This document is an Award Recommendation Notice for Request for Proposal (RFP) #240000000759 issued by the Michigan Department of Environment, Great Lakes, and Energy (EGLE) Procurement office. The RFP was to select a contractor to provide Michigan Home Energy Efficiency Rebate Planning services. Guidehouse LLP was recommended for award in the amount of $1,786,490, pending State Administrative Board approval. The contract term is two years with up to a one-year renewal option.
The evaluation process included technical criteria such as the vendor's questions worksheet, compliance with the statement of work requirements, staffing, and project management capabilities. Guidehouse scored the highest with a total of 100 points, demonstrating it met the requirements of the RFP. The award recommendation was based on Guidehouse providing the best value to the state, including its recognition of the connection between EGLE's recycling programs and the need to incorporate them into the rebate program design to support Michigan's recycling and decarbonization goals.
View the file
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Michigan.gov/MiProcurement
Michigan.gov/MiProcurement
AWARD RECOMMENDATION
Notice of Intent to Award Number: 240000000379 The Department of Environment, Great Lakes, and Energy’s Procurement office has completed the evaluation of RFP# 240000000759 for Michigan Home Energy Efficiency Rebate Planning and has recommended an award to Guidehouse Inc. in the amount of $1,786,490, pending State Administrative Board approval, if applicable. More information on the State Administrative Board can be found at: State Administrative Board.
Bidders who were not recommended for the award are encouraged to schedule a debriefing session with the Solicitation Manager. The debriefing session will provide the bidder with the State’s rationale on why the bidder was not recommended for the award. The Solicitation Manager may be contacted as follows:
Lisa VanOstran, Solicitation Manager.
vanostranl@michigan.gov
(517) 599-7680 Background Information:
This Request for Proposal (RFP) was to solicit responses for selection of a Contractor to provide Michigan Home Energy Efficiency Rebate Planning. The term of this contract is two years, with up to one one-year renewal option.
Bidders:
The RFP was posted on SIGMA VSS on December 21, 2024, for 42 days. The following bidders submitted proposals by the published due date of February 1, 2024.
| Bidder |
| Address, City, State, Zip Code |
| SDVOB* |
| GDBE** |
| Accenture LLP |
| 1001 Woodward Avenue, Suite 400 |
Detroit MI 48226
| No |
| No |
| Crowe LLP |
| 605 Seward Avenue, NW |
Grand Rapids MI 49504
| No |
| No |
| Guidehouse LLP |
| 1001 Woodward Avenue, Suite 500 |
Detroit MI 48226
| No |
| No |
| Indelible Health Solutions LLC |
| 3800 Esplanade Way, Suite 210 |
Tallahassee FL 32311
| No |
| No |
| MCL Jasco Inc |
| 7140 Fort Street |
Detroit MI 48209
| Yes |
| Unknown |
| Milepost Consulting SPC |
| 615 Main Street, #112 |
Nashville TN 37206
| No |
| No |
*SDVOB: Service-Disabled Veteran Owned Business **GDBE: Geographically Disadvantaged Business Enterprise
EVALUATION SYNOPSIS
I. Evaluation Process A Responsible Vendor is a vendor that demonstrates it has the ability to successfully perform the duties identified by the solicitation. A Responsive proposal is one that is submitted in accordance with the solicitation instructions and meets all mandatory requirements identified in the solicitation.
Proposal Instructions: Evaluation Process
| Technical Evaluation Criteria |
| Weight |
| 1. |
| Vendor Questions Worksheet |
| 25 |
| 2. |
| Schedule A, Statement of Work, Section 1 Requirements |
| 25 |
| 3. |
| Schedule A, Statement of Work, Section 2 Staffing |
| 25 |
| 4. |
| Schedule A, Statement of Work, Section 3 Project Management |
| 25 |
| Total |
| 100 |
Proposals receiving 80 or more technical evaluation points will have pricing evaluated and considered for award. The full evaluation process is stated in the RFP Proposal Instructions.
II. Evaluation Method Responses to this solicitation were reviewed by the Solicitation Manager in collaboration with Subject Matter Experts, which consisted of the following individuals:
Lisa VanOstran, Procurement Manager EGLE/Finance Division Julie Staveland, Assistant Division Director EGLE/Materials Management Division
Jake Wilkinson, Manager EGLE/Materials Management Division
III. Evaluation Results A. Bidder # 1 – Accenture LLP The Evaluation Team determined that Accenture LLP based on a score of 96, did meet the requirements of this RFP. This determination was accomplished by evaluating their responses to the Technical Evaluation Criteria.
1. Vendor Questions Worksheet The Evaluation Team determined that overall, the responses were mostly satisfactory, but the following deficiencies were noted:
a. Bidder took exception with Standard Terms and Conditions.
2. Schedule A, Statement of Work, Section 1 Requirements The Evaluation Team determined that overall, the responses were mostly satisfactory, but the following deficiencies were noted:
a. Bidder did not indicate involvement with DTE or utilities other than Consumers Energy.
b. Bidder’s plan seemed more focused on investor-owned utilities vs. municipal/coop utilities.
3. Schedule A, Statement of Work, Section 2 Staffing The Evaluation Team determined that the responses were satisfactory.
4. Schedule A, Statement of Work, Section 3 Project Management The Evaluation Team determined that the responses were satisfactory.
Total Score: 96/100
B. Bidder # 2 – Crowe LLP The Evaluation Team determined that Crowe LLP based on a score of 68, did not meet the requirements of this RFP. This determination was accomplished by evaluating their responses to the Technical Evaluation Criteria.
1. Vendor Questions Worksheet The Evaluation Team determined that overall, the responses were mostly satisfactory, but the following deficiencies were noted:
a. Bidder’s experience was not relevant to the size and scope of work described in the RFP.
b. Bidder took exception with Standard Terms and Conditions
2. Schedule A, Statement of Work, Section 1 Requirements The Evaluation Team determined that overall, the responses were mostly satisfactory, but the following deficiencies were noted:
a. Bidder does not have experience with rebate programs in Michigan.
3. Schedule A, Statement of Work, Section 2 Staffing The Evaluation Team determined that overall, the responses were mostly satisfactory, but the following deficiencies were noted:
a. Bidder indicates that they will employ a subcontractor but does not provide the required details.
4. Schedule A, Statement of Work, Section 3 Project Management The Evaluation Team determined that the responses were satisfactory.
Total Score: 68/100
C. Bidder # 3 – Guidehouse LLP The Evaluation Team determined that Guidehouse LLP based on a score of 100, did meet the requirements of this RFP. This determination was accomplished by evaluating their responses to the Technical Evaluation Criteria.
1. Vendor Questions Worksheet The Evaluation Team determined that the responses were satisfactory.
2. Schedule A, Statement of Work, Section 1 Requirements The Evaluation Team determined that the responses were satisfactory.
3. Schedule A, Statement of Work, Section 2 Staffing The Evaluation Team determined that the responses were satisfactory.
4. Schedule A, Statement of Work, Section 3 Project Management The Evaluation Team determined that the responses were satisfactory.
Total Score: 100/100
D. Bidder # 4 – Indelible Health Solutions LLC The Evaluation Team determined that Indelible Health Solutions LLC based on a score of 94, did meet the requirements of this RFP. This determination was accomplished by evaluating their responses to the Technical Evaluation Criteria.
1. Vendor Questions Worksheet The Evaluation Team determined that the responses were satisfactory.
2. Schedule A, Statement of Work, Section 1 Requirements The Evaluation Team determined that overall, the responses were mostly satisfactory, but the following deficiencies were noted:
a. Bidder has limited knowledge of Michigan.
b. Justice40 map referenced in bidder’s proposal did not include southeast Michigan.
c. Bidder did not provide adequate detail when describing how they would meet the requirements.
3. Schedule A, Statement of Work, Section 2 Staffing The Evaluation Team determined that the responses were satisfactory.
4. Schedule A, Statement of Work, Section 3 Project Management The Evaluation Team determined that the responses were satisfactory.
Total Score: 94/100
E. Bidder # 5 – MCL Jasco Inc.
The Evaluation Team determined that MCL Jasco Inc. based on a score of 70, did not meet the requirements of this RFP. This determination was accomplished by evaluating their responses to the Technical Evaluation Criteria.
1. Vendor Questions Worksheet The Evaluation Team determined that the responses were satisfactory.
2. Schedule A, Statement of Work, Section 1 Requirements The Evaluation Team determined that overall, the responses were mostly satisfactory, but the following deficiencies were noted:
a. Bidder did not provide adequate detail when describing how they would meet the requirements.
3. Schedule A, Statement of Work, Section 2 Staffing The Evaluation Team determined that the responses were satisfactory.
4. Schedule A, Statement of Work, Section 3 Project Management The Evaluation Team determined that the responses were mostly satisfactory, but the following deficiencies were noted:
a. Bidder did not provide adequate detail when describing their project plan.
Total Score: 70/100
F. Bidder # 6 – Milepost Consulting SPC The Evaluation Team determined that Milepost Consulting SPC based on a score of 61, did not meet the requirements of this RFP. This determination was accomplished by evaluating their responses to the Technical Evaluation Criteria.
1. Vendor Questions Worksheet The Evaluation Team determined that overall, the responses were mostly satisfactory, but the following deficiencies were noted:
a. Bidder did not provide a response to question #6 Standard Terms and Conditions.
b. Bidder’s experience was not relevant to the size and scope of work described in the RFP.
2. Schedule A, Statement of Work, Section 1 Requirements The Evaluation Team determined that overall, the responses were mostly satisfactory, but the following deficiencies were noted:
a. Bidder did not provide adequate detail when describing how they would meet the requirements.
3. Schedule A, Statement of Work, Section 2 Staffing The Evaluation Team determined that overall, the responses were mostly satisfactory, but the following deficiencies were noted:
a. Bidder did not provide Contractor Representative Name or Customer Service Phone Number.
4. Schedule A, Statement of Work, Section 3 Project Management The Evaluation Team determined that overall, the responses were mostly satisfactory, but the following deficiencies were noted:
a. Bidder did not provide adequate detail when describing their project plan.
b. Bidder did not include required sample reports.
Total Score: 61/100
IV. Technical Evaluation Summary
| Selection Criteria |
| Accenture |
| Crowe |
| Guidehouse |
| Indelible |
| MCL Jasco |
| Milepost |
| 1 |
| Vendor Questions Worksheet |
| 23 |
| 8 |
| 25 |
| 25 |
| 25 |
| 8 |
| 2 |
| Schedule A, Statement of Work, Section 1 Requirements |
| 23 |
| 20 |
| 25 |
| 19 |
| 5 |
| 20 |
| 3 |
| Schedule A, Statement of Work, Section 2 Staffing |
| 25 |
| 15 |
| 25 |
| 25 |
| 25 |
| 23 |
| 4 |
| Schedule A, Statement of Work, Section 3 Project Management |
| 25 |
| 25 |
| 25 |
| 25 |
| 15 |
| 10 |
| Total |
| 96 |
| 68 |
| 100 |
| 94 |
| 70 |
| 61 |
V. Pricing Summary Pricing was evaluated for the bidders who passed technical. The following is a summary of their price proposals:
| Deliverable |
| Accenture |
| Guidehouse |
| Indelible |
| 1 |
| Two-year project cost |
| $1,584,208 |
| $1,786,490 |
| $2,465,000 |
| Total Price |
| $1,584,208 |
| $1,786,490 |
| $2,465,000 |
VI. Award Recommendation Award recommendation is made to the responsive and responsible Bidder who offers the best value to the State of Michigan. Best value is based on the proposal meeting the minimum point threshold and offering the best combination of the factors stated in the Proposal Instructions Evaluation Process section, and price.
Guidehouse LLP provided the best value to the State. Best value factors for Award Recommendation include: Guidehouse recognized the connection between EGLE's recycling programs and the need to incorporate and coordinate them into the program design for Sec. 50121 rebate program. EGLE has a goal of increasing equitable access to recycling, supporting Michigan manufacturers, and building the foundation for a decarbonized and thriving Michigan economy. One of the goals stated in the MI Healthy Climate Plan is to triple Michigan's recycling rate to 45 percent. Recycling prevents the generation of greenhouse gases at several points along the lifecycle of a product, including avoided energy consumption associated with the mining and extraction of virgin materials and reduced methane emissions from landfills. Recycling is important in facilitating the safe management of waste materials and helping to maintain the flow of vital raw materials for Michigan manufacturing by supporting domestic supply chains.
Award Recommendation is made to Guidehouse LLP in the amount of $1,786,490.