This is a Request for Qualifications (RFQ) advertisement issued by the Auburn Water District in Auburn, Massachusetts, for the construction of a new 1.3 million gallon per day PFAS water treatment facility. The project, estimated at $12.5 million, encompasses construction of a concrete masonry unit water treatment building featuring granular activated carbon filter vessels for PFAS removal, chemical feed systems, backwash residuals holding tank, restroom, HVAC, plumbing, fire protection, and electrical systems, along with site work including below-grade utilities, grading, paved and gravel driveways, stormwater collection and treatment, and selective demolition and equipment replacement at existing well pump buildings. The RFQ is available for download from the Tata & Howard, Inc. website beginning October 28, 2026 at 2:00 PM. Statements of Qualifications must be submitted to the Auburn Water District Office at 75 Church Street, Auburn, MA 01501, Attention: Gregory Woods, Superintendent, by 3:00 PM Eastern Standard Time on Wednesday, November 18, 2026. Construction is anticipated to begin in January 2027 and must be completed within 570 consecutive calendar days of the Notice to Proceed issuance. Participation in the subsequent bidding phase is restricted to general contractors and filed subcontractors who submit a complete Statement of Qualifications and supporting documentation and receive prequalification approval from the Auburn Water District.

The project includes nine filed sub-bidder categories with estimated costs as follows: Masonry ($750,000), Electrical ($1,200,000), HVAC ($250,000), Plumbing ($200,000), Roofing and Flashing ($250,000), Waterproofing, Damp proofing and Caulking ($200,000), Miscellaneous and Ornamental Iron ($150,000), Painting ($150,000), and Fire Protection ($75,000). Contractors seeking prequalification in multiple capacities, such as both general contractor and subcontractor for specific trades, are required to submit separate responses to the respective RFQs. The RFQ includes additional information regarding prequalification evaluation criteria and the selection process, available through Tata & Howard, Inc.

View the file

Other files

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

REQUEST FOR QUALIFICATIONS

CONTRACTOR PREQUALIFICATIONS

The Auburn Water District hereby requests qualifications from prospective General Contractors and

Sub-Contractors for the construction of the new 1.3 million gallon per day (mgd) Church Street PFAS

Water Treatment Facility in accordance with M.G.L. C. 149, ss 44D¾. The project with an estimated cost of twelve million five hundred thousand dollars ($12,500,000) includes construction of the new concrete masonry unit (CMU) water treatment facility with GAC filter vessels for PFAS removal, chemical feed systems, backwash residuals holding tank below the first floor within the proposed building footprint, restroom, HVAC, plumbing, fire protection system, and electrical systems. Site work includes all below grade utilities, grading, a new paved driveway and gravel driveway area for vehicular access and chemical delivery, stormwater collection and treatment, and selective demolition of existing chemical feed equipment and replacement of well pumps and motors within the existing well pump buildings. Work shall be completed within 570 consecutive calendar days of the date fixed in the Notice to Proceed.

Filed Sub-Bidder Categories for the project include Masonry ($750,000); Miscellaneous and

Ornamental Iron ($150,000); Waterproofing, Damp proofing and Caulking ($200,000); Roofing and

Flashing ($250,000); Painting ($150,000); Fire Protection ($75,000); Plumbing ($200,000); HVAC

($250,000); and Electrical ($1,200,000).

Prequalification is a prerequisite for bidding on the Project, which is anticipated to begin in January

2027. The Request for Qualifications (RFQ) may be obtained on or after October 28, 2026 at 2:00 pm, and downloaded electronically from the Tata & Howard, Inc. website at https://tataandhoward.com/projects-out-to-bid/.

Statements of Qualifications (SOQ) shall be received by the Auburn Water District at the Auburn Water

District Office, 75 Church Street, Auburn, MA 01501, Attn: Gregory Woods, Superintendent, until

3:00 PM E.S.T., on Wednesday, November 18, 2026.

Participation in the bidding phase of this Project will be limited to General Contractors and filed Sub-bidders who have submitted a SOQ (and required supporting documentation) in response to the RFQs and that have been deemed prequalified by the Auburn Water District.

Any contractor seeking to be prequalified as both a General Contractor and Subcontractor for a particular filed sub-bid trade(s) is required to file separate responses to BOTH the RFQ issued to prospective General Contractors and the RFQ issued to prospective filed Subcontractors for this Project.

Additional required information regarding the Construction of the Church Street PFAS Water

Treatment Facility, including the prequalification evaluation criteria and the selection process, is included in the RFQ available to the interested Contractors electronically by using the contact information set forth in this advertisement.

AUBURN WATER DISTRICT

AUBURN, MASSACHUSETTS

https://tataandhoward.com/projects-out-to-bid/

File details come from the government source that posted it. Updated .