Awarded Bid Tabulation_ID FLAP FS SC MULTI(1).pdf
PDF 596 KB Posted
- Attached to
- ID FLAP FS SC MULTI(1), Custer Motorway Stabilization Project Federal contract opportunity
- Solicitation number
- 69056726F00022N
About this file
This is a Bid Tabulation Report for the Custer Motorway Stabilization Project (Project No. ID FLAP FS SC MULTI(1)), a federal lands construction project located in Custer County, Idaho on the Salmon-Challis National Forest. The solicitation (No. 69056725R000008) was opened on January 29, 2026, by the Western Federal Lands Highway Division (WFLHD) in Vancouver, Washington. The report documents bids received for two separate schedules of work. For Schedule A (Base), three contractors submitted bids: M.A. DeAtley Construction, Inc. ($2,007,370.00), Granite Construction Company ($1,303,240.00), and MJ Hughes Construction ($1,079,880.00), compared against an Engineer's Estimate of $830,000.00. For Schedule B (Base), the same three contractors bid $3,758,640.00, $2,550,966.00, and $1,991,647.00 respectively, against an Engineer's Estimate of $1,920,000.00.
The contract was awarded to MJ Hughes Construction on February 11, 2026, for Schedule B at $1,991,647.00. The report was certified by Contracting Officer Rebekah Ruth Webb on February 3, 2026, and generated on January 29, 2026. The detailed bid tabulation includes line-item pricing for all pay items across both schedules, encompassing mobilization, surveying, quality control, testing, erosion control, clearing and grubbing, riprap placement, reinforced soil slopes, equipment rental, labor, topsoil, mulching, plantings, stream diversion, traffic control, and environmental design elements including log barriers, root wads, fish passage boulders, and streambed material.
View the file
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
BID TABULATION REPORT
Project No. : ID FLAP FS SC MULTI(1) Project Name: Custer Motorway Stabilization Project
Contractor Responsive? Base Schedule A M.A. DeAtley Construction, Inc. $2,007,370.00 Granite Construction Company $1,303,240.00 MJ Hughes Construction $1,079,880.00 Engineer's Estimate $830,000.00
Report Generated on 01/29/2026 6:33 PM [Timezone: (UTC-05:00) Eastern Time (US & Canada)]
Generated by : Rebekah Webb
Awarded Schedule B
Contractor Responsive? Base Schedule B M.A. DeAtley Construction, Inc. $3,758,640.00 Granite Construction Company $2,550,966.00 MJ Hughes Construction $1,991,647.00 Engineer's Estimate $1,920,000.00
Report Generated on 01/29/2026 6:33 PM [Timezone: (UTC-05:00) Eastern Time (US & Canada)]
Generated by : Rebekah Webb
Project No. : ID FLAP FS SC MULTI (1)
Project Name: Custer Motorway Stabilization Project
Division: Western Federal Lands
Schedule: A Schedule Type: Base Lead Designer: Emily King Solicitation No. : 69056725R000008 Opened at: WFLHD Vancouver, WA
Opened by: Rebekah Webb
State: ID County: Custer Federal Land: Salmon-Challis
National Forest Bid Open Date and Time: 01/29/2026
Contract Awarded to: Award Date:
Contractor Comment Bid Amount Responsive M.A. DeAtley Construction, Inc., 829 Evans Rd., Clarkston, WA, 99403
$2,007,370.00
Granite Construction Company, 585 West Beach Street, Watsonville, CA, 95076
$1,303,240.00
MJ Hughes Construction, 11510 NE 87th Ave, Vancouver, WA, 98662
$1,079,880.00
Engineer's Estimate $830,000.00
I certify that this Bid Tabulation reflects the offers received for this solicitation
Signed:
Title:
Date:
Project No. : ID FLAP FS SC MULTI(1) Project Name: Custer Motorway Stabilization Project
Schedule: A Schedule Type: Base
Line Item Number
Pay Item Number Description Contractor Quantity Unit Unit Price Amount
A0020 15101-0000 MOBILIZATION M.A. DeAtley Construction, Inc. $348,100.00
Granite Construction Company $331,000.00
Report Generated on 01/29/2026 6:33 PM [Timezone: (UTC-05:00) Eastern Time (US & Canada)]
Generated by : Rebekah Webb
Contracting Officer
2/3/2026
Awarded Schedule B 2/11/2026
A0020 15101-0000 MOBILIZATION MJ Hughes Construction $242,000.00
Engineer's Estimate ALL LPSM LPSM $87,800.00
A0040 15201-0000 CONSTRUCTION
SURVEY AND
STAKING
M.A. DeAtley Construction, Inc. $100,000.00
MJ Hughes Construction $50,000.00
Granite Construction Company $40,000.00
Engineer's Estimate ALL LPSM LPSM $14,000.00
A0060 15301-0000 CONTRACTOR
QUALITY CONTROL
M.A. DeAtley Construction, Inc. $200,000.00
MJ Hughes Construction $135,000.00
Granite Construction Company $100,000.00
Engineer's Estimate ALL LPSM LPSM $14,000.00
A0080 15401-0000 CONTRACTOR
TESTING
M.A. DeAtley Construction, Inc. $100,000.00
Granite Construction Company $50,000.00
MJ Hughes Construction $50,000.00
Engineer's Estimate ALL LPSM LPSM $21,000.00
A0100 15501-0000 CONSTRUCTION
SCHEDULE
MJ Hughes Construction $7,000.00
Granite Construction Company $5,000.00
M.A. DeAtley Construction, Inc. $5,000.00
Engineer's Estimate ALL LPSM LPSM $3,000.00
A0120 15705-0100 SOIL EROSION
CONTROL, SILT
FENCE
Granite Construction Company 200.000 $10.00 $2,000.00
M.A. DeAtley Construction, Inc. 200.000 $9.00 $1,800.00
MJ Hughes Construction 200.000 $8.00 $1,600.00
Engineer's Estimate 200.000 LNFT $6.00 $1,200.00
A0140 15705-1400 SOIL EROSION
CONTROL, FIBER
ROLL
Granite Construction Company 410.000 $11.00 $4,510.00
MJ Hughes Construction 410.000 $8.00 $3,280.00
M.A. DeAtley Construction, Inc. 410.000 $7.00 $2,870.00
Engineer's Estimate 410.000 LNFT $10.00 $4,100.00
A0160 20102-0000 CLEARING AND
GRUBBING
Granite Construction Company $100,000.00
Report Generated on 01/29/2026 6:33 PM [Timezone: (UTC-05:00) Eastern Time (US & Canada)]
Generated by : Rebekah Webb
A0160 20102-0000 CLEARING AND
GRUBBING
M.A. DeAtley Construction, Inc. $50,000.00
MJ Hughes Construction $35,000.00
Engineer's Estimate ALL LPSM LPSM $12,000.00
A0180 25101-0200 PLACED RIPRAP,
CLASS 2
M.A. DeAtley Construction, Inc. 330.000 $295.00 $97,350.00
Granite Construction Company 330.000 $225.00 $74,250.00
MJ Hughes Construction 330.000 $160.00 $52,800.00
Engineer's Estimate 330.000 CUYD $240.00 $79,200.00
A0200 26101-1000 REINFORCED SOIL
SLOPE, WELDED
WIRE FACE
(VEGETATED)
M.A. DeAtley Construction, Inc. 2,000.000 $280.00 $560,000.00
MJ Hughes Construction 2,000.000 $125.00 $250,000.00
Granite Construction Company 2,000.000 $90.00 $180,000.00
Engineer's Estimate 2,000.000 SQFT $100.00 $200,000.00
A0220 62201-0250 DUMP TRUCK, 10
CUBIC YARD
MINIMUM
CAPACITY
Granite Construction Company 15.000 $300.00 $4,500.00
M.A. DeAtley Construction, Inc. 15.000 $230.00 $3,450.00
MJ Hughes Construction 15.000 $200.00 $3,000.00
Engineer's Estimate 15.000 HOUR $200.00 $3,000.00
A0240 62201-0900 WHEEL LOADER, 2
CUBIC YARD
MINIMUM RATED
CAPACITY
Granite Construction Company 10.000 $290.00 $2,900.00
M.A. DeAtley Construction, Inc. 10.000 $280.00 $2,800.00
MJ Hughes Construction 10.000 $175.00 $1,750.00
Engineer's Estimate 10.000 HOUR $275.00 $2,750.00
A0260 62201-2800 MOTOR GRADER, 8
FOOT MINIMUM
BLADE
M.A. DeAtley Construction, Inc. 5.000 $400.00 $2,000.00
Granite Construction Company 5.000 $360.00 $1,800.00
MJ Hughes Construction 5.000 $175.00 $875.00
Engineer's Estimate 5.000 HOUR $240.00 $1,200.00
A0280 62201-3150 HYDRAULIC
EXCAVATOR, 1.0
CUBIC YARD
MINIMUM
CAPACITY WITH
THUMB
ATTACHMENT
Granite Construction Company 20.000 $300.00 $6,000.00
M.A. DeAtley Construction, Inc. 20.000 $250.00 $5,000.00
MJ Hughes Construction 20.000 $250.00 $5,000.00
Engineer's Estimate 20.000 HOUR $250.00 $5,000.00
Report Generated on 01/29/2026 6:33 PM [Timezone: (UTC-05:00) Eastern Time (US & Canada)]
A0300 62301-0000 GENERAL LABOR Granite Construction Company 10.000 $150.00 $1,500.00
MJ Hughes Construction 10.000 $100.00 $1,000.00
M.A. DeAtley Construction, Inc. 10.000 $90.00 $900.00
Engineer's Estimate 10.000 HOUR $100.00 $1,000.00
A0320 62403-0000 PROVIDING AND
PLACING TOPSOIL
Granite Construction Company 120.000 $175.00 $21,000.00
M.A. DeAtley Construction, Inc. 120.000 $150.00 $18,000.00
MJ Hughes Construction 120.000 $110.00 $13,200.00
Engineer's Estimate 120.000 CUYD $130.00 $15,600.00
A0340 62516-2000 MULCHING,
HYDRAULIC
METHOD
M.A. DeAtley Construction, Inc. 840.000 $20.00 $16,800.00
MJ Hughes Construction 840.000 $20.00 $16,800.00
Granite Construction Company 840.000 $2.00 $1,680.00
Engineer's Estimate 840.000 SQYD $5.00 $4,200.00
A0360 62603-0000 PLANTINGS (MP
25.3) MJ Hughes Construction $35,000.00
M.A. DeAtley Construction, Inc. $17,000.00
Granite Construction Company $15,000.00
Engineer's Estimate ALL LPSM LPSM $20,000.00
A0380 62801-0000 TEMPORARY
STREAM
DIVERSION (MP
25.3)
M.A. DeAtley Construction, Inc. $300,000.00
Granite Construction Company $125,000.00
MJ Hughes Construction $105,000.00
Engineer's Estimate ALL LPSM LPSM $80,000.00
A0400 63502-0600 TEMPORARY
TRAFFIC CONTROL,
BARRICADE TYPE 3
M.A. DeAtley Construction, Inc. 10.000 $1,500.00 $15,000.00
MJ Hughes Construction 10.000 $250.00 $2,500.00
Granite Construction Company 10.000 $200.00 $2,000.00
Engineer's Estimate 10.000 EACH $300.00 $3,000.00
A0420 63502-1250 TEMPORARY
TRAFFIC CONTROL,
TUBULAR MARKER,
TYPE 42-INCH
M.A. DeAtley Construction, Inc. 25.000 $100.00 $2,500.00
Granite Construction Company 25.000 $60.00 $1,500.00
Report Generated on 01/29/2026 6:33 PM [Timezone: (UTC-05:00) Eastern Time (US & Canada)]
A0420 63502-1250 TEMPORARY
TRAFFIC CONTROL,
TUBULAR MARKER,
TYPE 42-INCH
MJ Hughes Construction 25.000 $5.00 $125.00
Engineer's Estimate 25.000 EACH $60.00 $1,500.00
A0440 63502-2000 TEMPORARY
TRAFFIC CONTROL,
PORTABLE
CHANGEABLE
MESSAGE SIGN
Granite Construction Company 2.000 $5,000.00 $10,000.00
MJ Hughes Construction 2.000 $3,000.00 $6,000.00
M.A. DeAtley Construction, Inc. 2.000 $1,500.00 $3,000.00
Engineer's Estimate 2.000 EACH $15,000.00 $30,000.00
A0460 63504-1000 TEMPORARY
TRAFFIC CONTROL,
CONSTRUCTION
SIGN
M.A. DeAtley Construction, Inc. 230.000 $100.00 $23,000.00
Granite Construction Company 230.000 $60.00 $13,800.00
MJ Hughes Construction 230.000 $25.00 $5,750.00
Engineer's Estimate 230.000 SQFT $35.00 $8,050.00
A0480 63506-0500 TEMPORARY
TRAFFIC CONTROL,
FLAGGER
Granite Construction Company 200.000 $165.00 $33,000.00
M.A. DeAtley Construction, Inc. 200.000 $40.00 $8,000.00
MJ Hughes Construction 200.000 $40.00 $8,000.00
Engineer's Estimate 200.000 HOUR $75.00 $15,000.00
A0500 63507-0700 TEMPORARY
TRAFFIC CONTROL,
TRAFFIC CONTROL
SUPERVISOR
Granite Construction Company 70.000 $800.00 $56,000.00
M.A. DeAtley Construction, Inc. 70.000 $250.00 $17,500.00
MJ Hughes Construction 70.000 $100.00 $7,000.00
Engineer's Estimate 70.000 DAY $1,100.00 $77,000.00
A0520 64702-2000 ENVIRONMENTAL
DESIGN, LOG
BARRIER
(GOVERNMENT
FURNISHED)
M.A. DeAtley Construction, Inc. 70.000 $110.00 $7,700.00
Granite Construction Company 70.000 $40.00 $2,800.00
MJ Hughes Construction 70.000 $40.00 $2,800.00
Engineer's Estimate 70.000 LNFT $100.00 $7,000.00
A0540 64703-5000 ENVIRONMENTAL
DESIGN, ROOT
WAD
(GOVERNMENT
FURNISHED)
Granite Construction Company 20.000 $2,600.00 $52,000.00
M.A. DeAtley Construction, Inc. 20.000 $1,900.00 $38,000.00
MJ Hughes Construction 20.000 $500.00 $10,000.00
Engineer's Estimate 20.000 EACH $2,000.00 $40,000.00
Report Generated on 01/29/2026 6:33 PM [Timezone: (UTC-05:00) Eastern Time (US & Canada)]
A0560 64703-6000 ENVIRONMENTAL
DESIGN, FISH
PASSAGE BOULDER
M.A. DeAtley Construction, Inc. 140.000 $190.00 $26,600.00
Granite Construction Company 140.000 $100.00 $14,000.00
MJ Hughes Construction 140.000 $100.00 $14,000.00
Engineer's Estimate 140.000 EACH $400.00 $56,000.00
A0580 64704-1000 ENVIRONMENTAL
DESIGN,
STREAMBED
MATERIAL
Granite Construction Company 140.000 $300.00 $42,000.00
M.A. DeAtley Construction, Inc. 140.000 $210.00 $29,400.00
MJ Hughes Construction 140.000 $100.00 $14,000.00
Engineer's Estimate 140.000 CUYD $150.00 $21,000.00
A0600 64704-1700 ENVIRONMENTAL
DESIGN, BANK
STABILIZATION
(COARSE WOODY
DEBRIS)
Granite Construction Company 40.000 $250.00 $10,000.00
M.A. DeAtley Construction, Inc. 40.000 $140.00 $5,600.00
MJ Hughes Construction 40.000 $35.00 $1,400.00
Engineer's Estimate 40.000 CUYD $60.00 $2,400.00
Report Generated on 01/29/2026 6:33 PM [Timezone: (UTC-05:00) Eastern Time (US & Canada)]
Project No. : ID FLAP FS SC MULTI (1)
Project Name: Custer Motorway Stabilization Project
Division: Western Federal Lands
Schedule: B Schedule Type: Base Lead Designer: Emily King Solicitation No. : 69056725R000008 Opened at: WFLHD Vancouver, WA
Opened by: Rebekah Webb
State: ID County: Custer Federal Land: Salmon-Challis
National Forest Bid Open Date and Time: 01/29/2026
Contract Awarded to: Award Date:
Contractor Comment Bid Amount Responsive M.A. DeAtley Construction, Inc., 829 Evans Rd., Clarkston, WA, 99403
$3,758,640.00
Granite Construction Company, 585 West Beach Street, Watsonville, CA, 95076
$2,550,966.00
MJ Hughes Construction, 11510 NE 87th Ave, Vancouver, WA, 98662
$1,991,647.00
Engineer's Estimate $1,920,000.00
I certify that this Bid Tabulation reflects the offers received for this solicitation
Signed:
Title:
Date:
Project No. : ID FLAP FS SC MULTI(1) Project Name: Custer Motorway Stabilization Project
Schedule: B Schedule Type: Base
Line Item Number
Pay Item Number Description Contractor Quantity Unit Unit Price Amount
B0020 15101-0000 MOBILIZATION Granite Construction Company $412,000.00
M.A. DeAtley Construction, Inc. $407,100.00
Report Generated on 01/29/2026 6:33 PM [Timezone: (UTC-05:00) Eastern Time (US & Canada)]
Generated by : Rebekah Webb
Contracting Officer
02/03/2026
MJ Hughes 2/11/2026
B0020 15101-0000 MOBILIZATION MJ Hughes Construction $242,000.00
Engineer's Estimate ALL LPSM LPSM $209,005.00
B0040 15201-0000 CONSTRUCTION
SURVEY AND
STAKING
M.A. DeAtley Construction, Inc. $150,000.00
MJ Hughes Construction $75,000.00
Granite Construction Company $50,000.00
Engineer's Estimate ALL LPSM LPSM $32,000.00
B0060 15301-0000 CONTRACTOR
QUALITY CONTROL
M.A. DeAtley Construction, Inc. $350,000.00
MJ Hughes Construction $250,000.00
Granite Construction Company $200,000.00
Engineer's Estimate ALL LPSM LPSM $32,000.00
B0080 15401-0000 CONTRACTOR
TESTING
M.A. DeAtley Construction, Inc. $150,000.00
Granite Construction Company $105,000.00
MJ Hughes Construction $75,000.00
Engineer's Estimate ALL LPSM LPSM $48,000.00
B0100 15501-0000 CONSTRUCTION
SCHEDULE
MJ Hughes Construction $7,000.00
Granite Construction Company $5,000.00
M.A. DeAtley Construction, Inc. $5,000.00
Engineer's Estimate ALL LPSM LPSM $8,000.00
B0120 15705-0100 SOIL EROSION
CONTROL, SILT
FENCE
Granite Construction Company 420.000 $10.00 $4,200.00
M.A. DeAtley Construction, Inc. 420.000 $9.00 $3,780.00
MJ Hughes Construction 420.000 $8.00 $3,360.00
Engineer's Estimate 420.000 LNFT $9.00 $3,780.00
B0140 15705-1400 SOIL EROSION
CONTROL, FIBER
ROLL
Granite Construction Company 900.000 $11.00 $9,900.00
MJ Hughes Construction 900.000 $8.00 $7,200.00
M.A. DeAtley Construction, Inc. 900.000 $7.00 $6,300.00
Engineer's Estimate 900.000 LNFT $10.00 $9,000.00
B0160 20102-0000 CLEARING AND
GRUBBING
Granite Construction Company $175,000.00
Report Generated on 01/29/2026 6:33 PM [Timezone: (UTC-05:00) Eastern Time (US & Canada)]
B0160 20102-0000 CLEARING AND
GRUBBING
M.A. DeAtley Construction, Inc. $100,000.00
MJ Hughes Construction $30,000.00
Engineer's Estimate ALL LPSM LPSM $28,000.00
B0180 25101-0200 PLACED RIPRAP,
CLASS 2
M.A. DeAtley Construction, Inc. 480.000 $295.00 $141,600.00
Granite Construction Company 480.000 $215.00 $103,200.00
MJ Hughes Construction 480.000 $155.00 $74,400.00
Engineer's Estimate 480.000 CUYD $240.00 $115,200.00
B0200 25101-0300 PLACED RIPRAP,
CLASS 3
M.A. DeAtley Construction, Inc. 400.000 $295.00 $118,000.00
Granite Construction Company 400.000 $250.00 $100,000.00
MJ Hughes Construction 400.000 $195.00 $78,000.00
Engineer's Estimate 400.000 CUYD $275.00 $110,000.00
B0220 26101-1000 REINFORCED SOIL
SLOPE, WELDED
WIRE FACE
(VEGETATED)
M.A. DeAtley Construction, Inc. 5,700.000 $220.00 $1,254,000.00
MJ Hughes Construction 5,700.000 $125.00 $712,500.00
Granite Construction Company 5,700.000 $90.00 $513,000.00
Engineer's Estimate 5,700.000 SQFT $100.00 $570,000.00
B0240 62201-0250 DUMP TRUCK, 10
CUBIC YARD
MINIMUM
CAPACITY
Granite Construction Company 30.000 $300.00 $9,000.00
M.A. DeAtley Construction, Inc. 30.000 $230.00 $6,900.00
MJ Hughes Construction 30.000 $150.00 $4,500.00
Engineer's Estimate 30.000 HOUR $200.00 $6,000.00
B0260 62201-0900 WHEEL LOADER, 2
CUBIC YARD
MINIMUM RATED
CAPACITY
Granite Construction Company 20.000 $290.00 $5,800.00
M.A. DeAtley Construction, Inc. 20.000 $280.00 $5,600.00
MJ Hughes Construction 20.000 $150.00 $3,000.00
Engineer's Estimate 20.000 HOUR $275.00 $5,500.00
B0280 62201-2800 MOTOR GRADER, 8
FOOT MINIMUM
BLADE
M.A. DeAtley Construction, Inc. 10.000 $400.00 $4,000.00
Granite Construction Company 10.000 $360.00 $3,600.00
MJ Hughes Construction 10.000 $175.00 $1,750.00
Engineer's Estimate 10.000 HOUR $240.00 $2,400.00
Report Generated on 01/29/2026 6:33 PM [Timezone: (UTC-05:00) Eastern Time (US & Canada)]
B0300 62201-3150 HYDRAULIC
EXCAVATOR, 1.0
CUBIC YARD
MINIMUM
CAPACITY WITH
THUMB
ATTACHMENT
Granite Construction Company 40.000 $300.00 $12,000.00
M.A. DeAtley Construction, Inc. 40.000 $250.00 $10,000.00
MJ Hughes Construction 40.000 $250.00 $10,000.00
Engineer's Estimate 40.000 HOUR $250.00 $10,000.00 B0320 62301-0000 GENERAL LABOR Granite Construction
Company 20.000 $150.00 $3,000.00
MJ Hughes Construction 20.000 $100.00 $2,000.00
M.A. DeAtley Construction, Inc. 20.000 $90.00 $1,800.00
Engineer's Estimate 20.000 HOUR $100.00 $2,000.00
B0340 62403-0000 PROVIDING AND
PLACING TOPSOIL
Granite Construction Company 320.000 $175.00 $56,000.00
M.A. DeAtley Construction, Inc. 320.000 $150.00 $48,000.00
MJ Hughes Construction 320.000 $90.00 $28,800.00
Engineer's Estimate 320.000 CUYD $130.00 $41,600.00
B0360 62516-2000 MULCHING,
HYDRAULIC
METHOD
M.A. DeAtley Construction, Inc. 2,433.000 $20.00 $48,660.00
MJ Hughes Construction 2,433.000 $14.00 $34,062.00
Granite Construction Company 2,433.000 $2.00 $4,866.00
Engineer's Estimate 2,433.000 SQYD $5.00 $12,165.00
B0380 62603-0000 PLANTINGS (MP
24.0) MJ Hughes Construction $35,000.00
Granite Construction Company $20,000.00
M.A. DeAtley Construction, Inc. $17,000.00
Engineer's Estimate ALL LPSM LPSM $20,000.00
B0400 62603-0000 PLANTINGS (MP
25.3) MJ Hughes Construction $35,000.00
M.A. DeAtley Construction, Inc. $17,000.00
Granite Construction Company $15,000.00
Engineer's Estimate ALL LPSM LPSM $20,000.00
B0420 62801-0000 TEMPORARY
STREAM
DIVERSION (MP
24.0)
M.A. DeAtley Construction, Inc. $300,000.00
Report Generated on 01/29/2026 6:33 PM [Timezone: (UTC-05:00) Eastern Time (US & Canada)]
B0420 62801-0000 TEMPORARY
STREAM
DIVERSION (MP
24.0)
Granite Construction Company $175,000.00
MJ Hughes Construction $75,000.00
Engineer's Estimate ALL LPSM LPSM $80,000.00
B0440 62801-0000 TEMPORARY
STREAM
DIVERSION (MP
25.3)
M.A. DeAtley Construction, Inc. $300,000.00
Granite Construction Company $125,000.00
MJ Hughes Construction $75,000.00
Engineer's Estimate ALL LPSM LPSM $80,000.00
B0460 63502-0600 TEMPORARY
TRAFFIC CONTROL,
BARRICADE TYPE 3
M.A. DeAtley Construction, Inc. 10.000 $1,500.00 $15,000.00
Granite Construction Company 10.000 $200.00 $2,000.00
MJ Hughes Construction 10.000 $200.00 $2,000.00
Engineer's Estimate 10.000 EACH $300.00 $3,000.00
B0480 63502-1250 TEMPORARY
TRAFFIC CONTROL,
TUBULAR MARKER,
TYPE 42-INCH
M.A. DeAtley Construction, Inc. 25.000 $100.00 $2,500.00
Granite Construction Company 25.000 $60.00 $1,500.00
MJ Hughes Construction 25.000 $5.00 $125.00
Engineer's Estimate 25.000 EACH $60.00 $1,500.00
B0500 63502-2000 TEMPORARY
TRAFFIC CONTROL,
PORTABLE
CHANGEABLE
MESSAGE SIGN
Granite Construction Company 2.000 $10,000.00 $20,000.00
MJ Hughes Construction 2.000 $6,000.00 $12,000.00
M.A. DeAtley Construction, Inc. 2.000 $1,500.00 $3,000.00
Engineer's Estimate 2.000 EACH $15,000.00 $30,000.00
B0520 63504-1000 TEMPORARY
TRAFFIC CONTROL,
CONSTRUCTION
SIGN
M.A. DeAtley Construction, Inc. 230.000 $100.00 $23,000.00
Granite Construction Company 230.000 $60.00 $13,800.00
MJ Hughes Construction 230.000 $25.00 $5,750.00
Engineer's Estimate 230.000 SQFT $35.00 $8,050.00
B0540 63506-0500 TEMPORARY
TRAFFIC CONTROL,
FLAGGER
Granite Construction Company 200.000 $165.00 $33,000.00
M.A. DeAtley Construction, Inc. 200.000 $40.00 $8,000.00
MJ Hughes Construction 200.000 $40.00 $8,000.00
Engineer's Estimate 200.000 HOUR $75.00 $15,000.00
Report Generated on 01/29/2026 6:33 PM [Timezone: (UTC-05:00) Eastern Time (US & Canada)]
B0560 63507-0700 TEMPORARY
TRAFFIC CONTROL,
TRAFFIC CONTROL
SUPERVISOR
Granite Construction Company 150.000 $800.00 $120,000.00
M.A. DeAtley Construction, Inc. 150.000 $250.00 $37,500.00
MJ Hughes Construction 150.000 $100.00 $15,000.00
Engineer's Estimate 150.000 DAY $1,100.00 $165,000.00
B0580 64702-2000 ENVIRONMENTAL
DESIGN, LOG
BARRIER
(GOVERNMENT
FURNISHED)
M.A. DeAtley Construction, Inc. 190.000 $110.00 $20,900.00
Granite Construction Company 190.000 $40.00 $7,600.00
MJ Hughes Construction 190.000 $35.00 $6,650.00
Engineer's Estimate 190.000 LNFT $100.00 $19,000.00
B0600 64703-5000 ENVIRONMENTAL
DESIGN, ROOT
WAD
(GOVERNMENT
FURNISHED)
Granite Construction Company 30.000 $2,600.00 $78,000.00
M.A. DeAtley Construction, Inc. 30.000 $1,900.00 $57,000.00
MJ Hughes Construction 30.000 $500.00 $15,000.00
Engineer's Estimate 30.000 EACH $2,000.00 $60,000.00
B0620 64703-6000 ENVIRONMENTAL
DESIGN, FISH
PASSAGE BOULDER
M.A. DeAtley Construction, Inc. 280.000 $190.00 $53,200.00
Granite Construction Company 280.000 $100.00 $28,000.00
MJ Hughes Construction 280.000 $100.00 $28,000.00
Engineer's Estimate 280.000 EACH $400.00 $112,000.00
B0640 64704-1000 ENVIRONMENTAL
DESIGN,
STREAMBED
MATERIAL
Granite Construction Company 360.000 $300.00 $108,000.00
M.A. DeAtley Construction, Inc. 360.000 $210.00 $75,600.00
MJ Hughes Construction 360.000 $100.00 $36,000.00
Engineer's Estimate 360.000 CUYD $150.00 $54,000.00
B0660 64704-1700 ENVIRONMENTAL
DESIGN, BANK
STABILIZATION
(COARSE WOODY
DEBRIS)
Granite Construction Company 130.000 $250.00 $32,500.00
M.A. DeAtley Construction, Inc. 130.000 $140.00 $18,200.00
MJ Hughes Construction 130.000 $35.00 $4,550.00
Engineer's Estimate 130.000 CUYD $60.00 $7,800.00
Report Generated on 01/29/2026 6:33 PM [Timezone: (UTC-05:00) Eastern Time (US & Canada)]
| 2026-02-11T10:31:24-0800 | |
| REBEKAH RUTH WEBB |
| 2026-02-11T10:31:03-0800 | |
| REBEKAH RUTH WEBB |
File details come from the government source that posted it. Updated .