About this file
This file comprises the meeting minutes and agenda from the City of Cumming, Georgia Work Session held on September 7, 2021, documenting council actions on multiple municipal contracts and projects. The city accepted proposals for four separate utility and infrastructure projects: Site Landscaping and Irrigation for the Cumming City Center (RFP issued June 23, 2021), Habersham Marina Road Water Line Replacement, State Barn Road Elevated Water Storage Tank painting and renovation, and a Cyber Security Upgrade for utility infrastructure protection. The painting project for the 500,000-gallon elevated leg tank received thirteen proposals, with sealed pricing proposals due by 10:00 a.m. on August 18, 2021. Award decisions were made during the September 7 work session meeting. All awarded contracts were 2021 budgeted items except the cyber security project, which was funded through federal infrastructure funds.
The city awarded the Site Landscaping and Irrigation contract to Watson Landscaping, Inc. at $932,945.76 from four proposals ranging from $932,945.76 to $1,144,809.51. The Habersham Marina Water Line Replacement contract was awarded to North Georgia Pipeline for $651,095.00. The State Barn Road Water Tank painting project was awarded to Onyx Blasting and Coating for $111,211.21 from thirteen proposals received. The Cyber Security Upgrade contract was awarded to Layer3 Communications for a five-year Fortinet Upgrade Solution at $448,942.82, with this vendor holding the state contract for this type of protection. All contract awards passed with unanimous or near-unanimous council approval. No proposal withdrawals were permitted within 90 days of the proposal opening date.
Text of this file
City of Cumming
Work Session Agenda
September 7, 2021
I. Meeting Called to Order-Troy Brumbalow, Mayor.
II. Invocation
III. Pledge to Flag
IV. Consider Agenda for Adoption
V. Consider for adoption the following meeting minutes:
A. Regular Meeting of August 17, 2021
VI. Acknowledgements, Proclamations, Resolutions, etc.
VII. Old Business
A. Utilities
1. City/ County Water Storage IGA (Removed from agenda)
VIII. New Business
A. Administration
1. Reschedule November Work Session
B. City Center
1. RFP Results- Site Landscaping and Irrigation
C. Utilities
1. Update to Utility Specifications
2. RFP Results- Habersham Marina Water Line Replacement
3. RFP Results- Painting the State Barn Road Water Tank
4. Cyber Security Upgrade
IX. Announcements
X. Executive Session (If Needed)
XI. Adjourn.
CITY OF CUMMING
COUNCIL MINUTES
WORK SESSION
SEPTEMBER 7, 2021
I. There was a Work Session meeting of the Mayor and Council of the City of Cumming on Tuesday, September 7, 2021, at 6:00 P.M., at City Hall in Cumming, Georgia. The
Mayor and all Council Members were properly notified as required by law and all were present. Mayor Troy Brumbalow presided over the meeting and called the meeting to order.
II. Invocation: Mayor Brumbalow asked Mr. Phil Higgins to deliver the invocation.
III. Pledge to the Flag. Mayor Brumbalow led everyone in the Pledge to the American
Flag.
IV. Consider Agenda for Adoption- Mayor Brumbalow requested to remove under Old
Business, A. Utilities: 1. City/ County Water Storage IGA. A motion was made by Jason
Evans and seconded by Chad Crane to amend the agenda as requested by Mayor
Brumbalow and adopt the remainder of the agenda as presented. The motion carried unanimously.
V. Consider for adoption the following meeting minutes: A. Regular Council Meeting of August 17, 2021: A motion was made by Chad Crane and seconded by Jason Evans to approve the minutes of the Regular Council Meeting of August 17, 2021 as presented. The motion carried unanimously.
VI. Acknowledgements, Proclamations, Resolutions, etc.-none
VII. Old Business A. Utilities: 1. City/ County Water Storage IGA: (Removed from agenda).
VIII. New Business A. Administration: 1. Reschedule November Work Session: City
Administrator Phil Higgins requested to reschedule the November Work Session due to the
November 2nd Municipal Election on the same date. A motion was made by Joey Cochran and seconded by Chad Crane to reschedule the November Work Session to Wednesday, November 3, 2021. The motion carried unanimously.
B. City Center: 1. RFP Results- Site Landscaping and Irrigation: City Administrator
Phil Higgins explained that on June 23, 2021 an RFP was sent out for proposals on the Site
Landscaping and Irrigation for the Cumming City Center. Four (4) proposals were received ranging from $932,945.76 to $1,144,809.51. The City staff and the Construction
Management team recommends the low proposal from Watson Landscaping, Inc. A motion was made by Christopher Light and seconded by Chad Crane to accept the low proposal from Watson Landscape, Inc. in the amount of $932,945.76. The motion carried 4-0 with
Councilmember Linda Ledbetter abstained.
C. Utilities: 1. Update to Utility Specifications: The Department of Utilities requests to adopt revised water, sewer, and storm water specifications and detail drawings. Director of
Utilities Jon Heard asked that the Mayor and Council read over the Utility Specifications and revisit at the regular meeting on September 21, 2021.
2. RFP Results- Habersham Marina Road Water Line Replacement: The Department of Utilities requests the Council to accept the lowest proposal for the replacement of the
Habersham Marina Water Line from North Georgia Pipeline. This was a 2021 budgeted item. A motion was made by Chad Crane, and seconded by Jason Evans to accept the low proposal from North Georgia Pipeline in the amount of $651,095.00. The motion carried unanimously.
3. RFP Results- Painting the State Barn Road Water Tank: The Department of Utilities received thirteen (13) proposals for the renovation and repainting of the State Barn
Elevated Water Storage Tank. This was a 2021 budgeted item. It is their recommendation to accept the low proposal from Onyx Blasting and Coating. A motion was made by Jason
Evans, and seconded by Chad Crane to accept the low proposal from Onyx Blasting and
Coating in the amount of $111,211.21. The motion carried unanimously.
4. Cyber Security Upgrade: The Department of Utilities requests that the Mayor and City
Council accept the proposal for the installation of advanced cyber security hardware and
Software to protect the Utility’s twenty-one (21) sites. This was not a budgeted item for
2021. The City did receive Federal Funds to complete infrastructure projects. IT Director
Shad Faulkner recommended to go with proposal from Layer3 Communications for the 5-year Fortinet Upgrade Solution. This company has the State Contract on this type of cyber security protection. A motion was made by Jason Evans and seconded by Chad Crane to accept the proposal from Layer3 Communications for the five (5) year Fortinet Upgrade
Solution in the amount of $448,942.82. The motion carried unanimously.
IX. Announcements-none.
X. Executive Session: Mayor Brumbalow stated there was a need to have Executive
Session to discuss the Sale or Lease of Real Property and Pending Litigation. A motion was made by Christopher Light and seconded by Chad Crane to recess into Executive
Session.
After a brief Executive Session, a motion was made by Christopher Light and seconded by
Jason Evans to reopen the regular meeting. A motion was made by Christopher Light and seconded by Jason Evans to authorize the sale of 7.58 acres (Parcel 195 221) located on
Aquatic Circle to the Board of Regents of the University System of Georgia for
$785,000.00 which amount was in excess of the appraised value of the land. The motion carried 4-0 with Councilmember Ledbetter absent.
XI. Adjournment: A motion was made by Chad Crane and seconded by Jason Evans to adjourn. The motion carried unanimously.
Approved this 21th day of September, 2021.
Mayor
Councilmember Councilmember
Councilmember Councilmember
Attest:
City Clerk Councilmember
Other files
| File | Type | Posted |
|---|---|---|
| 2021 Wtr Tank Painting Project | — | |
| 2021 Wtr Tank Painting Specs | — |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
File details come from the government source that posted it. Updated .