AutoRecovery save of BARCO FM200 Replacement SOW.docx
DOCX document 33 KB Posted
- Solicitation number
- 52000QR260024318
About this file
This is a Statement of Work (SOW) for the refurbishment and redelivery of FM200 fire suppression system bottles for the USCGC Bailey Barco. The U.S. Coast Guard Surface Force Logistics Center seeks a contractor to receive two Chemtron 40-pound FM200 bottles from the USCGC Donald Horsley at Coast Guard Base Galveston, Texas (3000 Fort Point Rd, Galveston, TX 77550), perform all required maintenance and refurbishment, refill the bottles with the specified agent, and ship the certified repaired bottles to USCGC Bailey Barco in Ketchikan, Alaska (1360 Stedman St, Ketchikan, AK 99901). The completion deadline is 15 May 2026, with work performed Monday through Friday, 0730-1600 hours.
The contractor must possess specific technical knowledge and experience with the discontinued Chemtron FM200 system, as this is the only available source of replacement parts from the FRC fleet. All replaced parts shall be warranted against manufacturing and installation defects for a minimum of one year. The contractor is responsible for furnishing all equipment and services required, including personnel safety equipment compliant with OSHA standards (29 CFR 1915, 1910, 1926.62), and must comply with all federal, state, and local environmental regulations and Base Galveston policies. The contractor assumes full responsibility for proper transportation and disposal of all waste materials in accordance with 40 CFR requirements, with written notification required to the Base Environmental Specialist for any activities potentially causing environmental violations. This is a total small business set aside procurement being processed as a Request for Quote under FAR Part 12 simplified acquisition procedures on a firm-fixed price basis.
View the file
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
SCOPE OF WORK
CGC BAILEY BARCO EDG SPACE FM200 Bottle Replacement
1. SCOPE
Vendor shall receive 02 Chemtron bottles from Coast, Guard cutter Donald Horsley in Galveston, Texas and perform all required maintenance to referbish bottles, refill and ship to Coast Guard Cutter Bailey Barco in Ketchikan, AK
2. BACKGROUND
The Chemtron FM200 system on earlier FRCs has been discontinued. The only available source of parts are provided by the FRC fleet itself, sent to a vendor with the capability to refurbish them and send them back out. Technicians must have specific knowledge and experience with this outdated system.
3. REFERENCES
a. CG-DWG-154-WPC_555_201 FIXED FIRE EXTINGUISHING SYSTEM
b. CG-TP-8095_555_A FIRE PROTECTION SYSTEM, FM-200 - DESIGN, INSTALLATION, OPS & SVC MANUAL
c. MPC N31025.D FM200 CYLINDER REPLACE
4. REQUIREMENTS
5. Vendor shall receive 02 Chemtron bottles picked up from Galveston Texas and taken to their repair facility, perform all required maintenance to refurbish bottles, refill them with required amount of agent, to provide a certified repaired bottles, package and ship to CGC Bailey Barco in Ketchikan, AK. Once CGC Bailey Barco has received bottles Barco crew will install on the cutter. For additional information or requirements, please coordinate with SFLC Contact CWO Travis Batman. Travis.j.batman@uscg.mil 207-405-1231
5.1 The bottles supplied will be from the Coast Guard in Galveston. There is no suitable alternative at this time other than the original Chemtron 40lb bottles that were installed when the cutter was constructed.
5.2 Contractor shall pick up bottles at:
3000 Fort Point Rd Galveston, TX 77550
5.3 Contractor shall ship repaired bottles to:
1360 Stedman St Ketchikan, AK 99901
5.4 Period of Performance for completion of bottles is 15 MAY 2026. Working hours are Mon-Fri 0730-1600
5.5 Parts replaced shall be warrantied against manufacturing and installation defects for a minimum of one year.
5.6 Contractor shall comply with all required base access / security requirements, and applicable local, state, and federal safety and environmental regulations.
6 ADDITIONAL INFORMATION:
FAR 52.237-1 Site Visit: Offerors or quoters are urged and expected to inspect the site where services are to be performed and to satisfy themselves regarding all general and local conditions that may affect the cost of contract performance, to the extent that the information is reasonably obtainable. In no event shall failure to inspect the site constitute grounds for a claim after contract award.
Controlled Unclassified Information: JCP certification is required for United States (U.S.) or Canadian contractors who wish to obtain access to unclassified technical data disclosing militarily critical technology with military or space application that is under the control of, or in the possession of the U.S. Department of Defense (DOD) or the Canadian Department of National Defense (DND).
ORAL MODIFICATION: No oral statement of any person other than the contracting officer shall in any manner or degree, modify, or otherwise affect the terms of this contract.
ACCEPTANCE CRITERIA: Criteria evaluated for payment approval. The government will review work in its entirety prior to issuing invoice approval.
GOVERNMENT FURNISHED ITEMS AND SERVICES:
Utilities: The Government will provide 2 Chemtron 40 LB bottes to be refurbished.
CONTRACTOR FURNISHED ITEMS, SERVICES AND RESPONSIBILITIES:
General: The Contractor shall furnish all equipment and services required to perform work under this SOW, other than those explicitly addressed in government furnished services.
The Contractor shall report to the designated work site on the date specified on the written notification by the Contracting Officer in the form of a signed order. No other individual has the authority to direct the Contractor to begin work, other than a warranted Contracting Officer.
Contractor Equipment: vehicles and trucks which holds or can hold hazardous materials that is left on Base Galveston premises must have the Contractor’s contact information placed in the driver’s side window indicating the Emergency Contact Number (answered 24/7/365) for the owner/operator of the vehicle. If a tank is left on the premises, the Emergency Contact Number (answered 24/7/365) for the owner/operator of the tank must be painted on the tank in a prominent location. The government will not assume liability for any vehicles/tanks left on Base Galveston property. The POC will coordinate approved storage locations.
General: The Contractor will be required to follow 29 CFR 1915 (OSHA Shipyard Industry Standard), 16 CFR1303, 29 CFR 1910, 29 CFR 1915.1025, 29 CFR 1926.62, 15 U.S.C. 2601, while performing this work at the U.S. Coast Guard Base Galveston.
Safety Equipment: The Contractor will provide all required personnel safety equipment for their employees, including, but not limited to, safety helmet and safety glasses with side shields. All safety equipment shall meet OSHA standards. The Contractor shall follow all applicable OSHA guidelines and regulations.
EMERGENCY SERVICES: Base Galveston has 24-hour first aid and spill response. If necessary, the Contractor may call the Base Officer of the Day at 409-682-0142 for emergency situations. Injuries shall be reported immediately and followed up with a written report to the COR.
ENVIRONMENTAL PROTECTION REQUIREMENTS: Contractor shall abide by all federal, state, and local environmental regulations as published by the Environmental Protection Agency, 40 CFR (series) and any applicable Base Galveston plans/policies:
Transport and Disposal: The Contractor must properly remove and dispose of all materials in compliance with applicable Federal, state, and local environmental laws and regulations. Contractor assumes all responsibility and liability for the transport and proper disposal of materials and in particular the following requirements:
1. If a spill occurs, the Contractor shall notify the Cutter’s Officer of the Day immediately.
1. The Contractor MUST follow Base Galveston Response Plan, when operating on its property.
1. Written notification must be provided to the Base Environmental Specialist, Nick Duin (Nicholas.M.Duin@uscg.mil), of any activity that could potentially cause an environmental violation. Some examples of these activities are: any activity that could result in a spill or discharge into a waterway or introducing a hazardous material into the environment.
1. The Contractor will be solely responsible for the transportation and proper disposal of waste material. Contractor must submit disposal sites to Base Galveston Environmental Department for site approvals and copies of Bill Of Lading or waste manifests. If Contractor elects to use dumpsters for holding or transportation of waste, dumpsters must be covered to prevent waste from becoming airborne.
1. Only the Base Galveston Environmental Dept is authorized to sign hazardous waste manifest.
File details come from the government source that posted it. Updated .