AWC-373 Torrington WTP Caustic Chemical Feed and Storage Improvements - Contract Specs - 11.6.2026.pdf
PDF 9 MB Posted
- Solicitation number
- AWC-373
- Issued by
- Middlesex County, Connecticut
About this file
Contract Specifications Summary
This document comprises the contract specifications and bidding requirements for the Torrington Water Treatment Plant (WTP) Caustic Chemical Feed and Storage Improvements project issued by Aquarion Water Authority in Torrington, Connecticut. The project involves demolition of the existing caustic chemical feed and storage system, installation of a spare chemical feed system during the transition period, and installation of a new caustic chemical feed and storage system with associated infrastructure improvements including concrete work, piping, valves, electrical work, instrumentation and controls, treatment equipment, painting, heating and ventilation equipment, and miscellaneous facility furnishings. Bidders are required to submit sealed bids through Aquarion's electronic bid portal (aquarion.procureware.com) by 3:00 p.m. on December 11, 2026, with bids remaining subject to acceptance for 90 days following the bid opening. A mandatory pre-bid meeting is scheduled for 1:00 p.m. on November 24, 2026, at the project site located at 277 Norfolk Road, Torrington, Connecticut. The deadline for submitting clarification requests is 3:00 p.m. on December 4, 2026. The Notice of Award will be issued within 90 days of bid opening, with the successful bidder required to execute the contract and provide required bonds and insurance within 15 days of the Notice of Award.
The bid structure includes four line items: Item 1 for Torrington WTP Caustic Chemical Feed and Storage Improvements (lump sum); Item 2 for Furnish Caustic Bulk Chemical Storage Tanks ($110,000.00 allowance); Item 3 for Chemical Waste Disposal ($50,000.00 allowance); and Item 4 for Allowance for Permits ($10,000.00 allowance). Bid security of 5 percent of the maximum bid price is required in the form of a certified check or bid bond. The successful bidder must comply with Connecticut prevailing wage requirements under General Statute 31-53 and possess appropriate Connecticut contractor licenses prior to award. Bidders must demonstrate qualifications including financial capability, safety record compliance with Experience Modification Rating (EMR) requirements, OSHA injury and illness rate documentation, completion of at least five similar water company projects within the past five years with satisfactory references, and submission of a Responsible Contractor Certification affirming compliance with wage, safety, and labor standards. The project is subject to Connecticut prevailing wage regulations and federal Davis Bacon wage requirements if funded through the Connecticut Drinking Water State Revolving Fund.
View the file
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
TORRINGTON WTP CAUSTIC CHEMICAL FEED
AND STORAGE IMPROVEMENTS
Torrington, Connecticut
AQUARION WATER
AUTHORITY
Bridgeport, Connecticut
NOVEMBER 2026
CONTRACT SPECIFICATIONS
Rev. 8/21/2026 00003-1
T A B L E O F C O N T E N T S
DOCUMENTS
00001 Title Sheet 00003 Table of Contents
BIDDING REQUIREMENTS, CONTRACT FORMS AND CONDITIONS OF THE CONTRACT
00010 Invitation for Bid 00100 Instructions to Bidders 00300 Bid Form 00310 Bid Bond 00320 Certification of Responsible Contractor Status 00330 Affidavit of Non-Collusion and Independent Price Determination 00350 Bidder’s Qualification Statement 00360 Contractor Safety Qualification Guidelines 00370 Nondiscrimination Certification 00380 Site Visitation Statement 00385 List of Subcontractors 00386 Named Subcontractor Bidder’s Qualification Statement 00430 Notice of Award 00500 Form of Agreement 00600 Payment Bond 00610 Performance Bond 00650 Notice to Proceed 00700 General Conditions 00800 Supplementary Conditions 00852 Special Conditions – General 00905 Change Order 00945 Certificate of Substantial Completion 00950 Waiver of Liens 00960 Certificate of Final Payment and Completion of Work 00965 Transfer of Title
T E C H N I C A L S P E C I F I C A T I O N S
DIVISION 1 - GENERAL REQUIREMENTS
01028 Change Orders 01140 Work Restrictions 01200 Measurement and Payment 01310 Project Coordination and Scheduling 01320 Lines and Grades 01330 Shop Drawings 01420 References 01450 Testing Laboratory Services 01500 Temporary Utilities, Facilities and Controls 01660 Startup and Testing 01710 Existing Conditions 01740 Site Maintenance 01780 Operations and Maintenance Manuals
Rev. 8/21/2026 00003-2
D E T A I L E D S P E C I F I C A T I O N S
Item Description
Item 1 Water Treatment Plant Improvements
Div. 1 Concrete Work Div. 2 Piping and Valves Div. 3 Electrical Work Div. 4 Instrumentation and Controls Div. 5 Misc. Facility Furnishings Div. 6 Treatment Equipment Div. 7 Painting Div. 8 Heating and Ventilation Equipment Div. 9 Spare Chemical Feed System Div. 10 Demolition Div. 11 Payment
Item 2 Furnish Caustic Bulk Chemical Storage Tanks Item 3 Chemical Waste Disposal Item 4 Allowance for Permits
A P P E N D I C E S
Appendix A: AWC Electrical Group Standards
NOTE: Bidders shall check the attached documents with the above list before submitting a bid.
Rev. 8/21/2026 00010-1
DOCUMENT 00010
INVITATION FOR BID
TORRINGTON WTP CAUSTIC CHEMICAL FEED AND STORAGE IMPROVEMENTS
Torrington, Connecticut
All proposals for the Torrington WTP Caustic Chemical Feed and Storage Improvements in
Torrington, Connecticut, will be submitted through Aquarion Water Authority’s (AWA) E-Bid system and will remain sealed and safeguarded until 3:00 p.m, current local time, on December
11, 2026, at which time they will be publicly opened on Aquarion Water Authority’s E-Bid system. Bidders may access the bid document, bid requirements and submit their bids on
Aquarion’s E-Bid System accessible at https://aquarion.procureware.com.
A mandatory pre-bid meeting will be held at 1:00 p.m. on November 24, 2026 at the project site located at 277 Norfolk Rd, CT.
Deadline to Submit Requests for Clarifications: 3:00 p.m. December 4, 2026.
Bid Closing: 3:00 p.m. December 11, 2026.
Upon receipt of this Request For Proposal, please be sure to indicate your intention to bid, or not bid by communicating your decision through the “Clarifications” tab in this electronic bid portal
(Aquarion.Procureware.com).
Note: Bid, Performance, and Payment Bonds will be required for this project.
All Bids will remain subject to acceptance for a period of ninety (90) days after the Bid opening.
No bidder may withdraw his bid within this time period.
Any technical or commercial questions regarding the bid or bid documents should be communicated through the “Clarifications Tab” in the Aquarion.Procureware.com system portal.
Questions or issues regarding working or navigating in the Aquarion.Procureware.com portal should be directed to Ken Feldkamp (203) 362-3064, email: kfeldkamp@aquarionwater.com.
Ken Feldkamp
Buyer mailto:kfeldkamp@aquarionwater.com
Rev. 8/21/2026 00100-1
DOCUMENT 00100
INSTRUCTIONS TO BIDDERS
TABLE OF ARTICLES
Page
Article 1 - Defined Terms 1
Article 2 - Copies of Bidding Documents 1
Article 3 - Qualifications of Bidders 2
Article 4 - Examination of Bidding Documents, Other Related Data, and Site 3
Article 5 - Pre-Bid Conference 5
Article 6 - Site and Other Areas 5
Article 7 - Interpretations and Addenda 5
Article 8 - Bid Security 5
Article 9 - Contract Times 6
Article 10 - Liquidated Damages 6
Article 11 - Substitute and “Or-Equal” Items 6
Article 12 - Subcontractors, Suppliers, and Others 6
Article 13 - Preparation of Bid 7
Article 14 - Basis of Bid; Comparison of Bids 7
Article 15 - Submittal of Bid 8
Article 16 - Modification and Withdrawal of Bid 8
Article 17 - Opening of Bids 8
Article 18 - Bids to Remain Subject to Acceptance 8
Article 19 - Evaluation of Bids and Award of Contract 9
Article 20 - Contract Security and Insurance 10
Article 21 - Signing of Agreement 10
Article 22 - Sales and Use Taxes 10
Article 23 - Contracts to be Assigned - Omitted 10
Article 24 - Statement of Tax Compliance - Omitted 10
Article 25 - Notice to Proceed 11
Article 26 - Wage Rates 11
Article 27 - Laws and Regulations 11
Article 28 - Inspection of the Work 11
Article 29 - Warranty 12
Article 30 - Responsible Contractor Policy 12
Article 31 – Nonresident Contractors 13
ARTICLE 1 - DEFINED TERMS
1.01 Terms used in these Instructions to Bidders will have the meanings indicated in the General Conditions and
Supplementary Conditions. Additional terms used in these Instructions to Bidders have the meanings indicated below:
A. Issuing Office -The office from which the Bidding Documents are to be issued and where the bidding procedures are to be administered.
ARTICLE 2 - COPIES OF BIDDING DOCUMENTS
2.01 Complete sets of Bidding Documents must be used in preparing Bids; neither Owner nor Engineer assumes any responsibility for errors or misinterpretations resulting from the use of incomplete sets of Bidding
Documents.
2.02 Owner and Engineer in making copies of Bidding Documents available on the above terms do so only for the purpose of obtaining Bids for the Work and do not confer a license or grant for any other use.
Rev. 8/21/2026 00100-2
ARTICLE 3 - QUALIFICATIONS OF BIDDERS
To demonstrate Bidder’s qualifications to perform the Work, within five days of Owner’s request, Bidder shall submit written evidence such as financial data, previous experience, present commitments, and such other data as may be called for below.
A. Standard Equipment and Wage Rates: Within five (5) days (not including Sunday) from the date of the award, the party to whom the contract is awarded shall submit to the Engineer its Standard Hourly Wage
Rates and its Standard Equipment Billing Rate Schedule.
B. Guidelines for Contractors Engaged By Aquarion Water Company - Agreement and Acknowledgement:
Within five (5) days (not including Sunday) from the date of the award, the party to whom the contract is awarded shall submit to the Engineer a completed AGREEMENT AND ACKNOWLEDGEMENT form contained in the Guidelines for Contractors Engaged By Aquarion Water Company, included in
Document 00852 Special Conditions.
C. Each Bid must contain evidence of Bidder's qualification to do business in Connecticut or covenant to obtain such qualification prior to contract award.
D. Bidders are advised that Section 12-430(7) of the Connecticut General Statutes, as amended, puts certain responsibilities on parties that enter into agreements with non-resident contractors. Any bidder which is a
“non-resident contractor” as the term is defined in section 12-430(7) of the Connecticut General Statutes shall be required to file a bond with the Connecticut Department of Revenue Services to ensure compliance with the Act.
E. All Contracts that exceed $100,000 for construction, renovations or repairs must follow Section 31-53b of the Connecticut General Statutes, as amended, “Construction Safety Training”.
F. License Requirements - Contractors and Subcontractors, in order to perform public work in the State of
Connecticut, are required to hold prior to award of contract State of Connecticut Contractor's Licenses of the class required to perform the specified Work. Such licenses shall be submitted with the Bid.
G. Contractor Safety Qualification Program Submittal - Construction projects can affect the safety of the
Owner’s, Engineer’s, and Contractor’s employees, equipment, buildings, and the quality and quantity of the water we provide to our customers. So we may assure that the contractors chosen for AWA projects are of the highest quality in both performance and safety, the following process shall be used prior to awarding contracts. The process makes it mandatory that the past safety record of a contractor be considered as part of the qualifying process. The quality of a contractor’s safety record shall be a major element of the
Owner’s determination of whether the bidder is qualified to perform the contract.
Contractor’s that meet the requirements of G.1.A below shall automatically be deemed qualified from a safety perspective. Contractors who do not meet the requirements of G.1.A shall be presumed to be unqualified. At the Owner’s discretion, the Contractor may be given the option to rebut that presumption by providing the information required by subparts G.1.B, C and D. The sufficiency of that information to establish the bidder as qualified shall be determined by the Owner in its sole discretion.
1. Safety Requirements:
A. The most recent Workers Compensation Experience Modification Rating* (EMR) shall be less than or equal to 1.0.
B. The three-year average of the injury and illness rate of the contractor is less than or equal to the most recent rate as published by the Bureau of Labor Statistics (BLS) Occupational Injury and Illness incidence rate (for the appropriate North American Industrial Classification System
Code).
C. Three-year trend showing a decrease in EMR and/or annual number of recordable injuries as shown on the OSHA log. Contractors with less than ten (10) employees who are not required to fill out the OSHA 300A form must still provide the number of injuries for the previous three years.
Rev. 8/21/2026 00100-3
D. Documented references from two recent previous customers of the contractor acknowledging appropriate safety performance on the job and approval by the Leadership Team Member of the division awarding the work.
The required safety information is included at the end of this section, titled “Contractor Safety Qualification
Guidelines Submittal Sheet”, and shall be used by the bidder in order to provide the required information. It must be submitted at the time of the bid.
This requirement is not applicable to materials or equipment to be purchased, leased, or rented.
*EMR – The EMR is a percentage modifier that is applied to the basic insurance premium established for a company. A company with an EMR of 0.6 would pay 60% of the base insurance premium, while a company with a poorer accident frequency rate and an EMR of 1.4 would pay 140% of the base insurance premium.
ARTICLE 4 - EXAMINATION OF BIDDING DOCUMENTS, OTHER RELATED DATA, AND SITE
4.01 Subsurface and Physical Conditions
A. The Supplementary Conditions identify:
1. Those reports of explorations and tests of subsurface conditions at or contiguous to the Site that
Engineer has used in preparing the Bidding Documents.
2. Those drawings of physical conditions in or relating to existing surface and subsurface structures at or contiguous to the Site (except Underground Facilities) that Engineer has used in preparing the
Bidding Documents.
B. Copies of reports and drawings referenced in paragraph 4.01.A will be made available by Owner to any
Bidder on request. Those reports and drawings are not part of the Contract Documents, but the
“technical data” contained therein upon which Bidder is entitled to rely as provided in paragraph 4.02 of the General Conditions has been identified and established in paragraph 4.02 of the Supplementary
Conditions. Bidder is responsible for any interpretation or conclusion Bidder draws from any
“technical data” or any other data, interpretations, opinions, or information contained in such reports or shown or indicated in such drawings.
4.02 Underground Facilities
A. Information and data shown or indicated in the Bidding Documents with respect to existing
Underground Facilities at or contiguous to the Site is based upon information and data furnished to
Owner and Engineer by owners of such Underground Facilities, including Owner, or others.
4.03 Hazardous Environmental Condition
A. The Supplementary Conditions identify those reports and drawings relating to a Hazardous
Environmental Condition identified at the Site, if any, that ENGINEER has used in preparing the
Bidding Documents.
B. Copies of reports and drawings referenced in paragraph 4.03.A will be made available by Owner to any
Bidder on request. Those reports and drawings are not part of the Contract Documents, but the
“technical data” contained therein upon which Bidder is entitled to rely as provided in paragraph 4.06 of the General Conditions has been identified and established in paragraph 4.06 of the Supplementary
Conditions. Bidder is responsible for any interpretation or conclusion Bidder draws from any
“technical data” or any other data, interpretations, opinions, or information contained in such reports or shown or indicated in such drawings.
4.04 Provisions concerning responsibilities for the adequacy of data furnished to prospective Bidders with respect to subsurface conditions, other physical conditions and Underground Facilities, and possible
Rev. 8/21/2026 00100-4 changes in the Bidding Documents due to differing or unanticipated conditions appear in paragraphs 4.02, 4.03, and 4.04 of the General Conditions. Provisions concerning responsibilities for the adequacy of data furnished to prospective Bidders with respect to a Hazardous Environmental Condition at the Site, if any, and possible changes in the Contract Documents due to any Hazardous Environmental Condition uncovered or revealed at the Site which was not shown or indicated in the Drawings or Specifications or identified in the Contract Documents to be within the scope of the Work appear in paragraph 4.06 of the General
Conditions.
4.05 Upon request, Owner will provide Bidder access to the Site to conduct such examinations, investigations, explorations, tests, and studies as Bidder deems necessary for submission of a Bid. Bidder shall fill all holes and clean up and restore the Site to its former condition upon completion of such explorations, investigations, tests, and studies. Bidder shall comply with all applicable Laws and Regulations relative to excavation and utility locates.
4.06 Reference is made to Article 7 of the Supplementary Conditions for the identification of the general nature of other work that is to be performed at the Site by Owner or others (such as utilities and other prime contractors) that relates to the Work contemplated by these Bidding Documents. Upon request, Owner will provide to each Bidder for examination access to or copies of Contract Documents (other than portions thereof related to price) for such other work.
4.07 It is the responsibility of each Bidder before submitting a Bid to:
A. Examine and carefully study the Bidding Documents, the other related data identified in the Bidding
Documents, and any Addenda;
B. Visit the Site and become familiar with and satisfy Bidder as to the general, local, and Site conditions that may affect cost, progress, and performance of the Work;
C. Become familiar with and satisfy Bidder as to all Federal, State, and local Laws and Regulations that may affect cost, progress, or performance of the Work;
D. Carefully study all: (1) reports of explorations and tests of subsurface conditions at or contiguous to the
Site and all drawings of physical conditions in or relating to existing surface or subsurface structures at or contiguous to the Site (except Underground Facilities) which have been identified in the
Supplementary Conditions as provided in paragraph 4.02 of the General Conditions, and (2) reports and drawings of Hazardous Environmental Conditions at the Site which have been identified in the
Supplementary Conditions as provided in paragraph 4.06 of the General Conditions;
E. Obtain and carefully study (or accept consequences for not doing so) all additional or supplementary examinations, investigations, explorations, tests, studies, and data concerning conditions (surface, subsurface, and Underground Facilities) at or contiguous to the Site which may affect cost, progress, or performance of the Work or which relate to any aspect of the means, methods, techniques, sequences, and procedures of construction to be employed by Bidder, including applying any specific means, methods, techniques, sequences, and procedures of construction expressly required by the Bidding
Documents, and safety precautions and programs incident thereto;
F. Agree at the time of submitting its Bid that no further examinations, investigations, explorations, tests, studies, or data are necessary for the determination of its Bid for performance of the Work at the price(s) bid and within the times and in accordance with the other terms and conditions of the Bidding
Documents;
G. Become aware of the general nature of the work to be performed by Owner and others at the Site that relates to the Work as indicated in the Bidding Documents;
H. Correlate the information known to Bidder, information and observations obtained from visits to the
Site, reports and drawings identified in the Bidding Documents, and all additional examinations, investigations, explorations, tests, studies, and data with the Bidding Documents;
Rev. 8/21/2026 00100-5
I. Promptly give Engineer written notice of all conflicts, errors, ambiguities, or discrepancies that Bidder discovers in the Bidding Documents and confirm that the written resolution thereof by Engineer is acceptable to Bidder; and
J. Determine that the Bidding Documents are generally sufficient to indicate and convey understanding of all terms and conditions for the performance of the Work.
4.08 The submission of a Bid will constitute an incontrovertible representation by Bidder that Bidder has complied with every requirement of this Article 4, that without exception the Bid is premised upon performing and furnishing the Work required by the Bidding Documents and applying any specific means, methods, techniques, sequences, and procedures of construction that may be shown or indicated or expressly required by the Bidding Documents, that Bidder has given Engineer written notice of all conflicts, errors, ambiguities, and discrepancies that Bidder has discovered in Bidding Documents and the written resolutions thereof by Engineer are acceptable to Bidder, and that the Bidding Documents are generally sufficient to indicate and convey understanding of all terms and conditions for performing and furnishing the Work.
ARTICLE 5 - PRE-BID CONFERENCE
5.01 A pre-bid meeting will be held at the location, date and time as stated in Document 00010 INVITATION
FOR BID.
ARTICLE 6 - SITE AND OTHER AREAS
6.01 The Site is identified in the Bidding Documents. Easements for permanent structures or permanent changes to existing facilities are to be obtained and paid for by Owner unless otherwise provided in the Bidding
Documents. All additional lands and access thereto required for temporary construction facilities, construction equipment, or storage of materials and equipment to be incorporated in the Work are to be obtained and paid for by Contractor.
ARTICLE 7 - INTERPRETATIONS AND ADDENDA
7.01 All questions about the meaning or intent of the Bidding Documents are to be submitted through the
Clarifications tab of Aquarion’s E-Bid system: aquarion.procureware.com. Interpretations or clarifications considered necessary by Engineer in response to such questions will be issued by Addenda through
Aquarion’s E-Bid system to all parties recorded by Aquarion’s Procurement Department as having received the Bidding Documents. Questions received less than five days prior to the date for opening of Bids may not be answered. Only questions answered by Addenda will be binding. Oral and other interpretations or clarifications will be without legal effect.
7.02 Addenda may be issued to clarify, correct, or change the Bidding Documents as deemed advisable by
Owner or Engineer.
ARTICLE 8 - BID SECURITY
8.01 A Bid must be accompanied by Bid security made payable to Owner in an amount of 5% of Bidder’s maximum Bid price and in the form of a certified check or a Bid Bond (DOCUMENT 00310, BID BOND) issued by a surety meeting the requirements of paragraphs 5.01 and 5.02 of the General Conditions.
8.02 The Bid security of the Successful Bidder will be retained until such Bidder has executed the Contract
Documents, furnished the required contract security and met the other conditions of the Notice of Award, whereupon the Bid security will be returned. If the Successful Bidder fails to execute and deliver the
Contract Documents and furnish the required contract security within 15 days after the Notice of Award, Owner may annul the Notice of Award and the Bid security of that Bidder will be forfeited. The Bid security of other Bidders whom Owner believes to have a reasonable chance of receiving the award may be retained by Owner until the earlier of seven days after the Effective Date of the Agreement or 1 day following the period when bids are subject to acceptance as stated in 00010 Invitation for Bid, whereupon
Bid security furnished by such Bidders will be returned.
Rev. 8/21/2026 00100-6
8.03 Bid security of other Bidders whom OWNER believes do not have a reasonable chance of receiving the award will be returned within seven days after the Bid opening.
ARTICLE 9 - CONTRACT TIMES
9.01 The number of days within which, or the dates by which, the Work is to be substantially completed and ready for final payment are set forth in the Agreement.
ARTICLE 10 -LIQUIDATED DAMAGES
10.01 Provisions for liquidated damages are set forth in the Agreement.
ARTICLE 11 - SUBSTITUTE AND “OR-EQUAL” ITEMS
11.01 The Contract, if awarded, will be on the basis of materials and equipment specified or described in the
Bidding Documents, or “or-equal” materials and equipment as defined in paragraph 6.05 of the General
Conditions, or those substitute materials and equipment approved by the Engineer and identified by
Addendum. The materials and equipment described in the Bidding Documents establish a standard of required type, function and quality to be met by any proposed substitute or “or-equal” item. Request for
Engineer’s clarification of materials and equipment considered “or-equal” prior to the Effective Date of the
Agreement must be received by the Engineer at least 5 days prior to the date for receipt of Bids. No item of material or equipment will be considered by Engineer as a substitute unless written request for approval has been submitted by Bidder and has been received by Engineer at least 15 days prior to the date for receipt of
Bids. Each request shall conform to the requirements of paragraph 6.05 of the General Conditions. The burden of proof of the merit of the proposed item is upon the Bidder. Engineer’s decision of approval or disapproval of a proposed item will be final. If Engineer approves any proposed substitute item, such approval will be set forth in an Addendum issued to all prospective Bidders. Bidders shall not rely upon approvals made in any other manner.
ARTICLE 12 - SUBCONTRACTORS, SUPPLIERS, AND OTHERS
12.01 If the Supplementary Conditions require the identity of certain Subcontractors, Suppliers, individuals, or entities to be submitted to Owner in advance of a specified date prior to the Effective Date of the
Agreement, the apparent Successful Bidder, and any other Bidder so requested, shall within five days after
Bid opening, submit to Owner a list of all such Subcontractors, Suppliers, individuals, or entities proposed for those portions of the Work for which such identification is required. Such list shall be accompanied by an experience statement with pertinent information regarding similar projects and other evidence of qualification for each such Subcontractor, Supplier, individual, or entity if requested by Owner. If Owner or Engineer, after due investigation, has reasonable objection to any proposed Subcontractor, Supplier, individual, or entity, Owner may, before the Notice of Award is given, request apparent Successful Bidder to submit a substitute, without an increase in the Bid.
12.02 If apparent Successful Bidder declines to make any such substitution, Owner may award the Contract to the next lowest responsible Bidder that proposes to use acceptable Subcontractors, Suppliers, individuals, or entities. Declining to make requested substitutions will not constitute grounds for forfeiture of the Bid security of any Bidder. Any Subcontractor, Supplier, individual, or entity so listed and against which
Owner and Engineer makes no written objection prior to the giving of the Notice of Award will be deemed acceptable to Owner and Engineer subject to revocation of such acceptance after the Effective Date of the
Agreement as provided in paragraph 6.06 of the General Conditions.
12.03 Contractor shall not be required to employ any Subcontractor, Supplier, individual, or entity against whom
Contractor has reasonable objection.
12.04 The Contractor shall not award work to Subcontractor(s) in excess of the limits stated in paragraph 6.06 of the Supplementary Conditions.
Rev. 8/21/2026 00100-7
ARTICLE 13 - PREPARATION OF BID
13.01 The Bid form is included with the Bidding Documents. Additional copies may be obtained from Engineer.
13.02 All blanks on the Bid form shall be completed by printing in ink or by typewriter and the Bid signed in ink.
Erasures or alterations shall be initialed in ink by the person signing the Bid From. A Bid price shall be indicated for each bid item listed therein, or the words “No Bid,” “No Change,” or “Not Applicable” entered.
13.03 A Bid by a corporation shall be executed in the corporate name by the president or a vice-president or other corporate officer accompanied by evidence of authority to sign. If required by State where work is to be performed, the corporate seal shall be affixed and attested by the secretary or an assistant secretary. The corporation business address and state of incorporation shall be provided on the Bid Form.
13.04 A Bid by a partnership shall be executed in the partnership name and signed by a partner (whose title must appear under the signature), accompanied by evidence of authority to sign. The business address of the partnership shall be provided on the Bid Form.
13.05 A Bid by a limited liability company shall be executed in the name of the firm by a member and accompanied by evidence of authority to sign. The state of formation of the firm and the business address of the firm must be provided on the Bid Form.
13.06 A Bid by an individual shall show the Bidder’s name and business address.
13.07 A Bid by a joint venture shall be executed by each joint venturer in the manner indicated on the Bid form.
The business address of the joint venture must be provided on the Bid Form.
13.08 All names shall be typed or printed in ink below the signatures.
13.09 The Bid shall contain an acknowledgment of receipt of all Addenda, the numbers and dates of which shall be filled in on the Bid form.
13.10 The address and telephone number for communication regarding the Bid shall be shown.
13.11 The Bid shall contain evidence of Bidder’s authority and qualification to do business in the state where the
Project is located or covenant to obtain such qualification prior to award of the Contract. Bidder’s state contractor license number for the state of the Project, if any, shall also be shown on the Bid Form.
ARTICLE 14 - BASIS OF BID; COMPARSION OF BIDS
14.01 Unit Price
A. Bidders shall submit a Bid on a unit price basis for each item of Work listed in the Bid schedule.
B. The total of all bid prices will be the sum of the products of the estimated quantity of each item and the corresponding unit price. The final quantities and Contract Price will be determined in accordance with paragraph 11.03 of the General Conditions.
C. Discrepancies between the multiplication of units of Work and unit prices will be resolved in favor of the unit prices. Discrepancies between the indicated sum of any column of figures and the correct sum thereof will be resolved in favor of the correct sum. Discrepancies between words and figures will be resolved in favor of the words.
Rev. 8/21/2026 00100-8
ARTICLE 15 - SUBMITTAL OF BID
15.01 With the electronic copy of the Bidding Documents, a Bidder is furnished with the Bid Form, Bid Bond form, and Certification of Responsible Contractor Status form. The Bid Form is to be completed and submitted with all the attachments outlined in Article 7 of the Bid Form.
15.02 A Bid shall be submitted no later than the date and time prescribed in the Invitation for Bids through the electronic bid portal (Aquarion.Procureware.com), and shall be accompanied by the Bid security and other required documents. If a Bid is sent by mail or other delivery system, the sealed envelope containing the Bid shall be enclosed in a separate envelope plainly marked on the outside with the notation “BID ENCLOSED.” When using the mail or other delivery system, the Bidder is totally responsible for the mail or other delivery system delivering the Bid at the place and prior to the time indicated in the Invitation for Bid. A mailed Bid shall be addressed to Owner at address in Article 1.01 of Bid Form.
15.03 List of required Documents to be completed (uploaded) for General Bid submission:
00300 Bid Form 00310 Bid Bond 00320 Certification of Responsible Contractor Status 00330 Affidavit of Non-Collusion and Independent Price Determination 00350 Bidder’s Qualification Statement 00360 Contractor Safety Qualification Guidelines 00370 Nondiscrimination Certification 00380 Site Visitation Statement 00385 List of Subcontractors 00386 Named Subcontractor Bidder’s Qualification Statement
ARTICLE 16 - MODIFICATION AND WITHDRAWAL OF BID
16.01 A Bid may be modified or withdrawn by an appropriate document duly executed in the manner that a Bid must be executed and delivered to the place where Bids are to be submitted prior to the date and time for the opening of Bids.
16.02 If within 24 hours after Bids are opened any Bidder files a duly signed written notice with Owner and promptly thereafter demonstrates to the reasonable satisfaction of Owner that there was a material and substantial mistake in the preparation of its Bid, that Bidder may withdraw its Bid, and the Bid security will be returned. Thereafter, if the Work is rebid or negotiated, that Bidder will be disqualified from further bidding on the Work. This provision to withdraw a Bid without forfeiting the Bid security does not apply to
Bidder’s errors in judgment in preparing the Bid.
ARTICLE 17 - OPENING OF BIDS
17.01 Bids will be opened at the time and place indicated in the Invitation for Bid.
ARTICLE 18 - BIDS TO REMAIN SUBJECT TO ACCEPTANCE
18.01 All Bids will remain subject to acceptance for the period of time stated in the Bid Form.
Rev. 8/21/2026 00100-9
ARTICLE 19 - EVALUATION OF BIDS AND AWARD OF CONTRACT
19.01 Owner reserves its right to reject any or all Bids, including without limitation the rights to reject any or all nonconforming, nonresponsive, unbalanced or conditional Bids, and to reject the Bid of any Bidder if
Owner believes that it would not be in the best interest of the Project to make an award to that Bidder, whether because the Bid is not responsive or the Bidder is unqualified or of doubtful financial ability or fails to meet any other pertinent standard or criteria established by Owner. Owner also reserves the right to waive all informalities not involving price, time, or changes in the Work. Discrepancies in the quantity multiplied by unit price and the extended total amount will be resolved in favor of the quantity multiplied by unit price. Discrepancies between the indicated sum of any column of figures and the correct sum thereof will be resolved in favor of the correct sum. Discrepancies between words and figures will be resolved in favor of the words. The Owner reserves the right to correct obvious errors in the multiplication of unit price items or in the placement of the extended unit price.
19.02 More than one Bid for the same Work from an individual or entity under the same or different names will not be considered. Reasonable grounds for believing that any Bidder has an interest in more than one Bid for the Work may be cause for disqualification of that Bidder and the rejection of all Bids in which that
Bidder has an interest.
19.03 In evaluating Bids, Owner will consider whether or not the Bids comply with the prescribed requirements, and such alternates, unit prices and other data, as may be requested in the Bid Form or prior to the Notice of
Award. Owner shall have the right to accept alternates in any order or combination unless otherwise provided in the Bidding Documents.
19.04 In evaluating Bidders, Owner may consider the qualifications of Bidders and experience of Subcontractors, Suppliers, and other persons and organizations proposed for those portions of the Work for which the identity was required. Owner also may consider the operating costs, maintenance requirements, performance data, and guarantees of major items of materials and equipment proposed for incorporation in the Work when such data are required to be submitted prior to the Notice of Award.
19.05 Owner may conduct such investigations as Owner deems necessary to establish the responsibility, qualifications, and financial ability of Bidders, proposed Subcontractors, Suppliers, individuals, or entities to perform the Work in accordance with the Contract Documents. The Bidders will be evaluated based on the responses provided to Section 00350, Section 00385, Section 00386 and based on additional information as requested by the Owner. The investigation of a Bidder will seek to determine whether:
(a.) The Bidder has adequate financial resources to perform the Contract;
(b.) The Bidder has the resources to meet the project schedule contained in the Bid documents;
(c.) The Bidder has a satisfactory record of performing similar work;
(d.) The Bidder has a satisfactory record of integrity and business ethics;
(e.) The Bidder has the necessary organization to perform the Contract;
(f.) The Bidder has the necessary technical resources and equipment needed to perform the Work;
(g.) The Bidder does not have other work engaged or to which it is committed which would impact its ability to meet the requirements of the contract;
(h.) The Bidder has a satisfactory record of safe work practices;
(i.) The Bidder has completed a minimum of 5 projects of similar scope and cost for a Water Company and has proper references from the Project Owner and Engineer / Architect to verify a positive performance on those projects;
(j.) There are no other matters which, in the Owner’s opinion, may impact the Bidder’s ability to complete the work satisfactorily to the Owner’s requirements.
19.06 Bids received from Bidders who have previously failed to complete work within the time required, or who have previously performed similar work in an unsatisfactory manner, may be rejected. A Bid may be rejected if Bidder cannot show that he has the necessary ability, plant and equipment to commence the
Work at the time prescribed and thereafter to prosecute and complete the Work at the rate or within the time specified. A Bid may be rejected if Bidder is already obligated for the performance of other work which would delay the commencement, prosecution or completion of the Work.
Rev. 8/21/2026 00100-10
19.07 Owner may conduct such investigations as Owner deems necessary to assist in Bid evaluation and to establish responsibility, qualifications, and financial ability of Bidders, proposed Subcontractors, Suppliers, and other persons and organizations to execute Work in accordance with the Bidding Documents to Owner's satisfaction within the prescribed time.
19.08 If, at the time this contract is to be awarded, the total of the lowest acceptable Bid exceeds the funds then estimated by the Owner as available, the Owner may reject all Bids or take such other action as best serves the Owner's interests.
19.09 If the contract is to be awarded, it will be awarded to lowest Bidder whose evaluation by Owner indicates to
Owner that the award will be in the best interests of the Owner.
19.10 In the event of failure of the Successful Bidder to sign the Agreement and provide an acceptable
Performance and Payment Bond(s), insurance certificate(s), and other required documents, the Owner may award the contract to the next lowest responsive, responsible Bidder.
19.11 The award of the attached bid will be made to one vendor. When award is to be to more than one vendor in cases of requests for multiple items, it will be noted on bid sheets.
19.12 All bid protests must be in writing and mailed to the Procurement Manager within ten (10) days from the bid award notification date.
19.13 The award will not be made to parties listed on the government wide exclusions in the System for Award
Management (SAM). SAM exclusions contains the names of parties debarred, suspended, or otherwise excluded by agencies, as well as parties declared ineligible under statutory or regulatory authority other than
Executive Order 12549
19.14 If the Contract is to be awarded, Owner will award the Contract to the responsible Bidder whose Bid, conforms with all the material terms and conditions stated in the Instructions to Bidders, is lowest, price and other factors considered. The Owner will issue a Notice of Award to the Successful Bidder within 90 days following the day of the Bid opening.
ARTICLE 20 - CONTRACT SECURITY AND INSURANCE
20.01 Article 5 of the General Conditions, as may be modified by the Supplementary Conditions, sets forth
Owner’s requirements as to performance and payment bonds and insurance. When the Successful Bidder delivers the executed Agreement to Owner, it must be accompanied by such bonds.
ARTICLE 21 - SIGNING OF AGREEMENT
21.01 When Owner gives a Notice of Award to the Successful Bidder, it shall be accompanied by the required number of unsigned counterparts of the Agreement with the other Contract Documents which are identified in the Agreement as attached thereto. Within 15 days thereafter, Successful Bidder shall sign and deliver the required number of counterparts of the Agreement and attached documents to Owner. Within ten days thereafter, Owner shall deliver one fully signed counterpart to Successful Bidder with a complete set of the
Drawings with appropriate identification.
ARTICLE 22 - SALES AND USE TAXES
22.01 Instructions for applicability of Sales and Use Taxes are found in sections 00700 General Conditions and
00800 Supplementary Conditions.
ARTICLE 23 - CONTRACTS TO BE ASSIGNED - OMITTED
ARTICLE 24 - STATEMENT OF TAX COMPLIANCE - OMITTED
Rev. 8/21/2026 00100-11
ARTICLE 25 - NOTICE TO PROCEED
25.01 DOCUMENT 00650, NOTICE TO PROCEED shall be issued within ten (10) days of execution of
DOCUMENT 00500, FORM OF AGREEMENT by the Owner. Should there be reasons why
DOCUMENT 00650, NOTICE TO PROCEED cannot be issued within such period, the time may be extended by mutual agreement between the Owner and Contractor. If DOCUMENT 00650, NOTICE TO
PROCEED has not been issued within the ten (10) day period or within the period mutually agreed upon, the Contractor may terminate DOCUMENT 00500, FORM OF AGREEMENT without further liability on the part of either party.
ARTICLE 26 - WAGE RATES
26.01 The Successful Bidder will be required to comply with State of Connecticut General Statute 31-53 relating to prevailing wages.
26.02 The Work under these Bidding Documents is to be paid for by public funds; therefore, per Connecticut
General Statutes Sec. 31-53., minimum prevailing wage rates published by the State Commissioner of
Labor are applicable unless the total Bid is less than $1,000,000 for new construction or $100,000 for remodeling, refinishing, etc. projects. Additional information and documents can be found at:
https://portal.ct.gov/dol/divisions/wage-and-workplace-standards/prevailing-wage?language=en_US
26.03 For projects funded by the Connecticut Drinking Water State Revolving Fund, refer to Document 00005 and Attachments for Davis Bacon Federal Prevailing Wage Rates.
ARTICLE 27 - LAWS AND REGULATIONS
27.01 Applicable provisions of the General Laws and regulations of the State where work under this contract is being performed and/or the United States Code and Code of Federal Regulations govern this Contract; and any provision violation of the foregoing shall be deemed null, void and of no effect. Where conflict between Code of Federal Regulations and state laws and regulations exist, the more stringent requirement shall apply.
27.02. All applicable laws, ordinances, and the rules and regulations of all authorities having jurisdiction over construction of the Project shall apply to the Contract throughout.
27.03 This Project is subject to the OSHA Safety and Health Regulations of the U.S. Department of Labor set forth in Title 29 CFR, Part 1926 and to all subsequent amendments. Contractors shall be familiar with the requirements of these regulations.
27.04 Whenever it is written that an equipment manufacturer must have a specified period of experience with his product, equipment which does not meet the specified experience period can be considered if the equipment supplier or manufacturer is willing to provide an "Efficiency Guarantee Bond" or cash deposit for the duration of the specified time period which will guarantee replacement of that equipment in the event of failure.
27.05 Compliance with Laws. The Bidder shall comply with all applicable federal, state, and local laws, regulations, ordinances, codes, rules, orders, and requirements in the performance of any contract awarded pursuant to this solicitation, including, without limitation, all applicable laws of the State of Connecticut.
The Bidder shall obtain and maintain all licenses, permits, certifications, verifications, and approvals required to perform the work.
ARTICLE 28 - INSPECTION OF THE WORK
28.01 The Contractor shall provide at all times proper facilities for access and inspection by representatives of the
Owner, federal, state or other agency having jurisdiction over the Work of this Project.
ARTICLE 29 - WARRANTY
https://portal.ct.gov/dol/divisions/wage-and-workplace-standards/prevailing-wage?language=en_US
Rev. 8/21/2026 00100-12
29.01 For information on required warranties, refer to 00700 General Conditions and 00800 Supplementary
Conditions contained herein.
ARTICLE 30 – RESPONSIBLE CONTRACTOR POLICY - NOTICE OF RESPONSIBLE
CONTRACTOR REQUIREMENTS TO BIDDERS
30.01 Aquarion has adopted a Responsible Contractor Policy (“RCP”) that is given considerable weight in selecting contractors for the performance of capital or maintenance projects or infrastructure operating services (collectively known as “Services”). The successful bidder should meet the requirements of the
RCP. A “Responsible Contractor” is a contractor or subcontractor who:
(a.) Abides by applicable federal, state and local employment laws.
(b.) Protects the health and safety of all persons at the work site from hazards (including by observing
OSHA and environmental legal requirements) arising from the “Services” provided by them.
(c.) Provides high quality services (including but not limited to construction, repairs, maintenance and infrastructure operating services) to Aquarion on a comparable and relevant basis in the applicable local market consistent with the desired contracting criteria.
(d.) Pays workers a “fair wage” and “fair benefits.”
1. “Fair benefits” are defined as including, but not limited to, health care coverage, and pension benefits.
2. What constitutes a “fair wage” and a “fair benefit” will depend on the wages and benefits paid on comparable infrastructure projects, based upon local market factors that include the nature of the project (e.g., municipal or commercial, public or private), comparable job or trade classifications, and the scope and complexity of the services provides.
3. In determining “fair wages” and “fair benefits” concerning a specific contract in a specific market, items that may be considered include local wage practices, state laws, prevailing wages, labor market conditions and other items.
(e.) Provides appropriate worker training and/or apprenticeship programs.
(f.) Abides by their legal obligations in the event a union is determined to have majority employee support.
30.02 As part of the qualification process, bidders must certify their status as Responsible Contractors by completing and submitting to Aquarion the attached Document 00320, CERTIFICATION OF
RESPONSIBLE CONTRACTOR STATUS form. Thereafter, successful bidders must inform any subcontractors of the requirements of the RCP, must confirm their continuing RCP compliance every twelve months by re-submitting to Aquarion a signed CERTIFICATION OF RESPONSIBLE
CONTRACTOR STATUS form (or as such document may be revised from time to time), may be required to substantiate through payroll, employee and/or other records that they are in compliance with the RCP, and must participate in training programs as Aquarion may offer in furtherance of the RCP.
Rev. 8/21/2026 00100-13
ARTICLE 31 – NONRESIDENT CONTRACTORS
31.01 The Successful Bidder, if not a resident of the State of Connecticut, or, in the case of a partnership, the partners, if not residents, shall appoint a registered agent for service of process pursuant to Connecticut
General Statutes Sec. 33-926, upon whom all lawful processes, proceedings or notices may be served. The
Bidder, if a corporation not organized under the laws of Connecticut, shall comply with the provisions of the Connecticut General Statutes Sec. 12-430(7) regarding Foreign Corporations before engaging in performance of any construction activity under the Contract Documents.
31.02 The successful out-of-state bidder shall comply with the requirements of Section 6.09 of the Supplementary
General Conditions.
31.03 Successful nonresident contractors (bidder) shall comply with the requirements of a verified or un-verified contractor as required by Connecticut General Statutes Sec. 12-430, including the requirement that unverified nonresident contractors post a surety bond with the Connecticut Department of Revenue Services and provide proof of such posting to AWA.
END OF DOCUMENT
Rev. 8/21/2026 00300-1 EJCDC No. C-410 (2002 Edition) Prepared by the Engineers' Joint Contract Documents Committee and endorsed by the Associated General Contractors of America and the Construction Specifications Institute.
DOCUMENT 00300
BID FORM
Project Name: ___________________________________________________________________________
TABLE OF ARTICLES
Page
Article 1 - Bid Recipient 1
Article 2 - Bidder’s Acknowledgments 1
Article 3 - Bidder’s Representations 1
Article 4 - Further Representations 2
Article 5 – Sales and Use Taxes 3
Article 6 - Basis of Bid 4
Article 7 - Time of Completion 4
Article 8 - Attachments to Bid 5
Article 9 - Defined Terms 5
Article 10 – License 5
Article 11 - Schedule of Values 5
Article 12 - Bid Submittal 6
ARTICLE 1 - BID RECIPIENT
1.01 This Bid Is Submitted To:
Aquarion Water Authority E-Bid System
600 Lindley Street, Bridgeport, CT 06606
Attn: Ken Feldkamp
1.02 The undersigned Bidder proposes and agrees, if this Bid is accepted, to enter into an Agreement with Owner in the form included in the Bidding Documents to perform all Work as specified or indicated in the Bidding
Documents for the prices and within the times indicated in the Bid and in accordance with the other terms and conditions of the Bidding Documents.
ARTICLE 2 - BIDDER’S ACKNOWLEDGMENTS
2.01 Bidder accepts all of the terms and conditions of the Invitation for Bid and Instructions to Bidders, including without limitations those dealing with the dispositions of Bid security. The Bid will remain subject to acceptance for 90 days after the Bid opening, or for such longer period of time that Bidder may agree to in writing upon request of Owner.
ARTICLE 3 - BIDDER’S REPRESENTATIONS
3.01 In submitting this Bid, Bidder represents that:
A. Bidder has examined and carefully studied the Bidding Documents, the other related data identified in the Bidding Documents, and the following Addenda, receipt of which is hereby acknowledged.
Addendum No. Addendum Date
Rev. 8/21/2026 00300-2 EJCDC No. C-410 (2002 Edition) and endorsed by the Associated General Contractors of America and the Construction Specifications Institute.
B. Bidder has visited the Site and become familiar with and is satisfied as to the general, local, and Site conditions that may affect cost, progress, and performance of the Work.
C. Bidder is familiar with and is satisfied as to all Federal, State, and local Laws and Regulations that may affect cost, progress, and performance of the Work.
D. Bidder has carefully studied all: (1) reports of explorations and tests of subsurface conditions at or contiguous to the Site and all drawings of physical conditions in or relating to existing surface or subsurface structures at or contiguous to the Site (except Underground Facilities) which have been identified in paragraph 4.02 of the Supplementary Conditions, and (2) reports and drawings of a Hazard
Environmental Condition, if any, which has been identified in paragraph 4.06 of the Supplementary
Conditions.
E. Bidder has obtained and carefully studied (or accepts the consequences for not doing so) all additional or supplementary examinations, investigations, explorations, tests, studies, and data concerning conditions (surface, subsurface and…