Award Bid Tab_AK FNSB TANANA(1).pdf
PDF 198 KB Posted
- Solicitation number
- 69056723C000015
About this file
This document contains bid tabulations for the federal contract opportunity AK FNSB TANANA(1), Tanana River Recreation Access Improvements. The project involves construction services such as clearing, grubbing, excavation, culverts, fencing, signage, and other site work to improve recreation access on federal land in Alaska. Three bids were received by the February 28, 2023 deadline and ranged from $8.6 million to $9.8 million. The contract was awarded to Doyon Management Services, LLC for $8,611,595.20 on March 27, 2023. The work will be overseen by the Department of Transportation Federal Highway Administration.
View the file
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Tabulation of Bids Report Date: 02/28/23
1 out of 14 Project No: AK FNSB TANANA(1)
Project Name: Tanana River Recreation Access Improvements
Schedule: A
Schedule Type: Base
Solcitation No: 69056722B000024
Division: Western Federal Lands
State: AK County: Fairbanks North Star
Federal Land: Tanana Flats Training Area Opened at: FHWA Vancouver, WA Office
Opened by: Angy Liljedahl
Date: 02/28/23
I certify that this Bid Tabulation accurately reflects the offers received for this solicitation.
Signed: _______________________________
Title: _______________________________
Date: _______________________________
Contract Awarded to: ____________________ Award Date: ____________________
Contractor Comment Bid Amount Responsive
Doyon Management Services, LLC $8,611,595.20 3450 South 344th Way Federal Way, WA 98001
ASRC Earthworks, LLC $9,301,878.60 3900 C Street, Suite 309 Anchorage, AK 99503
C.I. Contractors, Inc. $9,833,854.88 229 E. Whitney Road Anchorage, AK 99501
Engineer's Estimate $7,793,847.00
MICHAEL
ANDREW
KENDRO
Digitally signed by MICHAEL
ANDREW KENDRO
Date: 2023.03.01 06:40:26 -08'00'
Doyon Management Services, LLC 03/27/2023
2 out of 14 Project No: AK FNSB TANANA(1)
Project Name: Tanana River Recreation Access Improvements
Schedule: A
Schedule Type: Base
Line Item Pay Item No. Description Quantity Unit Unit Price Amount
Number
A1000 15101-0000 MOBILIZATION
Doyon Management Services, LLC Lump Sum $378,452.87 ASRC Earthworks, LLC Lump Sum $320,000.00 C.I. Contractors, Inc. Lump Sum $229,500.00 Engineer's Estimate ALL LPSM Lump Sum $710,000.00
A1020 15201-0000 CONSTRUCTION SURVEY AND STAKING
Doyon Management Services, LLC Lump Sum $214,132.38 ASRC Earthworks, LLC Lump Sum $175,000.00 C.I. Contractors, Inc. Lump Sum $148,000.00 Engineer's Estimate ALL LPSM Lump Sum $160,000.00
A1040 15301-0010 CONTRACTOR QUALITY CONTROL AND ASSURANCE
Doyon Management Services, LLC Lump Sum $163,847.44 ASRC Earthworks, LLC Lump Sum $275,000.00 C.I. Contractors, Inc. Lump Sum $931,000.00 Engineer's Estimate ALL LPSM Lump Sum $210,000.00
A1060 15401-0000 CONTRACTOR TESTING
Doyon Management Services, LLC Lump Sum $32,439.30 ASRC Earthworks, LLC Lump Sum $75,000.00 C.I. Contractors, Inc. Lump Sum $81,297.00 Engineer's Estimate ALL LPSM Lump Sum $140,000.00
A1080 15501-0000 CONSTRUCTION SCHEDULE
Doyon Management Services, LLC Lump Sum $32,584.56 ASRC Earthworks, LLC Lump Sum $20,000.00 C.I. Contractors, Inc. Lump Sum $41,000.00 Engineer's Estimate ALL LPSM Lump Sum $16,000.00
A1100 15702-5000 SOIL EROSION CONTROL, TEMPORARY DIVERSION BERM
Doyon Management Services, LLC Lump Sum $36,929.99 ASRC Earthworks, LLC Lump Sum $6,000.00 C.I. Contractors, Inc. Lump Sum $137,000.00 Engineer's Estimate ALL LPSM Lump Sum $18,000.00
3 out of 14 Project No: AK FNSB TANANA(1)
Project Name: Tanana River Recreation Access Improvements
Schedule: A
Schedule Type: Base
Line Item Pay Item No. Description Quantity Unit Unit Price Amount
Number
A1120 15703-2000 SOIL EROSION CONTROL, TEMPORARY TURF ESTABLISHMENT
Doyon Management Services, LLC $6,893.60 $19,164.21 ASRC Earthworks, LLC $7,000.00 $19,460.00 C.I. Contractors, Inc. $9,000.00 $25,020.00 Engineer's Estimate 2.78 ACRE $7,300.00 $20,294.00
A1140 15705-0600 SOIL EROSION CONTROL, TEMPORARY 24-INCH CULVERT PIPE
Doyon Management Services, LLC $147.72 $37,225.44 ASRC Earthworks, LLC $200.00 $50,400.00 C.I. Contractors, Inc. $80.00 $20,160.00 Engineer's Estimate 252 LNFT $140.00 $35,280.00
A1160 15705-1000 SOIL EROSION CONTROL, TEMPORARY 48-INCH CULVERT PIPE
Doyon Management Services, LLC $332.37 $33,237.00 ASRC Earthworks, LLC $330.00 $33,000.00 C.I. Contractors, Inc. $137.00 $13,700.00 Engineer's Estimate 100 LNFT $215.00 $21,500.00
A1180 15705-1400 SOIL EROSION CONTROL, FIBER ROLL
Doyon Management Services, LLC $4.31 $55,646.41 ASRC Earthworks, LLC $6.00 $77,466.00 C.I. Contractors, Inc. $10.00 $129,110.00 Engineer's Estimate 12,911 LNFT $6.00 $77,466.00
A1200 15706-1600 SOIL EROSION CONTROL, STABILIZED CONSTRUCTION EXIT
Doyon Management Services, LLC $4,308.50 $21,542.50 ASRC Earthworks, LLC $1,000.00 $5,000.00 C.I. Contractors, Inc. $2,600.00 $13,000.00 Engineer's Estimate 5 EACH $3,000.00 $15,000.00
A1220 20101-0000 CLEARING AND GRUBBING
Doyon Management Services, LLC $17,234.00 $99,440.18 ASRC Earthworks, LLC $30,000.00 $173,100.00 C.I. Contractors, Inc. $25,000.00 $144,250.00 Engineer's Estimate 5.77 ACRE $15,000.00 $86,550.00
4 out of 14 Project No: AK FNSB TANANA(1)
Project Name: Tanana River Recreation Access Improvements
Schedule: A
Schedule Type: Base
Line Item Pay Item No. Description Quantity Unit Unit Price Amount
Number
A1240 20104-0000 CLEARING
Doyon Management Services, LLC $7,386.00 $6,130.38 ASRC Earthworks, LLC $12,000.00 $9,960.00 C.I. Contractors, Inc. $13,800.00 $11,454.00 Engineer's Estimate 0.83 ACRE $8,000.00 $6,640.00
A1260 20301-0100 REMOVAL OF BOLLARD
Doyon Management Services, LLC $307.75 $1,231.00 ASRC Earthworks, LLC $275.00 $1,100.00 C.I. Contractors, Inc. $300.00 $1,200.00 Engineer's Estimate 4 EACH $500.00 $2,000.00
A1280 20301-1100 REMOVAL OF GATE
Doyon Management Services, LLC $738.60 $1,477.20 ASRC Earthworks, LLC $1,000.00 $2,000.00 C.I. Contractors, Inc. $465.00 $930.00 Engineer's Estimate 2 EACH $1,000.00 $2,000.00
A1300 20301-1900 REMOVAL OF PIPE CULVERT
Doyon Management Services, LLC $1,600.30 $9,601.80 ASRC Earthworks, LLC $420.00 $2,520.00 C.I. Contractors, Inc. $3,000.00 $18,000.00 Engineer's Estimate 6 EACH $2,000.00 $12,000.00
A1320 20301-2400 REMOVAL OF SIGN
Doyon Management Services, LLC $153.87 $3,385.14 ASRC Earthworks, LLC $420.00 $9,240.00 C.I. Contractors, Inc. $100.00 $2,200.00 Engineer's Estimate 22 EACH $250.00 $5,500.00
A1340 20302-0700 REMOVAL OF FENCE
Doyon Management Services, LLC $18.46 $2,344.42 ASRC Earthworks, LLC $24.00 $3,048.00 C.I. Contractors, Inc. $23.00 $2,921.00 Engineer's Estimate 127 LNFT $23.00 $2,921.00
5 out of 14 Project No: AK FNSB TANANA(1)
Project Name: Tanana River Recreation Access Improvements
Schedule: A
Schedule Type: Base
Line Item Pay Item No. Description Quantity Unit Unit Price Amount
Number
A1360 20401-0000 ROADWAY EXCAVATION
Doyon Management Services, LLC $16.01 $156,129.52 ASRC Earthworks, LLC $16.00 $156,032.00 C.I. Contractors, Inc. $9.00 $87,768.00 Engineer's Estimate 9,752 CUYD $13.00 $126,776.00
A1380 20402-0000 SUBEXCAVATION
Doyon Management Services, LLC $14.77 $302,829.31 ASRC Earthworks, LLC $19.00 $389,557.00 C.I. Contractors, Inc. $12.00 $246,036.00 Engineer's Estimate 20,503 CUYD $15.00 $307,545.00
A1400 20411-0000 SELECT BORROW (Type B)
Doyon Management Services, LLC $16.01 $1,502,506.48 ASRC Earthworks, LLC $21.00 $1,970,808.00 C.I. Contractors, Inc. $17.00 $1,595,416.00 Engineer's Estimate 93,848 TON $16.00 $1,501,568.00
A1420 20411-0000 SELECT BORROW
Doyon Management Services, LLC $23.39 $298,760.47 ASRC Earthworks, LLC $21.00 $268,233.00 C.I. Contractors, Inc. $16.00 $204,368.00 Engineer's Estimate 12,773 TON $18.00 $229,914.00
A1440 20426-1000 DITCH, EXCAVATION
Doyon Management Services, LLC $24.62 $7,041.32 ASRC Earthworks, LLC $17.00 $4,862.00 C.I. Contractors, Inc. $25.00 $7,150.00 Engineer's Estimate 286 CUYD $20.00 $5,720.00
A1460 20701-0300 SEPARATION-STABILIZATION GEOTEXTILE, CLASS 1, TYPE C (NONWOVEN)
Doyon Management Services, LLC $4.92 $738.00 ASRC Earthworks, LLC $5.00 $750.00 C.I. Contractors, Inc. $18.00 $2,700.00 Engineer's Estimate 150 SQYD $5.00 $750.00
6 out of 14 Project No: AK FNSB TANANA(1)
Project Name: Tanana River Recreation Access Improvements
Schedule: A
Schedule Type: Base
Line Item Pay Item No. Description Quantity Unit Unit Price Amount
Number
A1480 20701-0400 SEPARATION-STABILIZATION GEOTEXTILE, CLASS 1, TYPE D (WOVEN)
Doyon Management Services, LLC $3.69 $250,801.92 ASRC Earthworks, LLC $6.00 $407,808.00 C.I. Contractors, Inc. $5.75 $390,816.00 Engineer's Estimate 67,968 SQYD $3.50 $237,888.00
A1500 20703-0000 GEOGRID (BIAXIAL, TYPE III)
Doyon Management Services, LLC $3.69 $59,818.59 ASRC Earthworks, LLC $5.00 $81,055.00 C.I. Contractors, Inc. $7.00 $113,477.00 Engineer's Estimate 16,211 SQYD $4.00 $64,844.00
A1520 20801-0000 STRUCTURE EXCAVATION
Doyon Management Services, LLC $33.24 $5,384.88 ASRC Earthworks, LLC $25.00 $4,050.00 C.I. Contractors, Inc. $34.00 $5,508.00 Engineer's Estimate 162 CUYD $65.00 $10,530.00
A1540 20802-0000 FOUNDATION FILL
Doyon Management Services, LLC $92.32 $1,477.12 ASRC Earthworks, LLC $30.00 $480.00 C.I. Contractors, Inc. $134.00 $2,144.00 Engineer's Estimate 16 CUYD $100.00 $1,600.00
A1560 20803-0000 STRUCTURAL BACKFILL
Doyon Management Services, LLC $43.09 $4,955.35 ASRC Earthworks, LLC $30.00 $3,450.00 C.I. Contractors, Inc. $62.00 $7,130.00 Engineer's Estimate 115 CUYD $100.00 $11,500.00
A1580 21101-1000 ROADWAY OBLITERATION, METHOD 1
Doyon Management Services, LLC $9.85 $19,601.50 ASRC Earthworks, LLC $8.50 $16,915.00 C.I. Contractors, Inc. $6.00 $11,940.00 Engineer's Estimate 1,990 SQYD $7.30 $14,527.00
7 out of 14 Project No: AK FNSB TANANA(1)
Project Name: Tanana River Recreation Access Improvements
Schedule: A
Schedule Type: Base
Line Item Pay Item No. Description Quantity Unit Unit Price Amount
Number
A1600 21101-2000 ROADWAY OBLITERATION, METHOD 2
Doyon Management Services, LLC $3.69 $11,549.70 ASRC Earthworks, LLC $8.50 $26,605.00 C.I. Contractors, Inc. $6.00 $18,780.00 Engineer's Estimate 3,130 SQYD $12.00 $37,560.00
A1620 21102-3000 ROADWAY OBLITERATION, METHOD 3
Doyon Management Services, LLC Lump Sum $49,239.99 ASRC Earthworks, LLC Lump Sum $16,000.00 C.I. Contractors, Inc. Lump Sum $2,450.00 Engineer's Estimate ALL LPSM Lump Sum $5,500.00
A1640 25101-0100 PLACED RIPRAP, METHOD A, CLASS 1
Doyon Management Services, LLC $369.30 $738.60 ASRC Earthworks, LLC $385.00 $770.00 C.I. Contractors, Inc. $212.00 $424.00 Engineer's Estimate 2 CUYD $1,000.00 $2,000.00
A1660 25101-0200 PLACED RIPRAP, METHOD A, CLASS 2
Doyon Management Services, LLC $233.89 $12,863.95 ASRC Earthworks, LLC $270.00 $14,850.00 C.I. Contractors, Inc. $165.00 $9,075.00 Engineer's Estimate 55 CUYD $200.00 $11,000.00
A1680 25101-0400 PLACED RIPRAP, METHOD A, CLASS 4
Doyon Management Services, LLC $233.89 $18,009.53 ASRC Earthworks, LLC $300.00 $23,100.00 C.I. Contractors, Inc. $200.00 $15,400.00 Engineer's Estimate 77 CUYD $220.00 $16,940.00
A1700 25125-0000 BOULDER
Doyon Management Services, LLC $1,107.90 $128,516.40 ASRC Earthworks, LLC $540.00 $62,640.00 C.I. Contractors, Inc. $200.00 $23,200.00 Engineer's Estimate 116 EACH $300.00 $34,800.00
8 out of 14 Project No: AK FNSB TANANA(1)
Project Name: Tanana River Recreation Access Improvements
Schedule: A
Schedule Type: Base
Line Item Pay Item No. Description Quantity Unit Unit Price Amount
Number
A1720 25126-0000 REMOVE AND RESET BOULDER
Doyon Management Services, LLC $307.75 $11,079.00 ASRC Earthworks, LLC $700.00 $25,200.00 C.I. Contractors, Inc. $127.00 $4,572.00 Engineer's Estimate 36 EACH $180.00 $6,480.00
A1760 30105-2000 SUBBASE GRADING B
Doyon Management Services, LLC $21.54 $706,555.08 ASRC Earthworks, LLC $33.00 $1,082,466.00 C.I. Contractors, Inc. $28.00 $918,456.00 Engineer's Estimate 32,802 TON $23.00 $754,446.00
A1780 30202-2000 ROADWAY AGGREGATE, METHOD 2
Doyon Management Services, LLC $33.86 $443,498.28 ASRC Earthworks, LLC $36.00 $471,528.00 C.I. Contractors, Inc. $39.00 $510,822.00 Engineer's Estimate 13,098 TON $28.00 $366,744.00
A1800 30202-2100 ROADWAY AGGREGATE, METHOD 2, SURFACE COURSE
Doyon Management Services, LLC $92.32 $7,754.88 ASRC Earthworks, LLC $72.00 $6,048.00 C.I. Contractors, Inc. $53.00 $4,452.00 Engineer's Estimate 84 TON $100.00 $8,400.00
A1840 31103-3000 STABILIZED AGGREGATE SURFACE COURSE, CALCIUM CHLORIDE, IMPORTED AGGREGATE
Doyon Management Services, LLC $80.01 $463,337.91 ASRC Earthworks, LLC $36.00 $208,476.00 C.I. Contractors, Inc. $49.50 $286,654.50 Engineer's Estimate 5,791 TON $30.00 $173,730.00
A1860 31214-0000 CALCIUM CHLORIDE FLAKE
Doyon Management Services, LLC $1,723.40 $184,403.80 ASRC Earthworks, LLC $1,750.00 $187,250.00 C.I. Contractors, Inc. $1,550.00 $165,850.00 Engineer's Estimate 107 TON $1,400.00 $149,800.00
9 out of 14 Project No: AK FNSB TANANA(1)
Project Name: Tanana River Recreation Access Improvements
Schedule: A
Schedule Type: Base
Line Item Pay Item No. Description Quantity Unit Unit Price Amount
Number
A1880 31303-0000 AGGREGATE-TOPSOIL COURSE
Doyon Management Services, LLC $92.32 $15,325.12 ASRC Earthworks, LLC $60.00 $9,960.00 C.I. Contractors, Inc. $61.00 $10,126.00 Engineer's Estimate 166 CUYD $65.00 $10,790.00
A1900 40301-0000 ASPHALT CONCRETE PAVEMENT
Doyon Management Services, LLC $172.34 $907,714.78 ASRC Earthworks, LLC $170.00 $895,390.00 C.I. Contractors, Inc. $215.00 $1,132,405.00 Engineer's Estimate 5,267 TON $140.00 $737,380.00
A1920 60201-0800 24-INCH PIPE CULVERT
Doyon Management Services, LLC $172.34 $69,797.70 ASRC Earthworks, LLC $190.00 $76,950.00 C.I. Contractors, Inc. $122.00 $49,410.00 Engineer's Estimate 405 LNFT $150.00 $60,750.00
A1940 60201-1200 48-INCH PIPE CULVERT
Doyon Management Services, LLC $430.85 $43,085.00 ASRC Earthworks, LLC $350.00 $35,000.00 C.I. Contractors, Inc. $222.00 $22,200.00 Engineer's Estimate 100 LNFT $325.00 $32,500.00
A1960 60202-0200 18-INCH EQUIVALENT DIAMETER ARCH OR ELLIPTICAL PIPE CULVERT
Doyon Management Services, LLC $166.19 $37,060.37 ASRC Earthworks, LLC $215.00 $47,945.00 C.I. Contractors, Inc. $132.00 $29,436.00 Engineer's Estimate 223 LNFT $140.00 $31,220.00
A1980 60202-0400 24-INCH EQUIVALENT DIAMETER ARCH OR ELLIPTICAL PIPE CULVERT
Doyon Management Services, LLC $141.56 $8,210.48 ASRC Earthworks, LLC $190.00 $11,020.00 C.I. Contractors, Inc. $171.00 $9,918.00 Engineer's Estimate 58 LNFT $210.00 $12,180.00
10 out of 14 Project No: AK FNSB TANANA(1)
Project Name: Tanana River Recreation Access Improvements
Schedule: A
Schedule Type: Base
Line Item Pay Item No. Description Quantity Unit Unit Price Amount
Number
A2000 60211-0600 END SECTION FOR 18-INCH EQUIVALENT DIAMETER ARCH OR ELLIPTICAL PIPE CULVERT
Doyon Management Services, LLC $553.95 $1,107.90 ASRC Earthworks, LLC $720.00 $1,440.00 C.I. Contractors, Inc. $570.00 $1,140.00 Engineer's Estimate 2 EACH $650.00 $1,300.00
A2020 60915-1000 WHEELSTOP, CONCRETE
Doyon Management Services, LLC $369.30 $95,279.40 ASRC Earthworks, LLC $240.00 $61,920.00 C.I. Contractors, Inc. $350.00 $90,300.00 Engineer's Estimate 258 EACH $180.00 $46,440.00
A2040 61901-2300 FENCE, SPLIT RAIL
Doyon Management Services, LLC $49.24 $17,923.36 ASRC Earthworks, LLC $60.00 $21,840.00 C.I. Contractors, Inc. $64.00 $23,296.00 Engineer's Estimate 364 LNFT $65.00 $23,660.00
A2060 61902-0900 GATE, METAL
Doyon Management Services, LLC $8,703.16 $60,922.12 ASRC Earthworks, LLC $18,000.00 $126,000.00 C.I. Contractors, Inc. $9,100.00 $63,700.00 Engineer's Estimate 7 EACH $6,500.00 $45,500.00
A2080 61921-1000 REMOVE AND RESET FENCE
Doyon Management Services, LLC $58.80 $17,640.00 ASRC Earthworks, LLC $50.00 $15,000.00 C.I. Contractors, Inc. $75.00 $22,500.00 Engineer's Estimate 300 LNFT $40.00 $12,000.00
A2100 62201-0350 BACKHOE
Doyon Management Services, LLC $221.58 $2,658.96 ASRC Earthworks, LLC $200.00 $2,400.00 C.I. Contractors, Inc. $310.00 $3,720.00 Engineer's Estimate 12 HOUR $150.00 $1,800.00
11 out of 14 Project No: AK FNSB TANANA(1)
Project Name: Tanana River Recreation Access Improvements
Schedule: A
Schedule Type: Base
Line Item Pay Item No. Description Quantity Unit Unit Price Amount
Number
A2120 62201-0900 WHEEL LOADER, 2 CUBIC YARD MINIMUM RATED CAPACITY
Doyon Management Services, LLC $246.20 $2,954.40 ASRC Earthworks, LLC $300.00 $3,600.00 C.I. Contractors, Inc. $435.00 $5,220.00 Engineer's Estimate 12 HOUR $170.00 $2,040.00
A2140 62201-1200 BULLDOZER, 80HP MINIMUM FLYWHEEL POWER
Doyon Management Services, LLC $276.97 $1,661.82 ASRC Earthworks, LLC $240.00 $1,440.00 C.I. Contractors, Inc. $465.00 $2,790.00 Engineer's Estimate 6 HOUR $180.00 $1,080.00
A2160 62201-1350 BULLDOZER, 200HP MINIMUM FLYWHEEL POWER
Doyon Management Services, LLC $369.30 $2,215.80 ASRC Earthworks, LLC $250.00 $1,500.00 C.I. Contractors, Inc. $565.00 $3,390.00 Engineer's Estimate 6 HOUR $205.00 $1,230.00
A2180 62201-2100 COMPACTOR
Doyon Management Services, LLC $246.20 $2,954.40 ASRC Earthworks, LLC $200.00 $2,400.00 C.I. Contractors, Inc. $300.00 $3,600.00 Engineer's Estimate 12 HOUR $140.00 $1,680.00
A2200 62201-2750 MOTOR GRADER
Doyon Management Services, LLC $356.99 $4,283.88 ASRC Earthworks, LLC $350.00 $4,200.00 C.I. Contractors, Inc. $540.00 $6,480.00 Engineer's Estimate 12 HOUR $180.00 $2,160.00
A2220 62301-0000 GENERAL LABOR
Doyon Management Services, LLC $116.95 $7,017.00 ASRC Earthworks, LLC $180.00 $10,800.00 C.I. Contractors, Inc. $190.00 $11,400.00 Engineer's Estimate 60 HOUR $110.00 $6,600.00
12 out of 14 Project No: AK FNSB TANANA(1)
Project Name: Tanana River Recreation Access Improvements
Schedule: A
Schedule Type: Base
Line Item Pay Item No. Description Quantity Unit Unit Price Amount
Number
A2240 62501-0000 TURF ESTABLISHMENT
Doyon Management Services, LLC $24,619.99 $137,133.34 ASRC Earthworks, LLC $8,400.00 $46,788.00 C.I. Contractors, Inc. $58,500.00 $325,845.00 Engineer's Estimate 5.57 ACRE $8,000.00 $44,560.00
A2260 62701-0000 SOD (REHABILITATION)
Doyon Management Services, LLC $11.08 $9,938.76 ASRC Earthworks, LLC $130.00 $116,610.00 C.I. Contractors, Inc. $66.00 $59,202.00 Engineer's Estimate 897 SQYD $50.00 $44,850.00
A2280 62701-0000 SOD (RESTABLISHMENT)
Doyon Management Services, LLC $12.31 $24,496.90 ASRC Earthworks, LLC $6.00 $11,940.00 C.I. Contractors, Inc. $36.00 $71,640.00 Engineer's Estimate 1,990 SQYD $50.00 $99,500.00
A2300 63302-0000 SIGN SYSTEM
Doyon Management Services, LLC $172.34 $115,912.44 ASRC Earthworks, LLC $200.00 $134,516.00 C.I. Contractors, Inc. $136.00 $91,470.88 Engineer's Estimate 672.58 SQFT $140.00 $94,161.20
A2320 63316-1000 REMOVE AND RESET SIGN
Doyon Management Services, LLC $1,107.90 $24,373.80 ASRC Earthworks, LLC $1,200.00 $26,400.00 C.I. Contractors, Inc. $578.00 $12,716.00 Engineer's Estimate 22 EACH $500.00 $11,000.00
A2340 63401-0100 PAVEMENT MARKINGS, TYPE A, SOLID
Doyon Management Services, LLC $1.42 $71,261.28 ASRC Earthworks, LLC $2.40 $120,441.60 C.I. Contractors, Inc. $1.50 $75,276.00 Engineer's Estimate 50,184 LNFT $0.70 $35,128.80
13 out of 14 Project No: AK FNSB TANANA(1)
Project Name: Tanana River Recreation Access Improvements
Schedule: A
Schedule Type: Base
Line Item Pay Item No. Description Quantity Unit Unit Price Amount
Number
A2360 63405-0400 PAVEMENT MARKINGS, TYPE A, RAILROAD SYMBOL
Doyon Management Services, LLC $36,929.99 $73,859.98 ASRC Earthworks, LLC $9,000.00 $18,000.00 C.I. Contractors, Inc. $36,500.00 $73,000.00 Engineer's Estimate 2 EACH $500.00 $1,000.00
A2380 63405-0450 PAVEMENT MARKINGS, TYPE A, ACCESSIBILITY SYMBOL
Doyon Management Services, LLC $184.65 $8,863.20 ASRC Earthworks, LLC $290.00 $13,920.00 C.I. Contractors, Inc. $183.00 $8,784.00 Engineer's Estimate 48 EACH $220.00 $10,560.00
A2400 63502-0600 TEMPORARY TRAFFIC CONTROL, BARRICADE TYPE 3
Doyon Management Services, LLC $738.60 $5,170.20 ASRC Earthworks, LLC $600.00 $4,200.00 C.I. Contractors, Inc. $316.00 $2,212.00 Engineer's Estimate 7 EACH $450.00 $3,150.00
A2420 63502-1250 TEMPORARY TRAFFIC CONTROL, TUBULAR MARKER, TYPE 42-INCH
Doyon Management Services, LLC $61.55 $12,310.00 ASRC Earthworks, LLC $95.00 $19,000.00 C.I. Contractors, Inc. $65.00 $13,000.00 Engineer's Estimate 200 EACH $55.00 $11,000.00
A2440 63503-1000 TEMPORARY TRAFFIC CONTROL, PLASTIC FENCE (ORANGE)
Doyon Management Services, LLC $3.26 $17,203.02 ASRC Earthworks, LLC $3.00 $15,831.00 C.I. Contractors, Inc. $7.50 $39,577.50 Engineer's Estimate 5,277 LNFT $7.00 $36,939.00
A2460 63504-1000 TEMPORARY TRAFFIC CONTROL, CONSTRUCTION SIGN
Doyon Management Services, LLC $49.24 $35,206.60 ASRC Earthworks, LLC $40.00 $28,600.00 C.I. Contractors, Inc. $128.00 $91,520.00 Engineer's Estimate 715 SQFT $65.00 $46,475.00
14 out of 14 Project No: AK FNSB TANANA(1)
Project Name: Tanana River Recreation Access Improvements
Schedule: A
Schedule Type: Base
Line Item Pay Item No. Description Quantity Unit Unit Price Amount
Number
A2480 63506-0500 TEMPORARY TRAFFIC CONTROL, FLAGGER
Doyon Management Services, LLC $147.72 $73,860.00 ASRC Earthworks, LLC $140.00 $70,000.00 C.I. Contractors, Inc. $198.00 $99,000.00 Engineer's Estimate 500 HOUR $100.00 $50,000.00
A2500 63601-3000 SYSTEM INSTALLATION, ELECTRICAL
Doyon Management Services, LLC Lump Sum $259,052.58 ASRC Earthworks, LLC Lump Sum $190,000.00 C.I. Contractors, Inc. Lump Sum $256,000.00 Engineer's Estimate ALL LPSM Lump Sum $282,000.00
A2520 64603-0000 FIXTURE (BEACH ACCESS MAT SYSTEM)
Doyon Management Services, LLC $30,774.99 $30,774.99 ASRC Earthworks, LLC $30,000.00 $30,000.00 C.I. Contractors, Inc. $30,250.00 $30,250.00 Engineer's Estimate 1 EACH $23,000.00 $23,000.00
A2540 64603-0500 FIXTURE, BICYCLE STORAGE RACK
Doyon Management Services, LLC $4,308.50 $8,617.00 ASRC Earthworks, LLC $2,800.00 $5,600.00 C.I. Contractors, Inc. $4,000.00 $8,000.00 Engineer's Estimate 2 EACH $1,750.00 $3,500.00
A2560 64603-1000 FIXTURE, VAULT TOILET
Doyon Management Services, LLC $203,114.94 $609,344.82 ASRC Earthworks, LLC $145,000.00 $435,000.00 C.I. Contractors, Inc. $167,000.00 $501,000.00 Engineer's Estimate 3 EACH $115,000.00 $345,000.00
Total Schedule - All Items
Doyon Management Services, LLC $8,611,595.20 ASRC Earthworks, LLC $9,301,878.60 C.I. Contractors, Inc. $9,833,854.88 Engineer's Estimate $7,793,847.00