drainage ditches or waterways.
Rock Creek Day Use Area:
1. Rock creek day use shelter/shelter sidewalk/shelter parking lot on lower road
2. Rock Creek Boat Ramp, boat ramp parking lot, self-pay station, curbing, shelter, shelter parking, trash containment area, and all rip-rap around boat ramp (minimum 15 feet from edge of boat ramp lanes from the start of the launch lanes to the water’s edge)
3. Rock Creek Vault Toilet sidewalk at boat ramp
4. Base of all sign posts (12 inch diameter at base of all posts)
Thompsonville Park:
1. Dump Station
2. Restroom, parking lot, and sidewalk
3. Lagoon Fence and lagoon to control aquatic vegetation
4. Shelter, shelter parking lot
5. Gazebo
6. Vault toilet, parking lot, and sidewalk
7. Trash containment area
8. Base of all sign posts (12 inch diameter at base of all posts)
C.12 Applicable Publications and Forms
C.12.1 Information on Perry Lake can be found on the Internet at:
http://www.nwk.usace.army.mil/pe/
C.12.2 Contractor’s Daily Worksheet:
Pesticide Use Report Date:
Applicator:
Applicator Certification #:
Type of Chemical Sprayed:
Amount of Chemical Sprayed:
Location of Area Sprayed:
Target of Spraying:
C.12.3 OSHA Hazard Communication Standard 29 CFR 1910.1200 C.12.4 Engineer Manual (EM) 385-1-1 (Safety)
The above referenced manuals are hereby incorporated by reference and the contractor is required to perform this contract in accordance with the standards set forth therein.
(End of Performance Work Statement)
Section E - Inspection and Acceptance
INSPECTION AND ACCEPTANCE TERMS
Supplies/services will be inspected/accepted at:
CLIN INSPECT AT INSPECT BY ACCEPT AT ACCEPT BY
0001 Destination Government Destination Government 0002 Destination Government Destination Government 0003 Destination Government Destination Government
Section F - Deliveries or Performance
DELIVERY INFORMATION
CLIN DELIVERY DATE QUANTITY SHIP TO ADDRESS DODAAC /
CAGE
0001 POP 01-APR-2021 TO
30-SEP-2021
N/A USACE, KANSAS CITY +
JASON HURLEY
PERRY LAKE PROJECT OFFICE 10419
PERRY PARK DR
PERRY KS 66073
816-389-3035
966218
0002 POP 01-APR-2022 TO
30-SEP-2022
N/A (SAME AS PREVIOUS LOCATION)
0003 POP 01-APR-2023 TO
30-SEP-2023
N/A (SAME AS PREVIOUS LOCATION)
Section H - Special Contract Requirements
AT-OPSEC
ANTITERRORISM/OPERATION SECURITY REQUIREMENTS
All contractor and all associated sub-contractors employees shall comply with applicable installation, facility and area commander installation/facility access and local security policies and procedures (provided by government representative). The contractor shall also provide all information required for background checks to meet installation/facility access requirements to be accomplished by installation Provost Marshal Office, Director of Emergency Services or Security Office. Contractor workforce must comply with all personal identity verification requirements (https://www.ecfr.gov/cgi-bin/text-idx?rgn=div8&node=48:2.0.1.1.1.2.1.28 ) as directed by DOD, HQDA and/or local policy. In addition to the changes otherwise authorized by the changes clause of this contract, should the Force Protection Condition (FPCON) at any installation or facility change, the Government may require changes in contractor security matters or processes.
Contractor and all associated sub-contractors employees shall comply with adjudication standards and procedures using the National Crime Information Center Interstate Identification Index (NCIC-III) and Terrorist Screening Database (TSDB) (Army Directive 2014-05 / AR 190-13), applicable installation, facility and area commander installation/facility access and local security policies and procedures (provided by government representative, as NCIC and TSDB are available), or, at OCONUS locations, in accordance with status of forces agreements and other theater regulations.
The Contractor must pre-screen Candidates using the E-verify Program (http://www.uscis.gov/e-verify ) website to meet the established employment eligibility requirements. The Vendor must ensure that the Candidate has two valid forms of Government issued identification prior to enrollment to ensure the correct information is entered into the Everify system. An initial list of verified/eligible Candidates must be provided to the COR no later than 3 business days after the initial contract award."
Per the E-Verify Website the following exemptions apply:
Employers whose contracts are exempt from the E-Verify federal contractor rule are not required to enroll in EVerify. A contract is considered exempt if any one of the following applies: (1) It is for fewer than 120 days. (2) It is valued at less than $250,000, the simplified acquisition threshold (Source: http://www.uscis.gov/e-verify/federalcontractors/exemptions-and-exceptions).
Section I - Contract Clauses
CLAUSES INCORPORATED BY REFERENCE
52.204-7 System for Award Management OCT 2018 52.204-9 Personal Identity Verification of Contractor Personnel JAN 2011 52.204-19 Incorporation by Reference of Representations and
Certifications.
DEC 2014
52.204-21 Basic Safeguarding of Covered Contractor Information Systems
JUN 2016
52.204-25 Prohibition on Contracting for Certain Telecommunications and Video Surveillance Services or Equipment.
AUG 2020
52.212-4 Contract Terms and Conditions--Commercial Items OCT 2018 52.223-2 Affirmative Procurement of Biobased Products Under Service and Construction Contracts
SEP 2013
52.223-4 Recovered Material Certification MAY 2008 52.223-17 Affirmative Procurement of EPA-Designated Items in Service and Construction Contracts
AUG 2018
52.232-38 Submission of Electronic Funds Transfer Information with Offer
JUL 2013
52.232-39 Unenforceability of Unauthorized Obligations JUN 2013 52.232-40 Providing Accelerated…
This is the start of the file's text. The full file is on GovTribe.
File details come from the government source that posted it. Updated .