B-1 CPT SOW.pdf
PDF 686 KB Posted
- Attached to
- B-1 Cabin Pressure Tester (3)
- Solicitation number
- FA812626Q0049
About this file
This Statement of Work (SOW) defines requirements for the procurement of two (2) diesel-powered Cabin Pressure Testers (CPTs), part number 99421-100, specifically designed and certified for use on B-1 aircraft by the 76 Aircraft Maintenance Group at Tinker Air Force Base. The existing CPTs (MT006, MT007, MT021) are aging and unreliable, creating significant maintenance capability risks and increased downtime. The new equipment is intended to reduce current rework averaging 32 hours per job and eliminate down time associated with pressure leak testing in B-1 aircraft cabins.
The CPTs must meet specific technical and operational requirements including accurate pressurization and precise cabin leakage rate measurement per applicable B-1 Technical Orders, full compatibility with existing B-1 pressure system test ports and fittings with contractor-provided adapters, compliance with all applicable safety standards and certifications, and portability dimensions not exceeding 4 feet by 3 feet by 2 feet with a weight limit of 150 pounds. Reliability is identified as the most critical capability; contractors must provide documented Mean Time Between Failures (MTBF) hours. Deliverables include the equipment crate-packed without physical damage, two paper copies and one digital version (Adobe or Microsoft format) of user manuals, parts breakdowns, maintenance literature, system check procedures, and calibration certificates, deliverable via DoD SAFE or disc. Acceptance criteria require zero damaged components upon visual inspection and successful installation and configuration of all system components. No installation, training, or specialized setup is required from the contractor. The SOW emphasizes Tinker AFB's safety requirements, including contractor compliance with OSHA regulations, submission of a Safety and Health Plan, hazard communication procedures, and participation in emergency drills at no additional cost.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| Solicitation - FA812626Q0049.pdf |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
STATEMENT OF WORK
For
B-1 Cabin Pressure Tester
PREPARED BY: Creighton M. Gore
76 AMXG/MXDEO
10/9/2025
PREAMBLE
Commander’s Safety Intent
The safety of everyone on Tinker AFB is our top priority. All Individuals must accept personal responsibility for safety and seek opportunities for improving the safety of our work environment. Everyone working on Tinker AFB is challenged to find, fix (if able) and report all hazards and near-misses. It is our shared duty to take every reasonable step and precaution to prevent accidents and preserve the health/safety of each Contractor and Government employee.
1. SCOPE
This Statement of Work (SOW) defines the requirements for the procurement of two (2) Diesel-
Powered Cabin Pressure Testers (CPTs), specifically designed and certified for use on B-1 aircraft. These CPTs are intended to replace existing, obsolete, and unreliable equipment.
2. BACKGROUND
The 76 Aircraft Maintenance Group (AMXG) requires reliable CPTs to measure pressure leaks in B-1 aircraft cabins. Cabin pressure testing is crucial for B-1 aircraft maintainability and safety.
The existing CPTs (MT006, MT007, MT021) are aging and unreliable, posing a significant risk to the maintenance capabilities of the B-1 fleet. The high downtime and low Mean Time
Between Repair (MTBR) of existing units directly impacts aircraft availability and increases maintenance costs.
3. REQUIREMENTS AND ITEM DESCRIPTIONS
3.1. Item Description
The required items for the Diesel-Powered Cabin Pressure Testers are defined in the following table:
Part Number Description Quantity
99421-100 Diesel-Powered Cabin Pressure Tester 2
Table 1 - System Requirements
3.1.1 Support Documentation – Support documentation shall be included with items listed above. Supporting documentation shall include but is not limited to user manuals, parts breakdowns, maintenance literature, system check procedures, and applicable calibration certificates. Paper copies of calibration data shall be co-located in the system kit that includes items calibrated. Two paper copies and a digital version of manuals, parts break down and maintenance literature shall be included with first delivery. Digital manuals should be in Adobe or Microsoft format, capable of editing/notes. All digital content can be delivered via DoD Safe
(https://safe.apps.mil/) or disc.
3.2. Installation
No installation is required.
3.3. New and Unused Parts
The contractor shall manufacture the CPTs with new or unused components.
3.4. Training
No training is required.
3.5. Acceptance
System acceptance is dependent on the following criteria being met and verified:
Asset Condition:
Criteria:
Items crate packed for shipment.
• No physical damage to any system components (hardware, software media, documentation) as verified by visual inspection upon delivery.
• Verification Method: Visual inspection of all delivered items against the packing list.
• Acceptance Threshold: Zero damaged components. Minor cosmetic blemishes that do not affect functionality may be accepted at the discretion of [Accepting Party Name/Role].
System Setup:
Criteria: Successful installation and configuration of all system components according to the vendor's installation instructions and configuration guides. All software components are correctly installed.
3.5.1. Capabilities
Capabilities shall include, but not be limited to:
3.5.1.1 Testing
CPTs must accurately pressurize the B-1 aircraft cabin and precisely measure the cabin leakage rate as outlined in applicable B-1 Technical Orders.
3.5.1.2 Compatibility
The CPTs must be fully compatible with the B-1 aircraft's current pressure system, including existing test ports and fittings. The contractor will be responsible for providing any necessary adapters to connect to the existing B-1 cabin pressure test ports.
3.5.1.3 Safety
The CPTs must meet all applicable safety standards and certifications.
3.5.1.4 Portability
The CPT should be easily moveable in the limited spaces around a B-1. CPTs should not exceed
4ft x 3ft x 2ft. and should not exceed 150 lbs. If on wheels, the wheels must be lockable.
3.5.1.5 Reliability
This is the most important capability. The selected CPT MUST perform reliable leak test to prevent rework. The new CPT is intended to reduce current re-work from an average of 32 hours per job and eliminate down time.
Contractor will report the documented Mean Time Between Failures (MTBF) hours of the proposed system.
4. GENERAL REQUIREMENTS
Commander’s Safety Intent: The safety of everyone on Tinker AFB is our top priority. All
Individuals must accept personal responsibility for safety and seek opportunities for improving the safety of our work environment. Everyone working on Tinker AFB is challenged to find, fix
(if able) and report all hazards and near misses. It is our shared duty to take every reasonable step and precaution to prevent accidents and preserve the health/safety of each contractor and government employee.
4.11. Speak up for safety: Safety surety is an integral part of our overall goal of establishing a world class safety and health program. Our “Speak Out for Safety” initiative ensures a partnership with contractors and government employees to further enhance safety to ensure we are looking out for all our partners and empowers all employees to actively participate in each other’s safety. A safe workplace is everyone's business. As part of the contract team, military, civilian and contractor personnel are empowered to Speak Out for Safety (S.O.S.) when they observe an unsafe act. Events that present imminent danger to personnel or catastrophic damage to property we empower our employees to intercede to ensure continued safe operations.
4.12. Communicating Hazards of Workplace (CHOW): Contractor’s onsite representative communicates all hazards being introduced to the worksite by the Contractor. This is accomplished prior to commencement of work and refreshed daily during performance, IAW
Contractor’s Site Safety Plan.
4.13. Safety and Health Plan: The Contractor shall be responsible for compliance with the
OSHA Public Law 91-596. The Contractor shall submit a Safety and Health Plan (SHP) and corresponding site safety checklist to the CO and the COR (see Appendix C).
4.14. Emergency Procedures: The Contractor personnel shall follow the direction of the
Government personnel regarding emergency procedures, such as fire, tornado, active shooter, bomb threats, or other emergencies. It is the responsibility of the Contractor to provide guidance and to establish procedures for its employees to respond to an emergency. It is the Contractor’s responsibility to account for their employees following an emergency evacuation. The Contractor personnel shall participate with the Government personnel in all fire and tornado drills at no additional cost to the Government.
Appendix A – Weight and Dimensions
Overall Dimensions Height: 81 inches
Length: 127 inches
Width: 64 inches
Weight: (Dry) 6140 pounds
Appendix B – Specifications
File details come from the government source that posted it. Updated .