This is a Bid Tabulation Report for a federal construction project titled "Defense Access Roads FY 2026" (Project No. MT DAR MALM 2026(1)), managed by the Western Federal Lands Highway Division. The solicitation (69056726B000004) was opened on July 21, 2026, at the WFLHD Vancouver, WA office by Marino Chea, with bids tabulated by Contracting Officer Rebekah Ruth Webb.
The project consists of six contract schedules (A through F) for road reconstruction and maintenance work in Montana counties (Fergus, Judith Basin, and Wheatland). Three contractors submitted bids across all schedules: McKenzie Construction & Site Development, LLC (Washington, DC); Shumaker Trucking & Excavating Contractors, Inc. (Great Falls, MT); and KH Civil Contractors, Inc. (Lewistown, MT). Schedule C was awarded to KH Civil Contractors, Inc. on August 13, 2026, for $6,135,739.18. Bid amounts across all schedules ranged from approximately $3.9 million to $9.9 million, with Engineer's Estimates ranging from $4.3 million to $10.1 million. Line-item details cover standard road work including mobilization, surveying, quality control, testing, soil erosion control, culvert installation and maintenance, roadway aggregate placement, calcium chloride surface treatment, equipment rental, labor, turf establishment, and temporary traffic control. The report provides detailed unit pricing and quantities for each line item across all bidders and schedules, enabling comparison of contractor pricing strategies and responsiveness to the project requirements.
View the file
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
BID TABULATION REPORT
Project No. : MT DAR MALM 2026(1) Project Name: Defense Access Roads FY 2026
Contractor Responsive? Base Schedule A McKenzie Construction & Site Development, LLC $4,368,655.47
Shumaker Trucking & Excavating Contractors, Inc. $3,932,425.18
KH Civil Contractors, Inc. $3,979,351.29 Engineer's Estimate $4,346,362.00
Report Generated on 07/21/2026 8:05 PM [Timezone: (UTC-05:00) Eastern Time (US & Canada)]
Generated by : Rebekah Webb
Schedule C Awarded
Contractor Responsive? Base Schedule B McKenzie Construction & Site Development, LLC $5,493,097.24
Shumaker Trucking & Excavating Contractors, Inc. $4,902,788.85
KH Civil Contractors, Inc. $4,818,890.16 Engineer's Estimate $5,446,045.00
Report Generated on 07/21/2026 8:05 PM [Timezone: (UTC-05:00) Eastern Time (US & Canada)]
Generated by : Rebekah Webb
Contractor Responsive? Base Schedule C McKenzie Construction & Site Development, LLC $6,963,798.94
Shumaker Trucking & Excavating Contractors, Inc. $6,383,417.37
KH Civil Contractors, Inc. $6,135,739.18 Engineer's Estimate $7,097,260.00
Report Generated on 07/21/2026 8:05 PM [Timezone: (UTC-05:00) Eastern Time (US & Canada)]
Generated by : Rebekah Webb
Schedule C Awarded
Contractor Responsive? Base Schedule D McKenzie Construction & Site Development, LLC $7,940,597.70
Shumaker Trucking & Excavating Contractors, Inc. $6,937,510.01
KH Civil Contractors, Inc. $6,843,424.97 Engineer's Estimate $7,929,935.00
Report Generated on 07/21/2026 8:05 PM [Timezone: (UTC-05:00) Eastern Time (US & Canada)]
Contractor Responsive? Base Schedule E McKenzie Construction & Site Development, LLC $8,474,587.51
Shumaker Trucking & Excavating Contractors, Inc. $7,654,321.00
KH Civil Contractors, Inc. $7,566,223.70 Engineer's Estimate $8,524,520.00
Report Generated on 07/21/2026 8:05 PM [Timezone: (UTC-05:00) Eastern Time (US & Canada)]
Contractor Responsive? Base Schedule F McKenzie Construction & Site Development, LLC $9,979,146.29
Shumaker Trucking & Excavating Contractors, Inc. $9,180,866.90
KH Civil Contractors, Inc. $8,849,534.75 Engineer's Estimate $10,112,170.00
Report Generated on 07/21/2026 8:05 PM [Timezone: (UTC-05:00) Eastern Time (US & Canada)]
Project No. : MT DAR MALM 2026 (1)
Project Name: Defense Access Roads FY 2026
Division: Western Federal Lands
Schedule: A Schedule Type: Base Lead Designer:
Solicitation No. : 69056726B000004 Opened at: WFLHD Vancouver
WA
Opened by: Marino Chea
State: MT County: Fergus, Judith Basin, Wheatland
Federal Land: Bid Open Date and Time: 07/21/2026
Contract Awarded to: Award Date:
Contractor Comment Bid Amount Responsive McKenzie Construction & Site Development, LLC, 2301 Calvert St NW, Washington, DC, 20008
$4,368,655.47
KH Civil Contractors, Inc., 28 Robinson Way, Lewistown, MT, 59457
$3,979,351.29
Shumaker Trucking & Excavating Contractors, Inc., PO BOX 1279, Great Falls, MT, 59403
$3,932,425.18
Engineer's Estimate $4,346,362.00
I certify that this Bid Tabulation reflects the offers received for this solicitation
Signed:
Title:
Date:
Project No. : MT DAR MALM 2026(1) Project Name: Defense Access Roads FY 2026 Schedule: A Schedule Type: Base
Line Item Number
Pay Item Number Description Contractor Quantity Unit Unit Price Amount
A1000 15101-0000 MOBILIZATION KH Civil Contractors, Inc. $529,750.00
McKenzie Construction & Site Development, LLC
$480,842.33
Report Generated on 07/21/2026 8:05 PM [Timezone: (UTC-05:00) Eastern Time (US & Canada)]
Generated by : Rebekah Webb
REBEKAH
RUTH WEBB
Digitally signed by
REBEKAH RUTH WEBB
Date: 2026.07.21 17:11:20 -07'00'
A1000 15101-0000 MOBILIZATION Shumaker Trucking & Excavating Contractors, Inc.
$420,872.40
Engineer's Estimate ALL LPSM LPSM $500,000.00
A1020 15201-0000 CONSTRUCTION
SURVEY AND
STAKING
McKenzie Construction & Site Development, LLC
$154,967.60
Shumaker Trucking & Excavating Contractors, Inc.
$100,241.30
KH Civil Contractors, Inc. $10,010.00
Engineer's Estimate ALL LPSM LPSM $75,000.00
A1040 15301-0000 CONTRACTOR
QUALITY CONTROL
Shumaker Trucking & Excavating Contractors, Inc.
$380,399.30
McKenzie Construction & Site Development, LLC
$206,623.47
KH Civil Contractors, Inc. $71,500.00
Engineer's Estimate ALL LPSM LPSM $180,000.00
A1060 15401-0000 CONTRACTOR
TESTING
Shumaker Trucking & Excavating Contractors, Inc.
$203,421.20
KH Civil Contractors, Inc. $97,500.00
McKenzie Construction & Site Development, LLC
$93,009.26
Engineer's Estimate ALL LPSM LPSM $180,000.00
A1080 15501-0000 CONSTRUCTION
SCHEDULE
Shumaker Trucking & Excavating Contractors, Inc.
$92,940.45
McKenzie Construction & Site Development, LLC
$22,958.16
KH Civil Contractors, Inc. $13,000.00
Engineer's Estimate ALL LPSM LPSM $35,000.00
A1100 15705-1400 SOIL EROSION
CONTROL, FIBER
ROLL
McKenzie Construction & Site Development, LLC
700.000 $28.69 $20,083.00
Shumaker Trucking & Excavating Contractors, Inc.
700.000 $8.95 $6,265.00
KH Civil Contractors, Inc. 700.000 $6.50 $4,550.00
Engineer's Estimate 700.000 LNFT $9.00 $6,300.00
Report Generated on 07/21/2026 8:05 PM [Timezone: (UTC-05:00) Eastern Time (US & Canada)]
A1120 15802-0000 WATERING FOR
DUST CONTROL
Shumaker Trucking & Excavating Contractors, Inc.
$140,979.40
McKenzie Construction & Site Development, LLC
$91,832.65
KH Civil Contractors, Inc. $16,900.00
Engineer's Estimate ALL LPSM LPSM $25,000.00
A1140 20301-1900 REMOVAL OF PIPE
CULVERT (5 FEET
SPAN, 7 FEET RISE
CMP ARCH)
KH Civil Contractors, Inc. 1.000 $7,800.00 $7,800.00
Shumaker Trucking & Excavating Contractors, Inc.
1.000 $5,113.10 $5,113.10
McKenzie Construction & Site Development, LLC
1.000 $4,591.63 $4,591.63
Engineer's Estimate 1.000 EACH $10,500.00 $10,500.00
A1160 20403-0000 UNCLASSIFIED
BORROW
KH Civil Contractors, Inc. 60.000 $97.50 $5,850.00
Shumaker Trucking & Excavating Contractors, Inc.
60.000 $71.85 $4,311.00
McKenzie Construction & Site Development, LLC
60.000 $20.66 $1,239.60
Engineer's Estimate 60.000 CUYD $110.00 $6,600.00
A1180 25101-0200 PLACED RIPRAP,
CLASS 2 (RIPRAP
HEADWALL)
KH Civil Contractors, Inc. 5.000 $650.00 $3,250.00
McKenzie Construction & Site Development, LLC
5.000 $183.66 $918.30
Shumaker Trucking & Excavating Contractors, Inc.
5.000 $175.00 $875.00
Engineer's Estimate 5.000 CUYD $450.00 $2,250.00
A1200 30202-2000 ROADWAY
AGGREGATE,
METHOD 2
McKenzie Construction & Site Development, LLC
1,235.000 $57.39 $70,876.65
Shumaker Trucking & Excavating Contractors, Inc.
1,235.000 $42.05 $51,931.75
KH Civil Contractors, Inc. 1,235.000 $38.17 $47,139.95
Engineer's Estimate 1,235.000 TON $55.00 $67,925.00
A1220 30301-6000 ROADWAY
RECONDITIONING
McKenzie Construction & Site Development, LLC
18.050 $25,253.98 $455,834.34
Report Generated on 07/21/2026 8:05 PM [Timezone: (UTC-05:00) Eastern Time (US & Canada)]
A1220 30301-6000 ROADWAY
RECONDITIONING
Shumaker Trucking & Excavating Contractors, Inc.
18.050 $13,871.60 $250,382.38
KH Civil Contractors, Inc. 18.050 $4,550.00 $82,127.50
Engineer's Estimate 18.050 MILE $10,500.00 $189,525.00
A1240 31103-3000 STABILIZED
AGGREGATE
SURFACE COURSE,
CALCIUM
CHLORIDE
McKenzie Construction & Site Development, LLC
50,792.000 $43.43 $2,205,896.56
KH Civil Contractors, Inc. 50,792.000 $38.17 $1,938,730.64
Shumaker Trucking & Excavating Contractors, Inc.
50,792.000 $26.55 $1,348,527.60
Engineer's Estimate 50,792.000 TON $40.00 $2,031,680.00
A1260 31110-0000 CALCIUM
CHLORIDE
KH Civil Contractors, Inc. 880.000 $1,014.00 $892,320.00
Shumaker Trucking & Excavating Contractors, Inc.
880.000 $773.45 $680,636.00
McKenzie Construction & Site Development, LLC
880.000 $373.07 $328,301.60
Engineer's Estimate 880.000 TON $750.00 $660,000.00
A1280 60201-0800 24-INCH PIPE
CULVERT
Shumaker Trucking & Excavating Contractors, Inc.
78.000 $441.95 $34,472.10
McKenzie Construction & Site Development, LLC
78.000 $344.37 $26,860.86
KH Civil Contractors, Inc. 78.000 $283.40 $22,105.20
Engineer's Estimate 78.000 LNFT $250.00 $19,500.00
A1300 60201-1000 36-INCH PIPE
CULVERT
Shumaker Trucking & Excavating Contractors, Inc.
46.000 $555.35 $25,546.10
McKenzie Construction & Site Development, LLC
46.000 $401.76 $18,480.96
KH Civil Contractors, Inc. 46.000 $396.50 $18,239.00
Engineer's Estimate 46.000 LNFT $300.00 $13,800.00
A1320 60704-0000 CLEANING
CULVERT IN PLACE
McKenzie Construction & Site Development, LLC
2.000 $4,591.63 $9,183.26
Shumaker Trucking & Excavating Contractors, Inc.
2.000 $4,415.95 $8,831.90
Report Generated on 07/21/2026 8:05 PM [Timezone: (UTC-05:00) Eastern Time (US & Canada)]
A1320 60704-0000 CLEANING
CULVERT IN PLACE
KH Civil Contractors, Inc. 2.000 $3,250.00 $6,500.00
Engineer's Estimate 2.000 EACH $3,500.00 $7,000.00
A1340 62201-0300 DUMP TRUCK, 12
CUBIC YARD
MINIMUM
CAPACITY
KH Civil Contractors, Inc. 50.000 $185.90 $9,295.00
McKenzie Construction & Site Development, LLC
50.000 $177.92 $8,896.00
Shumaker Trucking & Excavating Contractors, Inc.
50.000 $175.00 $8,750.00
Engineer's Estimate 50.000 HOUR $250.00 $12,500.00
A1360 62201-0550 BACKHOE LOADER,
6 CUBIC FOOT
MINIMUM RATED
CAPACITY BUCKET,
24-INCH WIDTH
KH Civil Contractors, Inc. 50.000 $243.10 $12,155.00
Shumaker Trucking & Excavating Contractors, Inc.
50.000 $200.00 $10,000.00
McKenzie Construction & Site Development, LLC
50.000 $172.18 $8,609.00
Engineer's Estimate 50.000 HOUR $250.00 $12,500.00
A1380 62201-2850 MOTOR GRADER,
12 FOOT
MINIMUM BLADE
Shumaker Trucking & Excavating Contractors, Inc.
50.000 $250.00 $12,500.00
KH Civil Contractors, Inc. 50.000 $239.20 $11,960.00
McKenzie Construction & Site Development, LLC
50.000 $200.88 $10,044.00
Engineer's Estimate 50.000 HOUR $300.00 $15,000.00 A1400 62301-0000 GENERAL LABOR Shumaker Trucking &
Excavating Contractors, Inc.
50.000 $150.00 $7,500.00
McKenzie Construction & Site Development, LLC
50.000 $97.57 $4,878.50
KH Civil Contractors, Inc. 50.000 $93.60 $4,680.00
Engineer's Estimate 50.000 HOUR $90.00 $4,500.00
A1420 62405-0300 PLACING
CONSERVED
TOPSOIL, 4-INCH
DEPTH
McKenzie Construction & Site Development, LLC
270.000 $86.09 $23,244.30
KH Civil Contractors, Inc. 270.000 $10.00 $2,700.00
Shumaker Trucking & Excavating Contractors, Inc.
270.000 $3.55 $958.50
Engineer's Estimate 270.000 SQYD $10.00 $2,700.00
Report Generated on 07/21/2026 8:05 PM [Timezone: (UTC-05:00) Eastern Time (US & Canada)]
A1440 62502-0000 TURF
ESTABLISHMENT
(DRY METHOD)
McKenzie Construction & Site Development, LLC
667.000 $10.33 $6,890.11
KH Civil Contractors, Inc. 667.000 $7.00 $4,669.00
Shumaker Trucking & Excavating Contractors, Inc.
667.000 $1.50 $1,000.50
Engineer's Estimate 667.000 SQYD $6.00 $4,002.00
A1460 63501-0000 TEMPORARY
TRAFFIC CONTROL
KH Civil Contractors, Inc. $159,900.00
Shumaker Trucking & Excavating Contractors, Inc.
$133,114.20
McKenzie Construction & Site Development, LLC
$103,311.73
Engineer's Estimate ALL LPSM LPSM $275,000.00
A1480 63503-1000 TEMPORARY
TRAFFIC CONTROL,
PLASTIC FENCE
McKenzie Construction & Site Development, LLC
1,120.000 $9.18 $10,281.60
KH Civil Contractors, Inc. 1,120.000 $6.00 $6,720.00
Shumaker Trucking & Excavating Contractors, Inc.
1,120.000 $2.55 $2,856.00
Engineer's Estimate 1,120.000 LNFT $9.00 $10,080.00
Report Generated on 07/21/2026 8:05 PM [Timezone: (UTC-05:00) Eastern Time (US & Canada)]
(1)
Project Name: Defense Access Roads FY 2026
Division: Western Federal Lands
Schedule: B Schedule Type: Base Lead Designer:
Solicitation No. : 69056726B000004 Opened at: WFLHD Vancouver
WA
Opened by: Marino Chea
State: MT County: Fergus, Judith Basin, Wheatland
Federal Land: Bid Open Date and Time: 07/21/2026
Contract Awarded to: Award Date:
Contractor Comment Bid Amount Responsive McKenzie Construction & Site Development, LLC, 2301 Calvert St NW, Washington, DC, 20008
$5,493,097.24
Shumaker Trucking & Excavating Contractors, Inc., PO BOX 1279, Great Falls, MT, 59403
$4,902,788.85
KH Civil Contractors, Inc., 28 Robinson Way, Lewistown, MT, 59457
$4,818,890.16
Engineer's Estimate $5,446,045.00
I certify that this Bid Tabulation reflects the offers received for this solicitation
Signed:
Title:
Date:
Project No. : MT DAR MALM 2026(1) Project Name: Defense Access Roads FY 2026 Schedule: B Schedule Type: Base
Line Item Number
Pay Item Number Description Contractor Quantity Unit Unit Price Amount
B2000 15101-0000 MOBILIZATION KH Civil Contractors, Inc. $573,950.00
McKenzie Construction & Site Development, LLC
$570,095.12
Report Generated on 07/21/2026 8:05 PM [Timezone: (UTC-05:00) Eastern Time (US & Canada)]
Generated by : Rebekah Webb
REBEKAH
RUTH WEBB
Digitally signed by
REBEKAH RUTH WEBB
17:11:03 -07'00'
B2000 15101-0000 MOBILIZATION Shumaker Trucking & Excavating Contractors, Inc.
$500,818.20
Engineer's Estimate ALL LPSM LPSM $600,000.00
B2020 15201-0000 CONSTRUCTION
SURVEY AND
STAKING
McKenzie Construction & Site Development, LLC
$206,558.68
Shumaker Trucking & Excavating Contractors, Inc.
$124,053.15
KH Civil Contractors, Inc. $13,000.00
Engineer's Estimate ALL LPSM LPSM $90,000.00
B2040 15301-0000 CONTRACTOR
QUALITY CONTROL
Shumaker Trucking & Excavating Contractors, Inc.
$469,997.90
McKenzie Construction & Site Development, LLC
$275,411.58
KH Civil Contractors, Inc. $85,800.00
Engineer's Estimate ALL LPSM LPSM $230,000.00
B2060 15401-0000 CONTRACTOR
TESTING
Shumaker Trucking & Excavating Contractors, Inc.
$249,896.85
McKenzie Construction & Site Development, LLC
$121,508.14
KH Civil Contractors, Inc. $109,200.00
Engineer's Estimate ALL LPSM LPSM $230,000.00
B2080 15501-0000 CONSTRUCTION
SCHEDULE
Shumaker Trucking & Excavating Contractors, Inc.
$113,573.50
McKenzie Construction & Site Development, LLC
$28,688.70
KH Civil Contractors, Inc. $13,000.00
Engineer's Estimate ALL LPSM LPSM $40,000.00
B2100 15705-1400 SOIL EROSION
CONTROL, FIBER
ROLL
McKenzie Construction & Site Development, LLC
880.000 $28.68 $25,238.40
Shumaker Trucking & Excavating Contractors, Inc.
880.000 $8.95 $7,876.00
KH Civil Contractors, Inc. 880.000 $6.50 $5,720.00
Engineer's Estimate 880.000 LNFT $9.00 $7,920.00
Report Generated on 07/21/2026 8:05 PM [Timezone: (UTC-05:00) Eastern Time (US & Canada)]
B2120 15706-0200 SOIL EROSION
CONTROL, CHECK
DAM (FILTER ROCK)
Shumaker Trucking & Excavating Contractors, Inc.
41.000 $308.75 $12,658.75
KH Civil Contractors, Inc. 41.000 $227.50 $9,327.50
McKenzie Construction & Site Development, LLC
41.000 $57.37 $2,352.17
Engineer's Estimate 41.000 EACH $350.00 $14,350.00
B2140 15802-0000 WATERING FOR
DUST CONTROL
Shumaker Trucking & Excavating Contractors, Inc.
$177,051.05
McKenzie Construction & Site Development, LLC
$103,279.34
KH Civil Contractors, Inc. $20,800.00
Engineer's Estimate ALL LPSM LPSM $30,000.00
B2160 20301-1900 REMOVAL OF PIPE
CULVERT (5 FEET
SPAN, 7 FEET RISE
CMP ARCH)
KH Civil Contractors, Inc. 1.000 $7,800.00 $7,800.00
Shumaker Trucking & Excavating Contractors, Inc.
1.000 $5,113.10 $5,113.10
McKenzie Construction & Site Development, LLC
1.000 $4,590.19 $4,590.19
Engineer's Estimate 1.000 EACH $10,500.00 $10,500.00
B2180 20403-0000 UNCLASSIFIED
BORROW
KH Civil Contractors, Inc. 60.000 $97.50 $5,850.00
Shumaker Trucking & Excavating Contractors, Inc.
60.000 $71.85 $4,311.00
McKenzie Construction & Site Development, LLC
60.000 $20.65 $1,239.00
Engineer's Estimate 60.000 CUYD $110.00 $6,600.00
B2200 25101-0200 PLACED RIPRAP,
CLASS 2 (RIPRAP
HEADWALL)
KH Civil Contractors, Inc. 5.000 $650.00 $3,250.00
McKenzie Construction & Site Development, LLC
5.000 $183.60 $918.00
Shumaker Trucking & Excavating Contractors, Inc.
5.000 $175.00 $875.00
Engineer's Estimate 5.000 CUYD $450.00 $2,250.00
B2220 30202-2000 ROADWAY
AGGREGATE,
METHOD 2
McKenzie Construction & Site Development, LLC
1,515.000 $57.37 $86,915.55
Report Generated on 07/21/2026 8:05 PM [Timezone: (UTC-05:00) Eastern Time (US & Canada)]
B2220 30202-2000 ROADWAY
AGGREGATE,
METHOD 2
Shumaker Trucking & Excavating Contractors, Inc.
1,515.000 $42.05 $63,705.75
KH Civil Contractors, Inc. 1,515.000 $37.39 $56,645.85
Engineer's Estimate 1,515.000 TON $55.00 $83,325.00
B2240 30301-6000 ROADWAY
RECONDITIONING
McKenzie Construction & Site Development, LLC
23.000 $25,246.06 $580,659.38
Shumaker Trucking & Excavating Contractors, Inc.
23.000 $13,735.25 $315,910.75
KH Civil Contractors, Inc. 23.000 $4,550.00 $104,650.00
Engineer's Estimate 23.000 MILE $10,500.00 $241,500.00
B2260 31103-3000 STABILIZED
AGGREGATE
SURFACE COURSE,
CALCIUM
CHLORIDE
McKenzie Construction & Site Development, LLC
63,599.000 $43.42 $2,761,468.58
KH Civil Contractors, Inc. 63,599.000 $37.39 $2,377,966.61
Shumaker Trucking & Excavating Contractors, Inc.
63,599.000 $26.45 $1,682,193.55
Engineer's Estimate 63,599.000 TON $40.00 $2,543,960.00
B2280 31110-0000 CALCIUM
CHLORIDE
KH Civil Contractors, Inc. 1,102.000 $1,014.00 $1,117,428.00
Shumaker Trucking & Excavating Contractors, Inc.
1,102.000 $777.25 $856,529.50
McKenzie Construction & Site Development, LLC
1,102.000 $372.95 $410,990.90
Engineer's Estimate 1,102.000 TON $750.00 $826,500.00
B2300 60201-0800 24-INCH PIPE
CULVERT
Shumaker Trucking & Excavating Contractors, Inc.
78.000 $452.20 $35,271.60
McKenzie Construction & Site Development, LLC
78.000 $344.26 $26,852.28
KH Civil Contractors, Inc. 78.000 $283.40 $22,105.20
Engineer's Estimate 78.000 LNFT $250.00 $19,500.00
B2320 60201-1000 36-INCH PIPE
CULVERT
Shumaker Trucking & Excavating Contractors, Inc.
46.000 $572.70 $26,344.20
McKenzie Construction & Site Development, LLC
46.000 $401.64 $18,475.44
Report Generated on 07/21/2026 8:05 PM [Timezone: (UTC-05:00) Eastern Time (US & Canada)]
B2320 60201-1000 36-INCH PIPE
CULVERT
KH Civil Contractors, Inc. 46.000 $396.50 $18,239.00
Engineer's Estimate 46.000 LNFT $300.00 $13,800.00
B2340 60704-0000 CLEANING
CULVERT IN PLACE
McKenzie Construction & Site Development, LLC
4.000 $4,590.19 $18,360.76
Shumaker Trucking & Excavating Contractors, Inc.
4.000 $3,797.65 $15,190.60
KH Civil Contractors, Inc. 4.000 $3,250.00 $13,000.00
Engineer's Estimate 4.000 EACH $3,500.00 $14,000.00
B2360 62201-0300 DUMP TRUCK, 12
CUBIC YARD
MINIMUM
CAPACITY
KH Civil Contractors, Inc. 60.000 $185.90 $11,154.00
McKenzie Construction & Site Development, LLC
60.000 $177.86 $10,671.60
Shumaker Trucking & Excavating Contractors, Inc.
60.000 $175.00 $10,500.00
Engineer's Estimate 60.000 HOUR $250.00 $15,000.00
B2380 62201-0550 BACKHOE LOADER,
6 CUBIC FOOT
MINIMUM RATED
CAPACITY BUCKET,
24-INCH WIDTH
KH Civil Contractors, Inc. 60.000 $243.10 $14,586.00
Shumaker Trucking & Excavating Contractors, Inc.
60.000 $200.00 $12,000.00
McKenzie Construction & Site Development, LLC
60.000 $172.13 $10,327.80
Engineer's Estimate 60.000 HOUR $250.00 $15,000.00
B2400 62201-2850 MOTOR GRADER,
12 FOOT
MINIMUM BLADE
Shumaker Trucking & Excavating Contractors, Inc.
60.000 $250.00 $15,000.00
KH Civil Contractors, Inc. 60.000 $239.20 $14,352.00
McKenzie Construction & Site Development, LLC
60.000 $200.82 $12,049.20
Engineer's Estimate 60.000 HOUR $300.00 $18,000.00 B2420 62301-0000 GENERAL LABOR Shumaker Trucking &
Excavating Contractors, Inc.
60.000 $150.00 $9,000.00
McKenzie Construction & Site Development, LLC
60.000 $97.54 $5,852.40
KH Civil Contractors, Inc. 60.000 $93.60 $5,616.00
Engineer's Estimate 60.000 HOUR $90.00 $5,400.00
Report Generated on 07/21/2026 8:05 PM [Timezone: (UTC-05:00) Eastern Time (US & Canada)]
B2440 62405-0300 PLACING
CONSERVED
TOPSOIL, 4-INCH
DEPTH
McKenzie Construction & Site Development, LLC
270.000 $86.06 $23,236.20
KH Civil Contractors, Inc. 270.000 $10.00 $2,700.00
Shumaker Trucking & Excavating Contractors, Inc.
270.000 $3.55 $958.50
Engineer's Estimate 270.000 SQYD $10.00 $2,700.00
B2460 62502-0000 TURF
ESTABLISHMENT
(DRY METHOD)
McKenzie Construction & Site Development, LLC
1,500.000 $10.32 $15,480.00
KH Civil Contractors, Inc. 1,500.000 $7.00 $10,500.00
Shumaker Trucking & Excavating Contractors, Inc.
1,500.000 $1.50 $2,250.00
Engineer's Estimate 1,500.000 SQYD $6.00 $9,000.00
B2480 62901-0800 ROLLED EROSION
CONTROL
PRODUCT, TYPE
2.D
McKenzie Construction & Site Development, LLC
833.000 $28.68 $23,890.44
Shumaker Trucking & Excavating Contractors, Inc.
833.000 $11.45 $9,537.85
KH Civil Contractors, Inc. 833.000 $10.00 $8,330.00
Engineer's Estimate 833.000 SQYD $20.00 $16,660.00
B2500 63501-0000 TEMPORARY
TRAFFIC CONTROL
KH Civil Contractors, Inc. $187,200.00
Shumaker Trucking & Excavating Contractors, Inc.
$179,316.05
McKenzie Construction & Site Development, LLC
$137,705.79
Engineer's Estimate ALL LPSM LPSM $350,000.00
B2520 63503-1000 TEMPORARY
TRAFFIC CONTROL,
PLASTIC FENCE
McKenzie Construction & Site Development, LLC
1,120.000 $9.18 $10,281.60
KH Civil Contractors, Inc. 1,120.000 $6.00 $6,720.00
Shumaker Trucking & Excavating Contractors, Inc.
1,120.000 $2.55 $2,856.00
Engineer's Estimate 1,120.000 LNFT $9.00 $10,080.00
Report Generated on 07/21/2026 8:05 PM [Timezone: (UTC-05:00) Eastern Time (US & Canada)]
(1)
Project Name: Defense Access Roads FY 2026
Division: Western Federal Lands
Schedule: C Schedule Type: Base Lead Designer:
Solicitation No. : 69056726B000004 Opened at: WFLHD Vancouver
WA
Opened by: Marino Chea
State: MT County: Fergus, Judith Basin, Wheatland
Federal Land: Bid Open Date and Time: 07/21/2026
Contract Awarded to: Award Date:
Contractor Comment Bid Amount Responsive McKenzie Construction & Site Development, LLC, 2301 Calvert St NW, Washington, DC, 20008
$6,963,798.94
Shumaker Trucking & Excavating Contractors, Inc., PO BOX 1279, Great Falls, MT, 59403
$6,383,417.37
KH Civil Contractors, Inc., 28 Robinson Way, Lewistown, MT, 59457
$6,135,739.18
Engineer's Estimate $7,097,260.00
I certify that this Bid Tabulation reflects the offers received for this solicitation
Signed:
Title:
Date:
Project No. : MT DAR MALM 2026(1) Project Name: Defense Access Roads FY 2026 Schedule: C Schedule Type: Base
Line Item Number
Pay Item Number Description Contractor Quantity Unit Unit Price Amount
C3000 15101-0000 MOBILIZATION Shumaker Trucking & Excavating Contractors, Inc.
$672,261.15
McKenzie Construction & Site Development, LLC
$651,521.55
Report Generated on 07/21/2026 8:05 PM [Timezone: (UTC-05:00) Eastern Time (US & Canada)]
Generated by : Rebekah Webb
REBEKAH
RUTH WEBB
Digitally signed by
REBEKAH RUTH WEBB
Date: 2026.07.21 17:10:44 -07'00'
AWARDED SCHEDULE
KH Civil Contractors 08/13/2026
C3000 15101-0000 MOBILIZATION KH Civil Contractors, Inc. $638,950.00
Engineer's Estimate ALL LPSM LPSM $750,000.00
C3020 15201-0000 CONSTRUCTION
SURVEY AND
STAKING
McKenzie Construction & Site Development, LLC
$292,310.30
Shumaker Trucking & Excavating Contractors, Inc.
$160,265.20
KH Civil Contractors, Inc. $18,200.00
Engineer's Estimate ALL LPSM LPSM $115,000.00
C3040 15301-0000 CONTRACTOR
QUALITY CONTROL
Shumaker Trucking & Excavating Contractors, Inc.
$575,208.85
McKenzie Construction & Site Development, LLC
$389,747.07
KH Civil Contractors, Inc. $106,600.00
Engineer's Estimate ALL LPSM LPSM $310,000.00
C3060 15401-0000 CONTRACTOR
TESTING
Shumaker Trucking & Excavating Contractors, Inc.
$314,882.15
McKenzie Construction & Site Development, LLC
$129,940.52
KH Civil Contractors, Inc. $119,600.00
Engineer's Estimate ALL LPSM LPSM $310,000.00
C3080 15501-0000 CONSTRUCTION
SCHEDULE
Shumaker Trucking & Excavating Contractors, Inc.
$143,713.45
McKenzie Construction & Site Development, LLC
$34,389.44
KH Civil Contractors, Inc. $13,000.00
Engineer's Estimate ALL LPSM LPSM $45,000.00
C3100 15705-1400 SOIL EROSION
CONTROL, FIBER
ROLL
McKenzie Construction & Site Development, LLC
980.000 $28.65 $28,077.00
Shumaker Trucking & Excavating Contractors, Inc.
980.000 $8.95 $8,771.00
KH Civil Contractors, Inc. 980.000 $6.50 $6,370.00
Engineer's Estimate 980.000 LNFT $9.00 $8,820.00
Report Generated on 07/21/2026 8:05 PM [Timezone: (UTC-05:00) Eastern Time (US & Canada)]
C3120 15706-0200 SOIL EROSION
CONTROL, CHECK
DAM (FILTER ROCK)
McKenzie Construction & Site Development, LLC
41.000 $2,865.78 $117,496.98
Shumaker Trucking & Excavating Contractors, Inc.
41.000 $308.75 $12,658.75
KH Civil Contractors, Inc. 41.000 $227.50 $9,327.50
Engineer's Estimate 41.000 EACH $350.00 $14,350.00
C3140 15802-0000 WATERING FOR
DUST CONTROL
Shumaker Trucking & Excavating Contractors, Inc.
$229,915.75
McKenzie Construction & Site Development, LLC
$146,155.15
KH Civil Contractors, Inc. $29,900.00
Engineer's Estimate ALL LPSM LPSM $35,000.00
C3160 20301-1900 REMOVAL OF PIPE
CULVERT (5 FEET
SPAN, 7 FEET RISE
CMP ARCH)
KH Civil Contractors, Inc. 1.000 $7,800.00 $7,800.00
Shumaker Trucking & Excavating Contractors, Inc.
1.000 $5,113.10 $5,113.10
McKenzie Construction & Site Development, LLC
1.000 $4,585.25 $4,585.25
Engineer's Estimate 1.000 EACH $10,500.00 $10,500.00
C3180 20403-0000 UNCLASSIFIED
BORROW
KH Civil Contractors, Inc. 60.000 $97.50 $5,850.00
Shumaker Trucking & Excavating Contractors, Inc.
60.000 $71.85 $4,311.00
McKenzie Construction & Site Development, LLC
60.000 $20.63 $1,237.80
Engineer's Estimate 60.000 CUYD $110.00 $6,600.00
C3200 25101-0200 PLACED RIPRAP,
CLASS 2 (RIPRAP
HEADWALL)
KH Civil Contractors, Inc. 5.000 $650.00 $3,250.00
McKenzie Construction & Site Development, LLC
5.000 $183.41 $917.05
Shumaker Trucking & Excavating Contractors, Inc.
5.000 $175.00 $875.00
Engineer's Estimate 5.000 CUYD $450.00 $2,250.00
C3220 30202-2000 ROADWAY
AGGREGATE,
METHOD 2
McKenzie Construction & Site Development, LLC
1,515.000 $57.31 $86,824.65
Report Generated on 07/21/2026 8:05 PM [Timezone: (UTC-05:00) Eastern Time (US & Canada)]
C3220 30202-2000 ROADWAY
AGGREGATE,
METHOD 2
Shumaker Trucking & Excavating Contractors, Inc.
1,515.000 $42.05 $63,705.75
KH Civil Contractors, Inc. 1,515.000 $37.39 $56,645.85
Engineer's Estimate 1,515.000 TON $55.00 $83,325.00
C3240 30301-6000 ROADWAY
RECONDITIONING
McKenzie Construction & Site Development, LLC
32.490 $25,218.92 $819,362.71
Shumaker Trucking & Excavating Contractors, Inc.
32.490 $13,258.00 $430,752.42
KH Civil Contractors, Inc. 32.490 $4,550.00 $147,829.50
Engineer's Estimate 32.490 MILE $10,500.00 $341,145.00
C3260 31103-3000 STABILIZED
AGGREGATE
SURFACE COURSE,
CALCIUM
CHLORIDE
McKenzie Construction & Site Development, LLC
63,599.000 $43.37 $2,758,288.63
KH Civil Contractors, Inc. 63,599.000 $37.39 $2,377,966.61
Shumaker Trucking & Excavating Contractors, Inc.
63,599.000 $26.30 $1,672,653.70
Engineer's Estimate 63,599.000 TON $40.00 $2,543,960.00
C3280 31103-3000 STABILIZED
AGGREGATE
SURFACE COURSE,
CALCIUM
CHLORIDE (IN-
PLACE
STABILIZATION)
KH Civil Contractors, Inc. 13,981.000 $44.92 $628,026.52
McKenzie Construction & Site Development, LLC
13,981.000 $36.68 $512,823.08
Shumaker Trucking & Excavating Contractors, Inc.
13,981.000 $34.55 $483,043.55
Engineer's Estimate 13,981.000 TON $50.00 $699,050.00
C3300 31110-0000 CALCIUM
CHLORIDE
KH Civil Contractors, Inc. 1,592.000 $1,014.00 $1,614,288.00
Shumaker Trucking & Excavating Contractors, Inc.
1,592.000 $759.45 $1,209,044.40
McKenzie Construction & Site Development, LLC
1,592.000 $372.55 $593,099.60
Engineer's Estimate 1,592.000 TON $750.00 $1,194,000.00
C3320 60201-0800 24-INCH PIPE
CULVERT
Shumaker Trucking & Excavating Contractors, Inc.
78.000 $467.50 $36,465.00
McKenzie Construction & Site Development, LLC
78.000 $343.89 $26,823.42
Report Generated on 07/21/2026 8:05 PM [Timezone: (UTC-05:00) Eastern Time (US & Canada)]
C3320 60201-0800 24-INCH PIPE
CULVERT
KH Civil Contractors, Inc. 78.000 $283.40 $22,105.20
Engineer's Estimate 78.000 LNFT $250.00 $19,500.00
C3340 60201-1000 36-INCH PIPE
CULVERT
Shumaker Trucking & Excavating Contractors, Inc.
46.000 $598.70 $27,540.20
McKenzie Construction & Site Development, LLC
46.000 $401.21 $18,455.66
KH Civil Contractors, Inc. 46.000 $396.50 $18,239.00
Engineer's Estimate 46.000 LNFT $300.00 $13,800.00
C3360 60704-0000 CLEANING
CULVERT IN PLACE
McKenzie Construction & Site Development, LLC
4.000 $4,585.25 $18,341.00
Shumaker Trucking & Excavating Contractors, Inc.
4.000 $4,096.55 $16,386.20
KH Civil Contractors, Inc. 4.000 $3,250.00 $13,000.00
Engineer's Estimate 4.000 EACH $3,500.00 $14,000.00
C3380 60705-0000 REPAIRING
DRAINAGE
STRUCTURE
McKenzie Construction & Site Development, LLC
1.000 $16,048.40 $16,048.40
Shumaker Trucking & Excavating Contractors, Inc.
1.000 $8,973.80 $8,973.80
KH Civil Contractors, Inc. 1.000 $3,250.00 $3,250.00
Engineer's Estimate 1.000 EACH $4,500.00 $4,500.00
C3400 62201-0300 DUMP TRUCK, 12
CUBIC YARD
MINIMUM
CAPACITY
KH Civil Contractors, Inc. 70.000 $185.90 $13,013.00
McKenzie Construction & Site Development, LLC
70.000 $177.67 $12,436.90
Shumaker Trucking & Excavating Contractors, Inc.
70.000 $175.00 $12,250.00
Engineer's Estimate 70.000 HOUR $250.00 $17,500.00
C3420 62201-0550 BACKHOE LOADER,
6 CUBIC FOOT
MINIMUM RATED
CAPACITY BUCKET,
24-INCH WIDTH
KH Civil Contractors, Inc. 70.000 $243.10 $17,017.00
Shumaker Trucking & Excavating Contractors, Inc.
70.000 $200.00 $14,000.00
McKenzie Construction & Site Development, LLC
70.000 $171.94 $12,035.80
Engineer's Estimate 70.000 HOUR $250.00 $17,500.00
Report Generated on 07/21/2026 8:05 PM [Timezone: (UTC-05:00) Eastern Time (US & Canada)]
C3440 62201-2850 MOTOR GRADER,
12 FOOT
MINIMUM BLADE
Shumaker Trucking & Excavating Contractors, Inc.
70.000 $250.00 $17,500.00
KH Civil Contractors, Inc. 70.000 $239.20 $16,744.00
McKenzie Construction & Site Development, LLC
70.000 $200.60 $14,042.00
Engineer's Estimate 70.000 HOUR $300.00 $21,000.00 C3460 62301-0000 GENERAL LABOR Shumaker Trucking &
Excavating Contractors, Inc.
70.000 $150.00 $10,500.00
McKenzie Construction & Site Development, LLC
70.000 $97.43 $6,820.10
KH Civil Contractors, Inc. 70.000 $93.60 $6,552.00
Engineer's Estimate 70.000 HOUR $90.00 $6,300.00
C3480 62405-0300 PLACING
CONSERVED
TOPSOIL, 4-INCH
DEPTH
McKenzie Construction & Site Development, LLC
315.000 $85.97 $27,080.55
KH Civil Contractors, Inc. 315.000 $10.00 $3,150.00
Shumaker Trucking & Excavating Contractors, Inc.
315.000 $3.55 $1,118.25
Engineer's Estimate 315.000 SQYD $10.00 $3,150.00
C3500 62502-0000 TURF
ESTABLISHMENT
(DRY METHOD)
McKenzie Construction & Site Development, LLC
1,545.000 $10.31 $15,928.95
KH Civil Contractors, Inc. 1,545.000 $7.00 $10,815.00
Shumaker Trucking & Excavating Contractors, Inc.
1,545.000 $1.50 $2,317.50
Engineer's Estimate 1,545.000 SQYD $6.00 $9,270.00
C3520 62901-0800 ROLLED EROSION
CONTROL
PRODUCT, TYPE
2.D
McKenzie Construction & Site Development, LLC
833.000 $28.65 $23,865.45
Shumaker Trucking & Excavating Contractors, Inc.
833.000 $11.45 $9,537.85
KH Civil Contractors, Inc. 833.000 $10.00 $8,330.00
Engineer's Estimate 833.000 SQYD $20.00 $16,660.00
C3540 63501-0000 TEMPORARY
TRAFFIC CONTROL
Shumaker Trucking & Excavating Contractors, Inc.
$236,797.35
Report Generated on 07/21/2026 8:05 PM [Timezone: (UTC-05:00) Eastern Time (US & Canada)]
C3540 63501-0000 TEMPORARY
TRAFFIC CONTROL
KH Civil Contractors, Inc. $213,200.00
McKenzie Construction & Site Development, LLC
$194,873.53
Engineer's Estimate ALL LPSM LPSM $475,000.00
C3560 63503-1000 TEMPORARY
TRAFFIC CONTROL,
PLASTIC FENCE
McKenzie Construction & Site Development, LLC
1,120.000 $9.17 $10,270.40
KH Civil Contractors, Inc. 1,120.000 $6.00 $6,720.00
Shumaker Trucking & Excavating Contractors, Inc.
1,120.000 $2.55 $2,856.00
Engineer's Estimate 1,120.000 LNFT $9.00 $10,080.00
Report Generated on 07/21/2026 8:05 PM [Timezone: (UTC-05:00) Eastern Time (US & Canada)]
(1)
Project Name: Defense Access Roads FY 2026
Division: Western Federal Lands
Schedule: D Schedule Type: Base Lead Designer:
Solicitation No. : 69056726B000004 Opened at: WFLHD Vancouver
WA
Opened by: Marino Chea
State: MT County: Fergus, Judith Basin, Wheatland
Federal Land: Bid Open Date and Time: 07/21/2026
Contract Awarded to: Award Date:
Contractor Comment Bid Amount Responsive McKenzie Construction & Site Development, LLC, 2301 Calvert St NW, Washington, DC, 20008
$7,940,597.70
Shumaker Trucking & Excavating Contractors, Inc., PO BOX 1279, Great Falls, MT, 59403
$6,937,510.01
KH Civil Contractors, Inc., 28 Robinson Way, Lewistown, MT, 59457
$6,843,424.97
Engineer's Estimate $7,929,935.00
I certify that this Bid Tabulation reflects the offers received for this solicitation
Signed:
Title:
Date:
Project No. : MT DAR MALM 2026(1) Project Name: Defense Access Roads FY 2026 Schedule: D Schedule Type: Base
Line Item Number
Pay Item Number Description Contractor Quantity Unit Unit Price Amount
D4000 15101-0000 MOBILIZATION McKenzie Construction & Site Development, LLC
$875,637.34
Shumaker Trucking & Excavating Contractors, Inc.
$688,634.60
Report Generated on 07/21/2026 8:05 PM [Timezone: (UTC-05:00) Eastern Time (US & Canada)]
Generated by : Rebekah Webb
REBEKAH
RUTH WEBB
Digitally signed by
REBEKAH RUTH WEBB
17:10:26 -07'00'
D4000 15101-0000 MOBILIZATION KH Civil Contractors, Inc. $672,750.00
Engineer's Estimate ALL LPSM LPSM $800,000.00
D4020 15201-0000 CONSTRUCTION
SURVEY AND
STAKING
McKenzie Construction & Site Development, LLC
$344,919.82
Shumaker Trucking & Excavating Contractors, Inc.
$162,206.70
KH Civil Contractors, Inc. $20,800.00
Engineer's Estimate ALL LPSM LPSM $125,000.00
D4040 15301-0000 CONTRACTOR
QUALITY CONTROL
Shumaker Trucking & Excavating Contractors, Inc.
$632,791.60
McKenzie Construction & Site Development, LLC
$459,893.09
KH Civil Contractors, Inc. $114,400.00
Engineer's Estimate ALL LPSM LPSM $355,000.00
D4060 15401-0000 CONTRACTOR
TESTING
Shumaker Trucking & Excavating Contractors, Inc.
$323,993.90
McKenzie Construction & Site Development, LLC
$138,111.64
KH Civil Contractors, Inc. $127,400.00
Engineer's Estimate ALL LPSM LPSM $355,000.00
D4080 15501-0000 CONSTRUCTION
SCHEDULE
Shumaker Trucking & Excavating Contractors, Inc.
$145,615.35
McKenzie Construction & Site Development, LLC
$40,240.64
KH Civil Contractors, Inc. $13,000.00
Engineer's Estimate ALL LPSM LPSM $50,000.00
D4100 15705-1400 SOIL EROSION
CONTROL, FIBER
ROLL
McKenzie Construction & Site Development, LLC
1,160.000 $28.74 $33,338.40
Shumaker Trucking & Excavating Contractors, Inc.
1,160.000 $8.95 $10,382.00
KH Civil Contractors, Inc. 1,160.000 $6.50 $7,540.00
Engineer's Estimate 1,160.000 LNFT $9.00 $10,440.00
Report Generated on 07/21/2026 8:05 PM [Timezone: (UTC-05:00) Eastern Time (US & Canada)]
D4120 15706-0200 SOIL EROSION
CONTROL, CHECK
DAM (FILTER ROCK)
McKenzie Construction & Site Development, LLC
41.000 $2,874.33 $117,847.53
Shumaker Trucking & Excavating Contractors, Inc.
41.000 $308.75 $12,658.75
KH Civil Contractors, Inc. 41.000 $227.50 $9,327.50
Engineer's Estimate 41.000 EACH $350.00 $14,350.00
D4140 15802-0000 WATERING FOR
DUST CONTROL
Shumaker Trucking & Excavating Contractors, Inc.
$234,290.30
McKenzie Construction & Site Development, LLC
$172,459.91
KH Civil Contractors, Inc. $33,800.00
Engineer's Estimate ALL LPSM LPSM $40,000.00
D4160 20301-1900 REMOVAL OF PIPE
CULVERT (5 FEET
SPAN, 7 FEET RISE
CMP ARCH)
KH Civil Contractors, Inc. 1.000 $7,800.00 $7,800.00
Shumaker Trucking & Excavating Contractors, Inc.
1.000 $5,113.10 $5,113.10
McKenzie Construction & Site Development, LLC
1.000 $4,598.93 $4,598.93
Engineer's Estimate 1.000 EACH $10,500.00 $10,500.00
D4180 20403-0000 UNCLASSIFIED
BORROW
KH Civil Contractors, Inc. 60.000 $97.50 $5,850.00
Shumaker Trucking & Excavating Contractors, Inc.
60.000 $71.85 $4,311.00
McKenzie Construction & Site Development, LLC
60.000 $20.69 $1,241.40
Engineer's Estimate 60.000 CUYD $110.00 $6,600.00
D4200 25101-0200 PLACED RIPRAP,
CLASS 2 (RIPRAP
HEADWALL)
KH Civil Contractors, Inc. 5.000 $650.00 $3,250.00
McKenzie Construction & Site Development, LLC
5.000 $183.95 $919.75
Shumaker Trucking & Excavating Contractors, Inc.
5.000 $175.00 $875.00
Engineer's Estimate 5.000 CUYD $450.00 $2,250.00
D4220 30202-2000 ROADWAY
AGGREGATE,
METHOD 2
McKenzie Construction & Site Development, LLC
1,515.000 $57.48 $87,082.20
Report Generated on 07/21/2026 8:05 PM [Timezone: (UTC-05:00) Eastern Time (US & Canada)]
D4220 30202-2000 ROADWAY
AGGREGATE,
METHOD 2
Shumaker Trucking & Excavating Contractors, Inc.
1,515.000 $42.05 $63,705.75
KH Civil Contractors, Inc. 1,515.000 $37.39 $56,645.85
Engineer's Estimate 1,515.000 TON $55.00 $83,325.00
D4240 30301-6000 ROADWAY
RECONDITIONING
McKenzie Construction & Site Development, LLC
37.380 $25,294.12 $945,494.21
Shumaker Trucking & Excavating Contractors, Inc.
37.380 $12,595.55 $470,821.66
KH Civil Contractors, Inc. 37.380 $4,550.00 $170,079.00
Engineer's Estimate 37.380 MILE $10,500.00 $392,490.00
D4260 31103-3000 STABILIZED
AGGREGATE
SURFACE COURSE,
CALCIUM
CHLORIDE
McKenzie Construction & Site Development, LLC
63,599.000 $43.50 $2,766,556.50
KH Civil Contractors, Inc. 63,599.000 $37.39 $2,377,966.61
Shumaker Trucking & Excavating Contractors, Inc.
63,599.000 $26.30 $1,672,653.70
Engineer's Estimate 63,599.000 TON $40.00 $2,543,960.00
D4280 31103-3000 STABILIZED
AGGREGATE
SURFACE COURSE,
CALCIUM
CHLORIDE (IN-
PLACE
STABILIZATION)
KH Civil Contractors, Inc. 20,759.000 $46.59 $967,161.81
McKenzie Construction & Site Development, LLC
20,759.000 $36.79 $763,723.61
Shumaker Trucking & Excavating Contractors, Inc.
20,759.000 $33.05 $686,084.95
Engineer's Estimate 20,759.000 TON $50.00 $1,037,950.00
D4300 31110-0000 CALCIUM
CHLORIDE
KH Civil Contractors, Inc. 1,829.000 $1,014.00 $1,854,606.00
Shumaker Trucking & Excavating Contractors, Inc.
1,829.000 $756.90 $1,384,370.10
McKenzie Construction & Site Development, LLC
1,829.000 $373.66 $683,424.14
Engineer's Estimate 1,829.000 TON $750.00 $1,371,750.00
D4320 60201-0800 24-INCH PIPE
CULVERT
Shumaker Trucking & Excavating Contractors, Inc.
78.000 $467.75 $36,484.50
McKenzie Construction & Site Development, LLC
78.000 $344.91 $26,902.98
Report Generated on 07/21/2026 8:05 PM [Timezone: (UTC-05:00) Eastern Time (US & Canada)]
D4320 60201-0800 24-INCH PIPE
CULVERT
KH Civil Contractors, Inc. 78.000 $283.40 $22,105.20
Engineer's Estimate 78.000 LNFT $250.00 $19,500.00
D4340 60201-1000 36-INCH PIPE
CULVERT
Shumaker Trucking & Excavating Contractors, Inc.
46.000 $599.10 $27,558.60
McKenzie Construction & Site Development, LLC
46.000 $402.40 $18,510.40
KH Civil Contractors, Inc. 46.000 $396.50 $18,239.00
Engineer's Estimate 46.000 LNFT $300.00 $13,800.00
D4360 60704-0000 CLEANING
CULVERT IN PLACE
McKenzie Construction & Site Development, LLC
5.000 $4,598.93 $22,994.65
Shumaker Trucking & Excavating Contractors, Inc.
5.000 $3,836.95 $19,184.75
KH Civil Contractors, Inc. 5.000 $3,250.00 $16,250.00
Engineer's Estimate 5.000 EACH $3,500.00 $17,500.00
D4380 60705-0000 REPAIRING
DRAINAGE
STRUCTURE
McKenzie Construction & Site Development, LLC
4.000 $16,096.25 $64,385.00
Shumaker Trucking & Excavating Contractors, Inc.
4.000 $5,027.85 $20,111.40
KH Civil Contractors, Inc. 4.000 $3,250.00 $13,000.00
Engineer's Estimate 4.000 EACH $4,500.00 $18,000.00
D4400 62201-0300 DUMP TRUCK, 12
CUBIC YARD
MINIMUM
CAPACITY
KH Civil Contractors, Inc. 80.000 $185.90 $14,872.00
McKenzie Construction & Site Development, LLC
80.000 $178.20 $14,256.00
Shumaker Trucking & Excavating Contractors, Inc.
80.000 $175.00 $14,000.00
Engineer's Estimate 80.000 HOUR $250.00 $20,000.00
D4420 62201-0550 BACKHOE LOADER,
6 CUBIC FOOT
MINIMUM RATED
CAPACITY BUCKET,
24-INCH WIDTH
KH Civil Contractors, Inc. 80.000 $243.10 $19,448.00
Shumaker Trucking & Excavating Contractors, Inc.
80.000 $200.00 $16,000.00
McKenzie Construction & Site Development, LLC
80.000 $172.45 $13,796.00
Engineer's Estimate 80.000 HOUR $250.00 $20,000.00
Report Generated on 07/21/2026 8:05 PM [Timezone: (UTC-05:00) Eastern Time (US & Canada)]
D4440 62201-2850 MOTOR GRADER,
12 FOOT
MINIMUM BLADE
Shumaker Trucking & Excavating Contractors, Inc.
80.000 $250.00 $20,000.00
KH Civil Contractors, Inc. 80.000 $239.20 $19,136.00
McKenzie Construction & Site Development, LLC
80.000 $201.20 $16,096.00
Engineer's Estimate 80.000 HOUR $300.00 $24,000.00 D4460 62301-0000 GENERAL LABOR Shumaker Trucking &
Excavating Contractors, Inc.
80.000 $150.00 $12,000.00
McKenzie Construction & Site Development, LLC
80.000 $97.72 $7,817.60
KH Civil Contractors, Inc. 80.000 $93.60 $7,488.00
Engineer's Estimate 80.000 HOUR $90.00 $7,200.00
D4480 62405-0300 PLACING
CONSERVED
TOPSOIL, 4-INCH
DEPTH
McKenzie Construction & Site Development, LLC
450.000 $86.22 $38,799.00
KH Civil Contractors, Inc. 450.000 $10.00 $4,500.00
Shumaker Trucking & Excavating Contractors, Inc.
450.000 $3.55 $1,597.50
Engineer's Estimate 450.000 SQYD $10.00 $4,500.00
D4500 62502-0000 TURF
ESTABLISHMENT
(DRY METHOD)
McKenzie Construction & Site Development, LLC
1,680.000 $10.34 $17,371.20
KH Civil Contractors, Inc. 1,680.000 $7.00 $11,760.00
Shumaker Trucking & Excavating Contractors, Inc.
1,680.000 $1.50 $2,520.00
Engineer's Estimate 1,680.000 SQYD $6.00 $10,080.00
D4520 62901-0800 ROLLED EROSION
CONTROL
PRODUCT, TYPE
2.D
McKenzie Construction & Site Development, LLC
833.000 $28.74 $23,940.42
Shumaker Trucking & Excavating Contractors, Inc.
833.000 $11.45 $9,537.85
KH Civil Contractors, Inc. 833.000 $10.00 $8,330.00
Engineer's Estimate 833.000 SQYD $20.00 $16,660.00
D4540 63501-0000 TEMPORARY
TRAFFIC CONTROL
Shumaker Trucking & Excavating Contractors, Inc.
$257,318.95
Report Generated on 07/21/2026 8:05 PM [Timezone: (UTC-05:00) Eastern Time (US & Canada)]
D4540 63501-0000 TEMPORARY
TRAFFIC CONTROL
KH Civil Contractors, Inc. $239,200.00
McKenzie Construction & Site Development, LLC
$229,946.54
Engineer's Estimate ALL LPSM LPSM $550,000.00
D4560 63503-1000 TEMPORARY
TRAFFIC CONTROL,
PLASTIC FENCE
McKenzie Construction & Site Development, LLC
1,120.000 $9.19 $10,292.80
KH Civil Contractors, Inc. 1,120.000 $6.00 $6,720.00
Shumaker Trucking & Excavating Contractors, Inc.
1,120.000 $2.40 $2,688.00
Engineer's Estimate 1,120.000 LNFT $9.00 $10,080.00
Report Generated on 07/21/2026 8:05 PM [Timezone: (UTC-05:00) Eastern Time (US & Canada)]
(1)
Project Name: Defense Access Roads FY 2026
Division: Western Federal Lands
Schedule: E Schedule Type: Base Lead Designer:
Solicitation No. : 69056726B000004 Opened at: WFLHD Vancouver
WA
Opened by: Marino Chea
State: MT County: Fergus, Judith Basin, Wheatland
Federal Land: Bid Open Date and Time: 07/21/2026
Contract Awarded to: Award Date:
Contractor Comment Bid Amount Responsive McKenzie Construction & Site Development, LLC, 2301 Calvert St NW, Washington, DC, 20008
$8,474,587.51
Shumaker Trucking & Excavating Contractors, Inc., PO BOX 1279, Great Falls, MT, 59403
$7,654,321.00
KH Civil Contractors, Inc., 28 Robinson Way, Lewistown, MT, 59457
$7,566,223.70
Engineer's Estimate $8,524,520.00
I certify that this Bid Tabulation reflects the offers received for this solicitation
Signed:
Title:
Date:
Project No. : MT DAR MALM 2026(1) Project Name: Defense Access Roads FY 2026 Schedule: E Schedule Type: Base
Line Item Number
Pay Item Number Description Contractor Quantity Unit Unit Price Amount
E5000 15101-0000 MOBILIZATION McKenzie Construction & Site Development, LLC
$838,052.26
Shumaker Trucking & Excavating Contractors, Inc.
$772,369.15
Report Generated on 07/21/2026 8:05 PM [Timezone: (UTC-05:00) Eastern Time (US & Canada)]
Generated by : Rebekah Webb
REBEKAH
RUTH WEBB
Digitally signed by
REBEKAH RUTH WEBB
17:10:03 -07'00'
E5000 15101-0000 MOBILIZATION KH Civil Contractors, Inc. $759,200.00
Engineer's Estimate ALL LPSM LPSM $850,000.00
E5020 15201-0000 CONSTRUCTION
SURVEY AND
STAKING
McKenzie Construction & Site Development, LLC
$378,752.11
Shumaker Trucking & Excavating Contractors, Inc.
$182,432.35
KH Civil Contractors, Inc. $23,400.00
Engineer's Estimate ALL LPSM LPSM $135,000.00
E5040 15301-0000 CONTRACTOR
QUALITY CONTROL
Shumaker Trucking & Excavating Contractors, Inc.
$709,449.35
McKenzie Construction & Site Development, LLC
$505,002.81
KH Civil Contractors, Inc. $128,700.00
Engineer's Estimate ALL LPSM LPSM $375,000.00
E5060 15401-0000 CONTRACTOR
TESTING
Shumaker Trucking & Excavating Contractors, Inc.
$359,267.05
KH Civil Contractors, Inc. $154,700.00
McKenzie Construction & Site Development, LLC
$145,641.66
Engineer's Estimate ALL LPSM LPSM $375,000.00
E5080 15501-0000 CONSTRUCTION
SCHEDULE
Shumaker Trucking & Excavating Contractors, Inc.
$163,312.90
McKenzie Construction & Site Development, LLC
$45,909.34
KH Civil Contractors, Inc. $13,000.00
Engineer's Estimate ALL LPSM LPSM $55,000.00
E5100 15705-1400 SOIL EROSION
CONTROL, FIBER
ROLL
McKenzie Construction & Site Development, LLC
1,220.000 $28.69 $35,001.80
Shumaker Trucking & Excavating Contractors, Inc.
1,220.000 $8.95 $10,919.00
KH Civil Contractors, Inc. 1,220.000 $6.50 $7,930.00
Engineer's Estimate 1,220.000 LNFT $9.00 $10,980.00
Report Generated on 07/21/2026 8:05 PM [Timezone: (UTC-05:00) Eastern Time (US & Canada)]
E5120 15706-0200 SOIL EROSION
CONTROL, CHECK
DAM (FILTER ROCK)
McKenzie Construction & Site Development, LLC
41.000 $2,869.33 $117,642.53
Shumaker Trucking & Excavating Contractors, Inc.
41.000 $308.75 $12,658.75
KH Civil Contractors, Inc. 41.000 $227.50 $9,327.50
Engineer's Estimate 41.000 EACH $350.00 $14,350.00
E5140 15802-0000 WATERING FOR
DUST CONTROL
Shumaker Trucking & Excavating Contractors, Inc.
$264,196.05
McKenzie Construction & Site Development, LLC
$189,376.05
KH Civil Contractors, Inc. $37,700.00
Engineer's Estimate ALL LPSM LPSM $45,000.00
E5160 20301-1900 REMOVAL OF PIPE
CULVERT (5 FEET
SPAN, 7 FEET RISE
CMP ARCH)
KH Civil Contractors, Inc. 1.000 $7,800.00 $7,800.00
Shumaker Trucking & Excavating Contractors, Inc.
1.000 $5,113.10 $5,113.10
McKenzie Construction & Site Development, LLC
1.000 $4,590.93 $4,590.93
Engineer's Estimate 1.000 EACH $10,500.00 $10,500.00
E5180 20403-0000 UNCLASSIFIED
BORROW
KH Civil Contractors, Inc. 60.000 $97.50 $5,850.00
Shumaker Trucking & Excavating Contractors, Inc.
60.000 $71.85 $4,311.00
McKenzie Construction & Site Development, LLC
60.000 $20.65 $1,239.00
Engineer's Estimate 60.000 CUYD $110.00 $6,600.00
E5200 25101-0200 PLACED RIPRAP,
CLASS 2 (RIPRAP
HEADWALL)
KH Civil Contractors, Inc. 5.000 $650.00 $3,250.00
McKenzie Construction & Site Development, LLC
5.000 $183.63 $918.15
Shumaker Trucking & Excavating Contractors, Inc.
5.000 $175.00 $875.00
Engineer's Estimate 5.000 CUYD $450.00 $2,250.00
E5220 30202-2000 ROADWAY
AGGREGATE,
METHOD 2
McKenzie Construction & Site Development, LLC
1,515.000 $57.38 $86,930.70
Report Generated on 07/21/2026 8:05 PM [Timezone: (UTC-05:00) Eastern Time (US & Canada)]
E5220 30202-2000 ROADWAY
AGGREGATE,
METHOD 2
Shumaker Trucking & Excavating Contractors, Inc.
1,515.000 $42.05 $63,705.75
KH Civil Contractors, Inc. 1,515.000 $37.39 $56,645.85
Engineer's Estimate 1,515.000 TON $55.00 $83,325.00
E5240 30301-6000 ROADWAY
RECONDITIONING
McKenzie Construction & Site Development, LLC
41.770 $25,250.14 $1,054,698.35
Shumaker Trucking & Excavating Contractors, Inc.
41.770 $11,983.70 $500,559.15
KH Civil Contractors, Inc. 41.770 $4,550.00 $190,053.50
Engineer's Estimate 41.770 MILE $10,500.00 $438,585.00
E5260 31103-3000 STABILIZED
AGGREGATE
SURFACE COURSE,
CALCIUM
CHLORIDE
McKenzie Construction & Site Development, LLC
63,599.000 $43.43 $2,762,104.57
KH Civil Contractors, Inc. 63,599.000 $37.39 $2,377,966.61
Shumaker Trucking & Excavating Contractors, Inc.
63,599.000 $26.40 $1,679,013.60
Engineer's Estimate 63,599.000 TON $40.00 $2,543,960.00
E5280 31103-3000 STABILIZED
AGGREGATE
SURFACE COURSE,
CALCIUM
CHLORIDE (IN-
PLACE
STABILIZATION)
KH Civil Contractors, Inc. 27,384.000 $46.76 $1,280,475.84
McKenzie Construction & Site Development, LLC
27,384.000 $36.72 $1,005,540.48
Shumaker Trucking & Excavating Contractors, Inc.
27,384.000 $32.35 $885,872.40
Engineer's Estimate 27,384.000 TON $45.00 $1,232,280.00
E5300 31110-0000 CALCIUM
CHLORIDE
KH Civil Contractors, Inc. 2,061.000 $1,006.20 $2,073,778.20
Shumaker Trucking & Excavating Contractors, Inc.
2,061.000 $757.75 $1,561,722.75
McKenzie Construction & Site Development, LLC
2,061.000 $373.01 $768,773.61
Engineer's Estimate 2,061.000 TON $750.00 $1,545,750.00
E5320 60201-0800 24-INCH PIPE
CULVERT
Shumaker Trucking & Excavating Contractors, Inc.
78.000 $476.45 $37,163.10
McKenzie Construction & Site Development, LLC
78.000 $344.32 $26,856.96
Report Generated on 07/21/2026 8:05 PM [Timezone: (UTC-05:00) Eastern Time (US & Canada)]
E5320 60201-0800 24-INCH PIPE
CULVERT
KH Civil Contractors, Inc. 78.000 $283.40 $22,105.20
Engineer's Estimate 78.000 LNFT $250.00 $19,500.00
E5340 60201-1000 36-INCH PIPE
CULVERT
Shumaker Trucking & Excavating Contractors, Inc.
46.000 $613.85 $28,237.10
McKenzie Construction & Site Development, LLC
46.000 $401.70 $18,478.20
KH Civil Contractors, Inc. 46.000 $396.50 $18,239.00
Engineer's Estimate 46.000 LNFT $300.00 $13,800.00
E5360 60704-0000 CLEANING
CULVERT IN PLACE
McKenzie Construction & Site Development, LLC
5.000 $4,590.93 $22,954.65
Shumaker Trucking & Excavating Contractors, Inc.
5.000 $3,972.40 $19,862.00
KH Civil Contractors, Inc. 5.000 $3,250.00 $16,250.00
Engineer's Estimate 5.000 EACH $3,500.00 $17,500.00
E5380 60705-0000 REPAIRING
DRAINAGE
STRUCTURE
McKenzie Construction & Site Development, LLC
4.000 $16,068.27 $64,273.08
Shumaker Trucking & Excavating Contractors, Inc.
4.000 $5,197.15 $20,788.60
KH Civil Contractors, Inc. 4.000 $3,250.00 $13,000.00
Engineer's Estimate 4.000 EACH $4,500.00 $18,000.00
E5400 62201-0300 DUMP TRUCK, 12
CUBIC YARD
MINIMUM
CAPACITY
KH Civil Contractors, Inc. 90.000 $185.90 $16,731.00
McKenzie Construction & Site Development, LLC
90.000 $177.89 $16,010.10
Shumaker Trucking & Excavating Contractors, Inc.
90.000 $175.00 $15,750.00
Engineer's Estimate 90.000 HOUR $250.00 $22,500.00
E5420 62201-0550 BACKHOE LOADER,
6 CUBIC FOOT
MINIMUM RATED
CAPACITY BUCKET,
24-INCH WIDTH
KH Civil Contractors, Inc. 90.000 $243.10 $21,879.00
Shumaker Trucking & Excavating Contractors, Inc.
90.000 $200.00 $18,000.00
McKenzie Construction & Site Development, LLC
90.000 $172.16 $15,494.40
Engineer's Estimate 90.000 HOUR $250.00 $22,500.00
Report Generated on 07/21/2026 8:05 PM [Timezone: (UTC-05:00) Eastern Time (US & Canada)]
E5440 62201-2850 MOTOR GRADER,
12 FOOT
MINIMUM BLADE
Shumaker Trucking & Excavating Contractors, Inc.
90.000 $250.00 $22,500.00
KH Civil Contractors, Inc. 90.000 $239.20 $21,528.00
McKenzie Construction & Site Development, LLC
90.000 $200.85 $18,076.50
Engineer's Estimate 90.000 HOUR $300.00 $27,000.00 E5460 62301-0000 GENERAL LABOR Shumaker Trucking &
Excavating Contractors, Inc.
90.000 $150.00 $13,500.00
McKenzie Construction & Site Development, LLC
90.000 $97.55 $8,779.50
KH Civil Contractors, Inc. 90.000 $93.60 $8,424.00
Engineer's Estimate 90.000 HOUR $90.00 $8,100.00
E5480 62405-0300 PLACING
CONSERVED
TOPSOIL, 4-INCH
DEPTH
McKenzie Construction & Site Development, LLC
450.000 $86.08 $38,736.00
KH Civil Contractors, Inc. 450.000 $10.00 $4,500.00
Shumaker Trucking & Excavating Contractors, Inc.
450.000 $3.55 $1,597.50
Engineer's Estimate 450.000 SQYD $10.00 $4,500.00
E5500 62502-0000 TURF
ESTABLISHMENT
(DRY METHOD)
McKenzie Construction & Site Development, LLC
1,680.000 $10.32 $17,337.60
KH Civil Contractors, Inc. 1,680.000 $7.00 $11,760.00
Shumaker Trucking & Excavating Contractors, Inc.
1,680.000 $1.50 $2,520.00
Engineer's Estimate 1,680.000 SQYD $6.00 $10,080.00
E5520 62901-0800 ROLLED EROSION
CONTROL
PRODUCT, TYPE
2.D
McKenzie Construction & Site Development, LLC
833.000 $28.69 $23,898.77
Shumaker Trucking & Excavating Contractors, Inc.
833.000 $11.45 $9,537.85
KH Civil Contractors, Inc. 833.000 $10.00 $8,330.00
Engineer's Estimate 833.000 SQYD $20.00 $16,660.00
E5540 63501-0000 TEMPORARY
TRAFFIC CONTROL
Shumaker Trucking & Excavating Contractors, Inc.
$286,207.50
Report Generated on 07/21/2026 8:05 PM [Timezone: (UTC-05:00) Eastern Time (US & Canada)]
E5540 63501-0000 TEMPORARY
TRAFFIC CONTROL
KH Civil Contractors, Inc. $266,500.