STATEMENT OF WORK

FOR

A21-019 B52 Nose Cowl Foreign Object Debris (FOD) Removal Fixture

FOR

76 AMXG

OC-ALC/OBCA

04 February 2021

1.0 Scope:

The Contractor shall provide all labor, tools, equipment, material, parts, quality control and transportation necessary to provide fabrication, delivery, offloading, installation/assemble for two (2) B52 Nose Cowl Fod Removal Fixture in building 2121, addressed to the 565th AMXS Tool Crib on the Oklahoma City- Air Logistics Complex (OC-ALC). The Contractor shall also provide Personal Protective Equipment (PPE) and clothing, to include reflective clothing (belt, vest, etc); hearing and eye protection, to include prescription safety glasses; safety harnesses; fall protection equipment; lifting equipment and any incidentals necessary to perform the requirements of this Statement of Work (SOW).

1.1 The Contractor shall be responsible for insuring all services, parts and components provided under this contract are in IAW the terms and conditions outlined in this SOW.

1.1.2 The contractor shall make all necessary adjustments to the one (1) B52 Nose Cowl Fod Removal Fixture until it is fully operational in accordance with (IAW) the Technical POC (Engineering) specifications/drawing X201961718 and to what is stated in this Statement of Work (SOW).

1.2 Item Description:

76 AMXG/565 AMXS request the purchase of the following item (s):

· Fabricate two (2) X201961718 "B-52 Engine Nose Cowl FOD Removal Fixture" per drawing.

· The first article shall be made as a prototype.

· The second article shall be fabricated only after Engineering has validated and verified (val/ver) the first article and made any necessary changes to the design of the fixture.

· Installation

1.3 Required Services:

· Fabricate two (2) X201961718 "B-52 Engine Nose Cowl FOD Removal Fixture" per drawing.

· The first article shall be made as a prototype.

· The second article shall be fabricated only after Engineering has validated and verified (val/ver) the first article and made any necessary changes to the design of the fixture. An updated drawing will be furnished to the contractor if changes are made.

· The second article shall be delivered no more than sixty (60) days after Engineering has val/ver the first. Engineering shall val/ver the first article within thirty (30) days after delivery.

· Deliver fully assembled or the contractor shall fully assemble the fixtures upon delivery on-site.

· All substitutions or deviations from drawing must be approved by Technical POC (Engineering).

· Delivery shall be directly to Building 2121, addressed to the 565th AMXS Tool Crib.

· Contractor must have access to all standards or specifications referenced in the drawing.

· For the purposes of the correction of fabrication errors and/or discussion of design changes, the contractor shall be available for no more than three (3) on-site visits of one business day or less.

· Any operations manuals, technical information, instruction guidance, etc. included with Consumer Off-The-Shelf (COTS) items on the fixtures shall be furnished by the contractor to Engineering.

· All welders must be AWS Certified Welders (CW) with at least 5 years’ experience.

· Parts which include Geometric Dimensions and Tolerance (GD&T / GDT) must be fabricated by personnel who have received formal GD&T training with experience machining GD&T parts.

· Components which re-quire electrical wiring must be inspected by a licensed electrician. Contractor must have access to all standards or specifications referenced in the drawing.

1.4 Special Qualifications: The Contractor shall provide personnel with the following special qualifications:

· All welders must be AWS Certified Welders (CW) with at least 5 years’ experience.

· Personnel who have received formal GD&T training with experience machining GD&T parts.

· Licensed electrician

1.5 Training: Not required.

1.6 Environmental Protection & Safety: The Contractor shall be knowledgeable of and comply with all applicable federal, state and local laws, regulations, instructions and requirements regarding environmental protection and occupational safety and health. The Contractor shall comply with any laws, instructions or regulation changes during the term of this contract.

1.6.1 Contractors shall be compliant with Tinker Air Force Base (TAFB) Supplement to Air Force Instruction (AFI) 32-7086, “Hazardous Materials Management”, Tinker AFB procedures per Tinker Air Force Base Instruction (TAFBI) 32-7004, “Hazardous Waste Management”, and Complex procedures per Oklahoma City Air Logistics Complex (OC-ALC) Supplement to AFI 32-7086, “Hazardous Material Management” and OC-ALCI 32-101 “Air Quality Record Keeping Procedure”. Publications are available digitally on e-Publishing website at www.e-publishing.af.mil for downloading or ordering.

1.7 Safety Data Sheet (SDS) and Labeling: Upon GPOC receipt of the “No HAZMAT Usage” certification, the requirements of this section no longer apply.

1.7.1.

The Contractor shall not transport, ship or use any chemical, material or substance used in the performance of this purchase description on Tinker AFB before written approval is provided by 72 ABW/CEIE, Natural Infrastructure Management (Environmental Compliance). The Contractor shall submit to the GPOC, ten (10) calendar days after contract award date all Safety Data Sheets (SDSs) and a completed OC-ALC Form 152, SDS Information Sheet. The Contractor shall receive approval from the GPOC prior to shipping any chemical, material or substance to Tinker AFB. A copy of the manufacturer SDS shall accompany the shipment. Contractor shall comply with the effective dates for SDS requirements IAW the Occupational Safety and Health Administrations (OSHA) Hazardous Communication Standard, Title 29, Code of Federal Regulation (CFR) Part 1910.1200. The Contractor shall ensure containers of hazardous chemicals are labeled with the following information, prior to shipping to Tinker AFB IAW OSHA Hazardous Communication Standard, Title 29, CFR Part 1910.1200 (2012): product identifier; signal word; hazard statement(s); precautionary statement(s); pictogram(s); and name, address and telephone number of the chemical manufacturer, importer, or other responsible party. The GPOC will forward all SDS submittals to 72 ABW/CEIE for approval. A current manufacturer SDS shall be submitted to the GPOC if the Contractor changes manufacturer or vendor for any chemicals that were prior approved. The Contractor shall maintain copies of manufacturer SDSs for all chemicals and SDSs shall be readily accessible at all times by Contractor personnel as well as government employees.

1.8 Spills: Upon occurrence of any spill that could enter the storm system or cause any harmful environment effects, the Contractor shall immediately call 911 to report the incident. When possible, the Contractor shall use a base telephone to receive help from Tinker AFB 911. If using a cell phone, the Contractor shall request Tinker AFB 911. The Contractor shall immediately report all environmental violations to the GPOC and UEC. The Contractor shall provide five (5) copies of a typed or written report about the incident within four (4) clock hours as follows:

1.8.1 One (1) copy to the CO, two (2) copies to the GPOC, a copy for UEC and one (1) copy for record. The format of the report shall be left up to the Contractor, but the report shall contain the following information:

1.) Name and contact number of person reporting the spill

2.) Date and time of incident

3.) Location and source of spill

4.) Substance or pollutant spilled

5.) Amount spilled and rate of discharge

6.) Any damages or injuries involved

7.) Extent of area impacted

8.) Potential hazards

9.) Actions taken

10.) Organizations contacted

11.) Remarks Section - that addresses the cause of the spill (e.g. human error, equipment, etc.) and whether 911 were called and which agencies responded.

1.9 Forms, Technical Orders (T.O.), AFI, Air Force Material Command Instructions (AFMCI), and Publications: The Contractor shall obtain the forms and publications expressly required to perform the work in this contract via the internet at www.e-publishing.af.mil. In the event a form or publication is not available online, the GPOC will provide the form, instruction, or publication to the Contractor upon the Contractor’s written request (e-mail is acceptable). In the event, laws, regulations, T.O.’s, AFI’s, or AFMCI’s change during the term of this contract, the Contractor shall be required to comply as the changes come into effect. Contractors delivering or handling official United States Air Force (USAF) records shall comply with the applicable records management regulations in AFI 33-322, Chapter 3, in its entirety.

1.10 Housekeeping: The Contractor shall keep the work areas clean and neat IAW industry standards, OSHA, fire and safety standards, and this SOW.

1.11 Foreign Object Damage (FOD) and Dropped Object Prevention: Contractor personnel who work in or travel though areas near operational and production aircraft, engines, munitions, missiles, drones, space systems, support equipment, Aerospace Ground Equipment (AGE), trainers, and the Contactor personnel operating vehicles and equipment on flight lines, runways, taxiways, parking ramps, and in aircraft hangers and maintenance areas are required to receive the FOD/DOP training and to comply with AFI 36-2650, AFMC Supplement 1, paragraph 9.2., and A4.4.4. (Initial)/A4.4.5. (Refresher). The Contractor and Contractor personnel shall acknowledge the FOD/DOP training either by viewing the Digital Versatile Disc (DVD) provided by the GPOC or the You Tube site, http://www.youtube.com/watch?v=tYcbodjFPnM.

1.11.1 The Contract Manager shall provide written certification to the GPOC for each employee within ten (10) business days after the contract award date. The certification shall have the title of the training, the name of the person who received the training, and the date of the training. The Contractor shall also ensure all new employees view the FOD/DOP training and provide written certification of training to the GPOC prior to the employees starting work in the OC-ALC shops. Every 36 Months, the Contractor and Contractor personnel shall be required to review the FOD/DOP training and to provide written certification to the GPOC.

1.12 Tool Control and Accountability: While performing contract services in or around Maintenance Production Shops, which includes ramp areas, the Contractor shall comply with AFI 21-101_AFMC Supplement 1, 21-101, Chapter 10 (all paragraphs) and OC-ALCI 21-112, paragraph 14.1. and 14.5.3. The Contractor shall provide the completed MXRIWRS Form 032 prior to performing work in the OC-ALC industrial areas. The MXRIWRS Form 032 is available from the GPOC. The Contractor shall provide a Contractor Tool Listing, MXRIWRS Form 032, to the GPOC within five (5) business days after PM/RM actions. The Contractor or Contractor’s personnel shall inventory the container or bag of tools at the beginning of each work day and at the end of each work day. The Contractor personnel shall immediately notify the GPOC of any tools that are missing or lost from the work area or container (e.g. tool or job box or tool bag). The GPOC will report any missing Contractor’s tools which have not been located within one (1) hour after notification to the appropriate Government personnel. The Contractor shall obtain the Form 32 from the GPOC. The CM shall ensure each employee on the job site receives a briefing from the GPOC about Housekeeping, FOD/DOP, and Tool Control prior to starting work in OC-ALC Industrial Areas.

1.13 Privately Owned Motor Vehicles (POV): Contractor personnel shall comply with the directives pertaining to operation of POVs on Tinker AFB per AFMAN 31-116, in its entirety, “Motor Vehicle Traffic Supervision”. The Contractor shall comply with Tinker AFBI 24-302, in its entirety for the operation of POVs within Tinker AFB.

1.14 Visitors Pass: The Contractor shall contact the Government POC seven (7) business days before arriving on Tinker AFB in order to make arrangements for Visitors Passes. The Government POC will assign a sponsor for the Contractor from within the organization. The Contractor and the sponsor shall arrange to meet at Pass and Registration, Building 6611 at the Tinker Gate which is South of I-40 off of Air Depot. The Contractor shall provide two (2) forms of identification, one of which shall be a picture ID, to the 72 SFS. The 72 SFS will provide an AF Form 75, Visitors Pass, which will be valid for up to thirty (30) calendar days.

1.15 Foreign Nationals: The Contractor shall notify the Government POC before sending a Foreign National representative to perform services. Special rules apply for foreign nationals visiting a US Government facility.

1.16 Safety and Health on Government Installations: While performing work under this contract on a Government installation, the Contractor shall comply with federal, state and local regulations, and AFI 91-203, “Air Force Consolidated Occupational Safety Instruction”, as established by this contract and Appendix C. The Contractor shall notify the CO, GPOC, and Government Contract Administrator (CA) within one (1) business day of any injuries that occur to contractor personnel while they are on the installation. The Contractor shall notify the CO, GPOC, and Government CA within one (1) business day of damage to Government property or equipment during the execution of the contract.

1.17 Emergency Procedures: The Contractor personnel shall follow the direction of the Government personnel with regard to emergency procedures, such as fire, tornado, active shooter, bomb threats, or other emergency. It is the responsibility of the Contractor to provide guidance and to establish procedures for its employees to respond to an emergency. It is the Contractor’s responsibility to account for their employees following an emergency evacuation. The Contractor personnel shall participate with the Government personnel in all fire and tornado drills at no additional cost to the Government.

1.18 Shipping: The Contractor shall provide to the COR, the date equipment was shipped out, shipment identification information and include contract number on the shipping paper work with a Free On Board (FOB) Destination. The ship to address is listed below.

ATTN: SURVEILLANCE COR #/Contract No: _____________

OC-ALC/OBC

Bldg. 3001 Staff Dr. Door G70 Post N68

Tinker AFB, OK 73145-3052