PRICING WORKSHEET

HAYSTACK MOUNTAIN WATER WELL

ROSWELL FIELD OFFICE

Item Pay Item Estimated Unit Total No. Number Description Quantity Unit Price Amount

1. 02671(1) *Drilling Pilot Hole 300LF Lump Sum $______ $_____ (5-inch min dia.)

2. 02671(2) *Drilling Well Hole 300LF Lump Sum $ $ (10-inch min. Dia.)

3. 02671(3) *Furnish and Install 240LF Lump Sum $ $ 5-Inch PVC Casing

4. 02671(4) *Furnish and Install 60LF Lump Sum $____ $_______ 5-Inch Slotted PVC Casing

5. 02671(5) *Gravel Packing/ 100LF Lump Sum $ $ Bentonite Seal

6. 02671(6) *Formation 180LF Lump Sum $ $ Stabilizer/Grout

7. 02671(7) *Surface Grout 50LF Lump Sum $ $ Stabilizer/Grout

8. 02672(1) Well Development 12HR Lump Sum $ $

9. 02672(2) Well Testing 12HR Lump Sum $ $

10. 02672(3) Water Quality 1 Lump Sum $ $

11. 01505(1) Mobilization 1 Lump Sum $ $

12. 02670(1) *Well Abandonment 300LF Lump Sum $ $

TOTAL BID (All or none) $

* 52.211-18 Variation in Estimated Quantity applies to this item. The Unit Price proposed shall be incorporated into the resultant contract and will be the basis for any adjustments.

Total bid cost includes all overhead, profit, applicable Federal, State and Local taxes.