Attch 4 - Pricing Worksheet.pdf
PDF 65 KB Posted
- Attached to
- HAYSTACK OHV WATER WELL CONSTRUCTION
- Solicitation number
- 140L0621Q0008
View the file
Other files
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
PRICING WORKSHEET
HAYSTACK MOUNTAIN WATER WELL
ROSWELL FIELD OFFICE
Item Pay Item Estimated Unit Total No. Number Description Quantity Unit Price Amount
1. 02671(1) *Drilling Pilot Hole 300LF Lump Sum $______ $_____ (5-inch min dia.)
2. 02671(2) *Drilling Well Hole 300LF Lump Sum $ $ (10-inch min. Dia.)
3. 02671(3) *Furnish and Install 240LF Lump Sum $ $ 5-Inch PVC Casing
4. 02671(4) *Furnish and Install 60LF Lump Sum $____ $_______ 5-Inch Slotted PVC Casing
5. 02671(5) *Gravel Packing/ 100LF Lump Sum $ $ Bentonite Seal
6. 02671(6) *Formation 180LF Lump Sum $ $ Stabilizer/Grout
7. 02671(7) *Surface Grout 50LF Lump Sum $ $ Stabilizer/Grout
8. 02672(1) Well Development 12HR Lump Sum $ $
9. 02672(2) Well Testing 12HR Lump Sum $ $
10. 02672(3) Water Quality 1 Lump Sum $ $
11. 01505(1) Mobilization 1 Lump Sum $ $
12. 02670(1) *Well Abandonment 300LF Lump Sum $ $
TOTAL BID (All or none) $
* 52.211-18 Variation in Estimated Quantity applies to this item. The Unit Price proposed shall be incorporated into the resultant contract and will be the basis for any adjustments.
Total bid cost includes all overhead, profit, applicable Federal, State and Local taxes.
File details come from the government source that posted it. Updated .